Loading...
Monthly Reports 2014-03 (Mar)   Page  |  1     MONTHLY  PROGRESS  REPORTMONTHLY  PROGRESS  REPORT       Through   March  2014       Strong  Schools  Bond   Capital  Improvement  Projects   Prepared  by       fs3|Hodges   &   Gilbane  Building  Company     Page  |  2     TABLE  OF  CONTENTS    Executive  Summary                  page  3    Attachment  1  –  Consolidated  Expenditure  Report                    Capital  Projects      Gunn  High  School  –  Phase  I  -­‐  Parking  and  Drop-­‐off  Sitework  Improvement    page  6     Gunn  High  School  –  E  and  K  (L31  and  MS)  Buildings  Renovation      page  7     Gunn  High  School  –  Central  Building  Project            page  8    Palo  Alto  High  School  –  New  Classroom  Building  and  Media  Arts      page  9     Palo  Alto  High  School  –  Performing  Arts  Center          page  10     Palo  Alto  High  School  –  Science  Building  Addition          Page  11    Palo  Alto  High  School  –  New  Gymnasium            Page  12     J.L.  Stanford  Middle  School              page  13         Duveneck  Elementary  School  –  New  Classroom  Buildings  and  Modernization    page  14    Technology                    page  15      Completed  Capital  Projects    Gunn  High  School  –  New  Classroom  Building  and  World  Languages  Building    page  16   Gunn  High  School  –  New  Gymnasium              page  17   Gunn  High  School  –  Existing  Gymnasium  Modernization        page  18   Palo  Alto  High  School  –  Athletic  Stadium  Improvements        page  19   Palo  Alto  High  School  –  Haymarket  and  Tower  Building  Improvements      page  20   Jordan  Middle  School                page  21   J.L.  Stanford  Middle  School  –  Landscape  and  Site  Improvements      page  22   Terman  Middle  School                page  23     Fairmeadow  Elementary  School  –  New  Classroom  Buildings  and  Modernization    page  24   Ohlone  Elementary  School                page  25   Property  Acquisition  –  525  San  Antonio  Rd              page  26   Jordan  Middle  School  –  Interim  Classrooms            page  27   Gunn  High  School  –  Air  Conditioning  of  Existing  Buildings        page  28   J.L.  Stanford  Middle  School  –  Interim  Classrooms          page  29   Fairmeadow  Elementary  School  –  Portable  Relocation        page  30   Elementary  Classroom  Improvements  –  Interactive  Whiteboard  &  Sound  Assist  System  page  31   Palo  Alto  High  School  –  Multi-­‐use  Field            page  32   Gunn  High  School  –  Industrial  Arts  Renovation          page  33   Gunn  High  School  –  Aquatic  Center              page  34   Middle  School  Pre-­‐Design                page  35     Inactive  Capital  Projects    Garland  Elementary  School              page  36   High  School  Master  Plan                page  37   Hoover  Elementary  School                page  38   Elementary  Classroom  Improvements            page  39   Appendix   Exhibit  A  –  Bond  Project  List           Page  |  3     EXECUTIVE  SUMMARY     Gunn  High  School  –  Miranda  Ave.  Drop-­‐Off  (Phase  I  -­‐  Parking  and  Drop-­‐Off  Improvements)   Grade   Tech,   Inc.  continued  to   pour  concrete  for   curbs,  gutters  and   walkways.    Grade   Tech   also  continued   compaction  and  fine  grading  in  preparation  for  asphalt  work,  which  is  scheduled  to  occur  in  April  2014.     Gunn  High  School  –  E  and  K  (L-­‐31  and  MS)  Buildings  Renovation   DLM  received  DSA  approval  on  March  27,  2014.    Authorization  to  solicit  bids  was  discussed  at  the  March  25,  2014   BOE  meeting.    Bids  are  scheduled  to  be  opened  on  April  29,  2014  with  the  Board  awarding  a  contract  on  May  6,   2014.    The  project  is  scheduled  for  construction  during  late  spring  and  summer  of  2014.     Gunn  High  School  –  Central  Building  Project   Conceptual  design  approval  was  received  on  March  11,  2014.    DLM  commenced  schematic  design  meetings  with   the  various  user  groups,  which  are  anticipated  to  conclude  in  April  2014.    The  project  includes  the  replacement  of   the  current  RC  building  and  music  building,  and  expands  the  Spangenberg  Theater  lobby.     Palo  Alto  High  School  –  New  Math/Social  Sciences  Building  and  Media  Arts  Building   Taisei   Construction  continued   punch-­‐list   corrections   the   new  Math/Social   Sciences   building.    New   classroom   furniture  for  the  second  floor  of  the  Math/Social  Science  Building  arrived  on  March  31,  2014.    At  the  Media  Arts   building,  the  contractor  continued  the  installation  of  the  audio  visual  equipment.     Palo  Alto  High  School  –  Performing  Arts  Center  (PAC)   Prequalification  of  general  contractors  and  mechanical,  electrical,  and  plumbing  subcontractors  is  complete,  and   staff  will  begin  soliciting  bids  in  early  April,  with  the  bid  opening  scheduled  for  May  13,  2014.  Award  is  anticipated   to  occur  at  the  May  20,  2014  Board  meeting.         Palo  Alto  High  School  –  Science  Building  Addition     DLM  will  begin  meeting  with  faculty  and  staff  in  April  2014  for  review  of  design  development.    The  construction   schedule  was  adjusted  to  occur  after  construction  of  the  new  gymnasium,  due  to  space  constraints  and  access  to   the  site.     Palo  Alto  High  School  –  Indoor  PE  and  Athletic  Facilities     Construction  documents  were  submitted  to  DSA  on  January  27,  2014  by  the  project  architect,  Jeremiah  Tolbert   Design  Architects  (JTDA).    Construction  is  currently  anticipated  to  begin  during  the  summer  of  2014.     Duveneck  Elementary  School  –  New  Classroom  Buildings  and  Modernization   Alpha  Bay  Builders  (ABB)  completed  rough-­‐in  for  mechanical,  electrical,  plumbing,  and  fire  sprinkler  on  building  1,   with  window  flashing  installation  beginning  in  April.    The  new  foundation  is  in  place  and  framing  commenced  in   building  F,  which  will  be  renovated  into  the  new  library.     Technology   Installation  of  exterior  wireless  antennas  and  repeaters  at  each  campus  continued.     COMPLETED  CAPITAL  PROJECTS     Gunn  High  School  –  New  Classroom  Building  and  World  Languages  Building   The  new  Math  and  English  Building  was  occupied  by  staff  and  students  on  August  15,  2013.    World  Language   Building  classrooms  have  been  in  use  since  February,  2013.     Gunn  High  School  –  New  Gymnasium   The  new  gymnasium  was  occupied  on  June  7,  2013  and  PE  classes  were  held  in  the  new  gym  on  August  15,  2013.     The  tennis  courts  surfacing  and  striping  was  installed  and  completed  August  27,  2013.     Page  |  4       Gunn  High  School  –  Existing  Gymnasium  Modernization   The  modernized  Bow  gym  was  occupied  by  the  campus  on  November  4,  2013.     Palo  Alto  High  School  –  Athletics  Stadium  Improvements   The  main  project  including  a  concessions  building,  track  re-­‐surfacing,  new  ornamental  fence,  signage  and  entry   lighting  has  been  completed.     Palo  Alto  High  School  –  Haymarket  and  Tower  Building  Improvements   All  Trusty  Builders  completed  the  installation  of  the  new  windows  on  August  9,  2013.     Jordan  Middle  School   Close-­‐out  efforts  continued  through  March  2014.     J.L.  Stanford  Middle  School   SAUSAL  Corp.  continued  to  correct  punch  list  items.    Close-­‐out  efforts  continued  through  March  2014.     J.L.  Stanford  Middle  School  –  Landscape  and  Sitework  Improvements       Close-­‐out  efforts  continued  through  March  2014.     Terman  Middle  School   Close-­‐out  efforts  continued  through  March  2014.     Fairmeadow  Elementary  School  –  New  Classroom  Building  and  Modernization     Close-­‐out  efforts  continued  through  March  2014.     525  San  Antonio  Road  –  Site  Acquisition   This  site  has  been  leased  to  Athena  Academy.       Ohlone  Elementary  School  –  New  Classroom  Building  and  Modernization   Move-­‐in  to  the  new  building  and  other  existing  classrooms  occurred  in  December  2011.    Students  occupied  the   new  building  on  January  3,  2012.         Jordan  Middle  School  -­‐  Interim  Classrooms   The  portables  were  installed  and  moved  into  for  fall  2011.    DSA  closeout  received  November  19,  2012.     Gunn  High  School  –  Air  Conditioning  of  Existing  Buildings   Best  Contracting  Services  Inc.  completed  the  installation  of  air  conditioning  units  and  cool  roof  coating  in  the   summer  2011.     