Loading...
Monthly Reports 2011-08 (Aug) MMOONNTTHHLLYY  PPRROOGGRREESSSS  RREEPPOORRTT     Through  August 2011      Current Strong Schools Bond  Capital Improvement Projects  Prepared by     O’Connor Construction Management, Inc.  &  Gilbane Building Company  Page | 2   TABLE OF CONTENTS    Executive Summary         page 3   Attachment 1 – Consolidated Expenditure Report          Attachment 2 – Master Program Schedule Summary         Capital Projects     Gunn High School – New Classroom Buildings A & B     page 7    Gunn High School – Parking and Drop‐off Sitework Improvement    page 8    Gunn High School – New Gymnasium       page 9    Palo Alto High School – Athletic Stadium Improvements    page 10    Palo Alto High School – Classroom Building and Media Arts    page 11    Palo Alto High School – Performing Arts Center     page 12    Jordan Middle School        page 13    Jordan Middle School – Interim Classrooms      page 14    J.L. Stanford Middle School       page 15    Terman Middle School        page 16     Fairmeadow Elementary School       page 17    Ohlone Elementary School        page 18    Duveneck Elementary School       page 19    Technology          page 20    Completed Capital Projects    Gunn High School – Air Conditioning of Existing Buildings    page 21    J.L. Stanford Middle School – Interim Classrooms     page 22    Fairmeadow Elementary School – Portable Relocation    page 23    Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 24    Palo Alto High School – Multi‐use Field      page 25    Gunn High School – Industrial Arts Renovation     page 26    Gunn High School – Aquatic Center       page 27    Middle School Pre‐Design        page 28    Inactive Capital Projects    Garland Elementary School       page 29    Elementary School Teaching Walls – Phase 1 Schools     page 30    High School Master Plan        page 31    Hoover Elementary School        page 32    Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo page 33    Appendix  Exhibit A – Bond Project List  Page | 3   EXECUTIVE SUMMARY    Gunn High School – New Classroom Buildings A & B  Six bids were received on July 14, 2011 and the contract was awarded for $17.6M to BRCO Constructors at the July  22, 2011 BOE meeting.  A kick‐off meeting was conducted on August 2, 2011 and the notice to proceed was issued  on August 24, 2011.  BRCO mobilized, temporary construction site fencing is installed, and grading efforts have  commenced.      Gunn High School – Parking and Drop‐off Sitework Improvement  Design for the parking and drop‐off improvements will recommence in conjunction with the planning of group 2  projects.    Gunn High School – New Gymnasium  Six bids were opened July 13, 2011 and the contract was awarded for $8.35M to SJ Amoroso Construction at the  July 20, 2011 BOE meeting.  Contracts were executed and a construction kick‐off meeting was conducted on  August 2, 2011.  SJ Amoroso has mobilized, temporary construction site fencing is installed and demolition efforts  are underway.      Palo Alto High School – Athletics Stadium Improvements  Four bids were received for the bleacher project on August 18, 2011 and the low bid was significantly over budget.  The Concessions and Site Improvements project estimate was also over budget, so it was determined to reject all  the bleacher bids and consolidate the two projects into one bid package.  A budget augmentation and/or de‐ scoping of the project will be discussed with the Stadium subcommittee and facilities steering committee (FSC) in  early September.  If the FSC approves a budget increase, the project is anticipated to bid in November 2011 and  construction on the concessions building would likely commence in January 2012.  The structural design for the  bleachers will be submitted by the successful bidder for DSA approval.    Palo Alto High School – Classroom Building and Media Arts Building  A contract was awarded to Taisei Construction Corporation (TCC) on July 12, 2011.  Staff issued a notice to proceed  on July 27, 2011 and TCC began tree protection and installing construction fencing on August 1, 2011.  Existing  asphalt paving was demolished, which has been ground up for reuse on site. The rest of the material is being  shipped offsite for recycling.  Utility demolition commenced and will continue into next month.    Palo Alto High School – Performing Arts Center (PAC)  On June 28, 2011 the BOE requested that DLM and staff consider a facility to accommodate at least 100 more  seats above the 466 seat scheme recommended by staff.  DLM completed a design that meets this request, which  includes a small balcony that accommodates 175 seats, for a total of 575 seats.  The design and estimate will be  presented to the FSC on September 7, 2011.      Jordan Middle School  DSA is requiring campus‐wide ADA compliance improvements, therefore DSA approval is not expected until  October 2011, which will also add cost to the project.  