Monthly Reports 2012-09 (Sep) Page | 1   MMOONNTTHHLLYY  PPRROOGGRREESSSS  RREEPPOORRTT     Through  September 2012      Current Strong Schools Bond  Capital Improvement Projects  Prepared by     T. J. Hodges and Associates  &  Gilbane Building Company  Page | 2   TABLE OF CONTENTS    Executive Summary         page 3   Attachment 1 – Consolidated Expenditure Report            Capital Projects     Gunn High School – New Classroom Buildings A & B     page 6    Gunn High School – Phase I ‐ Parking and Drop‐off Sitework Improvement  page 7    Gunn High School – New Gymnasium       page 8    Palo Alto High School – Athletic Stadium Improvements    page 9    Palo Alto High School – Classroom Building and Media Arts    page 10    Palo Alto High School – Performing Arts Center     page 11    Palo Alto High School – Haymarket and Tower Building Improvements    page 12    Jordan Middle School        page 13    J.L. Stanford Middle School       page 14    Terman Middle School        page 15     Fairmeadow Elementary School – New Classroom Buildings and Modernization  page 16    Duveneck Elementary School – New Classroom Buildings and Modernization  page 17    Technology          page 18    Completed Capital Projects    Ohlone Elementary School        page 19    Property Acquisition – 525 San Antonio Rd       page 20    Jordan Middle School – Interim Classrooms      page 21    Gunn High School – Air Conditioning of Existing Buildings    page 22    J.L. Stanford Middle School – Interim Classrooms     page 23    Fairmeadow Elementary School – Portable Relocation    page 24    Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 25    Palo Alto High School – Multi‐use Field      page 26    Gunn High School – Industrial Arts Renovation     page 27    Gunn High School – Aquatic Center       page 28    Middle School Pre‐Design        page 29    Inactive Capital Projects    Garland Elementary School       page 30    High School Master Plan        page 31    Hoover Elementary School        page 32    Elementary Classroom Improvements      page 33    Appendix  Exhibit A – Bond Project List    Page | 3   EXECUTIVE SUMMARY    Gunn High School – New Classroom Buildings A & B  BRCO Constructors removed and replaced the concrete slab of the second floor slabs at the Math English building,  due to missing reinforcing steel in the initial deck pour.  Also, plumbing and electrical rough‐in continued  throughout both buildings.  At the World Language Building, BRCO continued with stucco installation.  The  windows and metal roof and gutters were also installed.    Gunn High School – Phase I ‐ Parking and Drop‐off Sitework Improvement  DLM will meet with the City of Palo Alto and County of Santa Clara to review ingress and egress requirements  along Miranda Ave.  After review with the City of Palo Alto, DLM will present their recommended plan to the site  committee in November 2012.  Construction will commence after the completion of classroom building A.    Gunn High School – New Gymnasium  S.J. Amoroso continued interior painting, installation of exterior plaster, and windows.  Structural steel was  installed for the new canopy to the existing gym building and installation of reinforcing steel continued on the  ramps.  DSA continues to review the bleacher submittal therefore occupancy of the gym will occur after the  installation of the bleachers.    Palo Alto High School – Athletics Stadium Improvements  Taisei (TCC) completed the concessions building for occupancy, with final finishes and punchlist corrections  wrapping up in September.  Work will resume with the demolition of the bleachers, press box and existing snack  shack in late November 2012, after football season is completed.    Palo Alto High School – Classroom Building and Media Arts Building  TCC continued site activities on the new Math/Social Sciences building, including grading, heating and cooling  piping and concrete curb installation.  At the interior of the Math/Social Sciences building, installation continued  on the mechanical and electrical systems and wall and ceiling framing.  At the Media Arts building, the second floor  deck railing installation commenced and mechanical piping to classroom air handlers are in progress.    Palo Alto High School – Performing Arts Center (PAC)  DLM submitted 50% construction documents on September 22, 2012 for district backcheck of DD comments.  DLM  continued working construction documents with submission to DSA anticipated in December 2012.      Palo Alto High School – Haymarket and Tower Building Improvements   Bids for the tower building window replacement were opened on September 7, 2012, and Pinguelo Construction  was the apparent low bidder.  BOE award is scheduled for September 18, 2012.   Jordan Middle School  S.J. Amoroso continued work on the new classroom and new cafetorium buildings. At both buildings, exterior work  continued with roofing, lath and plaster, and window system installation.  The new classroom building interior  work included drywall installation and paint.  Mechanical system rough‐in continued at the interior of the  cafetorium.  The two new music classrooms are nearing completion with the installation of casework and ceiling  systems.    J.L. Stanford Middle School  Sausal Corporation continued work on the structural foundation of the new two‐story classroom.  Concrete  footings were set in place with the concrete pour for the slab on grade scheduled next month.  Work continued on  underground utility installation of electrical and plumbing systems below the slab.        Page | 4   Terman Middle School  Hagensen Pacific continued work on exterior lath and window installation at new Library Building.  At the new  Administration building and new Drama classroom work continued on interior finishes and site work.  Both  buildings are anticipated to be complete ahead of schedule, with move in scheduled during winter break.  Plumbing, electrical and automated controls continued at the furnace exterior closets for classroom wings A, C,  and H.  Drywall installation is complete in the gymnasium and the exercise room.    Fairmeadow Elementary School – New Classroom Building and Modernization  Best Contracting Services (BCS) is working on the CMU wall installation of the new classroom building. Two CMU  walls on the second floor failed the shear test, so Best had to rebuild the two walls. Interior framing and  mechanical, electrical and plumbing rough‐in continued on the first floor.      Duveneck Elementary School – New Classroom Buildings and Modernization  Gelfand submitted construction documents for the project to DSA on February 27, 2012, and has received  comments back from DSA.  Gelfand is incorporating DSA and constructability review comments.  DSA backcheck is  scheduled for November 28, 2012.    Technology  Implementation of the district‐wide Voice‐over‐IP (VoIP) telephone system is complete.  Installation of access  points to increase the broadband of wireless access is also complete.  