J.L.  Stanford  Middle  School  -­‐  Interim  Classrooms   Coulter  Construction  completed  the  work  on  the  relocated  portables  in  August  2011.         Fairmeadow  Elementary  School  –  Portable  Relocation   Relocation  of  the  portable  was  complete  and  occupied  on  August  8,  2011.     Elementary  Classroom  Improvements  –  Installation  of  Interactive  Whiteboards  and  Sound  Assist  Systems   Installation   of   SmartBoards   and   Lightspeed   sound   assist   systems   were   completed   for  all   elementary   school   classrooms  and  libraries  in  April  2011.               Page  |  5     Palo  Alto  High  School  –  Multi-­‐use  Field   The  fields  were  available  for  play  on  February  1,  2011,  and  final  change  order  negotiations  completed  on  March  9,   2011.     Gunn  High  School  –  Industrial  Arts  Addition  &  Renovation   This  facility  was  available  for  instruction  in  January  2010.  DSA  closeout  received  on  July  18,  2011.     Gunn  High  School  –  Aquatic  Center     This  facility  was  available  for  use  in  July  2009,  and  has  been  closed  out  with  DSA.     Middle  Schools  Pre-­‐Design  –  Jordan,  J.L.  Stanford  and  Terman   AEDIS   presented   recommended   concept   plans   for   each   campus   to   the   Board   of   Education   for   approval  on   September  8,  which  became  the  program  documents  for  the  new  projects  at  each  campus.    These  projects  for  pre-­‐ design  work  have  been  closed,  and  funds  were  transferred  to  the  program  contingency  on  June  14,  2011.     INACTIVE  CAPITAL  PROJECTS       Garland  Elementary  School  Renovation   The  Board  of  Education  has  put  new  development  for  Garland  on  hold  until  a  growth  plan  is  established  for  the   elementary  schools.    Discussions  with  the  Board  on  future  plans  for  growth  at  the  elementary  schools  are  ongoing.     High  School  Master  Plan   The  Board  of  Education  (BOE)  approved  the  master  plans  for  both  high  schools,  and  these  projects  have  been   closed,  with  funds  transferred  to  the  respective  campus  reserve  funds.   Hoover  Elementary  School  –  Pre-­‐Design   This  project  has  been  put  on  hold  until  a  growth  plan  is  established  for  the  elementary  schools.         Elementary  Classroom  Improvements  –  Phase  1  Schools  Barron  Park  and  El  Carmelo   The  project  has  been  placed  on  hold  pending  further  discussions  with  the  BOE  about  elementary  growth  planning.           Board  Actions  in  March   March  11,  2014   Consent  5  –    Approval  of  DLM  Architects’  Conceptual  Design  for  the  Central  Building  Project  at  Gunn  High  School,   DLM  Architects’  Proposal  for  Schematic  Design  Services  and  Overall  Budget  for  this  Project     March  25,  2014   Consent  5  –  Approval  of  Strong  Schools  Bond  Change  Orders         A B C C / A B - C C / B A - BGunn High School - High School Master Plan 172,390 166,328 136,129 79.0% 30,199 81.84% 6,062Gunn High School 1 - Aquatic Center 4,865,425 4,862,530 4,862,530 99.9% 0 100.00% 2,895Gunn High School 2 - I.A Building 5,082,402 5,066,038 5,063,763 99.6% 2,275 99.96% 16,364Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 25,035,201 25,018,966 24,690,100 98.6% 328,866 98.69% 16,235Gunn High School 5 - Parking & Drop Off improvements 3,940,000 1,983,200 1,001,974 25.4% 981,226 50.52% 1,956,800Gunn High School 6- New/Auxiliary Gymnasium 12,914,800 12,520,516 12,193,574 94.4% 326,942 97.39% 394,284Gunn High School 7- A/C 2,600,000 2,103,866 2,102,366 80.9% 1,500 99.93% 496,134Gunn High School 8 - MS & L-31 Buildings 2,120,839 292,973 109,613 5.2% 183,360 37.41% 1,827,866Gunn High School 9 - Central building 19,374,242 1,415 1,415 0.0% 0 100.00% 19,372,827Gunn High School - Reserved 0 0 0 0.0% 0 0.00% 0Palo Alto High Schools - High School Master Plan 172,999 167,759 161,616 93.4% 6,143 96.34% 5,240Palo Alto High School 1 - Stadium Field 5,090,000 5,080,732 4,748,452 93.3% 332,280 93.46% 9,268Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,609,680 100.0% 0 100.00% 0Palo Alto high School 3 - New classroom & Media Art Building 38,415,001 34,685,569 32,122,150 83.6% 2,563,419 92.61% 3,729,432Palo Alto High School 4 - New Theater 24,395,049 3,015,169 1,197,542 4.9% 1,817,627 39.72% 21,379,880Palo Alto High School 5 - Haymarket and Tower Admin. Building 1,499,999 1,300,759 1,262,333 84.2% 38,426 97.05% 199,240Palo Alto High School 6- Science Addition 5,532,204 637,901 325,945 5.9% 311,956 51.10% 4,894,303Paly 7- indoor phusical ed and athletic facilities 250,000 159,890 154,722 61.9% 5,168 96.77% 90,110Palo Alto High School - Reserved 23,549,443 0 0 0.0% 0 0.00% 23,549,443Jordan Middle School -Program Management- MS Pre-Design 18,890 17,826 17,826 94.4% 0 100.00% 1,064Jordan Middle Schools 1- Interim Classrooms 600,342 488,684 481,520 80.2% 7,164 98.53% 111,658Jordan Middle School 2- Improvements 19,891,564 19,174,401 17,989,003 90.4% 1,185,398 93.82% 717,163J.L.S Middle School - Program Management- MS Pre-Design 18,799 18,408 18,408 97.9% 0 100.00% 391J.L.S Middle School 1 - Interim Classrooms 446,844 422,500 418,852 93.7% 3,648 99.14% 24,344 J.L.S Middle School 2- Improvements 17,184,699 16,601,642 15,252,976 88.8% 1,348,666 91.88% 583,057Terman Middle School - Program Management- MS Pre-Design 18,799 18,423 18,423 98.0% 0 100.00% 376Terman Middle School 1- Improvements 13,312,971 13,098,558 12,825,585 96.3% 272,973 97.92% 214,413PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 98,480 92,290 63.6% 6,190 93.71% 46,520Addison Elementary School 1-Phase I 21,267 21,267 21,267 100.0% 0 100.00% 0Duveneck Elementary School 1-Phase I 9,778,358 9,418,819 6,261,571 64.0% 3,157,248 66.48% 359,539Garland Elementary School 1- Phase I 22,178,544 280,113 280,113 1.3% 0 100.00% 21,898,431Fairmeadow Elementary School 1- Phase I 7,796,550 7,727,554 7,308,701 93.7% 418,853 94.58% 68,996Hoover Elementary School 1-Phase I 70,550 70,550 57,165 81.0% 13,385 81.03% 0Ohlone Elementary School 1- Phase I 10,597,870 10,578,054 10,481,389 98.9% 96,665 99.09% 19,816 Elementary Schools 1 - Elementary Classroom Improvements * 2,004,889 1,879,695 1,879,695 93.8% 0 100.00% 125,194Elementary Schools - Reserved 37,585,253 0 0 0.0% 0 0.00% 37,585,253PAUSD - Program Management 10,380,131 8,770,888 7,836,537 75.5% 934,351 89.35% 1,609,243PAUSD - Technology 10,485,054 9,332,373 9,280,752 88.5% 51,621 99.45% 1,152,681PAUSD - Technology -Reserved 3,422,312 0 0 0.0% 0 0.00% 3,422,312PAUSD - Reserved 6,055,697 0 0 0.0% 0 0.00% 6,055,697525 San Antonio -Property Acquisition 8,500,000 8,500,000 8,500,000 100.0% 0 100.00% 0Bond Issuance Cost & Other Transfer Out 19,927,288 19,927,288 19,927,288 100.0% 0 100.00% 0Total378,067,122 226,124,590 211,699,041 14,425,549 151,942,532Prepared by: Business Services Department based on QSS accounting SystemSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond3/31/2014Percent of ExpendedContract BalanceExpenditures Budget BalanceCommittedBudget   Page  |  6     Gunn  High  School   Miranda  Ave.  Drop  Off   Phase  I  –  Parking  and  Drop-­‐off  Improvements     A. PROJECT  STATUS     Grade  Tech,  Inc.  continued  to  pour  concrete  for  curbs,  gutters  and  walkways.     Grade  Tech  also  continued  compaction  and  fine  grading  in  preparation  for   asphalt  work,  which  is  scheduled  to  occur  in  April  2014.                     B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  5.5     D. PROJECT  OVERVIEW:   • Phase  I,  Miranda  Ave.  parking  and  drop-­‐off  project  is  proceeding  on  schedule  and  within  budget.       Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $3,940,000   Other  Funding  $0   Total  $3,940,000     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $919,858   Construction  &  Equipment  $2,919,840   Soft  Costs  Contingency  $100,302   Total  $3,940,000     Percent  of  Budget  Expended  25.4%     Change  Order  Contingency   • Starting  Contingency  Balance  $121,380   • Remaining  Contingency  Balance  $121,380   • Percent  of  Changes  0.0%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:    Construction    Schedule:   Architect  Contract  (2)  March  31,  2009   BOE  Approval  April  14,  2009    Conceptual  Design  (2)  June  19,  2012   BOE  Approval  June  26,  2012     Schematic  Design  (2)  December  18,  2012   BOE  Approval  January  15,  2013    Authorize  to  Bid  (2)  June  11,  2013   BOE  Approval  June18,  2013     Submit  to  DSA  July  17,  2013       Approval  by  DSA  October  2,  2013     Bid  Opening  November  12,  2013     Award  of  Contract  (1)  November  19,  2013    Notice  to  Proceed  December  4,  2013    Substantial  Completion  June  21,  2014*      *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  7     Gunn  High  School   E  and  K  (MS  and  L-­‐31)  Buildings  Renovation     A. PROJECT  STATUS     DLM  received  DSA  approval  on  March  27,  2014.    