Loading...
Monthly Reports 2013-10 (Oct) Page | 1   MMOONNTTHHLLYY  PPRROOGGRREESSSS  RREEPPOORRTT     Through  October 2013      Strong Schools Bond  Capital Improvement Projects  Prepared by     fs3|Hodges  &  Gilbane Building Company  Page | 2   TABLE OF CONTENTS    Executive Summary         page 3   Attachment 1 – Consolidated Expenditure Report            Capital Projects     Gunn High School – Phase I ‐ Parking and Drop‐off Sitework Improvement  page 6    Gunn High School – Existing Gymnasium Modernization    page 7    Gunn High School – E and K (L31 and MS) Buildings Renovation    page 8    Palo Alto High School – New Classroom Building and Media Arts    page 9    Palo Alto High School – Performing Arts Center     page 10    Palo Alto High School – Science Building Addition     Page 11    Palo Alto High School – New Gymnasium      Page 12    Jordan Middle School        page 13    J.L. Stanford Middle School       page 14    J.L. Stanford Middle School – Landscape and Site Improvements    page 15    Terman Middle School        page 16     Fairmeadow Elementary School – New Classroom Buildings and Modernization  page 17    Duveneck Elementary School – New Classroom Buildings and Modernization  page 18    Technology          page 19    Completed Capital Projects    Gunn High School – New Classroom Building and World Languages Building  page 20  Gunn High School – New Gymnasium       page 21  Palo Alto High School – Athletic Stadium Improvements    page 22  Palo Alto High School – Haymarket and Tower Building Improvements    page 23  Ohlone Elementary School        page 24  Property Acquisition – 525 San Antonio Rd       page 25  Jordan Middle School – Interim Classrooms      page 26  Gunn High School – Air Conditioning of Existing Buildings    page 27  J.L. Stanford Middle School – Interim Classrooms     page 28  Fairmeadow Elementary School – Portable Relocation    page 29  Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 30  Palo Alto High School – Multi‐use Field      page 31  Gunn High School – Industrial Arts Renovation     page 32  Gunn High School – Aquatic Center       page 33  Middle School Pre‐Design        page 34    Inactive Capital Projects    Garland Elementary School       page 35  High School Master Plan        page 36  Hoover Elementary School        page 37  Elementary Classroom Improvements      page 38  Appendix  Exhibit A – Bond Project List      Page | 3   EXECUTIVE SUMMARY    Gunn High School – Miranda Ave. Drop‐Off (Phase I ‐ Parking and Drop‐Off Improvements)  DLM received DSA approval on October 2, 2013, and submitted off‐site improvement drawings for work at the  Miranda Ave intersection for the City of Palo Alto and County of Santa Clara.  Bid documents were advertised to  contractors on October 7, 2013, and a pre‐bid job walk was conducted on October 17, 2013. Bids are due on  November 12, 2013, with award scheduled for the November 19, 2013 Board of Education (BOE) meeting.    Gunn High School – Existing Gymnasium Modernization  Romkon Inc. completed striping and finishing the gym floor, installation of doors, ceiling tiles and wresting wall  pads.  Punch list corrections to commence on November 1, 2013, and the gym will be occupied by the campus on  November 4, 2013.    Gunn High School – E and K (L‐31 and MS) Buildings Renovation  DLM continued with construction documents after receiving final input from the site staff.  DLM anticipates  submitting drawings to DSA in late November 2013.    Palo Alto High School – New Math/Social Sciences Building and Media Arts Building  Taisei Construction continued installation of casework, the HVAC system, and roofing work for the new  Math/Social Sciences building.  At the Media Arts building, the contractor continued installation of casework, the  glass curtain wall and interior drywall.      Palo Alto High School – Performing Arts Center (PAC)  DSA review of construction documents submitted on March 29, 2013 continues.  This project will be bid after  completion and contractor demobilization at the new Classroom and Media Arts buildings.    Palo Alto High School – Science Building Addition   DLM received schematic design approval on October 8, 2013.  Staff conducted various investigations including  geotechnical, fire hydrant flow, and survey for design development.    Palo Alto High School – New Gymnasium   The BOE approved the schematic design of the project and approved the appropriation of $5.47M of Strong  Schools Bond funds earmarked for the Weight & Fitness center at Paly for this project.  The balance of the project  is being funded by a private donation.  The architect, Jeremiah Tolbert Designs is moving forward with construction  documents, and plans to submit plans to DSA in late November 2013.     Jordan Middle School  S.J. Amoroso continued to correct punch list items.  Close‐out efforts continued through October 2013.    J.L. Stanford Middle School  The project, including the new classroom building and modernization work in the science building, gymnasium, all  classroom wings and the administration building, continued with project close‐out efforts.    J.L. Stanford Middle School – Landscape and Sitework Improvements    Scapes, Inc. completed the landscape and sitework improvements on schedule and has commenced project close‐ out.    Terman Middle School  Hagensen Pacific continued to work on punch list corrections throughout October 2013 and will continue into  November 2013.  Modernization work in the cafetorium building continued through October 2013, and received  health department sign‐off on October 31, 2013.  The cafetorium building will be occupied in November 2013.    Page | 4   Fairmeadow Elementary School – New Classroom Building and Modernization   BEST Contracting completed all work including sitework.  Fencing around landscape areas was removed October 1,  2013.  Commissioning of building systems continue and are anticipated to be complete in mid November 2013.    Duveneck Elementary School – New Classroom Buildings and Modernization  Alpha Bay Builders (ABB) completed roof installation and continued installation of exterior stucco and interior  drywall for buildings 2 and 3.   Steel erection for building 1 will continue through November 2013.      Technology  Installation of exterior wireless antennas and repeaters at each campus continued.    COMPLETED CAPITAL PROJECTS   Gunn High School – New Classroom Building and World Languages Building  The new Math and English Building was occupied by staff and students on August 15, 2013.  World Language  Building classrooms have been in use since February, 2013.    Gunn High School – New Gymnasium  The new gymnasium was occupied on June 7, 2013 and PE classes were held in the new gym on August 15, 2013.   The tennis courts surfacing and striping was installed and completed August 27, 2013.    Palo Alto High School – Athletics Stadium Improvements  The main project including a concessions building, track re‐surfacing, new ornamental fence, signage and entry  lighting has been completed.  Some minor site improvements and fencing work have also been completed.    Palo Alto High School – Haymarket and Tower Building Improvements  All Trusty Builders completed the installation of the new windows on August 9, 2013, on schedule and within  budget.    525 San Antonio Road – Site Acquisition  This site has been leased to Athena Academy.     Ohlone Elementary School – New Classroom Building and Modernization  Move‐in to the new building and other existing classrooms occurred in December 2011.  Students occupied the  new building on January 3, 2012.      Jordan Middle School ‐ Interim Classrooms  The portables were installed and moved into for fall 2011.  