Installation of wireless antennas at each  school is planned to commence in late fall 2012.    COMPLETED CAPITAL PROJECTS   525 San Antonio Road – Site Acquisition  This site has been leased to Athena Academy.  Athena Academy will begin to make rent payments once their  conditional use permit is approved by the City of Palo Alto.    Ohlone Elementary School – New Classroom Building and Modernization  Move‐in to the new building and other existing classrooms occurred in December 2011.  Students occupied the  new building on January 3, 2012.      Jordan Middle School ‐ Interim Classrooms  The portables were installed and moved into for fall 2011. All documents were submitted to DSA for closeout  November 2, 2011.     Gunn High School – Air Conditioning of Existing Buildings  Best Contracting Services Inc. completed the installation of air conditioning units and cool roof coating in the  summer 2011. Some warranty work on the cool roof coating needs to be completed by Best.    J.L. Stanford Middle School ‐ Interim Classrooms  Coulter Construction completed the work on the relocated portables in August 2011.      Fairmeadow Elementary School – Portable Relocation  Relocation of the portable was complete on August 8, 2011.  All documents were submitted to DSA for closeout  October 11, 2011.      Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems  Installation of SmartBoards and Lightspeed sound assist systems were completed for all elementary school  classrooms and libraries in April 2011.        Page | 5   Palo Alto High School – Multi‐use Field  The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9,  2011.    Gunn High School – Industrial Arts Addition & Renovation  This facility was available for instruction in January 2010. DSA closeout received on July 18, 2011.    Gunn High School – Aquatic Center   This facility was available for use in July 2009, and has been closed out with DSA.    Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman  AEDIS presented recommended concept plans for each campus to the Board of Education for approval on  September 8, which became the program documents for the new projects at each campus.  These projects for pre‐ design work have been closed, and funds were transferred to the program contingency on June 14, 2011.    INACTIVE CAPITAL PROJECTS     Garland Elementary School Renovation  The Board of Education has put new development for Garland on hold until a growth plan is established for the  elementary schools.  The board voted to terminate the lease with Stratford School in June 2011. Discussions with  the Board on future plans for growth at the elementary schools are ongoing.    High School Master Plan  The Board of Education (BOE) approved the master plans for both high schools, and these projects have been  closed, with funds transferred to the respective campus reserve funds.   Hoover Elementary School – Pre‐Design  This project has been put on hold until a growth plan is established for the elementary schools.      Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo  The project has been placed on hold pending further discussions with the BOE about elementary growth planning.          Board Actions in September  September 4, 2012  Consent 5 – Appointment of Three Members to the Citizens; Oversight Committee for the Strong Schools Bond    September 18, 2012    Consent 6 – Approval of Strong Schools Bond Change Orders    Action 13 – Authorization to Award a Contract for Replacement of Windows at the Tower Building and Haymarket  Theater at Palo Alto High School       A B C C / A B - C C / B A - BGunn High School - High School Master Plan 142,390 136,328 117,735 82.7% 18,593 86.4% 6,062Gunn High School 1 - Aquatic Center 4,865,425 4,862,530 4,862,530 99.9% 0 100.0% 2,895Gunn High School 2 - I.A Building 5,082,402 5,049,526 5,049,243 99.3% 283 100.0% 32,876Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.0% 0Gunn High School 4 - New classroom Buildings 25,035,201 23,904,980 11,440,525 45.7% 12,464,455 47.9% 1,130,221Gunn High School 5 - Parking & Drop Off improvements 3,940,000 444,711 123,378 3.1% 321,333 27.7% 3,495,289Gunn High School 6- New/Auxiliary Gymnasium 12,914,800 11,071,099 6,975,217 54.0% 4,095,882 63.0% 1,843,701Gunn High School 7- A/C 2,600,000 2,102,366 2,102,366 80.9% 0 100.0% 497,634Gunn High School - Reserved 21,525,081 0 0 0.0% 0 0.0% 21,525,081Palo Alto High Schools - High School Master Plan 142,999 137,759 133,386 93.3% 4,373 96.8% 5,240Palo Alto High School 1 - Stadium Field 5,090,000 4,785,413 2,940,034 57.8% 1,845,379 61.4% 304,587Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,609,680 100.0% 0 100.0% 0Palo Alto high School 3 - New classroom & Media Art Building 37,140,001 33,740,424 17,739,896 47.8% 16,000,528 52.6% 3,399,577Palo Alto High School 4 - New Theater 24,395,049 1,598,113 513,609 2.1% 1,084,504 32.1% 22,796,936Palo Alto High School 5 - Haymarket and Tower Admin. Building 1,499,999 414,618 414,618 27.6% 0 100.0% 1,085,381Palo Alto High School - Reserved 30,636,647 0 0 0.0% 0 0.0% 30,636,647Jordan Middle School -Program Management- MS Pre-Design 18,890 18,890 17,826 94.4% 1,064 94.4% 0Jordan Middle Schools 1- Interim Classrooms 600,342 445,293 440,733 73.4% 4,560 99.0% 155,049Jordan Middle School 2- Improvements 19,891,564 18,744,122 7,756,761 39.0% 10,987,361 41.4% 1,147,442J.L.S Middle School - Program Management- MS Pre-Design 18,799 18,799 18,408 97.9% 391 97.9% 0J.L.S Middle School 1 - Interim Classrooms 446,844 400,612 384,196 86.0% 16,416 95.9% 46,232 J.L.S Middle School 2- Improvements 17,184,699 15,313,722 4,683,949 27.3% 10,629,773 30.6% 1,870,977Terman Middle School - Program Management- MS Pre-Design 18,799 18,799 18,423 98.0% 376 98.0% 0Terman Middle School 1- Improvements 13,312,972 12,690,099 7,217,407 54.2% 5,472,692 56.9% 622,873PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 98,480 86,875 59.9% 11,605 88.2% 46,520Addison Elementary School 1-Phase I 21,267 21,267 21,267 100.0% 0 100.0% 0Duveneck Elementary School 1-Phase I 11,088,759 2,359,557 1,272,933 11.5% 1,086,624 53.9% 8,729,202Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.6% 21,897,265Fairmeadow Elementary School 1- Phase I 9,543,751 8,982,182 3,387,429 35.5% 5,594,753 37.7% 561,569Hoover Elementary School 1-Phase I 70,550 70,550 57,165 81.0% 13,385 81.0% 0Ohlone Elementary School 1- Phase I 11,667,965 11,043,679 10,103,524 86.6% 940,155 91.5% 624,286Elementary Schools 1 - Elementary Classroom Improvements 2,004,889 1,872,067 1,863,782 93.0% 8,285 99.6% 132,822Elementary Schools - Reserved 33,457,557 0 0 0.0% 0 0.0% 33,457,557PAUSD - Program Management 8,481,932 6,565,381 5,163,045 60.9% 1,402,336 78.6% 1,916,551PAUSD - Technology * 8,238,258 7,730,206 7,639,780 92.7% 90,426 98.8% 508,052PAUSD - Technology -Reserved* 5,669,108 0 0 0.0% 0 0.0% 5,669,108PAUSD - Reserved 5,759,069 0 0 0.0% 0 0.0% 5,759,069525 San Antonio -Property Acquisition 8,500,000 8,500,000 8,500,000 100.0% 0 100.0% 0Bond Issuance Cost 1,840,700 1,840,700 1,840,700 100.0% 0 100.0% 0Total357,785,709 187,879,007 115,782,309 72,096,698 169,906,702* PAUSD-Technology budget for FY 12-13 will be allocated from Technology reserved after 14th day enrollment during Sep. 2012Prepared by: Business Services Department based on QSS accounting SystemCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond9/30/2012Percent of ExpendedContract BalanceExpenditures Budget Balance Page | 6   Gunn High School   New Classroom Buildings A & B  A. PROJECT STATUS    BRCO Constructors removed and replaced the concrete slab of  the second floor slabs at the Math English building, due to  missing reinforcing steel in the initial deck pour.  