Authorization  to  solicit   bids   was   discussed   at   the   March   25,   2014   BOE   meeting.    Bids   are   scheduled  to  be  opened  on  April  29,  2014  with  the  Board  awarding  a   contract  on  May  6,  2014.    The  project  is  scheduled  for  construction  during   late  spring  and  summer  of  2014.                   B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  3.4,  3.5,  3.13     D. PROJECT  OVERVIEW:   • Plans  were  submitted  to  DSA  on  November  25,  2013.    Plans  were  approved  in  March  2014  and   authorization  to  bid  planned  for  March  25  and  April  22  board  meetings.   Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $2,120,839   Other  Funding  $0   Total  $2,120,839     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $428,000   Construction  &  Equipment  $1,689,952   Soft  Costs  Contingency  $2,887   Total  $2,120,839     Percent  of  Budget  Expended  5.2%       Current  Phase:      Bid  &  Award    Schedule:   Architect  Contract  (2)  March  31,  2009   BOE  Approval  April  14,  2009     Conceptual  Design  (2)  September  8,  2009   BOE  Approval  September  22,  2009    Schematic  Design  (2)  June  11,  2013   BOE  Approval  June  18,  2013    Submit  to  DSA  November  25,  2013     Authorize  to  Bid  (2)  March  25,  2014*   BOE  Approval  April  22,  2014*    Approval  by  DSA  March  27,  2014*    Bid  Opening  April  30,  2014*    Award  of  Contract  (1)  May  13,  2014*    Notice  to  Proceed  May  23,  2014*     Substantial  Completion  October  1,  2014*     Planned  Occupancy  October  16,  2014*     *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  8     Gunn  High  School   Central  Building  Project   A. PROJECT  STATUS     Conceptual  design  approval  was  received  on  March  11,  2014.    DLM   commenced  schematic  design  meetings  with  the  various  user  groups,   which  are  anticipated  to  conclude  in  April  2014.    The  project  includes   the  replacement  of  the  current  RC  building  and  music  building,  and   expands  the  Spangenberg  Theater  lobby.                         B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  5.5     D. PROJECT  OVERVIEW:   • Conceptual  design  approval  anticipated  on  March  11,  2014.    Schematic  design  is  in  progress.   Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $19,374,242   Other  Funding  $0   Total  $19,374,242     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $3,237,823   Construction  &  Equipment  $15,936,419   Soft  Costs  Contingency  $200,000   Total  $19,374,242     Percent  of  Budget  Expended  0.0%       Current  Phase:    Schematic  Design    Schedule:   Architect  Contract  (2)  March  31,  2009   BOE  Approval  April  14,  2009     Conceptual  Design  (2)  February  25,  2014   BOE  Approval  March  11,  2014     Schematic  Design  (2)  May  20,  2014*   BOE  Approval  June  3,  2014*     Submit  to  DSA  October  20,  2014*    Authorize  to  Bid  (2)  May  20,  2015*   BOE  Approval  June  11,  2015*      Approval  by  DSA  May  25,  2015*    Bid  Opening  July  12,  2015*     Award  of  Contract  (1)  August  1,  2015*     Notice  to  Proceed  August  10,  2015*    Substantial  Completion  January,  2017*       *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  9     Palo  Alto  High  School   Classroom  Building  and  Media  Arts   A. PROJECT  STATUS     Taisei  Construction  continued  punch-­‐list  corrections  the  new  Math/Social  Sciences  building.    New   classroom  furniture  for  the  second  floor  of  the  Math/Social  Science  Building  arrived  on  March  31,   2014.    At  the  Media  Arts  building,  the  contractor  continued  the  installation  of  the  audio  visual   equipment.                         B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  4.1  -­‐  4.3     D. PROJECT  OVERVIEW:   • The  project  continues  to  be  delayed  by  the  contractor,  with  occupancy  of  the  Media  Arts  and  Math/Social   Sciences  buildings  now  anticipated  in  Summer  2014.       Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $38,415,001   Other  Funding  $0   Total  $38,415,001     Budget   Salaries  and  Benefits  $18,448   Supplies  $1,301,519   Contracts  &  Services  $7,066,446   Construction  &  Equipment  $29,713,481   Soft  Costs  Contingency  $315,107   Total  $38,415,001     Percent  of  Budget  Expended  83.6%     Change  Order  Contingency   • Starting  Contingency  Balance  $2,515,000   • Remaining  Contingency  Balance  $85,252   • Percent  of  Changes  9.7%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:      Closeout       Schedule:   Architect  Contract  (2)  March  31,  2009   BOE  Approval  April  14,  2009    Conceptual  Design  (2)  September  8,  2009   BOE  Approval  September  22,  2009    Schematic  Design  (2)  January  12,  2010   BOE  Approval  January  26,  2010     Submit  to  DSA  August  4,  2010      Authorize  to  Bid  (2)  March  8,  2011   BOE  Approval  March  22,  2011     Approval  by  DSA  April  28,  2011    Bid  Opening  June  30,  2011     Award  of  Contract  (1)  July  12,  2011     Notice  to  Proceed  August  4,  2011    Substantial  Completion  April  15,  2014    Planned  Occupancy  August  1,  2014*    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  10     Palo  Alto  High  School   Performing  Arts  Center  (PAC)   A. PROJECT  STATUS     Prequalification   of   general   contractors   and   mechanical,   electrical,  and   plumbing  subcontractors  is  complete,  and  staff  will  begin  soliciting  bids  in   early  April,  with  the  bid  opening  scheduled  for  May  13,  2014.  Award  is   anticipated  to  occur  at  the  May  20,  2014  Board  meeting.                                                           B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  4.11     D. PROJECT  OVERVIEW:   • Project  is  currently  proceeding  on  schedule  and  within  budget.   Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $24,395,049   Other  Funding  $0   Total  $24,395,049     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $4,481,640   Construction  &  Equipment  $19,745,000   Soft  Costs  Contingency  $168,409   Total  $24,395,049     Percent  of  Budget  Expended  4.9%   Current  Phase:      Bid  &  Award    Schedule:   Architect  Contract  (2)  March  31,  2009   BOE  Approval  April  14,  2009     Conceptual  Design  (2)  June  1,  2010   BOE  Approval  June  22,  2010    Schematic  Design  (3)  June  14,  2011   BOE  Approval  December  13,  2011   BOE  Approval  January  17,  2012     Submit  to  DSA  March  28,  2013       Approval  by  DSA  January  16,  2014     Authorize  to  Bid  (2)  January  14,  2014   BOE  Approval  January  28,  2014     Bid  Opening  May  13,  2014*    Award  of  Contract  (1)  May  20,  2014*     Notice  to  Proceed  June  13,  2014*    Substantial  Completion  July  31,  2016*    Planned  Occupancy  August  15,  2016*    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  11     Palo  Alto  High  School   Science  Building  Addition     A. PROJECT  STATUS     DLM  will  begin  meeting  with  faculty  and  staff  in  April  2014  for  review  of   design  development.    The  construction  schedule  was  adjusted  to  occur  after   construction  of  the  new  gymnasium,  due  to  space  constraints  and  access  to   the  site.                         B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  4.1  -­‐  4.3     D. PROJECT  OVERVIEW:   • Design  development  proceeding.    The  construction  schedule  adjusted  to  occur  after  construction  of  the   new  gymnasium,  due  to  space  constraints  and  access  to  the  site.   Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $5,532,204   Other  Funding  $0   Total  $5,532,204     Budget   Salaries  and  Benefits  $0   Supplies  $48,121   Contracts  &  Services  $832,654   Construction  &  Equipment  $4,628,294   Soft  Costs  Contingency  $23,135   Total  $5,532,204     Percent  of  Budget  Expended  5.9%       Current  Phase:      Design  Development     Schedule:   Architect  Contract  (2)  March  12,  2013   BOE  Approval  March  19,  2013    Conceptual  Design  (2)  March  12,  2013   BOE  Approval  March  19,  2013     Schematic  Design  (2)  September  10,  2013   BOE  Approval  October  8,  2013    Submit  to  DSA  July  7,  2014*      Authorize  to  Bid  (2)  December  9,  2014*   BOE  Approval  January  11,  2015*     Approval  by  DSA  December  2,  2014*     Bid  Opening  March  30,  2015*     Award  of  Contract  (1)  May  4,  2015*    Notice  to  Proceed  August  1,  2015*    Substantial  Completion  May  20,  2016*    Planned  Occupancy  August  15,  2016*    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  12     Palo  Alto  High  School   Indoor  PE  and  Athletic  Facilities       A. PROJECT  STATUS     Construction  documents  were  submitted  to  DSA  on  January   27,   2014   by   the   project   architect,   Jeremiah   Tolbert   Design   Architects   (JTDA).     