Monthly Reports 2011-09 (Sep)
MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
September 2011
Current Strong Schools Bond
Capital Improvement Projects
Prepared by
O’Connor Construction Management, Inc.
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Capital Projects
Gunn High School – New Classroom Buildings A & B page 6
Gunn High School – Parking and Drop‐off Sitework Improvement page 7
Gunn High School – New Gymnasium page 8
Palo Alto High School – Athletic Stadium Improvements page 9
Palo Alto High School – Project Classroom Building and Media Arts page 12
Palo Alto High School – Performing Arts Center page 11
Palo Alto High School – Haymarket and Tower Building Boiler Replacement page 12
Jordan Middle School page 13
Jordan Middle School – Interim Classrooms page 14
J.L. Stanford Middle School page 15
Terman Middle School page 16
Fairmeadow Elementary School page 17
Ohlone Elementary School page 18
Duveneck Elementary School page 19
Technology page 20
Completed Capital Projects
Gunn High School – Air Conditioning of Existing Buildings page 21
J.L. Stanford Middle School – Interim Classrooms page 22
Fairmeadow Elementary School – Portable Relocation page 23
Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 24
Palo Alto High School – Multi‐use Field page 25
Gunn High School – Industrial Arts Renovation page 26
Gunn High School – Aquatic Center page 27
Middle School Pre‐Design page 28
Inactive Capital Projects
Garland Elementary School page 29
Elementary School Teaching Walls – Phase 1 Schools page 30
High School Master Plan page 31
Hoover Elementary School page 32
Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo page 33
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
Gunn High School – New Classroom Buildings A & B
Clearing and grubbing for buildings A and B is complete. Utility rerouting at building A is underway as well as
rough grading for the building pads. The concrete contractor has mobilized and will begin the installation of below
grade foundation systems as soon as the building pads are constructed.
Gunn High School – Parking and Drop‐off Sitework Improvement
Design for the parking and drop‐off improvements will recommence in conjunction with the planning of group 2
projects.
Gunn High School – New Gymnasium
Demolition of the existing tennis courts and basketball courts is complete. The contractor has brought in material
to balance the site and has started the process of over‐excavating and re‐compacting the building pad.
Palo Alto High School – Athletics Stadium Improvements
The Stadium subcommittee and facilities steering committee (FSC) approved a budget augmentation for the
project, which is being consolidated into one bid package. The project will go out to bid in November 2011, with
construction beginning in January 2012. The structural design for the bleachers will be submitted by the successful
bidder for DSA approval, and will likely be installed after the 2012 football season.
Palo Alto High School – Classroom Building and Media Arts Building
Demolition of the existing utilities and pavement is complete. Utility trenches have been backfilled and the
building pads are complete. New storm drain installation and foundation excavation will commence in October.
Palo Alto High School – Performing Arts Center (PAC)
On August 3, 2011 DLM presented a design scheme to the FSC with a layout of 575 seats as requested by the BOE.
This scheme would have resulted in a project budget of $24.9M. FSC members requested further discussions with
the BOE for clarifications on the size of facility. A meeting occurred on September 21, 2011 with the performing
arts’ staff and the Superintendent, and it was agreed to investigate options for 540 seat single‐story scheme. DLM
will meet with the subcommittee to review this additional scheme and present it to the FSC and BOE.
Palo Alto High School – Haymarket and Tower Building Boiler Replacement
The FSC approved funds from the Tower building project to be appropriated to replace two failing boilers located
in the basement of Haymarket Theater. Five bids were received for the boiler replacement project on September
28, 2011. Environmental Services Inc. is the apparent low bidder, and a recommendation to the BOE for award will
be made at the October 11, 2011 meeting. Proposals have been received for inspector of record, special
inspection and environmental inspectors and we will be processing them in the month of October. Construction is
anticipated to start in October.
Jordan Middle School
The additional campus‐wide ADA compliance improvements required by DSA has delayed their approval until early
October 2011. The project is now anticipated to bid in late October 2011, with construction to commence in
January 2012. Fifteen contractors were prequalified to provide bids on this project.
Jordan Middle School ‐ Interim Classrooms
The portables have been installed, and were cleaned and ready for occupancy a week ahead of schedule. School
staff requested additional time for packing and moved in on September 30, 2011. DSA closeout has commenced.
The project is funded with both bond funds and impact fees.
Page | 4
J.L. Stanford Middle School
Approval from DSA is anticipated in early 2012. The project is currently within budget. Final estimates, and
constructability reviews will occur in fall 2011.
Terman Middle School
DSA approval was received on September 1, 2011, and bidding is scheduled to commence in October 2011.