DSA closeout received November 19, 2012.    Gunn High School – Air Conditioning of Existing Buildings  Best Contracting Services Inc. completed the installation of air conditioning units and cool roof coating in the  summer 2011.    J.L. Stanford Middle School ‐ Interim Classrooms  Coulter Construction completed the work on the relocated portables in August 2011.      Fairmeadow Elementary School – Portable Relocation  Relocation of the portable was complete and occupied on August 8, 2011.    Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems  Installation of SmartBoards and Lightspeed sound assist systems were completed for all elementary school  classrooms and libraries in April 2011.    Page | 5   Palo Alto High School – Multi‐use Field  The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9,  2011.  Gunn High School – Industrial Arts Addition & Renovation  This facility was available for instruction in January 2010. DSA closeout received on July 18, 2011.    Gunn High School – Aquatic Center   This facility was available for use in July 2009, and has been closed out with DSA.    Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman  AEDIS presented recommended concept plans for each campus to the Board of Education for approval on  September 8, which became the program documents for the new projects at each campus.  These projects for pre‐ design work have been closed, and funds were transferred to the program contingency on June 14, 2011.    INACTIVE CAPITAL PROJECTS     Garland Elementary School Renovation  The Board of Education has put new development for Garland on hold until a growth plan is established for the  elementary schools.  The board voted to terminate the lease with Stratford School in June 2011. Discussions with  the Board on future plans for growth at the elementary schools are ongoing.    High School Master Plan  The Board of Education (BOE) approved the master plans for both high schools, and these projects have been  closed, with funds transferred to the respective campus reserve funds.   Hoover Elementary School – Pre‐Design  This project has been put on hold until a growth plan is established for the elementary schools.      Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo  The project has been placed on hold pending further discussions with the BOE about elementary growth planning.        Board Actions in October  October 8, 2013  Consent 4 – Authorization to Issue Addendum No. 2 to CIS Inc. Specialty Consultants for Inspection Services at  Fairmeadow Elementary School    Action 9 – Approval of Project and Schematic Design – Palo Alto High School Indoor Physical Education and Athletic  Facilities    Action 10 – Approval of Schematic Design for the Science Addition Project at Palo Alto High School    October 22, 2013  Consent 5 – Approval of Change Orders       A B C C / A B - C C / B A - BGunn High School - High School Master Plan 172,390 166,328 133,829 77.6% 32,499 80.46% 6,062Gunn High School 1 - Aquatic Center 4,865,425 4,862,530 4,862,530 99.9% 0 100.00% 2,895Gunn High School 2 - I.A Building 5,082,402 5,066,038 5,061,488 99.6% 4,550 99.91% 16,364Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 25,035,201 24,975,358 23,904,516 95.5% 1,070,842 95.71% 59,843Gunn High School 5 - Parking & Drop Off improvements 3,940,000 476,808 212,568 5.4% 264,240 44.58% 3,463,192Gunn High School 6- New/Auxiliary Gymnasium 12,914,800 12,460,922 11,178,954 86.6% 1,281,968 89.71% 453,878Gunn High School 7- A/C 2,600,000 2,103,866 2,102,366 80.9% 1,500 99.93% 496,134Gunn High School 8 - MS & L-31 Buildings 2,120,839 277,873 94,513 4.5% 183,360 34.01% 1,842,966Gunn High School - Reserved 19,374,242 0 0 0.0% 0 0.00% 19,374,242Palo Alto High Schools - High School Master Plan 172,999 167,759 161,616 93.4% 6,143 96.34% 5,240Palo Alto High School 1 - Stadium Field 5,090,000 5,043,383 4,592,542 90.2% 450,841 91.06% 46,617Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,609,680 100.0% 0 100.00% 0Palo Alto high School 3 - New classroom & Media Art Building 37,140,001 33,983,564 27,936,503 75.2% 6,047,061 82.21% 3,156,437Palo Alto High School 4 - New Theater 24,395,049 1,696,062 1,175,645 4.8% 520,417 69.32% 22,698,987Palo Alto High School 5 - Haymarket and Tower Admin. Building 1,499,999 1,205,125 1,167,989 77.9% 37,136 96.92% 294,874Palo Alto High School 6- Science Addition 5,532,204 624,169 282,422 5.1% 341,747 45.25% 4,908,035Palo Alto High School - Reserved 25,074,443 0 0 0.0% 0 0.00% 25,074,443Jordan Middle School -Program Management- MS Pre-Design 18,890 17,826 17,826 94.4% 0 100.00% 1,064Jordan Middle Schools 1- Interim Classrooms 600,342 488,684 469,862 78.3% 18,822 96.15% 111,658Jordan Middle School 2- Improvements 19,891,564 19,144,332 17,864,376 89.8% 1,279,956 93.31% 747,232J.L.S Middle School - Program Management- MS Pre-Design 18,799 18,408 18,408 97.9% 0 100.00% 391J.L.S Middle School 1 - Interim Classrooms 446,844 422,500 407,908 91.3% 14,592 96.55% 24,344 J.L.S Middle School 2- Improvements 17,184,699 16,558,769 14,515,234 84.5% 2,043,535 87.66% 625,930Terman Middle School - Program Management- MS Pre-Design 18,799 18,423 18,423 98.0% 0 100.00% 376Terman Middle School 1- Improvements 13,312,971 12,994,921 12,630,519 94.9% 364,402 97.20% 318,050PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 98,480 89,820 61.9% 8,660 91.21% 46,520Addison Elementary School 1-Phase I 21,267 21,267 21,267 100.0% 0 100.00% 0Duveneck Elementary School 1-Phase I 9,778,358 9,308,850 2,359,230 24.1% 6,949,620 25.34% 469,508Garland Elementary School 1- Phase I 22,178,544 280,113 280,113 1.3% 0 100.00% 21,898,431Fairmeadow Elementary School 1- Phase I 7,796,550 7,589,595 6,341,335 81.3% 1,248,260 83.55% 206,955Hoover Elementary School 1-Phase I 70,550 70,550 57,165 81.0% 13,385 81.03% 0Ohlone Elementary School 1- Phase I 10,597,870 10,578,005 10,460,027 98.7% 117,978 98.88% 19,865Elementary Schools 1 - Elementary Classroom Improvements 2,004,889 1,879,695 1,879,695 93.8% 0 100.00% 125,194Elementary Schools - Reserved 37,585,253 0 0 0.0% 0 0.00% 37,585,253PAUSD - Program Management 10,380,131 8,637,276 7,037,049 67.8% 1,600,227 81.47% 1,742,855PAUSD - Technology 10,485,054 9,244,512 9,222,908 88.0% 21,604 99.77% 1,240,542PAUSD - Technology -Reserved 3,422,312 0 0 0.0% 0 0.00% 3,422,312PAUSD - Reserved 6,055,697 0 0 0.0% 0 0.00% 6,055,697525 San Antonio -Property Acquisition 8,500,000 8,500,000 8,500,000 100.0% 0 100.00% 0Bond Issuance Cost & Other Transfer Out 19,927,288 19,927,288 19,927,288 100.0% 0 100.00% 0Total378,067,122 221,524,735 197,601,390 23,923,345 156,542,387Prepared by: Business Services Department based on QSS accounting SystemExpenditures Budget BalanceCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond10/31/2013Percent of ExpendedContract Balance Page | 6   Gunn High School  Miranda Ave. Drop Off  Phase I – Parking and Drop‐off Improvements   A. PROJECT STATUS    DLM received DSA approval on October 2, 2013, and submitted  off‐site improvement drawings for work at the Miranda Ave  intersection for the City of Palo Alto and County of Santa Clara.   Bid documents were advertised to contractors on October 7,  2013, and a pre‐bid job walk was conducted on October 17, 2013.  Bids are due on November 12, 2013, with award scheduled for  the November 19, 2013 BOE meeting.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:   Phase I, Miranda Ave. parking and drop‐off plans were submitted to DSA July 17, 2013 and are awaiting  DSA approval which is anticipated in early October 2013.  