Construction   is   currently   anticipated   to   begin  during  the  summer  of  2014.                       B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  4.1  -­‐  4.3     D. PROJECT  OVERVIEW:   • Plans  re-­‐submitted  into  DSA  for  review  on  January  27,  2014.       Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $250,000   Other  Funding  $0   Total  $250,000     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $225,000   Construction  &  Equipment  $25,000   Soft  Costs  Contingency  $0   Total  $250,000     Percent  of  Budget  Expended  61.9%       Current  Phase:      DSA  Review    Schedule:   Architect  Contract  (2)  N/A   BOE  Approval  N/A     Conceptual  Design  (2)  March  12,  2013   BOE  Approval  March  19,  2013    Schematic  Design  (2)  September  10,  2013   BOE  Approval  October  8,  2013    Submit  to  DSA  December  4,  2013   Re-­‐Submit  to  DSA  January  27,  2014       Review  Lease  Leaseback  Agreement  May  27,  2014*     Approval  by  DSA  June  22,  2014*    Award  of  Contract  (1)  June  24,  2014*    Notice  to  Proceed  July  1,  2014    Substantial  Completion  October  1,  2015*    Planned  Occupancy  August  15,  2015*     *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  13     Duveneck  Elementary  School   New  Classroom  Buildings  and  Modernization   A. PROJECT  STATUS     Alpha   Bay   Builders   (ABB)  completed   rough-­‐in   for   mechanical,   electrical,   plumbing,  and  fire  sprinkler  on  building  1,  with  window  flashing  installation   beginning  in  April.    The  new  foundation  is  in  place  and  framing  commenced   in  building  F,  which  will  be  renovated  into  the  new  library.                         B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  1.1  –  1.2,  1.4  –  1.10     D. PROJECT  OVERVIEW:   • The  project  is  proceeding  within  budget.  Construction  progress  has  been  slowed  by  poor  contractor   performance.   Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $9,778,358   Other  Funding  $0   Total  $9,778,358     Budget   Salaries  and  Benefits  $14,116   Supplies  $0   Contracts  &  Services  $2,104,850   Construction  &  Equipment  $7,648,045   Soft  Costs  Contingency  $11,347   Total  $9,778,358     Percent  of  Budget  Expended  64.0%     Change  Order  Contingency   • Starting  Contingency  Balance  $703  ,772   • Remaining  Contingency  Balance  $557,490   • Percent  of  Changes  2.0%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:      Construction     Schedule:   Architect  Contract  (2)  April  27,  2010   BOE  Approval  May  11,  2010    Conceptual  Design  (2)  December  14,  2010   BOE  Approval  January  11,  2011     Schematic  Design  (2)  June  14,  2011   BOE  Approval  June  28,  2011    Submit  to  DSA  February  27,  2012      Approval  by  DSA  December  10,  2012    Authorize  to  Bid  (2)  December  18  2012   BOE  Approval  January  15,  2013     Bid  Opening  February  28,  2013     Award  of  Contract  (1)  March  12,  2013    Notice  to  Proceed  March  25,  2013    Substantial  Completion  July  16,  2014*    Planned  Occupancy  August  1,  2014*    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  14     Technology  Improvements   A. PROJECT  STATUS       Installation  of  exterior  wireless  antennas  and  repeaters  at  each  campus  continued.           B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  1.5  –  1.7     D. PROJECT  OVERVIEW:   • Wireless  antennas  and  repeaters  installation  at  each  campus  is  on-­‐going.     Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $10,485,054   Other  Funding  $0   Total  $10,485,054     Budget   Salaries  and  Benefits  $0   Supplies  &  Computers  $6,850,644   Contracts  &  Services  $539,269   Construction  &  Equipment  $3,095,142   Soft  Costs  Contingency  $0   Total  $10,485,054     Percent  of  Budget  Expended  88.5%     Current  Phase:      N/A    Schedule:   Architect  Contract  (2)  N/A   BOE  Approval  N/A     Conceptual  Design  (2)  N/A   BOE  Approval  N/A    Schematic  Design  (2)  N/A   BOE  Approval  N/A     Submit  to  DSA  N/A       Approval  by  DSA  N/A    Authorize  to  Bid  (2)  N/A   BOE  Approval  N/A    Bid  Opening  N/A    Award  of  Contract  (1)  N/A     Notice  to  Proceed  N/A     Substantial  Completion  N/A     Planned  Occupancy  N/A    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  15     Gunn  High  School   New  Classroom  Buildings  A  &  B   A. PROJECT  STATUS     The  new  Math  and  English  Building  was  occupied  by  staff  and  students  on   August  15,  2013.    World  Language  Building  classrooms  have  been  in  use   since  February,  2013.                         B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  3.1,  3.3,  3.4     D. PROJECT  OVERVIEW:   • The  World  Languages  building  move-­‐in  occurred  on  February  8,  2013,  and  was  occupied  with  staff  and   students  on  February  11,  2013.    The  Math  &  English  building  move-­‐in  occurred  on  July  15,  2013,  and  was   occupied  with  staff  and  students  on  August  15,  2013.    The  project  completed  within  budget.         Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $25,035,201   Other  Funding  $0   Total  $25,035,201     Budget   Salaries  and  Benefits  $24,948   Supplies  $308,194   Contracts  &  Services  $3,789,909   Construction  &  Equipment  $20,911,873   Soft  Costs  Contingency  $277   Total  $25,035,201     Percent  of  Budget  Expended  98.6%     Change  Order  Contingency   • Starting  Contingency  Balance  $  1,763,200   • Remaining  Contingency  Balance  $  126,231   • Percent  of  Changes  9.3%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:    Close-­‐out  /  Occupancy  –  August  15,  2013    Schedule:   Architect  Contract  (2)  March  31,  2009   BOE  Approval  April  14,  2009    Conceptual  Design  (2)  September  8,  2009   BOE  Approval  September  22,  2009    Schematic  Design  (2)  January  12,  2010   BOE  Approval  January  26,  2010     Submit  to  DSA  August  4,  2010       Authorize  to  Bid  (2)  March  8,  2011   BOE  Approval  March  22,  2011     Approval  by  DSA  May  27,  2011     Bid  Opening  July  13,  2011     Award  of  Contract  (1)  July  22,  2011     Notice  to  Proceed  August  24,  2011    Substantial  Completion  July  15,  2013    Planned  Occupancy  August  15,  2013    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  16     Gunn  High  School   New  Gymnasium   A. PROJECT  STATUS     The  new  gymnasium  was  occupied  on  June  7,  2013  and  PE  classes  were   held  in  the  new  gym  on  August  15,  2013.    The  tennis  courts  surfacing  and   striping  was  installed  and  completed  August  27,  2013.               B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  3.4,  3.5,  3.13     D. PROJECT  OVERVIEW:   • The  new  gym  was  occupied  on  June  7,  2013.         Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $12,914,800   Other  Funding  $0   Total  $12,914,800     Budget   Salaries  and  Benefits  $0   Supplies  $19,706   Contracts  &  Services  $2,461,402   Construction  &  Equipment  $10,400,737   Soft  Costs  Contingency  $32,955   Total  $12,914,800     Percent  of  Budget  Expended  94.4%     Change  Order  Contingency   • Starting  Contingency  Balance  $834,700   • Remaining  Contingency  Balance  $7,909   • Percent  of  Changes  9.9%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:      Occupancy  –  June  7,  2013    Schedule:   Architect  Contract  (2)  March  31,  2009   BOE  Approval  April  14,  2009    Conceptual  Design  (2)  September  8,  2009   BOE  Approval  September  22,  2009    Schematic  Design  (2)  January  12,  2010   BOE  Approval  January  26,  2010     Submit  to  DSA  August  4,  2010     Authorize  to  Bid  (2)  March  8,  2011   BOE  Approval  March  22,  2011    Approval  by  DSA  May  27,  2011    Bid  Opening  July  13,  2011    Award  of  Contract  (1)  July  20,  2011    Notice  to  Proceed  August  1,  2011     Substantial  Completion  May  1,  2013     Planned  Occupancy  June  7,  2013    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  17     Gunn  High  School   Existing  Gymnasium  Modernization   A. PROJECT  STATUS     Romkon  Inc.  continued  punch  list  corrections  through  November  2013.     