Construction is expected to begin in December 2011. Recently completed construction document estimates show
the project to be over budget, therefore final alternates are being considered to provide a strategy to maintain the
project budget. Fifteen contractors were prequalified to provide bids on this project.
Fairmeadow Elementary School – New Classroom Building and Modernization
Gelfand received all DSA comments and has scheduled backcheck appointments with DSA on October 25 ‐ 27.
O’Connor is concurrently performing site verification, backchecking constructability review comments and
finalizing front end documents. Prequalification for contractors was publicized on September 23, 2011. The
project is anticipated to go out for bid in November 2011. Construction is planned to begin in early January 2012.
Ohlone Elementary School – New Classroom Building and Modernization
With the modernization work complete, the focus is on completion of the new classroom wing. Mechanical,
electrical, and plumbing trim work is underway, and finishes such as painting, casework, wood trim, and wall
coverings continue. Site irrigation and concrete walkways are in progress. The pavers, landscaping trays and
planters have been installed for the green roof.
Duveneck Elementary School – New Classroom Buildings and Modernization
Gelfand is wrapping up design development documents and anticipates submitting a package for district and
O’Connor review in early October 2011.
Technology
The District purchased computers, utilizing bond funds, throughout the 2010/11 school year. During the year
there was a notable shift from desktops and laptops to handheld devices, primarily at the elementary school level.
At the end of the 2010/11 school year, orders were placed for equipment to be used in the 2011/12 school year.
Implementation of the Voice‐over‐IP (VoIP) telephone system is scheduled to begin at the district office this fall. A
major upgrade to the District's network is currently out for re‐bid, with bids opening extended into October 2011.
COMPLETED CAPITAL PROJECTS
Gunn High School – Air Conditioning of Existing Buildings
Best Contracting Services Inc. completed the installation of air conditioning units and cool roof coating. Project
close‐out has commenced.
J.L. Stanford Middle School ‐ Interim Classrooms
Coulter Construction completed the work on the relocated portables in August. Project close‐out has commenced.
Fairmeadow Elementary School – Portable Relocation
The work on the relocated portable was complete on August 8, 2011. Project close‐out has commenced.
Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems
Installation of SmartBoards and Lightspeed sound assist systems were completed for all elementary school
classrooms and libraries on April 29, 2011.
Palo Alto High School – Multi‐use Field
The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9,
2011.
Page | 5
Gunn High School – Industrial Arts Addition & Renovation
This facility was available for instruction in January 2010. DSA closeout received on July 18, 2011.
Gunn High School – Aquatic Center
This facility was available for use in July 2009, and has been closed out with DSA.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education for approval on
September 8, which became the program documents for the new projects at each campus. These projects for pre‐
design work have been closed, and funds were transferred to the program contingency on June 14, 2011.
INACTIVE CAPITAL PROJECTS
Garland Elementary School Renovation
The Board of Education has put new development for Garland on hold until a growth plan is established for the
elementary schools. The board voted to terminate the lease with Stratford School in June 2011, so that future
plans for growth at the elementary schools can begin on this campus as early as June 2014.
Elementary School Teaching Walls – Phase 1 Schools
The district placed this project on hold after review of the implementation of other classroom improvements, as
recommended by the elementary school principals. This project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary below).
High School Master Plan
The Board of Education (BOE) approved the master plans for both high schools, and these projects have been
closed, with funds transferred to the respective campus reserve funds.
Hoover Elementary School – Pre‐Design
This project has been put on hold until a growth plan is established for the elementary schools.
Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo
DSA comments were returned to Gelfand for Phase 1 plans that include new lighting, adding operable windows
and coverings, ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo
elementary schools. The authorization to bid has been placed on hold pending further discussions with the BOE
about elementary growth planning.