Funding  State Funds $0  Strong Schools Bond Funds $3,940,000  Other Funding $0  Total $3,940,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $898,978  Construction & Equipment $2,919,840  Soft Costs Contingency $121,182  Total $3,940,000    Percent of Budget Expended 5.4%  Current Phase:Bid & Award   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 19, 2012  BOE Approval June 26, 2012    Schematic Design (2) December 18, 2012  BOE Approval January 15, 2013    Authorize to Bid (2) June 11, 2013  BOE Approval June18, 2013    Submit to DSA July 17, 2013     Approval by DSA October 2, 2013    Bid Opening November 12, 2013*    Award of Contract (1) November 19, 2013*    Notice to Proceed November 27, 2013*    Substantial Completion April 30, 2014*      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 7   Gunn High School   Existing Gymnasium Modernization  A. PROJECT STATUS    Romkon Inc. completed striping and finishing the gym floor, installation of  doors, ceiling tiles and wresting wall pads.  Punch list corrections to  commence on November 1, 2013, and the gym will be occupied by the  campus on November 4, 2013.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:   The project is proceeding on‐schedule and within budget. Occupancy is anticipated by November 1, 2013.      Funding and Budget  This project is funded by the New Gymnasium project  budget.  See that project budget for status.    Change Order Contingency   Starting Contingency Balance $99,800   Remaining Contingency Balance $99,800   Percent of Changes 0.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) February 12, 2013  BOE Approval February 26, 2013    Approval by DSA January 23, 2013    Bid Opening April 2, 2013    Award of Contract (1) April 9, 2013    Notice to Proceed May 31, 2013    Substantial Completion October 28, 2013*    Planned Occupancy November 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 8   Gunn High School   E and K (MS and L‐31) Buildings Renovation   A. PROJECT STATUS    DLM continued with construction documents after receiving final input from the  site staff.  DLM anticipates submitting drawings to DSA in late November 2013.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:   BOE schematic design approval was received on June 18, 2014.  Design will continue for submission into  DSA anticipated in Fall 2013.    Funding  State Funds $0  Strong Schools Bond Funds $2,120,839  Other Funding $0  Total $2,120,839    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $426,700  Construction & Equipment $1,689,952  Soft Costs Contingency $4,187  Total $2,120,839    Percent of Budget Expended 4.5%      Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) June 11, 2013  BOE Approval June 18, 2013    Submit to DSA November 20, 2013*    Authorize to Bid (2) March 8, 2014*  BOE Approval March 22, 2014*    Approval by DSA March 21, 2014*    Bid Opening April 30, 2014*    Award of Contract (1) May 13, 2014*    Notice to Proceed May 23, 2014*    Substantial Completion October 1, 2014*    Planned Occupancy October 16, 2014*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 9   Palo Alto High School   Classroom Building and Media Arts   A. PROJECT STATUS     Taisei Construction continued installation of casework, the HVAC system,  and roofing work for the new Math/Social Sciences building.  At the Media  Arts building, the contractor continued installation of casework, the glass  curtain wall and interior drywall.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   The project continues to be delayed by the contractor, with occupancy of the Media Arts and Math/Social  Sciences buildings now anticipated in Summer 2014.   Funding  State Funds $0  Strong Schools Bond Funds $37,140,000  Other Funding $0  Total $37,140,000    Budget  Salaries and Benefits $18,448  Supplies $26,519  Contracts & Services $7,066,446  Construction & Equipment $29,713,481  Soft Costs Contingency $315,107  Total $37,140,000    Percent of Budget Expended 75.2%    Change Order Contingency   Starting Contingency Balance $2,515,000   Remaining Contingency Balance $695,899   Percent of Changes 7.2%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA April 28, 2011    Bid Opening June 30, 2011    Award of Contract (1) July 12, 2011    Notice to Proceed August 4, 2011    Substantial Completion January 19, 2014*    Planned Occupancy August 1, 2014*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 10   Palo Alto High School  Performing Arts Center (PAC)  A. PROJECT STATUS    DSA review of construction documents submitted on March 29, 2013  continues.  This project will be bid after completion and contractor  demobilization at the new Classroom and Media Arts buildings.                                           B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.11    D. PROJECT OVERVIEW:   Project is proceeding on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $24,395,049  Other Funding $0  Total $24,395,049    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $4,481,640  Construction & Equipment $19,745,000  Soft Costs Contingency $168,409  Total $24,395,049    Percent of Budget Expended 4.8%  Current Phase: DSA Review   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (3) June 14, 2011  BOE Approval December 13, 2011  BOE Approval January 17, 2012    Submit to DSA March 28, 2013    Approval by DSA November 22, 2013*    Authorize to Bid (2) January 14, 2013*  BOE Approval January 28, 2013*    Bid Opening February 25, 2013*    Award of Contract (1) March 11, 2013*    Notice to Proceed April 1, 2013*    Substantial Completion July 13, 2015*    Planned Occupancy August 17, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 11   Palo Alto High School  Science Building Addition    A. PROJECT STATUS     DLM received schematic design approval on October 8, 2013.  Staff  conducted various investigations including geotechnical, fire hydrant flow,  and survey for design development.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   Schematic Design approval received October 8, 2013.    Funding  State Funds $0  Strong Schools Bond Funds $5,532,204  Other Funding $0  Total $5,532,204    Budget  Salaries and Benefits $0  Supplies $48,121  Contracts & Services $832,654  Construction & Equipment $4,628,294  Soft Costs Contingency $23,135  Total $5,532,204    Percent of Budget Expended 5.1%      Current Phase: Schematic Design    Schedule:  Architect Contract (2) March 12, 2013  BOE Approval March 19, 2013    Conceptual Design (2) March 12, 2013  BOE Approval March 19, 2013    Schematic Design (2) September 10, 2013  BOE Approval October 8, 2013    Submit to DSA February 7, 2014*    Authorize to Bid (2) June 9, 2014*  BOE Approval June 19, 2014*    Approval by DSA August 2, 2014*    Bid Opening October 3, 2014*    Award of Contract (1) October 11, 2014*    Notice to Proceed October 27, 2014*    Substantial Completion November 20, 2015*    Planned Occupancy January, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 12   Palo Alto High School  New Gymnasium    A. PROJECT STATUS     The BOE approved the schematic design of the project and  approved the appropriation of $5.47M of Strong Schools  Bond funds earmarked for the Weight & Fitness center at Paly  for this project.  The balance of the project is being funded by  a private donation.  The architect, Jeremiah Tolbert Designs is  moving forward with construction documents, and plans to  submit plans to DSA in late November 2013.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   Schematic Design approval planned for September 2013.  