Also, plumbing  and electrical rough‐in continued throughout both buildings.  At  the World Language Building, BRCO continued with stucco  installation.  The windows and metal roof and gutters were also  installed.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4    D. PROJECT OVERVIEW:   The World Languages building is two months behind schedule, but occupancy is still planned for Winter  break 2012. The Math & English building is on schedule. The project is currently within budget.  Funding  State Funds $0  Strong Schools Bond Funds $25,035,200  Other Funding $0  Total $25,035,200    Budget  Salaries and Benefits $13,253  Supplies $0  Contracts & Services $4,466,982  Construction & Equipment $20,482,302  Soft Costs Contingency $72,664  Total $25,035,200    Percent of Budget Expended 45.7%    Change Order Contingency   Starting Contingency Balance $ 1,763,200   Remaining Contingency Balance $ 1,602,729   Percent of Changes 9.9%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010     Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA May 27, 2011    Bid Opening July 13, 2011    Award of Contract (1) July 22, 2011    Notice to Proceed August 24, 2011    Substantial Completion May 29, 2013*    Planned Occupancy August 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 7   Gunn High School  Phase I – Parking and Drop‐off Sitework Improvement  A. PROJECT STATUS    DLM will meet with the City of Palo Alto and County of Santa Clara  to review ingress and egress requirements along Miranda Ave.   After review with the City of Palo Alto, DLM will present their  recommended plan to the site committee in November 2012.   Construction will commence after the completion of classroom  building A.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:   Phase I, Miranda Ave. parking and drop‐off design scheduled to meet with City of Palo Alto for off‐site  improvements and requirements.  Funding  State Funds $0  Strong Schools Bond Funds $3,940,000  Other Funding $0  Total $3,940,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $898,978  Construction & Equipment $2,919,840  Soft Costs Contingency $121,182  Total $3,940,000    Percent of Budget Expended 3.1%  Current Phase: Conceptual Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) December 18, 2012*  BOE Approval January 15, 2013*    Submit to DSA March 21, 2013*     Approval by DSA June 2, 2013*    Authorize to Bid (2) June 11, 2013*  BOE Approval June 25, 2013*    Bid Opening July 31, 2013*    Award of Contract (1) August 7, 2013*    Notice to Proceed August 16, 2013*    Substantial Completion February 15, 2014*      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 8   Gunn High School   New Gymnasium   A. PROJECT STATUS    S.J. Amoroso continued interior painting, installation of exterior  plaster, and windows.  Structural steel was installed for the new  canopy to the existing gym building and installation of reinforcing  steel continued on the ramps.  DSA continues to review the  bleacher submittal therefore occupancy of the gym will occur after  the installation of the bleachers.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:   The project is four months behind the original schedule, so occupancy of the gym is now anticipated in  April 2013.  The project is currently within budget.  Funding  State Funds $0  Strong Schools Bond Funds $12,914,800  Other Funding $0  Total $12,914,800    Budget  Salaries and Benefits $0  Supplies $1,001  Contracts & Services $2,677,293  Construction & Equipment $10,158,210  Soft Costs Contingency $78,296  Total $12,914,800    Percent of Budget Expended 54.0%    Change Order Contingency   Starting Contingency Balance $834,700   Remaining Contingency Balance $559,355   Percent of Changes 32.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA May 27, 2011    Bid Opening July 13, 2011    Award of Contract (1) July 20, 2011    Notice to Proceed August 1, 2011    Substantial Completion March 21, 2013*    Planned Occupancy April 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 9   Palo Alto High School   Athletic Stadium Improvements   A. PROJECT STATUS    Taisei (TCC) completed the concessions building for occupancy,  with final finishes and punchlist corrections wrapping up in  September.  Work will resume with the demolition of the  bleachers, press box and existing snack shack in late November  2012, after football season is completed.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.13    D. PROJECT OVERVIEW:   This concessions building is complete and occupied September 10, 2012.  The project is on hold as  planned until the bleacher replacement work begins after the 2012 Football season.  Funding  State Funds $0  Strong Schools Bond Funds $5,090,000  Other Funding $0  Total $5,090,000    Budget  Salaries and Benefits $882  Supplies $0  Contracts & Services $842,156  Construction & Equipment $4,221,162  Soft Costs Contingency $25,800  Total $5,090,000    Percent of Budget Expended 57.8%    Change Order Contingency   Starting Contingency Balance $310,200   Remaining Contingency Balance $284,737   Percent of Changes 9.2%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) January 26, 2010  BOE Approval February 9, 2010    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) February 22, 2011  BOE Approval March 8, 2011    Submit to DSA April 4, 2011    Authorize to Bid (2) June 28, 2011  BOE Approval July 19, 2011    Approval by DSA July 26, 2011     Bid Opening December 1, 2011    Award of Contract (1) December 13, 2011    Notice to Proceed January 4, 2012    Substantial Completion ‐ Concession  August 31, 2012  Planned Occupancy ‐ Concessions September 10, 2012    Bleachers March 1, 2013*  * Anticipated Dates – Subject to Change  ()Denotes number ofBoardofEducation Readings Page | 10   Palo Alto High School   Classroom Building and Media Arts   A. PROJECT STATUS     TCC continued site activities on the new Math/Social Sciences  building, including grading, heating and cooling piping and concrete  curb installation.  At the interior of the Math/Social Sciences  building, installation continued on the mechanical and electrical  systems and wall and ceiling framing.  