Board Actions in September
September 13, 2011
Consent 3 – Contract with Colbi Technologies, Inc. for School Construction Project Accounting System and Support
Consent 4 – Appointment of Replacement Member to the Citizens’ Oversight Committee for the Strong Schools
Bond
Action 9 – Testing and Inspection Services: (1) Approval of a Pool of Firms to Provide These Services for Strong
Schools Bond Projects; (2) Approval of Ninyo and Moore to Provide These Services for the Gunn Gymnasium and
Classroom Buildings; (3) Approval of HP Inspection, Inc., to Provide These Services for the Paly New Classroom and
Media Arts Buildings; (4) Authorization to Execute Change Orders
September 27, 2011
Consent 6 – Approval of Strong Schools Bond Change Orders
ABCC / AB - C C / BA - BGunn High School - High School Master Plan 142,389 136,008 117,415 82.5%18,593 86.33%6,381Gunn High School 1 - Aquatic Center 4,865,423 4,862,530 4,862,530 99.9%0 100.00%2,893Gunn High School 2 - I.A Building5,082,402 5,049,558 5,045,659 99.3%3,899 99.92% 32,844Gunn High School 3 - AD2- close out5,777 5,7775,777 100.0%0 100.00%0Gunn High School 4 - New classroom Buildings25,035,200 23,877,593 2,875,825 11.5% 21,001,768 12.04% 1,157,607Gunn High School 5 - Parking & Drop Off improvements3,940,000 321,841 101,564 2.6%220,277 31.56% 3,618,159Gunn High School 6- New/Auxiliary Gymnasium12,914,800 11,058,471 1,190,065 9.2%9,868,406 10.76% 1,856,329Gunn High School 7- A/C2,600,000 2,294,678 1,557,496 59.9%737,182 67.87% 305,322Gunn High School - Reserved21,525,08100 0.0%0 0.00% 21,525,081Palo Alto High Schools - High School Master Plan142,998 137,758 128,443 89.8%9,315 93.24%5,240Palo Alto High School 1 - Stadium Field3,626,101 903,407 599,678 16.5%303,729 66.38% 2,722,694Palo Alto High School 2 - Multi-Use Field (Multi-Fund)2,609,680 2,609,680 2,604,765 99.8%4,915 99.81%0Palo Alto high School 3 - New classroom & Media Art Building37,140,000 33,619,793 4,413,605 11.9% 29,206,188 13.13% 3,520,207Palo Alto High School 4 - New Theater17,720,000 1,364,139 221,891 1.3%1,142,248 16.27% 16,355,861Palo Alto High School 5 - Haymarket and Tower Admin. Building800,00000 0.0%0 0.00% 800,000Palo Alto High School - Reserved36,754,76600 0.0%0 0.00% 36,754,766Jordan Middle School -Program Management- MS Pre-Design18,890 18,89017,826 94.4%1,064 94.37%0Jordan Middle Schools 1- Interim Classrooms600,342 478,735 175,191 29.2%303,544 36.59% 121,607Jordan Middle School 2- Improvements17,943,194 2,842,475 1,447,202 8.1%1,395,273 50.91% 15,100,719J.L.S Middle School - Program Management- MS Pre-Design18,799 18,79918,408 97.9%391 97.92%0J.L.S Middle School 1 - Interim Classrooms 446,844 399,483 361,713 80.9%37,770 90.55% 47,361 J.L.S Middle School 2- Improvements17,184,699 3,281,355 1,763,543 10.3% 1,517,812 53.74% 13,903,344Terman Middle School - Program Management- MS Pre-Design18,799 18,79918,423 98.0%376 98.00%0Terman Middle School 1- Improvements12,850,071 2,009,744 1,041,859 8.1%967,885 51.84% 10,840,327PAUSD Elementary Schools - Program Management- Elem. Growth Plan145,000 98,48083,550 57.6%14,930 84.84% 46,520Addison Elementary School 1-Phase I5,199,727 21,26721,267 0.4%0 100.00% 5,178,460Briones Elementary School 1-Phase I701,92500 0.0%0 0.00% 701,925Duveneck Elementary School 1-Phase I11,088,757 186,931 183,331 1.7%3,600 98.07% 10,901,826Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3%1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I641,76000 0.0%0 0.00% 641,760Escondido Elementary School 1-Phase I6,202,34300 0.0%0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 1,552,324 796,338 8.5%755,986 51.30% 7,775,176Hays Elementary School 1-Phase I4,793,81400 0.0%0 0.00% 4,793,814Hoover Elementary School 1-Phase I8,575,389 70,55057,165 0.7%13,385 81.03% 8,504,839Nixon Elementary School 1-Phase I802,20000 0.0%0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 10,678,606 6,971,008 59.7% 3,707,598 65.28% 989,359Palo Verde Elementary School 1-Phase I3,482,88500 0.0%0 0.00% 3,482,885Barron Park Elementary School 1-Phase I641,76000 0.0%0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements *8,153,022 2,004,889 1,863,782 22.9%141,107 92.96% 6,148,133Elementary Schools - Reserved5,075,68800 0.0%0 0.00% 5,075,688PAUSD - Program Management6,651,989 4,971,605 3,738,255 56.2% 1,233,350 75.19% 1,680,384PAUSD - Technology 8,212,531 5,059,312 4,632,003 56.4%427,309 91.55% 3,153,219PAUSD - Technology -Reserved5,694,83400 0.0%0 0.00% 5,694,834PAUSD - Reserved7,230,20500 0.0%0 0.00% 7,230,205Bond Issuance Cost1,840,700 1,840,700 1,840,700 100.0%0 100.00%0Total352,294,793 122,075,455 49,036,38973,039,066230,219,338Prepared by: Business Services Department based on QSS accounting SystemSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond9/30/2011Percent of ExpendedContract BalanceExpenditures Budget BalanceCommittedBudget
Page | 6
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
Clearing and grubbing for buildings A and B is complete. Utility
rerouting at building A is underway as well as rough grading for the
building pads. The concrete contractor has mobilized and will begin
the installation of below grade foundation systems as soon as the