Funding  State Funds $0  Strong Schools Bond Funds $5,470,000  Other Funding $0  Total $5,470,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $5,470,000  Construction & Equipment $0  Soft Costs Contingency $0  Total $5,470,000    Percent of Budget Expended 0.0%      Current Phase: Schematic Design    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) March 12, 2013  BOE Approval March 19, 2013    Schematic Design (2) September 10, 2013  BOE Approval October 8, 2013    Submit to DSA November, 2013*    Authorize to Bid (2) N/A  BOE Approval N/A    Approval by DSA August 2, 2014*    Bid Opening N/A    Award of Contract (1) October 11, 2014*    Notice to Proceed N/A    Substantial Completion November 20, 2015*    Planned Occupancy January, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 13   Jordan Middle School   A. PROJECT STATUS     S.J. Amoroso continued to correct punch list items.  Close‐out efforts  continued through October 2013.                              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5    D. PROJECT OVERVIEW:   The project is completed on schedule and within budget.    Funding  State Funds $0  Strong Schools Bond Funds $19,891,564  Other Funding $0  Total $19,891,564    Budget  Salaries and Benefits $5,904  Supplies $84,897  Contracts & Services $3,723,370  Construction & Equipment $16,007,031  Soft Costs Contingency $70,362  Total $19,891,564    Percent of Budget Expended 89.8%    Change Order Contingency   Starting Contingency Balance $1,398,700   Remaining Contingency Balance $924,676   Percent of Changes 3.4%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Close‐out / Occupancy – August 15, 2013   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) March 23, 2010  BOE Approval April 27, 2010    Submit to DSA December 21, 2010     Authorize to Bid (2) June 28, 2011  BOE Approval July 19, 2011    Approval by DSA October 5, 2011    Bid Opening December 8, 2011    Award of Contract (1) December 13, 2011    Notice to Proceed December 27, 2011    Substantial Completion August 1, 2013    Planned Occupancy August 15, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 14   J.L. Stanford Middle School   A. PROJECT STATUS     The project, including the new classroom building and modernization work  in the science building, gymnasium, all classroom wings and the  administration building, continued with project close‐out efforts.                              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:   The project completed on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $17,184,699  Other Funding $0  Total $17,184,699    Budget  Salaries and Benefits $5,742  Supplies $144,790  Contracts & Services $3,541,940  Construction & Equipment $13,474,259  Soft Costs Contingency $17,968  Total $17,184,699    Percent of Budget Expended 84.5%    Change Order Contingency   Starting Contingency Balance $1,057,800   Remaining Contingency Balance $1,001,159   Percent of Changes 2.8%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Close‐out / Occupancy – August 15, 2013   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (3) June 1, 2010  BOE Approval June 22, 2010  BOE Approval (Sitework) September 28, 2010    Submit to DSA May 6, 2011     Authorize to Bid (2) November 29, 2011  BOE Approval December 13, 2011    Approval by DSA January 24, 2012    Bid Opening May 3, 2012    Award of Contract (1) May 8, 2012    Notice to Proceed May 30, 2012    Substantial Completion August 7, 2013    Planned Occupancy August 15, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings Page | 15   J.L. Stanford Middle School   Landscape and Site Improvements    A. PROJECT STATUS     Scapes, Inc. completed the landscape and sitework improvements on  schedule and has commenced project close‐out.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:   The project completed on schedule and within budget.    Funding and Budget  This project is funded by the J.L. Stanford Middle School  project budget.  See that project budget for status.    Percent of Budget Expended 84.5%    Change Order Contingency   Starting Contingency Balance $1,057,800   Remaining Contingency Balance $1,001,360   Percent of Changes 0.5%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Close‐out / Occupancy – August 16, 2013   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (3) June 1, 2010  BOE Approval June 22, 2010  BOE Approval (Sitework) September 28, 2010    Submit to DSA May 6, 2011     Authorize to Bid (2) November 29, 2011  BOE Approval December 13, 2011    Approval by DSA January 24, 2012    Bid Opening May 3, 2013    Award of Contract (1) May 8, 2013    Notice to Proceed May 23, 2013    Substantial Completion August 16, 2013    Completion August 16, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings Page | 16   Terman Middle School   A. PROJECT STATUS    Hagensen Pacific continued to work on punch list corrections throughout  October 2013 and will continue into November 2013.  Modernization work  in the cafetorium building continued through October 2013, and received  health department sign‐off on October 31, 2013.  The cafetorium building  will be occupied in November 2013.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12    D. PROJECT OVERVIEW:   The project completed on schedule, with exception of the Cafetorium, which was complete on October  31, 2013. The project is currently within budget.  Funding  State Funds $0  Strong Schools Bond Funds $13,312,971  Other Funding $0  Total $13,312,971    Budget  Salaries and Benefits $1,267  Supplies $68,668  Contracts & Services $2,718,013  Construction & Equipment $10,517,515  Soft Costs Contingency $7,508  Total $13,312,971    Percent of Budget Expended 94.9%    Change Order Contingency   Starting Contingency Balance $929,900   Remaining Contingency Balance $98,539   Percent of Changes 8.9%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) May 11, 2010  BOE Approval May 25, 2010    Submit to DSA December 21, 2010    Authorize to Bid (2) June 28, 2011  BOE Approval July 19, 2011    Approval by DSA September 1, 2011    Bid Opening December 6, 2011    Award of Contract (1) December 13, 2011    Notice to Proceed December 27, 2011    Substantial Completion October 31, 2013    Planned Occupancy November 8, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 17   Fairmeadow Elementary School   New Classroom Building and Modernization   A. PROJECT STATUS    BEST Contracting completed all work including sitework.  Fencing  around landscape areas was removed October 1, 2013.  Commissioning  of building systems continue and are anticipated to be complete in mid  November 2013.      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   The project completed on schedule and within budget.        Funding  State Funds $0  Strong Schools Bond Funds $7,796,550  Other Funding $0  Total $7,796,550    Budget  Salaries and Benefits $30,369  Supplies $98,969  Contracts & Services $2,077,069  Construction & Equipment $5,587,536  Soft Costs Contingency $2,614  Total $7,796,550    Percent of Budget Expended 81.3%    Change Order Contingency   Starting Contingency Balance $642 ,300   Remaining Contingency Balance $440,915   Percent of Changes 3.1%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase:Close‐out / Occupancy – August 15, 2013    Schedule:  Architect Contract (2) October 13, 2009  BOE Approval October 27, 2009    Conceptual Design (2) March 23, 2010  BOE Approval April 6, 2010    Schematic Design (2) September 14, 2010  BOE Approval September 28, 2010    Submit to DSA April 18, 2011     Authorize to Bid (2) October 11, 2011  BOE Approval October 25, 2011    Approval by DSA November 14, 2011    Bid Opening December 5, 2011    Award of Contract (1) December 13, 2011    Notice to Proceed January 3, 2012    Substantial Completion August 5, 2013    Planned Occupancy August 15, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 18   Duveneck Elementary School   New Classroom Buildings and Modernization  A. PROJECT STATUS    Alpha Bay Builders (ABB) completed roof installation and continued  installation of exterior stucco and interior drywall for buildings 2 and 3.    