At the Media Arts building,  the second floor deck railing installation commenced and  mechanical piping to classroom air handlers are in progress.                     B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   The project is three months behind schedule so occupancy is now anticipated in January 2014.  The  project is currently within budget.  Funding  State Funds $0  Strong Schools Bond Funds $37,140,000  Other Funding $0  Total $37,140,000    Budget  Salaries and Benefits $14,721  Supplies $5,654  Contracts & Services $7,066,446  Construction & Equipment $29,734,346  Soft Costs Contingency $318,834  Total $37,140,000    Percent of Budget Expended 47.8%    Change Order Contingency   Starting Contingency Balance $2,515,000   Remaining Contingency Balance $2,212,835   Percent of Changes 12.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA April 28, 2011    Bid Opening June 30, 2011    Award of Contract (1) July 12, 2011    Notice to Proceed August 4, 2011    Substantial Completion September 20, 2013*    Planned Occupancy January, 2014*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 11   Palo Alto High School  Performing Arts Center (PAC)  A. PROJECT STATUS    DLM submitted 50% construction documents on September 22, 2012 for  district backcheck of DD comments.  DLM continued working construction  documents with submission to DSA anticipated in December 2012.                                         B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.11    D. PROJECT OVERVIEW:   Project is proceeding on schedule and within budget.      Funding  State Funds $0  Strong Schools Bond Funds $24,395,049  Other Funding $0  Total $24,395,049    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $4,481,640  Construction & Equipment $19,745,000  Soft Costs Contingency $168,409  Total $24,395,049    Percent of Budget Expended 2.1%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (3) June 14, 2011  BOE Approval December 13, 2011  BOE Approval January 17, 2012    Submit to DSA December 19, 2012*    Approval by DSA August 27, 2013*    Authorize to Bid (2) August 20, 2013*  BOE Approval September 9, 2013*    Bid Opening October 22, 2013*    Award of Contract (1) October 28, 2013*    Notice to Proceed November 11, 2013*    Substantial Completion May 13, 2015*    Planned Occupancy August 17, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 12   Palo Alto High School  Haymarket and Tower Building Improvements    A. PROJECT STATUS     Bids for the tower building window replacement were opened on  September 7, 2012, and Pinguelo Construction was the apparent low  bidder.  BOE award occurred on September 18, 2012.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   Project completed on schedule and within budget.    Funding  State Funds $0  Strong Schools Bond Funds $1,500,000  Other Funding $0  Total $1,500,000    Budget  Salaries and Benefits $0  Supplies $400  Contracts & Services $179,000  Construction & Equipment $1,289,600  Soft Costs Contingency $31,000  Total $1,500,000    Percent of Budget Expended 27.6%    Change Order Contingency   Starting Contingency Balance $39,200   Remaining Contingency Balance $33,930   Percent of Changes 1.2%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA May 25, 2012    Authorize to Bid (2) April 24, 2012  BOE Approval May 6, 2012    Approval by DSA August 24, 2012    Bid Opening September 7, 2012    Award of Contract (1) September 18, 2012    Notice to Proceed October 15, 2012*    Substantial Completion January 1, 2013*      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 13   Jordan Middle School   A. PROJECT STATUS    S.J. Amoroso continued work on the new classroom and new  cafetorium buildings. At both buildings, exterior work  continued with roofing, lath and plaster, and window system  installation.  The new classroom building interior work  included drywall installation and paint.  Mechanical system  rough‐in continued at the interior of the cafetorium.  The two  new music classrooms are nearing completion with the  installation of casework and ceiling systems.                     B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5    D. PROJECT OVERVIEW:   The project is proceeding on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $19,891,546  Other Funding $0  Total $19,891,546    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,635,718  Construction & Equipment $16,007,031  Soft Costs Contingency $248,815  Total $19,891,564    Percent of Budget Expended 39.0 %    Change Order Contingency   Starting Contingency Balance $1,398,700   Remaining Contingency Balance $1,374,699   Percent of Changes 0.2%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) March 23, 2010  BOE Approval April 27, 2010    Submit to DSA December 21, 2010     Authorize to Bid (2) June 28, 2011  BOE Approval July 19, 2011    Approval by DSA October 5, 2011    Bid Opening December 8, 2011    Award of Contract (1) December 13, 2011    Notice to Proceed December 27, 2011    Substantial Completion August 1, 2013*    Planned Occupancy August 26, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 14   J.L. Stanford Middle School   A. PROJECT STATUS     Sausal Corporation continued work on the structural foundation of  the new two‐story classroom.  Concrete footings were set in place  with the concrete pour for the slab on grade scheduled next  month.  Work continued on underground utility installation of  electrical and plumbing systems below the slab.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:   The project is proceeding on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $17,184,699  Other Funding $0  Total $17,184,699    Budget  Salaries and Benefits $0  Supplies $3,458  Contracts & Services $3,503,856  Construction & Equipment $13,421,500  Soft Costs Contingency $255,885  Total $17,184,699    Percent of Budget Expended 27.3%    Change Order Contingency   Starting Contingency Balance $1,057,800   Remaining Contingency Balance $1,054,004   Percent of Changes 0.04%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (3) June 1, 2010  BOE Approval June 22, 2010  BOE Approval (Sitework) September 28, 2010    Submit to DSA May 6, 2011     Authorize to Bid (2) November 29, 2011  BOE Approval December 13, 2011    Approval by DSA January 24, 2012    Bid Opening May 3, 2012    Award of Contract (1) May 8, 2012    Notice to Proceed May 30, 2012    Substantial Completion August 24, 2013*    Planned Occupancy January 1, 2014*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings Page | 15   Terman Middle School   A. PROJECT STATUS    Hagensen Pacific continued work on exterior lath and window  installation at new Library Building.  At the new Administration  building and new Drama classroom work continued on interior  finishes and site work.  Both buildings are anticipated to be  complete ahead of schedule, with move in scheduled during  winter break. Plumbing, electrical and automated controls  continued at the furnace exterior closets for classroom wings A,  C, and H.  