building pads are constructed.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
• This project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $25,035,200
Other Funding $0
Total $25,035,200
Budget
Salaries and Benefits $13,253
Supplies $0
Contracts & Services $4,462,881
Construction & Equipment $20,482,302
Soft Costs Contingency $76,764
Total $25,035,200
Percent of Budget Expended 11.5%
Change Order Contingency
• Starting Contingency Balance $ 1,763,200
• Remaining Contingency Balance $ 1,731,006
• Percent of Changes 0.02%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 22, 2011
Notice to Proceed August 24, 2011
Substantial Completion February 23, 2013*
Planned Occupancy April 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 7
Gunn High School
Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
Design for the parking and drop‐off improvements will
recommence in conjunction with the planning of group 2 projects
in fall 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
• Design will recommence with the planning of group 2 projects.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $898,978
Construction & Equipment $2,919,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 2.4%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
New Gymnasium
A. PROJECT STATUS
Demolition of the existing tennis courts and basketball courts is
complete. The contractor has brought in material to balance the site
and has started the process of over‐excavating and re‐compacting the
building pad.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
• This project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $12,914,800
Other Funding $0
Total $12,914,800
Budget
Salaries and Benefits $0
Supplies $1,001
Contracts & Services $2,675,560
Construction & Equipment $10,158,210
Soft Costs Contingency $80,029
Total $12,914,800
Percent of Budget Expended 9.2%
Change Order Contingency
• Starting Contingency Balance $834,700
• Remaining Contingency Balance $834,700
• Percent of Changes 0.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed August 1, 2011
Substantial Completion September 11, 2012*
Planned Occupancy November 15, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Palo Alto High School
Athletic Stadium Improvements
A. PROJECT STATUS
The Stadium subcommittee and facilities steering committee (FSC)
approved a budget augmentation for the project, which is being
consolidated into one bid package. The project will go out to bid in
November 2011, with construction beginning in January 2012. The
structural design for the bleachers will be submitted by the
successful bidder for DSA approval, and will likely be installed after
the 2012 football season.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
• FSC authorized budget increase, which will be approved by the BOE at time of award.
• Project to be re‐bid in October as one package.
Funding
State Funds $0
Strong Schools Bond Funds $3,626,101
Other Funding $0
Total $3,626,101
Budget
Salaries and Benefits $882
Supplies $0
Contracts & Services $766,460
Construction & Equipment $2,836,213
Soft Costs Contingency $22,546
Total $3,626,101
• Percent of Budget Expended 16.5%
• Budget augmentation pending BOE approval
Current Phase: Bid & Award
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) February 22, 2011
BOE Approval March 8, 2011
Submit to DSA April 4, 2011
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA July 26, 2011
Bid Opening December 8, 2011*
Award of Contract (1) December 13, 2011*
Notice to Proceed January 3, 2012*
Substantial Completion March 1, 2012*
Planned Occupancy March 15, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
Demolition of the existing utilities and pavement is complete. Utility
trenches have been backfilled and the building pads are complete. New
storm drain installation and foundation excavation will commence in
October.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• This project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $37,140,000
Other Funding $0
Total $37,140,000
Budget
Salaries and Benefits $14,721
Supplies $0
Contracts & Services $7,051,446
Construction & Equipment $29,740,000
Soft Costs Contingency $333,833
Total $37,140,000
Percent of Budget Expended 11.9%
Change Order Contingency
• Starting Contingency Balance $2,515,000
• Remaining Contingency Balance $2,460,009
• Percent of Changes 2.2%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA April 28, 2011
Bid Opening June 30, 2011
Award of Contract (1) July 12, 2011
Notice to Proceed August 4, 2011
Substantial Completion June 20, 2013*
Planned Occupancy July 20, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Performing Arts Center (PAC)
A. PROJECT STATUS
On August 3, 2011 DLM presented a design scheme to the FSC with a layout
of 575 seats as requested by the BOE. This scheme would have resulted in a
project budget of $24.9M. FSC members requested further discussions with
the BOE for clarifications on the size of facility. A meeting occurred on
September 21, 2011 with the performing arts’ staff and the Superintendent,
and it was agreed to investigate options for 540 seat single‐story scheme.