The  modernized  Bow  gym  was  occupied  by  the  campus  on  November  4,   2013.                   B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  3.4,  3.5,  3.13     D. PROJECT  OVERVIEW:   • The  project  is  proceeding  on-­‐schedule  and  within  budget.  Occupancy  by  the  school  occurred  on   November  12,  2013.         Funding  and  Budget   This  project  is  funded  by  the  New  Gymnasium  project   budget.    See  that  project  budget  for  status.     Change  Order  Contingency   • Starting  Contingency  Balance  $99,800   • Remaining  Contingency  Balance  $99,800   • Percent  of  Changes  0.0%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:  Close-­‐out  /  Occupancy  –  November  12,  2013     Schedule:   Architect  Contract  (2)  March  31,  2009   BOE  Approval  April  14,  2009    Conceptual  Design  (2)  September  8,  2009   BOE  Approval  September  22,  2009     Schematic  Design  (2)  January  12,  2010   BOE  Approval  January  26,  2010    Submit  to  DSA  August  4,  2010    Authorize  to  Bid  (2)  February  12,  2013   BOE  Approval  February  26,  2013     Approval  by  DSA  January  23,  2013     Bid  Opening  April  2,  2013     Award  of  Contract  (1)  April  9,  2013    Notice  to  Proceed  May  31,  2013    Substantial  Completion  October  28,  2013    Planned  Occupancy  November  12,  2013    *  Anticipated  Dates  –  Subject  to  Change  (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  18     Palo  Alto  High  School   Athletic  Stadium  Improvements   A. PROJECT  STATUS     The  main  project  including  a  concessions  building,  track  re-­‐surfacing,   new  ornamental  fence,  signage  and  entry  lighting  has  been  completed.                             B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  4.13     D. PROJECT  OVERVIEW:   • The  ornamental  fence  was  completed  on  schedule  in  August  2013.    The  concessions  building  was   occupied  September  10,  2012.    The  bleacher  replacement  work  was  completed  on  schedule  in  June  2013.     Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $5,090,000   Other  Funding  $0   Total  $5,090,000     Budget   Salaries  and  Benefits  $882   Supplies  $2,746   Contracts  &  Services  $818,716   Construction  &  Equipment  $4,267,656   Soft  Costs  Contingency  $0   Total  $5,090,000     Percent  of  Budget  Expended  93.3%     Change  Order  Contingency   • Starting  Contingency  Balance  $310,200   • Remaining  Contingency  Balance  $225,587   • Percent  of  Changes  2.3%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:    Close-­‐out  /  Occupancy  –  August  1,  2013     Schedule:   Architect  Contract  (2)  January  26,  2010   BOE  Approval  February  9,  2010    Conceptual  Design  (2)  June  1,  2010   BOE  Approval  June  22,  2010    Schematic  Design  (2)  February  22,  2011   BOE  Approval  March  8,  2011     Submit  to  DSA  April  4,  2011    Authorize  to  Bid  (2)  June  28,  2011   BOE  Approval  July  19,  2011    Approval  by  DSA  July  26,  2011       Bid  Opening  December  1,  2011     Award  of  Contract  (1)  December  13,  2011     Notice  to  Proceed  January  4,  2012    Substantial  Completion  -­‐  Concession    August  31,  2012   Planned  Occupancy  -­‐  Concessions  September  10,  2012   Bleachers  March  31,  2013   Fence  Completion  August  1,  2013   *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  19     Palo  Alto  High  School   Haymarket  and  Tower  Building  Improvements     A. PROJECT  STATUS     All  Trusty  Builders  completed  the  installation  of  the  new  windows  on   August  9,  2013,  on  schedule  and  within  budget.                               B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  4.1  -­‐  4.3     D. PROJECT  OVERVIEW:   • The  project  completed  on  schedule  and  within  budget.   Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $1,500,000   Other  Funding  $0   Total  $1,500,000     Budget   Salaries  and  Benefits  $0   Supplies  $62,844   Contracts  &  Services  $179,000   Construction  &  Equipment  $1,258,159   Soft  Costs  Contingency  $0   Total  $1,500,000     Percent  of  Budget  Expended  81.9%     Change  Order  Contingency   • Starting  Contingency  Balance  $39,200   • Remaining  Contingency  Balance  $33,930   • Percent  of  Changes  1.3%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:    Close-­‐out  /  Occupancy  –  August  9,  2013     Schedule:   Architect  Contract  (2)  N/A   BOE  Approval  N/A    Conceptual  Design  (2)  N/A   BOE  Approval  N/A    Schematic  Design  (2)  N/A   BOE  Approval  N/A     Submit  to  DSA  May  25,  2012      Authorize  to  Bid  (2)  April  24,  2012   BOE  Approval  May  6,  2012    Approval  by  DSA  August  24,  2012     Bid  Opening  January  17,  2013     Award  of  Contract  (1)  January  29,  2013     Notice  to  Proceed  February  21,  2013    Substantial  Completion  August  9,  2013       *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  20     Jordan  Middle  School   A. PROJECT  STATUS      Close-­‐out  efforts  continued  through  March  2014.                                 B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  2.1  –  2.3,  2.6  –  2.8,  2.10  –  2.12,  6.3  –  6.5     D. PROJECT  OVERVIEW:   • The  project  is  completed  on  schedule  and  within  budget.     Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $19,891,564   Other  Funding  $0   Total  $19,891,564     Budget   Salaries  and  Benefits  $6,111   Supplies  $86,265   Contracts  &  Services  $3,723,370   Construction  &  Equipment  $16,007,031   Soft  Costs  Contingency  $68,787   Total  $19,891,564     Percent  of  Budget  Expended  90.4%     Change  Order  Contingency   • Starting  Contingency  Balance  $1,398,700   • Remaining  Contingency  Balance  $847,769   • Percent  of  Changes  4.0%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:    Close-­‐out  /  Occupancy  –  August  15,  2013     Schedule:   Architect  Contract  (2)  October  28,  2008   BOE  Approval  October  30,  2008    Conceptual  Design  (2)  June  23,  2009   BOE  Approval  September  8,  2009    Schematic  Design  (2)  March  23,  2010   BOE  Approval  April  27,  2010     Submit  to  DSA  December  21,  2010      Authorize  to  Bid  (2)  June  28,  2011   BOE  Approval  July  19,  2011    Approval  by  DSA  October  5,  2011     Bid  Opening  December  8,  2011     Award  of  Contract  (1)  December  13,  2011     Notice  to  Proceed  December  27,  2011    Substantial  Completion  August  1,  2013    Planned  Occupancy  August  15,  2013    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  21     J.L.  Stanford  Middle  School   A. PROJECT  STATUS     SAUSAL   Corp.  continued   to   correct   punch   list   items.     Close-­‐out   efforts   continued  through  March  2014.                                 B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  2.1  –  2.3,  2.5  –  2.8,  2.11  –  2.12,  6.4,  6.5     D. PROJECT  OVERVIEW:   • The  project  completed  on  schedule  and  within  budget.    Close-­‐out  in  progress.   Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $17,184,699   Other  Funding  $0   Total  $17,184,699     Budget   Salaries  and  Benefits  $8,879   Supplies  $144,790   Contracts  &  Services  $3,545,843   Construction  &  Equipment  $13,485,187   Soft  Costs  Contingency  $0   Total  $17,184,699     Percent  of  Budget  Expended  88.5%     Change  Order  Contingency   • Starting  Contingency  Balance  $1,057,800   • Remaining  Contingency  Balance  $902,445   • Percent  of  Changes  2.8%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:    Close-­‐out  /  Occupancy  –  August  15,  2013    Schedule:   Architect  Contract  (2)  October  28,  2008   BOE  Approval  October  30,  2008    Conceptual  Design  (2)  June  23,  2009   BOE  Approval  September  8,  2009    Schematic  Design  (3)  June  1,  2010   BOE  Approval  June  22,  2010   BOE  Approval  (Sitework)  September  28,  2010    Submit  to  DSA  May  6,  2011      Authorize  to  Bid  (2)  November  29,  2011   BOE  Approval  December  13,  2011    Approval  by  DSA  January  24,  2012     Bid  Opening  May  3,  2012     Award  of  Contract  (1)  May  8,  2012     Notice  to  Proceed  May  30,  2012     Substantial  Completion  August  7,  2013    Planned  Occupancy  August  15,  2013    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  22     J.L.  Stanford  Middle  School   Landscape  and  Site  Improvements     A. PROJECT  STATUS     Close-­‐out  efforts  continued  through  March  2014.                               