Steel erection for building 1 will continue through November 2013.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   The project is proceeding on schedule and within budget.    Funding  State Funds $0  Strong Schools Bond Funds $9,778,358  Other Funding $0  Total $9,778,358    Budget  Salaries and Benefits $8,378  Supplies $0  Contracts & Services $2,060,066  Construction & Equipment $7,678,803  Soft Costs Contingency $31,111  Total $9,778,358    Percent of Budget Expended 24.1%    Change Order Contingency   Starting Contingency Balance $703 ,700   Remaining Contingency Balance $703,700   Percent of Changes 0.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) December 14, 2010  BOE Approval January 11, 2011    Schematic Design (2) June 14, 2011  BOE Approval June 28, 2011    Submit to DSA February 27, 2012     Approval by DSA December 10, 2012    Authorize to Bid (2) December 18 2012  BOE Approval January 15, 2013    Bid Opening February 28, 2013    Award of Contract (1) March 12, 2013    Notice to Proceed March 25, 2013    Substantial Completion July 16, 2014*    Planned Occupancy August 1, 2014*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 19   Technology Improvements   A. PROJECT STATUS     Installation of exterior wireless antennas and repeaters at each campus continued.          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:   Wireless antennas and repeaters installation at each campus is on‐going.    Funding  State Funds $0  Strong Schools Bond Funds $10,485,054  Other Funding $0  Total $10,485,054    Budget  Salaries and Benefits $0  Supplies & Computers $6,850,644  Contracts & Services $539,269  Construction & Equipment $3,095,142  Soft Costs Contingency $0  Total $10,485,054    Percent of Budget Expended 88.0%    Current Phase: N/A   Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 20   Gunn High School   New Classroom Buildings A & B   A. PROJECT STATUS    The new Math and English Building was occupied by staff and students on  August 15, 2013.  World Language Building classrooms have been in use  since February, 2013.                         B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4    D. PROJECT OVERVIEW:   The World Languages building move‐in occurred on February 8, 2013, and was occupied with staff and  students on February 11, 2013.  The Math & English building move‐in occurred on July 15, 2013, and was  occupied with staff and students on August 15, 2013.  The project completed within budget.      Funding  State Funds $0  Strong Schools Bond Funds $25,035,201  Other Funding $0  Total $25,035,201    Budget  Salaries and Benefits $22,473  Supplies $308,194  Contracts & Services $3,982,449  Construction & Equipment $20,721,808  Soft Costs Contingency $277  Total $25,035,201    Percent of Budget Expended 95.5%    Change Order Contingency   Starting Contingency Balance $ 1,763,200   Remaining Contingency Balance $ 126,231   Percent of Changes 9.3%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Close‐out / Occupancy – August 15, 2013   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010     Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA May 27, 2011    Bid Opening July 13, 2011    Award of Contract (1) July 22, 2011    Notice to Proceed August 24, 2011    Substantial Completion July 15, 2013    Planned Occupancy August 15, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 21   Gunn High School   New Gymnasium   A. PROJECT STATUS    The new gymnasium was occupied on June 7, 2013 and PE classes were  held in the new gym on August 15, 2013.  The tennis courts surfacing and  striping was installed and completed August 27, 2013.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:   The new gym was occupied on June 7, 2013.      Funding  State Funds $0  Strong Schools Bond Funds $12,914,800  Other Funding $0  Total $12,914,800    Budget  Salaries and Benefits $0  Supplies $3,747  Contracts & Services $2,460,699  Construction & Equipment $10,407,910  Soft Costs Contingency $42,444  Total $12,914,800    Percent of Budget Expended 86.6%    Change Order Contingency   Starting Contingency Balance $834,700   Remaining Contingency Balance $325,453   Percent of Changes 6.1%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –June 7, 2013    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA May 27, 2011    Bid Opening July 13, 2011    Award of Contract (1) July 20, 2011    Notice to Proceed August 1, 2011    Substantial Completion May 1, 2013    Planned Occupancy June 7, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 22   Palo Alto High School  Haymarket and Tower Building Improvements     A. PROJECT STATUS     All Trusty Builders completed the installation of the new windows on  August 9, 2013, on schedule and within budget.                              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   The project completed on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $1,500,000  Other Funding $0  Total $1,500,000    Budget  Salaries and Benefits $0  Supplies $37,045  Contracts & Services $179,000  Construction & Equipment $1,283,955  Soft Costs Contingency $0  Total $1,500,000    Percent of Budget Expended 77.9%    Change Order Contingency   Starting Contingency Balance $39,200   Remaining Contingency Balance $33,930   Percent of Changes 1.3%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Close‐out / Occupancy – August 9, 2013    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA May 25, 2012    Authorize to Bid (2) April 24, 2012  BOE Approval May 6, 2012    Approval by DSA August 24, 2012    Bid Opening January 17, 2013    Award of Contract (1) January 29, 2013    Notice to Proceed February 21, 2013    Substantial Completion August 9, 2013      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 23   Palo Alto High School   Athletic Stadium Improvements   A. PROJECT STATUS    The main project including a concessions building, track re‐surfacing,  new ornamental fence, signage and entry lighting has been completed.   Some minor site improvements and fencing work have also been  completed.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.13    D. PROJECT OVERVIEW:   The ornamental fence was completed on schedule in August 2013.  The concessions building was  occupied September 10, 2012.  The bleacher replacement work was completed on schedule in June 2013.    Funding  State Funds $0  Strong Schools Bond Funds $5,090,000  Other Funding $0  Total $5,090,000    Budget  Salaries and Benefits $882  Supplies $2,746  Contracts & Services $850,021  Construction & Equipment $4,236,351  Soft Costs Contingency $0  Total $5,090,000    Percent of Budget Expended 90.2%    Change Order Contingency   Starting Contingency Balance $310,200   Remaining Contingency Balance $242,491   Percent of Changes 2.2%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Close‐out / Occupancy – August 1, 2013    Schedule:  Architect Contract (2) January 26, 2010  BOE Approval February 9, 2010    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) February 22, 2011  BOE Approval March 8, 2011    Submit to DSA April 4, 2011    Authorize to Bid (2) June 28, 2011  BOE Approval July 19, 2011    Approval by DSA July 26, 2011     Bid Opening December 1, 2011    Award of Contract (1) December 13, 2011    Notice to Proceed January 4, 2012    Substantial Completion ‐ Concession  August 31, 2012  Planned Occupancy ‐ Concessions September 10, 2012  Bleachers March 31, 2013  Fence Completion August 1, 2013  * Anticipated Dates – Subject to Change  ()Denotes number ofBoardofEducation Readings Page | 24   Ohlone Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS     Move‐in to the new building and other existing classrooms  occurred in December 2011.  