DLM will meet with the subcommittee to review this additional scheme and
present it to the FSC and BOE.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
• Project schematic design is anticipated to be submitted for BOE approval on December 13, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $17,720,000
Other Funding $0
Total $17,720,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,684,187
Construction & Equipment $13,926,590
Soft Costs Contingency $109,223
Total $17,720,000
Percent of Budget Expended 1.3%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (3) June 14, 2011
BOE Approval December 13, 2011*
BOE Approval January 17, 2012*
Submit to DSA August 13, 2012*
Approval by DSA March 26, 2013*
Authorize to Bid (2) March 12, 2013*
BOE Approval March 27, 2013*
Bid Opening June 4, 2013*
Award of Contract (1) June 19, 2013*
Notice to Proceed July 10, 2013*
Substantial Completion January 15, 2015*
Planned Occupancy February 15, 2015*
* Anticipated Dates – Subject to Change
( )b f d f d d
Page | 12
Palo Alto High School
Boiler Replacement System
A. PROJECT STATUS
The FSC approved funds from the Tower building project to
be appropriated to replace two failing boilers located in the
basement of Haymarket Theater. Five bids were received for
the boiler replacement project on September 28, 2011.
Environmental Services Inc. is the apparent low bidder, and a
recommendation to the BOE for award will be made at the
October 11, 2011 meeting. Proposals have been received for
inspector of record, special inspection and environmental
inspectors and we will be processing them in the month of
October. Construction is anticipated to start in October.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• Bids were received on September 28, 2011 and Environmental Services Inc. is the apparent low bidder.
• Recommendation to the BOE for award will be made at the October 11, 2011 meeting.
Funding
State Funds $0
Strong Schools Bond Funds $800,000
Other Funding $0
Total $800,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $0
Construction & Equipment $0
Soft Costs Contingency $800,000
Total $800,000
Percent of Budget Expended 0.0%
Current Phase: Bid & Award
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 30, 2011
Authorize to Bid (2) May 10, 2011
BOE Approval May 24, 2011
Approval by DSA August 24, 2011
Bid Opening September 28, 2011
Award of Contract (1) October 11, 2011*
Notice to Proceed October 17, 2011*
Substantial Completion January 6, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Jordan Middle School
A. PROJECT STATUS
The additional campus‐wide ADA compliance improvements
required by DSA has delayed their approval until early October
2011. The project is now anticipated to bid in late October 2011,
with construction to commence in January 2012. Fifteen
contractors were prequalified to provide bids on this project.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
• DSA’s anticipated review time has extended due to DSA access compliance requirements with approval
expected on October 5, 2011. Budget estimates are currently over budget.
Funding
State Funds $0
Strong Schools Bond Funds $17,943,194
Other Funding $0
Total $17,943,194
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,564,530
Construction & Equipment $13,949,500
Soft Costs Contingency $429,164
Total $17,943,194
Percent of Budget Expended 8.1%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA October 5, 2011*
Bid Opening December 6, 2011*
Award of Contract (1) December 13, 2011*
Notice to Proceed January 3, 2012*
Substantial Completion July 1, 2013*
Planned Occupancy August 15, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Jordan Middle Schools ‐ Interim Classrooms
A. PROJECT STATUS
The portables have been installed, and were cleaned and ready for
occupancy a week ahead of schedule. School staff requested
additional time for packing and moved in on September 30, 2011. DSA
closeout has commenced. The project is funded with both bond funds
and impact fees.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project completed ahead of schedule and under budget.