B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  2.1  –  2.3,  2.5  –  2.8,  2.11  –  2.12,  6.4,  6.5     D. PROJECT  OVERVIEW:   • The  project  completed  on  schedule  and  within  budget.     Funding  and  Budget   This  project  is  funded  by  the  J.L.  Stanford  Middle  School   project  budget.    See  that  project  budget  for  status.     Percent  of  Budget  Expended  88.5%     Change  Order  Contingency   • Starting  Contingency  Balance  $1,057,800   • Remaining  Contingency  Balance  $902,445   • Percent  of  Changes  2.8%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:    Close-­‐out  /  Occupancy  –  August  16,  2013    Schedule:   Architect  Contract  (2)  October  28,  2008   BOE  Approval  October  30,  2008     Conceptual  Design  (2)  June  23,  2009   BOE  Approval  September  8,  2009    Schematic  Design  (3)  June  1,  2010   BOE  Approval  June  22,  2010   BOE  Approval  (Sitework)  September  28,  2010     Submit  to  DSA  May  6,  2011       Authorize  to  Bid  (2)  November  29,  2011   BOE  Approval  December  13,  2011    Approval  by  DSA  January  24,  2012    Bid  Opening  May  3,  2013    Award  of  Contract  (1)  May  8,  2013     Notice  to  Proceed  May  23,  2013     Substantial  Completion  August  16,  2013     Completion  August  16,  2013     *  Anticipated  Dates  –  Subject  to  Change  (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  23     Terman  Middle  School   A. PROJECT  STATUS     Close-­‐out  efforts  continued  through  March  2014.                                 B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  2.1  –  2.8,  2.11  –  2.12     D. PROJECT  OVERVIEW:   • The  project  completed  on  schedule,  with  exception  of  the  Cafetorium,  which  was  occupied  on  November   15,  2013.    The  project  is  currently  within  budget.     Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $13,312,971   Other  Funding  $0   Total  $13,312,971     Budget   Salaries  and  Benefits  $4,153   Supplies  $75,747   Contracts  &  Services  $2,720,590   Construction  &  Equipment  $10,507,733   Soft  Costs  Contingency  $4,748   Total  $13,312,971     Percent  of  Budget  Expended  96.3%     Change  Order  Contingency   • Starting  Contingency  Balance  $929,900   • Remaining  Contingency  Balance  $12,909   • Percent  of  Changes  9.4%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:    Close-­‐out  /  Occupancy  –  November  15,  2013     Schedule:   Architect  Contract  (2)  October  28,  2008   BOE  Approval  October  30,  2008    Conceptual  Design  (2)  June  23,  2009   BOE  Approval  September  8,  2009    Schematic  Design  (2)  May  11,  2010   BOE  Approval  May  25,  2010     Submit  to  DSA  December  21,  2010      Authorize  to  Bid  (2)  June  28,  2011   BOE  Approval  July  19,  2011     Approval  by  DSA  September  1,  2011    Bid  Opening  December  6,  2011     Award  of  Contract  (1)  December  13,  2011     Notice  to  Proceed  December  27,  2011    Substantial  Completion  October  31,  2013    Planned  Occupancy  November  15,  2013    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  24     Fairmeadow  Elementary  School   New  Classroom  Building  and  Modernization   A. PROJECT  STATUS      Close-­‐out  efforts  continued  through  March  2014.       B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  1.1  –  1.2,  1.4  –  1.10     D. PROJECT  OVERVIEW:   • The  project  completed  on  schedule  and  within  budget.   Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $7,796,550   Other  Funding  $0   Total  $7,796,550     Budget   Salaries  and  Benefits  $32,381   Supplies  $98,962   Contracts  &  Services  $1,992,928   Construction  &  Equipment  $5,671,159   Soft  Costs  Contingency  $1,120   Total  $7,796,550     Percent  of  Budget  Expended  93.7%     Change  Order  Contingency   • Starting  Contingency  Balance  $642  ,300   • Remaining  Contingency  Balance  $186,122   • Percent  of  Changes  7.1%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:  Close-­‐out  /  Occupancy  –  August  15,  2013    Schedule:   Architect  Contract  (2)  October  13,  2009   BOE  Approval  October  27,  2009     Conceptual  Design  (2)  March  23,  2010   BOE  Approval  April  6,  2010    Schematic  Design  (2)  September  14,  2010   BOE  Approval  September  28,  2010     Submit  to  DSA  April  18,  2011      Authorize  to  Bid  (2)  October  11,  2011   BOE  Approval  October  25,  2011    Approval  by  DSA  November  14,  2011    Bid  Opening  December  5,  2011     Award  of  Contract  (1)  December  13,  2011     Notice  to  Proceed  January  3,  2012     Substantial  Completion  August  5,  2013     Planned  Occupancy  August  15,  2013    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  25     Ohlone  Elementary  School   New  Classroom  Building  and  Modernization   A. PROJECT  STATUS     Move-­‐in  to  the   new   building   and   other   existing   classrooms   occurred  in  December  2011.    Students  occupied  the  new  building   on  January  3,  2012.                               B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  1.1  –  1.2,  1.4  –  1.10     D. PROJECT  OVERVIEW:   • Occupancy  occurred  on  January  3,  2012.    Project  completed  on  schedule  and  within  budget.   Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $10,597,870   Other  Funding  $0   Total  $10,597,870     Budget   Salaries  and  Benefits  $7,461   Supplies  $49,049   Contracts  &  Services  $2,180,418   Construction  &  Equipment  $8,360,942   Soft  Costs  Contingency  $62,598   Total  $10,597,870     Percent  of  Budget  Expended  98.7%     Change  Order  Contingency   • Starting  Contingency  Balance  $748,400   • Remaining  Contingency  Balance  $459,113   • Percent  of  Changes  3.9%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:      Occupancy  –  January  3,  2012     Schedule:   Architect  Contract  (2)  September  30,  2008   BOE  Approval  October  14,  2008    Conceptual  Design  (2)  March  3,  2009   BOE  Approval  March  17,  2009     Schematic  Design  (2)  June  2,  2009   BOE  Approval  June  23,  2009    Submit  to  DSA  November  24,  2009     Authorize  to  Bid  (2)  April  27,  2010   BOE  Approval  May  11,  2010       Approval  by  DSA  May  18,  2010     Bid  Opening  July  13,  2010    Award  of  Contract  (1)  August  3,  2010    Notice  to  Proceed  August  19,  2010    Substantial  Completion  November  18,  2011    Planned  Occupancy  January  3,  2012     *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  26     Site  Acquisition   525  San  Antonio  Rd     A. PROJECT  STATUS     This  site  has  been  leased  to  Athena  Academy.                               B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  1.1  –  1.2,  1.4  –  1.10     D. PROJECT  OVERVIEW:   • The  site  has  been  leased  to  Athena  Academy.     Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $8,500,000   Other  Funding  $0   Total  $8,500,000     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $8,500,000   Construction  &  Equipment  $0   Soft  Costs  Contingency  $0   Total  $8,500,000     Percent  of  Budget  Expended  100.0%   Current  Phase:      N/A    Schedule:   Architect  Contract  (2)  N/A   BOE  Approval  N/A     Conceptual  Design  (2)  N/A   BOE  Approval  N/A    Schematic  Design  (2)  N/A   BOE  Approval  N/A    Submit  to  DSA  N/A       Approval  by  DSA  N/A     Authorize  to  Bid  (2)  N/A   BOE  Approval  N/A    Bid  Opening  N/A    Award  of  Contract  (1)  N/A    Notice  to  Proceed  N/A     Substantial  Completion  N/A     Planned  Occupancy  N/A     *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  27     Jordan  Middle  Schools  -­‐  Interim  Classrooms   A. PROJECT  STATUS     The  portables  were  installed  and  moved  into  for  fall  2011.    DSA  closeout  received  November  19,  2012.                                 B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  2.1,  6.4,  6.5     D. PROJECT  OVERVIEW:   • This  project  completed  ahead  of  schedule  and  under  budget.   • Move  in  occurred  on  September  30,  2011.       Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $392,120   Other  Funding  $208,222   Total  $600,342     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $180,286   Construction  &  Equipment  $419,292   Soft  Costs  Contingency  $764   Total  $600,342     Percent  of  Budget  Expended  76.8%*     *Budget  previously  expended       Current  Phase:      Move-­‐in     Schedule:   Approval  by  DSA  June  16,  2011    Authorize  to  Bid  (2)  June  14,  2011   BOE  Approval  June  28,  2011     Bid  Opening  July  14,  2011     Award  of  Contract  (1)  July  20,  2011     Notice  to  Proceed  July  27,  2011     Substantial  Completion  September  20,  2011    Occupancy  September  30,  2011    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  28     Gunn  High  School   Air  Conditioning  of  Existing  Buildings   A. PROJECT  STATUS     Best   Contracting  Services   Inc.   completed   the   installation   of   air   conditioning  units  and  cool  roof  coating  in  the  summer  2011.    