Drywall installation is complete in the gymnasium and  the exercise room.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12    D. PROJECT OVERVIEW:   The project is proceeding on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $13,312,972  Other Funding $0  Total $13,312,972    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,664,654  Construction & Equipment $10,517,515  Soft Costs Contingency $130,803  Total $13,312,972    Percent of Budget Expended 54.2%    Change Order Contingency   Starting Contingency Balance $929,900   Remaining Contingency Balance $479,228   Percent of Changes 4.8%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) May 11, 2010  BOE Approval May 25, 2010    Submit to DSA December 21, 2010    Authorize to Bid (2) June 28, 2011  BOE Approval July 19, 2011    Approval by DSA September 1, 2011    Bid Opening December 6, 2011    Award of Contract (1) December 13, 2011    Notice to Proceed December 27, 2011    Substantial Completion August 7, 2013*    Planned Occupancy September 4, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 16   Fairmeadow Elementary School   New Classroom Building and Modernization   A. PROJECT STATUS     Best Contracting Services (BCS) is working on the CMU wall  installation of the new classroom building. Two CMU walls on the  second floor failed the shear test, so Best had to rebuild the two  walls. Interior framing and mechanical, electrical and plumbing  rough‐in continued on the first floor.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   The project is proceeding on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $9,543,751  Other Funding $0  Total $9,543,751    Budget  Salaries and Benefits $0  Supplies $3,132  Contracts & Services $1,938,402  Construction & Equipment $7,500,180  Soft Costs Contingency $102,037  Total $9,543,751    Percent of Budget Expended 35.5%    Change Order Contingency   Starting Contingency Balance $642 ,300   Remaining Contingency Balance $642,300   Percent of Changes 0.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) October 13, 2009  BOE Approval October 27, 2009    Conceptual Design (2) March 23, 2010  BOE Approval April 6, 2010    Schematic Design (2) September 14, 2010  BOE Approval September 28, 2010    Submit to DSA April 18, 2011     Authorize to Bid (2) October 11, 2011  BOE Approval October 25, 2011    Approval by DSA November 14, 2011    Bid Opening December 5, 2011    Award of Contract (1) December 13, 2011    Notice to Proceed January 3, 2012    Substantial Completion August 5, 2013*    Planned Occupancy August 20, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 17   Duveneck Elementary School   New Classroom Buildings and Modernization  A. PROJECT STATUS    Gelfand submitted construction documents for the project to  DSA on February 27, 2012, and has received comments back  from DSA.  Gelfand is incorporating DSA and constructability  review comments.  DSA backcheck is scheduled for November  28, 2012.                     B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   The project is proceeding on schedule and within budget.      Funding  State Funds $0  Strong Schools Bond Funds $11,088,759  Other Funding $0  Total $11,088,759    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,159,389  Construction & Equipment $8,803,087  Soft Costs Contingency $126,283  Total $11,088,759    Percent of Budget Expended 11.5%  Current Phase: DSA Review   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) December 14, 2010  BOE Approval January 11, 2011    Schematic Design (2) June 14, 2011  BOE Approval June 28, 2011    Submit to DSA February 27, 2012     Approval by DSA November 28, 2012*    Authorize to Bid (2) November 24, 2012*  BOE Approval December 13, 2012*    Bid Opening January 22, 2013*    Award of Contract (1) January 27, 2013*    Notice to Proceed February 5, 2013*    Substantial Completion June 16, 2014*    Planned Occupancy August 1, 2014*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 18   Technology Improvements   A. PROJECT STATUS     Implementation of the district‐wide Voice‐over‐IP (VoIP) telephone system is complete.   Installation of access points to increase the broadband of wireless access is also  complete.  Installation of wireless antennas at each school is planned to  commence in late fall 2012.      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:   VOIP implementation and wireless access point installation completed.         Funding  State Funds $0  Strong Schools Bond Funds $8,238,258  Other Funding $0  Total $8,238,258    Budget  Salaries and Benefits $0  Supplies & Computers $4,603,848  Contracts & Services $539,269  Construction & Equipment $3,095,142  Soft Costs Contingency $0  Total $8,238,258    Percent of Budget Expended 92.7%    Current Phase: N/A   Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 19   Ohlone Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS     Move‐in to the new building and other existing classrooms occurred in  December 2011.  Students occupied the new building on January 3, 2012.                              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   Occupancy occurred on January 3, 2012.  Project completed on schedule and within budget.    Funding  State Funds $0  Strong Schools Bond Funds $11,667,965  Other Funding $0  Total $11,667,965    Budget  Salaries and Benefits $7,196  Supplies $44,253  Contracts & Services $2,364,457  Construction & Equipment $9,189,461  Soft Costs Contingency $62,598  Total $11,667,965    Percent of Budget Expended 86.2%    Change Order Contingency   Starting Contingency Balance $748,400   Remaining Contingency Balance $602,714   Percent of Changes 1.9%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –January 3, 2012    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) March 3, 2009  BOE Approval March 17, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA November 24, 2009    Authorize to Bid (2) April 27, 2010  BOE Approval May 11, 2010    Approval by DSA May 18, 2010    Bid Opening July 13, 2010    Award of Contract (1) August 3, 2010    Notice to Proceed August 19, 2010    Substantial Completion November 18, 2011    Planned Occupancy January 3, 2012    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 20   Site Acquisition  525 San Antonio Rd   A. PROJECT STATUS    This site has been leased to Athena Academy.  Athena  Academy will begin to make rent payments once their  conditional use permit is approved by the City of Palo  Alto.                             B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   The site has been leased to Athena Academy.  Funding  State Funds $0  Strong Schools Bond Funds $8,500,000  Other Funding $0  Total $8,500,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $8,500,000  Construction & Equipment $0  Soft Costs Contingency $0  Total $8,500,000    Percent of Budget Expended 100.0%  Current Phase: N/A   Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 21   Jordan Middle Schools ‐ Interim Classrooms  A. PROJECT STATUS    The portables were installed and moved into for fall 2011. All  documents were submitted to DSA for closeout November 2, 2011.