• Move in occurred on September 30, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $392,120
Other Funding $208,222
Total $600,342
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $180,286
Construction & Equipment $419,292
Soft Costs Contingency $764
Total $600,342
Percent of Budget Expended 29.2%*
*Budget previously expended
Current Phase: Move‐in
Schedule:
Approval by DSA June 16, 2011
Authorize to Bid (2) June 14, 2011
BOE Approval June 28, 2011
Bid Opening July 14, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed July 27, 2011
Substantial Completion September 20, 2011
Occupancy September 30, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
J.L. Stanford Middle School
A. PROJECT STATUS
Approval from DSA is anticipated in early 2012. The
project is currently within budget. Final estimates, and
constructability reviews will occur in fall 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule per DSA’s anticipated review time and is within budget.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,699
Other Funding $0
Total $17,184,699
Budget
Salaries and Benefits $0
Supplies $3,458
Contracts & Services $3,413,770
Construction & Equipment $13,421,500
Soft Costs Contingency $345,971
Total $17,184,699
Percent of Budget Expended 10.3%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28, 2010
Submit to DSA May 6, 2011
Authorize to Bid (2) November 29, 2011*
BOE Approval December 13, 2011*
Approval by DSA January 6, 2012*
Bid Opening February 21, 2012*
Award of Contract (1) February 28, 2012*
Notice to Proceed March 12, 2012*
Substantial Completion June 24, 2013*
Planned Occupancy August 6, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
Terman Middle School
A. PROJECT STATUS
DSA approval was received on September 1, 2011, and bidding is
scheduled to commence in October 2011. Construction is expected
to begin in December 2011. Recently completed construction
document estimates show the project to be over budget, therefore
final alternates are being considered to provide a strategy to maintain
the project budget. Fifteen contractors were prequalified to provide
bids on this project.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
• DSA approval received on September 1, 2011.
• Project currently over budget.
Funding
State Funds $0
Strong Schools Bond Funds $12,850,071
Other Funding $0
Total $12,850,071
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,533,760
Construction & Equipment $10,031,569
Soft Costs Contingency $284,742
Total $12,850,071
Percent of Budget Expended 8.1%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA September 1, 2011
Bid Opening November 29, 2011*
Award of Contract (1) December 13, 2011*
Notice to Proceed January 3, 2012*
Substantial Completion June 24, 2013*
Planned Occupancy August 2, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Gelfand received all DSA comments and has scheduled backcheck
appointments with DSA on October 25 ‐ 27. O’Connor is
concurrently performing site verification, backchecking
constructability review comments and finalizing front end
documents. Prequalification for contractors was publicized on
September 23, 2011. The project is anticipated to go out for bid in
November 2011. Construction is planned to begin in early January
2012.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule per DSA’s anticipated review time, and is within budget.
Funding
State Funds $0
Strong Schools Bond Funds $9,327,500
Other Funding $0
Total $9,327,500
Budget
Salaries and Benefits $0
Supplies $7,697
Contracts & Services $1,831,019
Construction & Equipment $7,443,000
Soft Costs Contingency $45,784
Total $9,327,500
Percent of Budget Expended 8.5%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010
BOE Approval September 28, 2010
Submit to DSA April 18, 2011
Authorize to Bid (2) October 11, 2011*
BOE Approval October 25, 2011*
Approval by DSA October 27, 2011*
Bid Opening December 6, 2011*
Award of Contract (1) December 13, 2011*
Notice to Proceed January 3, 2012*
Substantial Completion May 8, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
With the modernization work complete, the focus is on completion
of the new classroom wing. Mechanical, electrical, and plumbing
trim work is underway, and finishes such as painting, casework,
wood trim, and wall coverings continue. Site irrigation and concrete
walkways are in progress. The pavers, landscaping trays and
planters have been installed for the green roof.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $0
Supplies $5,467
Contracts & Services $2,364,267
Construction & Equipment $9,169,121
Soft Costs Contingency $129,110
Total $11,667,965
Percent of Budget Expended 59.7%
Change Order Contingency
• Starting Contingency Balance $748,400
• Remaining Contingency Balance $687,595
• Percent of Changes 0.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010
Award of Contract (1) August 3, 2010
Notice to Proceed August 19, 2010
Substantial Completion November 7, 2011*
Planned Occupancy January 3, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Duveneck Elementary School
New Classroom Buildings and Modernization
A. PROJECT STATUS
Gelfand is wrapping up design development documents and
anticipates submitting a package for district and O’Connor
review in early October 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand Partners proceeding with design development.
Funding
State Funds $0
Strong Schools Bond Funds $11,088,757
Other Funding $0
Total $11,088,757
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,129,387
Construction & Equipment $8,803,087
Soft Costs Contingency $156,283
Total $11,088,757
Percent of Budget Expended 1.7%
Current Phase: Design Development
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) December 14, 2010
BOE Approval January 11, 2011
Schematic Design (2) June 14, 2011
BOE Approval June 28, 2011
Submit to DSA January 19, 2012*
Approval by DSA September 6, 2012*
Authorize to Bid (2) September 28, 2012*
BOE Approval October 9, 2012*
Bid Opening November 22, 2012*
Award of Contract (1) November 27, 2012*
Notice to Proceed December 5, 2012*
Substantial Completion April 16, 2014*
Planned Occupancy August 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Technology Improvements
A. PROJECT STATUS
The District purchased computers, utilizing bond funds, throughout the
2010/11 school year. During the year there was a notable shift from
desktops and laptops to handheld devices, primarily at the elementary
school level. At the end of the 2010/11 school year, orders were placed for
equipment to be used in the 2011/12 school year. Implementation of the
Voice‐over‐IP (VoIP) telephone system is scheduled to begin at the district office
this fall. A major upgrade to the District's network is currently out for re‐bid, with
bids opening extended into October 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• New computers for 2011/12 school year being delivered to school sites.