Students occupied the new building  on January 3, 2012.                              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   Occupancy occurred on January 3, 2012.  Project completed on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $10,597,870  Other Funding $0  Total $10,597,870    Budget  Salaries and Benefits $7,461  Supplies $49,049  Contracts & Services $2,179,619  Construction & Equipment $8,361,744  Soft Costs Contingency $62,598  Total $10,597,870    Percent of Budget Expended 98.7%    Change Order Contingency   Starting Contingency Balance $748,400   Remaining Contingency Balance $569,113   Percent of Changes 2.4%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase:Occupancy –January 3, 2012    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) March 3, 2009  BOE Approval March 17, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA November 24, 2009    Authorize to Bid (2) April 27, 2010  BOE Approval May 11, 2010    Approval by DSA May 18, 2010    Bid Opening July 13, 2010    Award of Contract (1) August 3, 2010    Notice to Proceed August 19, 2010    Substantial Completion November 18, 2011    Planned Occupancy January 3, 2012    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 25   Site Acquisition  525 San Antonio Rd   A. PROJECT STATUS    This site has been leased to Athena Academy.                              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   The site has been leased to Athena Academy.    Funding  State Funds $0  Strong Schools Bond Funds $8,500,000  Other Funding $0  Total $8,500,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $8,500,000  Construction & Equipment $0  Soft Costs Contingency $0  Total $8,500,000    Percent of Budget Expended 100.0%  Current Phase: N/A   Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 26   Jordan Middle Schools ‐ Interim Classrooms  A. PROJECT STATUS    The portables were installed and moved into for fall 2011.  DSA closeout received November 19, 2012.                               B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:   This project completed ahead of schedule and under budget.   Move in occurred on September 30, 2011.      Funding  State Funds $0  Strong Schools Bond Funds $392,120  Other Funding $208,222  Total $600,342    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $180,286  Construction & Equipment $419,292  Soft Costs Contingency $764  Total $600,342    Percent of Budget Expended 76.8%*    *Budget previously expended     Current Phase: Move‐in   Schedule:  Approval by DSA June 16, 2011    Authorize to Bid (2) June 14, 2011  BOE Approval June 28, 2011    Bid Opening July 14, 2011    Award of Contract (1) July 20, 2011    Notice to Proceed July 27, 2011    Substantial Completion September 20, 2011    Occupancy September 30, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 27   Gunn High School  Air Conditioning of Existing Buildings  A. PROJECT STATUS    Best Contracting Services Inc. completed the installation of air  conditioning units and cool roof coating in the summer 2011.  Some  warranty work on the cool roof coating needs to be completed by  Best.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.7    D. PROJECT OVERVIEW:   Project has been closed‐out.    Funding  State Funds $0  Strong Schools Bond Funds $2,600,000  Other Funding $0  Total $2,600,000    Budget  Salaries and Benefits $1,919  Supplies $0  Contracts & Services $454,160  Construction & Equipment $2,120,580  Soft Costs Contingency $22,891  Total $2,600,000    Percent of Budget Expended 80.9%  Current Phase: Completed   Schedule:  Architect Contract (2) March 27, 2010  BOE Approval April 6, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA October 20, 2010    Approval by DSA February 10, 2011    Authorize to Bid (2) February 22, 2011  BOE Approval March 8, 2011    Bid Opening March 28, 2011    Award of Contract (1) April 8, 2011    Notice to Proceed April 11, 2011    Substantial Completion August 8, 2011      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 28   J.L. Stanford Middle School ‐ Interim Classrooms  A. PROJECT STATUS    Coulter Construction completed the work on the relocated  portables in August 2011.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:   Project completed on schedule and is currently in close‐out.            This portable relocation project funded by main  JLS project.  Refer to pg. 14    Current Phase: Occupancy ‐August 11, 2011    Schedule:  Approval by DSA April 19, 2011  Jordan Project June 16, 2011     Authorize to Bid (2) May 10, 2011  BOE Approval May 24, 2011    Bid Opening June 1, 2011    Award of Contract (1) June 13, 2011    Notice to Proceed June 20, 2011    Substantial Completion August 8, 2011    Planned Occupancy August 15, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 29   Fairmeadow Elementary School  Portable Relocation Project  A. PROJECT STATUS     Relocation of the portable was complete and occupied on August 8, 2011.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 6.4    D. PROJECT OVERVIEW:   Project completed ahead of schedule on August 8, 2011.               This portable relocation project funded by main  JLS project.  Refer to pg. 14  Current Phase: Occupancy ‐August 8, 2011    Schedule:  Architect Contract (2) February 15, 2011  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA March 3, 2011     Approval by DSA March 3, 2011    Authorize to Bid (2) May 11, 2011  BOE Approval May 24, 2011    Bid Opening June 14, 2011    Award of Contract (1) June 14, 2011    Notice to Proceed June 20, 2011    Substantial Completion August 1, 2011    Planned Occupancy August 8, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 30   Elementary Classroom Improvements  Interactive Whiteboards and Sound Assist System Installation  A. PROJECT STATUS    Installation of SmartBoards and Lightspeed sound assist systems were  completed for all elementary school classrooms and libraries in April  2011.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:   All SmartBoards and Lightspeed sound systems installed.      Funding  State Funds $0  Strong Schools Bond Funds $2,004,889  Other Funding $0  Total $2,004,889    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $275,488  Construction & Equipment $1,729,401  Soft Costs Contingency $0  Total $2,004,889    Percent of Budget Expended 93.9%    Current Phase: Complete ‐May 15, 2011    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) November 9, 2010  BOE Approval November 23, 2010    Bid Opening February 25, 2011    Award of Contract (1) March 8, 2011    Notice to Proceed March 9, 2011    Completion May 15, 2011      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 31   Palo Alto High School   Multi‐Use Field  A. PROJECT STATUS    The fields were available for play on February 1, 2011, and final  change order negotiations completed on March 9, 2011.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.14    D. PROJECT OVERVIEW:   Field was open for use on February 1, 2011.     