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:   This project completed ahead of schedule and under budget.   Move in occurred on September 30, 2011.      Funding  State Funds $0  Strong Schools Bond Funds $392,120  Other Funding $208,222  Total $600,342    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $180,286  Construction & Equipment $419,292  Soft Costs Contingency $764  Total $600,342    Percent of Budget Expended 70.4%*    *Budget previously expended     Current Phase: Move‐in   Schedule:  Approval by DSA June 16, 2011    Authorize to Bid (2) June 14, 2011  BOE Approval June 28, 2011    Bid Opening July 14, 2011    Award of Contract (1) July 20, 2011    Notice to Proceed July 27, 2011    Substantial Completion September 20, 2011    Occupancy September 30, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 22   Gunn High School  Air Conditioning of Existing Buildings  A. PROJECT STATUS    Best Contracting Services Inc. completed the installation of air  conditioning units and cool roof coating summer 2011.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.7    D. PROJECT OVERVIEW:   Project has been closed‐out.    Funding  State Funds $0  Strong Schools Bond Funds $2,600,000  Other Funding $0  Total $2,600,000    Budget  Salaries and Benefits $1,919  Supplies $0  Contracts & Services $454,160  Construction & Equipment $2,120,580  Soft Costs Contingency $22,891  Total $2,600,000    Percent of Budget Expended 80.9%  Current Phase: Completed   Schedule:  Architect Contract (2) March 27, 2010  BOE Approval April 6, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA October 20, 2010    Approval by DSA February 10, 2011    Authorize to Bid (2) February 22, 2011  BOE Approval March 8, 2011    Bid Opening March 28, 2011    Award of Contract (1) April 8, 2011    Notice to Proceed April 11, 2011    Substantial Completion August 8, 2011      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 23   J.L. Stanford Middle School ‐ Interim Classrooms  A. PROJECT STATUS    Coulter Construction completed the work on the relocated  portables in August 2011.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:   Project completed on schedule and is currently in close‐out.            This portable relocation project funded by main  JLS project.  Refer to pg. 14    Current Phase: Occupancy ‐August 11, 2011    Schedule:  Approval by DSA April 19, 2011  Jordan Project June 16, 2011     Authorize to Bid (2) May 10, 2011  BOE Approval May 24, 2011    Bid Opening June 1, 2011    Award of Contract (1) June 13, 2011    Notice to Proceed June 20, 2011    Substantial Completion August 8, 2011    Planned Occupancy August 15, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 24   Fairmeadow Elementary School  Portable Relocation Project  A. PROJECT STATUS     Relocation of the portable was complete on August 8, 2011.  All  documents were submitted to DSA for closeout October 11, 2011.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 6.4    D. PROJECT OVERVIEW:   Project completed ahead of schedule on August 8, 2011.             This portable relocation project funded by main  JLS project.  Refer to pg. 14  Current Phase: Occupancy ‐August 8, 2011    Schedule:  Architect Contract (2) February 15, 2011  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA March 3, 2011     Approval by DSA March 3, 2011    Authorize to Bid (2) May 11, 2011  BOE Approval May 24, 2011    Bid Opening June 14, 2011    Award of Contract (1) June 14, 2011    Notice to Proceed June 20, 2011    Substantial Completion August 1, 2011    Planned Occupancy August 8, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 25   Elementary Classroom Improvements  Interactive Whiteboards and Sound Assist System Installation  A. PROJECT STATUS    Coulter Construction installed SmartBoards and Lightspeed sound assist  systems, and completed the installation April 29, 2011.  Phase 4 and 5  schools were the final elementary schools to receive interactive  whiteboards and sound assist systems.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:   All SmartBoards and Lightspeed sound systems installed.      Funding  State Funds $0  Strong Schools Bond Funds $2,004,889  Other Funding $0  Total $2,004,889    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $325,488  Construction & Equipment $1,679,401  Soft Costs Contingency $0  Total $2,004,889    Percent of Budget Expended 93.0%    Current Phase: Complete ‐May 15, 2011    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) November 9, 2010  BOE Approval November 23, 2010    Bid Opening February 25, 2011    Award of Contract (1) March 8, 2011    Notice to Proceed March 9, 2011    Completion May 15, 2011      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 26   Palo Alto High School   Multi‐Use Field  A. PROJECT STATUS    The fields were available for play on February 1, 2011, and final  change order negotiations completed on March 9, 2011.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.14    D. PROJECT OVERVIEW:   Field was open for use on February 1, 2011.     Funding  State Funds $0  Strong Schools Bond Funds $2,609,680  Other Funding $1,007,255  Total $3,616,935    Budget  Salaries and Benefits $0  Supplies $1,506  Contracts & Services $698,293  Construction & Equipment $2,916,682  Soft Costs Contingency $454  Total $3,616,935     Percent of Budget Expended 100.0%    Change Order Contingency   Starting Contingency Balance $269,300   Remaining Contingency Balance $230,579   Percent of Changes 1.7%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –February 1, 2011    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 18, 2008  BOE Approval December 09, 2008    Submit to DSA March 19, 2009     Approval by DSA September 30, 2009    Authorize to Bid (2) February 24, 2009  BOE Approval March 17, 2009    Bid Opening March 16, 2010    Award of Contract (1) April 7, 2010    Notice to Proceed June 1, 2010    Substantial Completion January 31, 2011    Planned Occupancy February 1, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 27   Gunn High School  Industrial Arts Addition and Renovation  A. PROJECT STATUS    This facility was available for instruction in January 2010. DSA closeout  received on July 18, 2011.