Funding
State Funds $0
Strong Schools Bond Funds $8,212,531
Other Funding $0
Total $8,212,531
Budget
Salaries and Benefits $0
Supplies & Computers $7,829,936
Contracts & Services $180,173
Construction & Equipment $202,422
Soft Costs Contingency $0
Total $8,212,531
Percent of Budget Expended 52.5%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
Best Contracting Services Inc. completed the installation of air
conditioning units and cool roof coating. Project close‐out has
commenced.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
• Project in close‐out.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $1,919
Supplies $0
Contracts & Services $454,160
Construction & Equipment $2,120,580
Soft Costs Contingency $22,891
Total $2,600,000
Percent of Budget Expended 59.9%
Current Phase: Close‐out
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA October 20, 2010
Approval by DSA February 10, 2011
Authorize to Bid (2) February 22, 2011
BOE Approval March 8, 2011
Bid Opening March 28, 2011
Award of Contract (1) April 8, 2011
Notice to Proceed April 11, 2011
Substantial Completion August 8, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
J.L. Stanford Middle School ‐ Interim Classrooms
A. PROJECT STATUS
Coulter Construction completed the work on the relocated
portables. Project close‐out has commenced.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• Project completed on schedule and is currently in close‐out.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,699
Other Funding $0
Total $17,184,699
Budget
Salaries and Benefits $0
Supplies $3,458
Contracts & Services $3,408,170
Construction & Equipment $13,421,500
Soft Costs Contingency $351,571
Total $17,184,699
Percent of Budget Expended 10.3%
This portable relocation project funded by main JLS
project.
Current Phase: Occupancy ‐August 11, 2011
Schedule:
Approval by DSA April 19, 2011
Jordan Project June 16, 2011*
Authorize to Bid (2) May 10, 2011
BOE Approval May 24, 2011
Bid Opening June 1, 2011
Award of Contract (1) June 13, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 8, 2011
Planned Occupancy August 15, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Fairmeadow Elementary School
Portable Relocation Project
A. PROJECT STATUS
Guerra Construction Group completed the work on the relocated
portable on August 8, 2011. The JLS project is funding the relocation of
this portable for the construction of JLS’ new 2‐story classroom building.
Project close‐out has commenced.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 6.4
D. PROJECT OVERVIEW:
• Project completed ahead of schedule on August 8, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,699
Other Funding $0
Total $17,184,699
Budget
Salaries and Benefits $0
Supplies $3,458
Contracts & Services $3,408,170
Construction & Equipment $13,421,500
Soft Costs Contingency $351,571
Total $17,184,699
Percent of Budget Expended 10.3%
This portable relocation project funded by main JLS
project.
Current Phase: Occupancy ‐August 8, 2011
Schedule:
Architect Contract (2) February 15, 2011
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA March 3, 2011
Approval by DSA March 3, 2011
Authorize to Bid (2) May 11, 2011
BOE Approval May 24, 2011
Bid Opening June 14, 2011
Award of Contract (1) June 14, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 1, 2011
Planned Occupancy August 8, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Elementary Classroom Improvements
Interactive Whiteboards and Sound Assist System Installation
A. PROJECT STATUS
Coulter Construction installed SmartBoards and Lightspeed sound assist systems, and completed the
installation April 29, 2011. Phase 4 and 5 schools were the final elementary schools to receive interactive
whiteboards and sound assist systems.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• All SmartBoards and Lightspeed sound systems installed.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,195,880
Construction & Equipment $7,488,707
Soft Costs Contingency $202,935
Total $8,887,522
Percent of Budget Expended 22.9%
Current Phase: Complete ‐May 15, 2011
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) November 9, 2010
BOE Approval November 23, 2010
Bid Opening February 25, 2011
Award of Contract (1) March 8, 2011
Notice to Proceed March 9, 2011
Completion May 15, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
The fields were available for play on February 1, 2011, and final change
order negotiations completed on March 9, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
• Field was open for use on February 1, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $2,609,680
Other Funding $1,007,255
Total $3,616,934
Budget
Salaries and Benefits $0
Supplies $1,506
Contracts & Services $729,418
Construction & Equipment $2,883,316
Soft Costs Contingency $2,694
Total $3,616,934
Percent of Budget Expended 99.8%
Change Order Contingency
• Starting Contingency Balance $269,300
• Remaining Contingency Balance $230,579
• Percent of Changes 1.7%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –February 1, 2011
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 18, 2008
BOE Approval December 09, 2008
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) February 24, 2009
BOE Approval March 17, 2009
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion January 31, 2011
Planned Occupancy February 1, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
This facility was available for instruction in January 2010. DSA closeout
received on July 18, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
• The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,082,402