Funding  State Funds $0  Strong Schools Bond Funds $2,609,680  Other Funding $1,007,255  Total $3,616,935    Budget  Salaries and Benefits $0  Supplies $1,506  Contracts & Services $698,293  Construction & Equipment $2,916,682  Soft Costs Contingency $454  Total $3,616,935     Percent of Budget Expended 100.0%    Change Order Contingency   Starting Contingency Balance $269,300   Remaining Contingency Balance $230,579   Percent of Changes 1.7%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –February 1, 2011    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 18, 2008  BOE Approval December 09, 2008    Submit to DSA March 19, 2009     Approval by DSA September 30, 2009    Authorize to Bid (2) February 24, 2009  BOE Approval March 17, 2009    Bid Opening March 16, 2010    Award of Contract (1) April 7, 2010    Notice to Proceed June 1, 2010    Substantial Completion January 31, 2011    Planned Occupancy February 1, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 32   Gunn High School  Industrial Arts Addition and Renovation  A. PROJECT STATUS    This facility was available for instruction in January 2010. DSA closeout  received on July 18, 2011.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11    D. PROJECT OVERVIEW:   The building occupied as scheduled, and the project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,082,402  Other Funding $0  Total $5,082,402    Budget  Salaries and Benefits $1,061  Supplies $88,985  Contracts & Services $1,000,861  Construction & Equipment $3,991,495  Soft Costs Contingency $0  Total $5,082,402    Percent of Budget Expended 99.3%    Change Order Contingency   Starting Contingency Balance $349,000   Remaining Contingency Balance $141,967   Percent of Changes 41.6%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –January 4, 2010    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA June 17, 2008     Approval by DSA December 24, 2008    Authorize to Bid (2) October 14, 2008  BOE Approval October 28, 2008    Bid Opening December 16, 2008    Award of Contract (1) December 24, 2008    Notice to Proceed January 6, 2009    Substantial Completion November 25, 2009    Planned Occupancy January 4, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 33   Gunn High School  Aquatic Center  A. PROJECT STATUS    This facility was available for use in July 2009, and has been closed  out with DSA.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.12    D. PROJECT OVERVIEW:   This project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $4,865,423  Other Funding $0  Total $4,865,423    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $647,169  Construction & Equipment $4,218,253  Soft Costs Contingency $0  Total $4,865,423    Percent of Budget Expended 99.9%    Change Order Contingency   Starting Contingency Balance $389,887   Remaining Contingency Balance $195,148   Percent of Changes 49.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –June 15, 2009    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA December 11, 2007     Approval by DSA April 24, 2008    Authorize to Bid (2) April 8, 2008  BOE Approval April 22, 2008    Bid Opening May 28, 2008    Award of Contract (1) June 4, 2008    Notice to Proceed December 6, 2008    Substantial Completion June 15, 2009    Planned Occupancy June 15, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 34   Middle School Pre‐Design  Jordan, J.L. Stanford and Terman  A. PROJECT STATUS    AEDIS presented recommended concept plans for each campus to the  Board of Education for approval on September 8, which became the  program documents for the new projects at each campus.  These  projects for pre‐design work have been closed, and funds will be  transferred to the program contingency on June 14, 2011.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12    D. PROJECT OVERVIEW:   This project has been completed. Board approval received on September 8, 2009. Funding  State Funds $0  Strong Schools Bond Funds $56,488  Other Funding $0  Total $56,488    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $56,488  Construction & Equipment $0  Soft Costs Contingency $0  Total $56,488    Percent of Budget Expended 96.8%    Current Phase: Complete   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 35   Garland Elementary School  Campus Modernization  A. PROJECT STATUS    The Board of Education has put new development for Garland on  hold until a growth plan is established for the elementary schools.   The board voted to terminate the lease with Stratford School in  June 2011. Discussions with the Board on future plans for growth  at the elementary schools are ongoing.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10    D. PROJECT OVERVIEW:   This project has been placed on hold. Funding  State Funds $0  Strong Schools Bond Funds $22,178,544  Other Funding $0  Total $22,178,544    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,915,789  Construction & Equipment $17,400,000  Soft Costs Contingency $862,755  Total $22,178,544    Percent of Budget Expended 1.3%  Current Phase: On Hold   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) February 10, 2009  BOE Approval February 24, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 36   High School Master Plan  Palo Alto HS and Gunn HS  A. PROJECT STATUS    The Board of Education (BOE) approved the master plans for both  high schools, and these projects have been closed, with funds  transferred to the respective campus reserve funds.                    B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14    D. PROJECT OVERVIEW:   Master planning effort complete.                Funding  State Funds $0  Strong Schools Bond Funds $285,387  Other Funding $0  Total $285,387    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $285,387  Construction & Equipment $0  Soft Costs Contingency $0  Total $285,387    Percent of Budget Expended 86.2%  Current Phase: Complete   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Initial Master Plan Approval (2) September 8, 2009  BOE Approval September 22, 2009    Paly CEQA Approval (2) February 9, 2010  BOE Approval February 23, 2010    Gunn Master Plan Update (2) March 23, 2010  BOE Approval April 6, 2010    Gunn CEQA Approval (2) April 27, 2010   BOE Approval May 11, 2010     Master Plan Revision Approval (2) September 14, 2010  Paly MP Revision Approval (2) October 9, 2010  Gunn MP Revision Approval (2) October 12, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 37   Hoover Elementary School  Pre‐Design  A. PROJECT STATUS    This project has been put on hold until a growth plan is established for the  elementary schools.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   Project is currently on hold.                Funding  State Funds $0  Strong Schools Bond Funds $70,550  Other Funding $0  Total $70,550    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $70,550  Construction & Equipment $60  Soft Costs Contingency $0  Total $70,550    Percent of Budget Expended 81.0%  Current Phase: On Hold   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) November 9, 2010  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A  Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 38   Elementary Classroom Improvements  A. PROJECT STATUS    DSA comments were returned to Gelfand for Phase 1 plans that include  new lighting, adding operable windows and coverings, ventilation, and  replacement of ceiling tiles for classrooms at Barron Park and El  Carmelo elementary schools.  The authorization to bid has been placed  on hold pending further discussions with the BOE about elementary  growth planning.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:   This project has been placed on hold.          