The project is now scheduled to go out to bid in October  2011, with construction to commence in January 2012.     Jordan Middle School ‐ Interim Classrooms  Coulter Construction was awarded the project at the July 20, 2011 BOE meeting and commenced work on July 28,  2011. Coulter installed underground utilities and prepared the foundation pad on schedule for installation of the  portables on August 15 and 16, 2011.  Once the portables were placed, the remaining electrical, data, plumbing  and fire alarm installation work began and will continue through September 2011.  The portables are anticipated  to be complete and ready for occupancy by September 30, 2011.  The project is co‐funded with bond funds and  impact fees.    Page | 4    J.L. Stanford Middle School  Approval from DSA is anticipated in early 2012.  The project is currently within budget.  Final estimates, and  constructability reviews will occur in fall 2011.    Terman Middle School  DSA approval is anticipated in early September 2011, with bidding occurring in October 2011 and construction  commencing in November 2011.  Prequalification of approximately 19 contractors is almost complete.  The project  is currently within budget.      Fairmeadow Elementary School – New Classroom Building and Modernization  Gelfand received all DSA comments on August 29, 2011, and they have scheduled backcheck appointments for  October 25 ‐ 27. O’Connor is concurrently performing site verification and backchecking constructability review  comments with Gelfand, and finalizing front end documents. Prequalification of contractors will commence in  September.  Bidding is anticipated to occur in November 2011, with construction planned to begin in January 2012.    Ohlone Elementary School – New Classroom Building and Modernization  Jeff Luchetti Construction completed the modernization portion of the work prior to the beginning of classes on  August 23, 2011. This included the front parking and drop‐off area and the installation of Smartboards, sound  assist systems, ventilation improvements, and lighting systems.  The kindergarten bathrooms were also remodeled  with new ceramic tile, plumbing fixtures, flooring and ADA improvements.  Current work on the new two‐story  building is focused on casework installation, tackable surface wall covering, and t‐bar ceiling installation. Exterior  pavers, sealant on the green roof, and concrete flatwork around the building are also underway.    Duveneck Elementary School – New Classroom Buildings and Modernization  Gelfand conducted a pre‐submission meeting with DSA on August 22, 2011 and met the new principal to review  the scope of the project on August 25, 2011.  The master plan was on display at the Duveneck back‐to‐school night  on August 30, 2011 to promote project awareness and answer any questions.  Gelfand continues design  development documents and anticipates submitting a package for district review in early October 2011.    Technology  The District purchased computers, utilizing bond funds, throughout the 2010/11 school year.  During the year  there was a notable shift from desktops and laptops to handheld devices, primarily at the elementary school level.  At the end of the 2010/11 school year, orders were placed for equipment to be used in the 2011/12 school year.   Implementation of the Voice‐over‐IP (VoIP) telephone system is scheduled to begin at the district office this fall.   A  major upgrade to the District's network is currently out for re‐bid, with bids opening in September 2011.      COMPLETED CAPITAL PROJECTS   Gunn High School – Air Conditioning of Existing Buildings  Best Contracting Services Inc. completed the installation of air conditioning units and cool roof coating.  Remaining  punchlist items and EMS programming continues, though the units are functioning and in use.  The final change  order is negotiated and will be executed after all equipment is commissioned.  Project close‐out has commenced.    J.L. Stanford Middle School ‐ Interim Classrooms  Coulter Construction completed the work on the relocated portables.  Project close‐out has commenced.      Fairmeadow Elementary School – Portable Relocation  Guerra Construction Group completed the work on the relocated portable on August 8, 2011.  The JLS project is  funding the relocation of this portable for the construction of JLS’ new 2‐story classroom building.  Project close‐ out has commenced.        Page | 5   Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems  Coulter Construction installed SmartBoards and Lightspeed sound assist systems, and completed the installation  April 29, 2011.  Phase 4 and 5 schools were the final elementary schools to receive interactive whiteboards and  sound assist systems.      Palo Alto High School – Multi‐use Field  The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9,  2011.    