Other Funding $0
Total $5,082,402
Budget
Salaries and Benefits $1,061
Supplies $88,985
Contracts & Services $1,000,861
Construction & Equipment $3,991,495
Soft Costs Contingency $0
Total $5,082,402
Percent of Budget Expended 99.3%
Change Order Contingency
• Starting Contingency Balance $349,000
• Remaining Contingency Balance $141,967
• Percent of Changes 41.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
Gunn High School
Aquatic Center
A. PROJECT STATUS
This facility was available for use in July 2009, and has been closed
out with DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
• This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $4,865,423
Other Funding $0
Total $4,865,423
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $647,169
Construction & Equipment $4,218,253
Soft Costs Contingency $0
Total $4,865,423
Percent of Budget Expended 99.9%
Change Order Contingency
• Starting Contingency Balance $389,887
• Remaining Contingency Balance $195,148
• Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education for approval on September 8, which became the
program documents for the new projects at each campus. These
projects for pre‐design work have been closed, and funds will be
transferred to the program contingency on June 14, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
• This project has been completed. Board approval received on September 8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $56,489
Other Funding $0
Total $56,489
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $56,489
Construction & Equipment $0
Soft Costs Contingency $0
Total $56,489
Percent of Budget Expended 96.8%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 29
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education has put new development for Garland on
hold until a growth plan is established for the elementary schools.
The board voted to terminate the lease with Stratford School in
June 2011, so that future plans for growth at the elementary
schools can begin on this campus as early as June 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,915,789
Construction & Equipment $17,400,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: On Hold
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 30
Elementary School Teaching Walls
Phase 1 Schools
A. PROJECT STATUS
The district placed this project on hold after review of the
implementation of other classroom improvements, as
recommended by the elementary school principals. This
project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary below).
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.9
D. PROJECT OVERVIEW:
• This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary
above).
Funding
State Funds $0
Strong Schools Bond Funds $7,044,987
Other Funding $0
Total $7,044,987
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,341,394
Construction & Equipment $5,498,498
Soft Costs Contingency $205,095
Total $7,044,987
Percent of Budget Expended 1.6%
Current Phase: Project Renamed. See Classroom
Improvements Project
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates –Subject to Change
Page | 31
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
The Board of Education (BOE) approved the master plans for both
high schools, and these projects have been closed, with funds
transferred to the respective campus reserve funds.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
• Group 2 project planning at the high schools will re‐commence in fall 2011.
Funding
State Funds $0
Strong Schools Bond Funds $285,387
Other Funding $0
Total $285,387
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $285,387
Construction & Equipment $0
Soft Costs Contingency $0
Total $285,387
Percent of Budget Expended 86.2%
Current Phase: Master Planning
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010
Paly MP Revision Approval (2) October 9, 2010
Gunn MP Revision Approval (2) October 12, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 32
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
This project has been put on hold until a growth plan is established for the
elementary schools.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently on hold.
Funding
State Funds $0
Strong Schools Bond Funds $8,575,389
Other Funding $0
Total $8,575,389
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,643,477
Construction & Equipment $6,831,912
Soft Costs Contingency $100,000
Total $8,575,389
Percent of Budget Expended 0.7%
Current Phase: On Hold
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) November 9, 2010
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 33
Elementary Classroom Improvements
Phase 1 – Barron Park and El Carmelo
A. PROJECT STATUS
DSA comments were returned to Gelfand for Phase 1 plans that
include new lighting, adding operable windows and coverings,
ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo elementary schools.
The authorization to bid has been placed on hold pending further discussions with the BOE about elementary
growth planning.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $8,153,022
Other Funding $0
Total $8,153,022
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,195,880
Construction & Equipment $6,754,207
Soft Costs Contingency $202,935
Total $8,153,022
Percent of Budget Expended 22.9%
Phase 1 Schools: Barron Park and El Carmelo
Current Phase: On Hold
Schedule:
Architect Contract (2) June 8, 2010
BOE Approval June 22, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 9, 2010
BOE Approval December 7, 2010
Submit to DSA December 23, 2010
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.