Funding  State Funds $0  Strong Schools Bond Funds $2,004,889  Other Funding $0  Total $2,004,889    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $275,488  Construction & Equipment $1,729,401  Soft Costs Contingency $0  Total $2,004,889    Percent of Budget Expended 93.9%    Phase 1 Schools: Barron Park and El Carmelo  Current Phase:  On Hold    Schedule:  Architect Contract (2) June 8, 2010  BOE Approval June 22, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 9, 2010  BOE Approval December 7, 2010    Submit to DSA December 23, 2010     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  OHS WEST:260388860.1 A-1 EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. Numbers Added A-2 OHS WEST:260388860.1 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. A-3 OHS WEST:260388860.1 3. GUNN HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Demolish old library building. 3. Replace temporary classrooms with permanent classrooms. 4. Construct additional restrooms. 5. Construct second gymnasium. 6. Construct new soccer field. 7. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 9. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 10. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 11. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 12. Replace swimming pool with new 35-meter pool, pool equipment and support structures, pool decking, bleachers, storage, restrooms, showers, associated equipment. 13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace athletic equipment. 14. Modernize football stadium, including new bathrooms and concession stands. A-4 OHS WEST:260388860.1 4. PALO ALTO HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Construct additional restrooms. 4. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 6. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 7. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 8. Library modernization and building interior improvements, including infrastructure and major building system upgrades. 9. Renovation or replacement of the Tower Building to accommodate administration, classroom and program support space. 10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility improvements; construction of new restrooms; install new roofing; replace doors and windows; replace gymnasium floors and athletic equipment, bleachers and renovation of interior. Renovation or replacement of weight training facility. 11. Construct new theater building. 12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing and storage. 13. Modernize football stadium, including replace bleachers; new bathrooms and concession stands. 14. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. A-5 OHS WEST:260388860.1 5. OTHER DISTRICT-WIDE PROJECTS Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and equipment for all classrooms, athletic facilities and other facilities, as needed. 1. Replace existing or acquire new computers, technology and related equipment on an ongoing basis. 2. Establish a planned maintenance fund to address maintenance work expected to be needed to all District facilities on an ongoing basis (other than as may be necessary for current maintenance, operation or repairs), in order to implement the District’s comprehensive facilities maintenance plan. 3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease- purchase arrangements, or execute purchase option under a lease for any of these authorized facilities. 4. If and as opportunities become available, and to the extent the Board of Education determines that bond funds are available for the purpose, acquisition of land and other interests in real property for future school buildings and other District facilities, and construction of such facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise listed. 5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field equipment and facilities (including nets, basketball standards, goals and goalposts, backstops), field lighting, etc. 6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS 1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead, etc., where necessary. 2. Address unforeseen conditions revealed by construction/modernization (including plumbing or gas line breaks, dry rot, seismic, structural, etc.). 3. Other improvements required to comply with existing building codes, including the Field Act, and access requirements of the Americans with Disabilities Act (ADA). 4. Site preparation/restoration in connection with new construction, renovation or remodeling, or installation or removal of relocatable classrooms, including ingress and egress, demolition of existing structures, removing, replacing, or installing irrigation and drainage, utility lines (such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any necessary easements, licenses, or rights of way to the property. 5. Rental or construction of storage facilities and other space on an interim basis, as needed to accommodate construction materials, equipment, and personnel, and interim classrooms (including relocatables) for students and school functions or other storage for classroom materials displaced during construction. A-6 OHS WEST:260388860.1 7. RENOVATION/MODERNIZATION (DEFINED) For purposes of the Bond Project List, renovation and modernization projects are intended to restore the building systems and infrastructure, weather protections, finishes, and technology, or reallocate and reorganize space, to a condition that will provide a sustainable, functional educational and administrative environment for future years, comparable to new construction. Renovation projects may include, but are not limited to nor necessarily encompass, all of the following, depending upon the age, condition and needs of each particular school facility: 1. upgrade electrical, communication, fire alarm, and similar building systems as well as main power service and distribution, which may include active and passive solar power and heating system acquisition, installation and construction 2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply, meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within buildings and sites and to connect with city supply and drainage systems 3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient heating and air cooling systems (HVAC), including installing energy management systems (EMS); 4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and fixtures, as necessary; 5. Repair, modify and construct structural elements of the existing structure as necessary; 6. Replace or repair aging roofs with similar materials or District standard materials; 7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes, doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces (including white boards, marker boards, tack boards, television mounts, scoreboards, fire extinguishers, kitchen cabinets/equipment, etc.); 8. Upgrade, modify and construct restroom facilities; 9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24 requirements; 10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood siding, paint, etc.); replace doors and windows 11. Modify, expand, separate, convert and construct school support areas; staff work and lunch areas; and educational areas to provide adequate, functional environments; 12. Modify, replace and construct functional components of altered or replaced building components (including rainwater leaders, fascias, mansards, etc.); ™ For any project involving renovation, modernization, remodeling or rehabilitation of a building or the major portion of a building, the District may proceed with new replacement construction instead (including any necessary demolition), if the Board of Education determines that replacement and new construction is more practical than rehabilitation and renovation, considering the building’s age, condition, expected remaining life, comparative cost, and other relevant factors.