Some   warranty  work  on  the  cool  roof  coating  needs  to  be  completed  by   Best.                         B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  3.7     D. PROJECT  OVERVIEW:   • Project  has  been  closed-­‐out.     Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $2,600,000   Other  Funding  $0   Total  $2,600,000     Budget   Salaries  and  Benefits  $1,919   Supplies  $0   Contracts  &  Services  $454,610   Construction  &  Equipment  $2,120,580   Soft  Costs  Contingency  $22,891   Total  $2,600,000     Percent  of  Budget  Expended  80.9%   Current  Phase:      Completed    Schedule:   Architect  Contract  (2)  March  27,  2010   BOE  Approval  April  6,  2010     Conceptual  Design  (2)  N/A   BOE  Approval  N/A    Schematic  Design  (2)  N/A   BOE  Approval  N/A    Submit  to  DSA  October  20,  2010     Approval  by  DSA  February  10,  2011     Authorize  to  Bid  (2)  February  22,  2011   BOE  Approval  March  8,  2011    Bid  Opening  March  28,  2011    Award  of  Contract  (1)  April  8,  2011    Notice  to  Proceed  April  11,  2011     Substantial  Completion  August  8,  2011      *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  29     J.L.  Stanford  Middle  School  -­‐  Interim  Classrooms   A. PROJECT  STATUS     Coulter   Construction  completed   the   work   on   the   relocated   portables  in  August  2011.                             B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  2.1,  6.4,  6.5     D. PROJECT  OVERVIEW:   • Project  completed  on  schedule  and  is  currently  in  close-­‐out.             This  portable  relocation  project  funded  by  main   JLS  project.    Refer  to  pg.  14     Current  Phase:      Occupancy  -­‐  August  11,  2011     Schedule:   Approval  by  DSA  April  19,  2011   Jordan  Project  June  16,  2011      Authorize  to  Bid  (2)  May  10,  2011   BOE  Approval  May  24,  2011     Bid  Opening  June  1,  2011    Award  of  Contract  (1)  June  13,  2011     Notice  to  Proceed  June  20,  2011    Substantial  Completion  August  8,  2011    Planned  Occupancy  August  15,  2011     *  Anticipated  Dates  –  Subject  to  Change  (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  30     Fairmeadow  Elementary  School   Portable  Relocation  Project   A. PROJECT  STATUS       Relocation  of  the  portable  was  complete  and  occupied  on  August  8,  2011.                             B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  6.4     D. PROJECT  OVERVIEW:   • Project  completed  ahead  of  schedule  on  August  8,  2011.                 This  portable  relocation  project  funded  by  main   JLS  project.    Refer  to  pg.  14   Current  Phase:      Occupancy  -­‐  August  8,  2011    Schedule:   Architect  Contract  (2)  February  15,  2011   BOE  Approval  N/A    Conceptual  Design  (2)  N/A   BOE  Approval  N/A    Schematic  Design  (2)  N/A   BOE  Approval  N/A     Submit  to  DSA  March  3,  2011       Approval  by  DSA  March  3,  2011    Authorize  to  Bid  (2)  May  11,  2011   BOE  Approval  May  24,  2011    Bid  Opening  June  14,  2011    Award  of  Contract  (1)  June  14,  2011     Notice  to  Proceed  June  20,  2011     Substantial  Completion  August  1,  2011     Planned  Occupancy  August  8,  2011    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  31     Elementary  Classroom  Improvements   Interactive  Whiteboards  and  Sound  Assist  System  Installation   A. PROJECT  STATUS     Installation  of  SmartBoards  and  Lightspeed  sound  assist  systems  were   completed   for   all   elementary   school   classrooms   and   libraries   in   April   2011.                           B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  1.5  –  1.7     D. PROJECT  OVERVIEW:   • All  SmartBoards  and  Lightspeed  sound  systems  installed.       Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $2,004,889   Other  Funding  $0   Total  $2,004,889     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $275,488   Construction  &  Equipment  $1,729,401   Soft  Costs  Contingency  $0   Total  $2,004,889     Percent  of  Budget  Expended  93.9%     Current  Phase:    Complete  -­‐  May  15,  2011    Schedule:   Architect  Contract  (2)  N/A   BOE  Approval  N/A     Conceptual  Design  (2)  N/A   BOE  Approval  N/A    Schematic  Design  (2)  N/A   BOE  Approval  N/A    Submit  to  DSA  N/A       Approval  by  DSA  N/A     Authorize  to  Bid  (2)  November  9,  2010   BOE  Approval  November  23,  2010    Bid  Opening  February  25,  2011    Award  of  Contract  (1)  March  8,  2011    Notice  to  Proceed  March  9,  2011     Completion  May  15,  2011      *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  32     Palo  Alto  High  School    Multi-­‐Use  Field   A. PROJECT  STATUS     The  fields   were   available   for   play   on   February   1,   2011,   and   final   change  order  negotiations  completed  on  March  9,  2011.                         B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  4.14     D. PROJECT  OVERVIEW:   • Field  was  open  for  use  on  February  1,  2011.       Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $2,609,680   Other  Funding  $1,007,255   Total  $3,616,935     Budget   Salaries  and  Benefits  $0   Supplies  $1,506   Contracts  &  Services  $698,293   Construction  &  Equipment  $2,916,682   Soft  Costs  Contingency  $454   Total  $3,616,935       Percent  of  Budget  Expended  100.0%     Change  Order  Contingency   • Starting  Contingency  Balance  $269,300   • Remaining  Contingency  Balance  $230,579   • Percent  of  Changes  1.5%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:      Occupancy  –  February  1,  2011    Schedule:   Architect  Contract  (2)  September  30,  2008   BOE  Approval  October  14,  2008     Conceptual  Design  (2)  N/A   BOE  Approval  N/A    Schematic  Design  (2)  November  18,  2008   BOE  Approval  December  09,  2008     Submit  to  DSA  March  19,  2009       Approval  by  DSA  September  30,  2009     Authorize  to  Bid  (2)  February  24,  2009   BOE  Approval  March  17,  2009    Bid  Opening  March  16,  2010    Award  of  Contract  (1)  April  7,  2010     Notice  to  Proceed  June  1,  2010     Substantial  Completion  January  31,  2011     Planned  Occupancy  February  1,  2011    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  33     Gunn  High  School   Industrial  Arts  Addition  and  Renovation   A. PROJECT  STATUS     This  facility  was  available  for  instruction  in  January  2010.  DSA  closeout   received  on  July  18,  2011.                       B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  3.1,  3.7,  3.11     D. PROJECT  OVERVIEW:   • The  building  occupied  as  scheduled,  and  the  project  completed  within  budget. Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $5,082,402   Other  Funding  $0   Total  $5,082,402     Budget   Salaries  and  Benefits  $1,061   Supplies  $88,985   Contracts  &  Services  $1,002,057   Construction  &  Equipment  $3,990,300   Soft  Costs  Contingency  $0   Total  $5,082,402     Percent  of  Budget  Expended  99.3%     Change  Order  Contingency   • Starting  Contingency  Balance  $349,000   • Remaining  Contingency  Balance  $141,967   • Percent  of  Changes  41.6%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)     Current  Phase:      Occupancy  –  January  4,  2010    Schedule:   Architect  Contract  (2)  N/A   BOE  Approval  N/A     Conceptual  Design  (2)  N/A   BOE  Approval  N/A    Schematic  Design  (2)  N/A   BOE  Approval  N/A     Submit  to  DSA  June  17,  2008       Approval  by  DSA  December  24,  2008    Authorize  to  Bid  (2)  October  14,  2008   BOE  Approval  October  28,  2008     Bid  Opening  December  16,  2008     Award  of  Contract  (1)  December  24,  2008     Notice  to  Proceed  January  6,  2009    Substantial  Completion  November  25,  2009    Planned  Occupancy  January  4,  2010    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  34     Gunn  High  School   Aquatic  Center   A. PROJECT  STATUS     This  facility  was  available  for  use  in  July  2009,  and  has  been  closed   out  with  DSA.               B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  3.12     D. PROJECT  OVERVIEW:   • This  project  completed  within  budget. Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $4,865,423   Other  Funding  $0   Total  $4,865,423     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $647,169   Construction  &  Equipment  $4,218,253   Soft  Costs  Contingency  $0   Total  $4,865,423     Percent  of  Budget  Expended  99.9%     Change  Order  Contingency   • Starting  Contingency  Balance  $389,887   • Remaining  Contingency  Balance  $195,148   • Percent  of  Changes  49.9%   (Change  Orders  +  Construction  Change  Directives  vs.   Original  Contract)   Current  Phase:      Occupancy  –  June  15,  2009    Schedule:   Architect  Contract  (2)  N/A   BOE  Approval  N/A    Conceptual  Design  (2)  N/A   BOE  Approval  N/A     Schematic  Design  (2)  N/A   BOE  Approval  N/A     Submit  to  DSA  December  11,  2007       Approval  by  DSA  April  24,  2008     Authorize  to  Bid  (2)  April  8,  2008   BOE  Approval  April  22,  2008    Bid  Opening  May  28,  2008     Award  of  Contract  (1)  June  4,  2008    Notice  to  Proceed  December  6,  2008    Substantial  Completion  June  15,  2009     Planned  Occupancy  June  15,  2009    *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  35     Middle  School  Pre-­‐Design   Jordan,  J.L.  Stanford  and  Terman   A. PROJECT  STATUS     AEDIS  presented  recommended  concept  plans  for  each  campus  to  the   Board  of  Education  for  approval  on  September  8,  which  became  the   program   documents  for   the   new   projects   at   each   campus.    These   projects   for   pre-­‐design   work   have   been   closed,   and   funds   will   be   transferred  to  the  program  contingency  on  June  14,  2011.                 B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  2.1  –  2.12     D. PROJECT  OVERVIEW:   • This  project  has  been  completed.  Board  approval  received  on  September  8,  2009. Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $56,488   Other  Funding  $0   Total  $56,488     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $56,488   Construction  &  Equipment  $0   Soft  Costs  Contingency  $0   Total  $56,488     Percent  of  Budget  Expended  96.8%     Current  Phase:      Complete     Schedule:   Architect  Contract  (2)  October  28,  2008   BOE  Approval  October  30,  2008    Conceptual  Design  (2)  June  23,  2009   BOE  Approval  September  8,  2009     Schematic  Design  (2)  N/A   BOE  Approval  N/A    Submit  to  DSA  N/A       Approval  by  DSA  N/A     Authorize  to  Bid  (2)  N/A   BOE  Approval  N/A    Bid  Opening  N/A    Award  of  Contract  (1)  N/A    Notice  to  Proceed  N/A    Substantial  Completion  N/A     Planned  Occupancy  N/A     *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  36     Garland  Elementary  School   Campus  Modernization   A. PROJECT  STATUS     The  Board  of  Education  has  put  new  development  for  Garland  on   hold  until  a  growth  plan  is  established  for  the  elementary  schools.     The  board  voted  to  terminate  the  lease  with  Stratford  School  in   June  2011.  Discussions  with  the  Board  on  future  plans  for  growth   at  the  elementary  schools  are  ongoing.                 B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  1.1,  1.4  –  1.10     D. PROJECT  OVERVIEW:   • This  project  has  been  placed  on  hold. Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $22,178,544   Other  Funding  $0   Total  $22,178,544     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $3,915,789   Construction  &  Equipment  $17,400,000   Soft  Costs  Contingency  $862,755   Total  $22,178,544     Percent  of  Budget  Expended  1.3%   Current  Phase:      On  Hold     Schedule:   Architect  Contract  (2)  October  28,  2008   BOE  Approval  October  30,  2008    Conceptual  Design  (2)  February  10,  2009   BOE  Approval  February  24,  2009     Schematic  Design  (2)  June  2,  2009   BOE  Approval  June  23,  2009    Submit  to  DSA  N/A       Approval  by  DSA  N/A     Authorize  to  Bid  (2)  N/A   BOE  Approval  N/A    Bid  Opening  N/A    Award  of  Contract  (1)  N/A    Notice  to  Proceed  N/A    Substantial  Completion  N/A     Planned  Occupancy  N/A     *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  37     High  School  Master  Plan   Palo  Alto  HS  and  Gunn  HS   A. PROJECT  STATUS     The  Board  of  Education  (BOE)  approved  the  master  plans  for  both   high   schools,   and   these   projects   have   been   closed,   with   funds   transferred  to  the  respective  campus  reserve  funds.                     B. BUDGET  &  SCHEDULE  SUMMARY                                               C. BOND  PROJECT  LIST  REFERENCE:  3.1  –  3.14,  4.1  –  4.14     D. PROJECT  OVERVIEW:   • Master  planning  effort  complete.                 Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $285,387   Other  Funding  $0   Total  $285,387     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $285,387   Construction  &  Equipment  $0   Soft  Costs  Contingency  $0   Total  $285,387     Percent  of  Budget  Expended  86.2%   Current  Phase:      Complete     Schedule:   Architect  Contract  (2)  March  31,  2009   BOE  Approval  April  14,  2009     Initial  Master  Plan  Approval  (2)  September  8,  2009   BOE  Approval  September  22,  2009     Paly  CEQA  Approval  (2)  February  9,  2010   BOE  Approval  February  23,  2010     Gunn  Master  Plan  Update  (2)  March  23,  2010   BOE  Approval  April  6,  2010     Gunn  CEQA  Approval  (2)  April  27,  2010     BOE  Approval  May  11,  2010       Master  Plan  Revision  Approval  (2)  September  14,  2010   Paly  MP  Revision  Approval  (2)  October  9,  2010   Gunn  MP  Revision  Approval  (2)  October  12,  2010     *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  38     Hoover  Elementary  School   Pre-­‐Design   A. PROJECT  STATUS     This  project  has  been  put  on  hold  until  a  growth  plan  is  established  for  the   elementary  schools.                   B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  1.1  –  1.2,  1.4  –  1.10     D. PROJECT  OVERVIEW:   • Project  is  currently  on  hold.                 Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $70,550   Other  Funding  $0   Total  $70,550     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $70,550   Construction  &  Equipment  $60   Soft  Costs  Contingency  $0   Total  $70,550     Percent  of  Budget  Expended  81.0%   Current  Phase:      On  Hold     Schedule:   Architect  Contract  (2)  April  27,  2010   BOE  Approval  May  11,  2010     Conceptual  Design  (2)  November  9,  2010   BOE  Approval  N/A     Schematic  Design  (2)  N/A   BOE  Approval  N/A    Submit  to  DSA  N/A       Approval  by  DSA  N/A    Authorize  to  Bid  (2)  N/A   BOE  Approval  N/A     Bid  Opening  N/A    Award  of  Contract  (1)  N/A    Notice  to  Proceed  N/A    Substantial  Completion  N/A   Planned  Occupancy  N/A     *  Anticipated  Dates  –  Subject  to  Change   (  )  Denotes  number  of  Board  of  Education  Readings     Page  |  39     Elementary  Classroom  Improvements   A. PROJECT  STATUS     DSA  comments  were  returned  to  Gelfand  for  Phase  1  plans  that  include   new  lighting,  adding  operable  windows  and  coverings,  ventilation,  and   replacement   of  ceiling   tiles  for   classrooms   at   Barron   Park   and   El   Carmelo  elementary  schools.    The  authorization  to  bid  has  been  placed   on  hold  pending  further  discussions  with  the  BOE  about  elementary   growth  planning.               B. BUDGET  &  SCHEDULE  SUMMARY                                                   C. BOND  PROJECT  LIST  REFERENCE:  1.5  –  1.7     D. PROJECT  OVERVIEW:   • This  project  has  been  placed  on  hold.           Funding   State  Funds  $0   Strong  Schools  Bond  Funds  $2,004,889   Other  Funding  $0   Total  $2,004,889     Budget   Salaries  and  Benefits  $0   Supplies  $0   Contracts  &  Services  $275,488   Construction  &  Equipment  $1,729,401   Soft  Costs  Contingency  $0   Total  $2,004,889     Percent  of  Budget  Expended  93.9%     Phase  1  Schools:    Barron  Park  and  El  Carmelo   Current  Phase:    On  Hold    Schedule:   Architect  Contract  (2)  June  8,  2010   BOE  Approval  June  22,  2010     Conceptual  Design  (2)  N/A   BOE  Approval  N/A    Schematic  Design  (2)  November  9,  2010   BOE  Approval  December  7,  2010     Submit  to  DSA  December  23,  2010      Approval  by  DSA  N/A     Authorize  to  Bid  (2)  N/A   BOE  Approval  N/A    Bid  Opening  N/A     Award  of  Contract  (1)  N/A     Notice  to  Proceed  N/A     Substantial  Completion  N/A     Planned  Occupancy  N/A    *  Anticipated  Dates  –  Subject  to  Change  (  )  Denotes  number  of  Board  of  Education  Readings