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11    D. PROJECT OVERVIEW:   The building occupied as scheduled, and the project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,082,402  Other Funding $0  Total $5,082,402    Budget  Salaries and Benefits $1,061  Supplies $88,985  Contracts & Services $1,000,861  Construction & Equipment $3,991,495  Soft Costs Contingency $0  Total $5,082,402    Percent of Budget Expended 99.3%    Change Order Contingency   Starting Contingency Balance $349,000   Remaining Contingency Balance $141,967   Percent of Changes 41.6%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –January 4, 2010    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA June 17, 2008     Approval by DSA December 24, 2008    Authorize to Bid (2) October 14, 2008  BOE Approval October 28, 2008    Bid Opening December 16, 2008    Award of Contract (1) December 24, 2008    Notice to Proceed January 6, 2009    Substantial Completion November 25, 2009    Planned Occupancy January 4, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 28   Gunn High School  Aquatic Center  A. PROJECT STATUS    This facility was available for use in July 2009, and has been closed  out with DSA.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.12    D. PROJECT OVERVIEW:   This project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $4,865,423  Other Funding $0  Total $4,865,423    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $647,169  Construction & Equipment $4,218,253  Soft Costs Contingency $0  Total $4,865,423    Percent of Budget Expended 99.9%    Change Order Contingency   Starting Contingency Balance $389,887   Remaining Contingency Balance $195,148   Percent of Changes 49.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –June 15, 2009    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA December 11, 2007     Approval by DSA April 24, 2008    Authorize to Bid (2) April 8, 2008  BOE Approval April 22, 2008    Bid Opening May 28, 2008    Award of Contract (1) June 4, 2008    Notice to Proceed December 6, 2008    Substantial Completion June 15, 2009    Planned Occupancy June 15, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 29   Middle School Pre‐Design  Jordan, J.L. Stanford and Terman  A. PROJECT STATUS    AEDIS presented recommended concept plans for each campus to the  Board of Education for approval on September 8, which became the  program documents for the new projects at each campus.  These  projects for pre‐design work have been closed, and funds will be  transferred to the program contingency on June 14, 2011.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12    D. PROJECT OVERVIEW:   This project has been completed. Board approval received on September 8, 2009. Funding  State Funds $0  Strong Schools Bond Funds $56,488  Other Funding $0  Total $56,488    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $56,488  Construction & Equipment $0  Soft Costs Contingency $0  Total $56,488    Percent of Budget Expended 96.8%    Current Phase: Complete   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 30   Garland Elementary School  Campus Modernization  A. PROJECT STATUS    The Board of Education has put new development for Garland on  hold until a growth plan is established for the elementary schools.   The board voted to terminate the lease with Stratford School in  June 2011. Discussions with the Board on future plans for growth  at the elementary schools are ongoing.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10    D. PROJECT OVERVIEW:   This project has been placed on hold. Funding  State Funds $0  Strong Schools Bond Funds $22,178,544  Other Funding $0  Total $22,178,544    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,915,789  Construction & Equipment $17,400,000  Soft Costs Contingency $862,755  Total $22,178,544    Percent of Budget Expended 1.3%  Current Phase: On Hold   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) February 10, 2009  BOE Approval February 24, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 31   High School Master Plan  Palo Alto HS and Gunn HS  A. PROJECT STATUS    The Board of Education (BOE) approved the master plans for both  high schools, and these projects have been closed, with funds  transferred to the respective campus reserve funds.                    B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14    D. PROJECT OVERVIEW:   Master planning effort complete.                Funding  State Funds $0  Strong Schools Bond Funds $285,387  Other Funding $0  Total $285,387    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $285,387  Construction & Equipment $0  Soft Costs Contingency $0  Total $285,387    Percent of Budget Expended 86.2%  Current Phase: Complete   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Initial Master Plan Approval (2) September 8, 2009  BOE Approval September 22, 2009    Paly CEQA Approval (2) February 9, 2010  BOE Approval February 23, 2010    Gunn Master Plan Update (2) March 23, 2010  BOE Approval April 6, 2010    Gunn CEQA Approval (2) April 27, 2010   BOE Approval May 11, 2010     Master Plan Revision Approval (2) September 14, 2010  Paly MP Revision Approval (2) October 9, 2010  Gunn MP Revision Approval (2) October 12, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 32   Hoover Elementary School  Pre‐Design  A. PROJECT STATUS    This project has been put on hold until a growth plan is established for the  elementary schools.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   Project is currently on hold.                Funding  State Funds $0  Strong Schools Bond Funds $70,550  Other Funding $0  Total $70,550    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $70,550  Construction & Equipment $60  Soft Costs Contingency $0  Total $70,550    Percent of Budget Expended 100.0%  Current Phase: On Hold   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) November 9, 2010  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A  Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 33   Elementary Classroom Improvements  A. PROJECT STATUS    DSA comments were returned to Gelfand for Phase 1 plans that  include new lighting, adding operable windows and coverings,  ventilation, and replacement of ceiling tiles for classrooms at Barron  Park and El Carmelo elementary schools.  The authorization to bid has been placed on hold pending further  discussions with the BOE about elementary growth planning.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:   This project has been placed on hold.          Funding  State Funds $0  Strong Schools Bond Funds $2,004,889  Other Funding $0  Total $2,004,889    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $325,488  Construction & Equipment $1,679,401  Soft Costs Contingency $0  Total $2,004,889    Percent of Budget Expended 93.0%    Phase 1 Schools: Barron Park and El Carmelo  Current Phase:  On Hold    Schedule:  Architect Contract (2) June 8, 2010  BOE Approval June 22, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 9, 2010  BOE Approval December 7, 2010    Submit to DSA December 23, 2010     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  OHS WEST:260388860.1 A-1 EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. Numbers Added A-2 OHS WEST:260388860.1 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. A-3 OHS WEST:260388860.1 3. GUNN HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Demolish old library building. 3. Replace temporary classrooms with permanent classrooms. 4. Construct additional restrooms. 5. Construct second gymnasium. 6. Construct new soccer field. 7. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 9. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 10. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 11. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 12. Replace swimming pool with new 35-meter pool, pool equipment and support structures, pool decking, bleachers, storage, restrooms, showers, associated equipment. 13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace athletic equipment. 14. Modernize football stadium, including new bathrooms and concession stands. A-4 OHS WEST:260388860.1 4. PALO ALTO HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Construct additional restrooms. 4. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 6. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 7. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 8. Library modernization and building interior improvements, including infrastructure and major building system upgrades. 9. Renovation or replacement of the Tower Building to accommodate administration, classroom and program support space. 10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility improvements; construction of new restrooms; install new roofing; replace doors and windows; replace gymnasium floors and athletic equipment, bleachers and renovation of interior. Renovation or replacement of weight training facility. 11. Construct new theater building. 12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing and storage. 13. Modernize football stadium, including replace bleachers; new bathrooms and concession stands. 14. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. A-5 OHS WEST:260388860.1 5. OTHER DISTRICT-WIDE PROJECTS Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and equipment for all classrooms, athletic facilities and other facilities, as needed. 1. Replace existing or acquire new computers, technology and related equipment on an ongoing basis. 2. Establish a planned maintenance fund to address maintenance work expected to be needed to all District facilities on an ongoing basis (other than as may be necessary for current maintenance, operation or repairs), in order to implement the District’s comprehensive facilities maintenance plan. 3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease- purchase arrangements, or execute purchase option under a lease for any of these authorized facilities. 4. If and as opportunities become available, and to the extent the Board of Education determines that bond funds are available for the purpose, acquisition of land and other interests in real property for future school buildings and other District facilities, and construction of such facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise listed. 5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field equipment and facilities (including nets, basketball standards, goals and goalposts, backstops), field lighting, etc. 6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS 1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead, etc., where necessary. 2. Address unforeseen conditions revealed by construction/modernization (including plumbing or gas line breaks, dry rot, seismic, structural, etc.). 3. Other improvements required to comply with existing building codes, including the Field Act, and access requirements of the Americans with Disabilities Act (ADA). 4. Site preparation/restoration in connection with new construction, renovation or remodeling, or installation or removal of relocatable classrooms, including ingress and egress, demolition of existing structures, removing, replacing, or installing irrigation and drainage, utility lines (such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any necessary easements, licenses, or rights of way to the property. 5. Rental or construction of storage facilities and other space on an interim basis, as needed to accommodate construction materials, equipment, and personnel, and interim classrooms (including relocatables) for students and school functions or other storage for classroom materials displaced during construction. A-6 OHS WEST:260388860.1 7. RENOVATION/MODERNIZATION (DEFINED) For purposes of the Bond Project List, renovation and modernization projects are intended to restore the building systems and infrastructure, weather protections, finishes, and technology, or reallocate and reorganize space, to a condition that will provide a sustainable, functional educational and administrative environment for future years, comparable to new construction. Renovation projects may include, but are not limited to nor necessarily encompass, all of the following, depending upon the age, condition and needs of each particular school facility: 1. upgrade electrical, communication, fire alarm, and similar building systems as well as main power service and distribution, which may include active and passive solar power and heating system acquisition, installation and construction 2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply, meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within buildings and sites and to connect with city supply and drainage systems 3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient heating and air cooling systems (HVAC), including installing energy management systems (EMS); 4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and fixtures, as necessary; 5. Repair, modify and construct structural elements of the existing structure as necessary; 6. Replace or repair aging roofs with similar materials or District standard materials; 7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes, doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces (including white boards, marker boards, tack boards, television mounts, scoreboards, fire extinguishers, kitchen cabinets/equipment, etc.); 8. Upgrade, modify and construct restroom facilities; 9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24 requirements; 10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood siding, paint, etc.); replace doors and windows 11. Modify, expand, separate, convert and construct school support areas; staff work and lunch areas; and educational areas to provide adequate, functional environments; 12. Modify, replace and construct functional components of altered or replaced building components (including rainwater leaders, fascias, mansards, etc.); ™ For any project involving renovation, modernization, remodeling or rehabilitation of a building or the major portion of a building, the District may proceed with new replacement construction instead (including any necessary demolition), if the Board of Education determines that replacement and new construction is more practical than rehabilitation and renovation, considering the building’s age, condition, expected remaining life, comparative cost, and other relevant factors.