Gunn High School – Industrial Arts Addition & Renovation  This facility was available for instruction in January 2010. DSA closeout is anticipated to occur by the end of August  2011.    Gunn High School – Aquatic Center   This facility was available for use in July 2009, and has been closed out with DSA.    Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman  AEDIS presented recommended concept plans for each campus to the Board of Education for approval on  September 8, which became the program documents for the new projects at each campus.  These projects for pre‐ design work have been closed, and funds will be transferred to the program contingency on June 14, 2011.    INACTIVE CAPITAL PROJECTS     Garland Elementary School Renovation  The Board of Education has put new development for Garland on hold until a growth plan is established for the  elementary schools.  The board voted to terminate the lease with Stratford School in June 2011, so that future  plans for growth at the elementary schools can begin on this campus as early as June 2014.    Elementary School Teaching Walls – Phase 1 Schools  The district placed this project on hold after review of the implementation of other classroom improvements, as  recommended by the elementary school principals.  This project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary below).     High School Master Plan  The Board of Education (BOE) approved the master plans for both high schools, and these projects have been  closed, with funds transferred to the respective campus reserve funds.   Hoover Elementary School – Pre‐Design  This project has been put on hold until a growth plan is established for the elementary schools.      Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo  DSA comments were returned to Gelfand for Phase 1 plans that include new lighting, adding operable windows  and coverings, ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo  elementary schools.  The authorization to bid has been placed on hold pending further discussions with the BOE  about elementary growth planning.         Page | 6     Board Actions in August  August 23, 2011  Action 16 – Inspector of Record (IOR) Services: Approval of DSA School Inspectors, LLC to Provide These Services  for the Gunn High School Classroom Building Project, the Gunn High School Gymnasium Project, and the Palo Alto  High School Classroom and Media Arts Buildings Project    A B C C / A B - C C / B A - BGunn High School - High School Master Plan 142,389 136,009 117,416 82.5% 18,593 86.33% 6,381Gunn High School 1 - Aquatic Center 4,865,423 4,862,530 4,862,530 99.9% 0 100.00% 2,893Gunn High School 2 - I.A Building 5,082,402 5,049,559 5,045,206 99.3% 4,354 99.91% 32,843Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 25,035,200 23,554,877 2,846,373 11.4% 20,708,504 12.08% 1,480,323Gunn High School 5 - Parking & Drop Off improvements 3,940,000 322,491 95,979 2.4% 226,512 29.76% 3,617,509Gunn High School 6- New/Auxiliary Gymnasium 12,914,800 10,889,534 856,284 6.6% 10,033,250 7.86% 2,025,266Gunn High School 7- A/C 2,600,000 2,243,435 1,510,851 58.1% 732,584 67.35% 356,566Gunn High School - Reserved 21,525,081 0 0 0.0% 0 0.00% 21,525,081Palo Alto High Schools - High School Master Plan 142,998 137,757 128,442 89.8% 9,315 93.24% 5,240Palo Alto High School 1 - Stadium Field 3,626,101 815,597 566,241 15.6% 249,356 69.43% 2,810,504Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,604,765 99.8% 4,915 99.81% 0Palo Alto high School 3 - New classroom & Media Art Building 37,140,000 33,467,857 3,299,362 8.9% 30,168,495 9.86% 3,672,143Palo Alto High School 4 - New Theater 17,720,000 1,364,138 221,891 1.3% 1,142,248 16.27% 16,355,862Palo Alto High School 5 - Haymarket and Tower Admin. Building 800,000 0 0 0.0% 0 0.00% 800,000Palo Alto High School - Reserved 36,754,766 0 0 0.0% 0 0.00% 36,754,766Jordan Middle School -Program Management- MS Pre-Design 18,890 18,890 17,826 94.4% 1,064 94.37% 0Jordan Middle Schools 1- Interim Classrooms 600,342 459,981 171,745 28.6% 288,236 37.34% 140,361Jordan Middle School 2- Improvements 17,943,194 2,835,285 1,393,895 7.8% 1,441,390 49.16% 15,107,909J.L.S Middle School - Program Management- MS Pre-Design 18,799 18,799 18,408 97.9% 391 97.92% 0J.L.S Middle School 1 - Interim Classrooms 446,844 377,598 359,522 80.5% 18,076 95.21% 69,246 J.L.S Middle School 2- Improvements 17,184,699 3,067,221 1,665,632 9.7% 1,401,589 54.30% 14,117,478Terman Middle School - Program Management- MS Pre-Design 18,799 18,799 18,423 98.0% 376 98.00% 0Terman Middle School 1- Improvements 12,850,071 2,009,745 1,028,607 8.0% 981,137 51.18% 10,840,326PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 98,480 83,550 57.6% 14,930 84.84% 46,520Addison Elementary School 1-Phase I 5,199,727 21,267 21,267 0.4% 0 100.00% 5,178,460Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 11,088,757 186,931 183,331 1.7% 3,600 98.07% 10,901,826Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 1,552,324 792,178 8.5% 760,146 51.03% 7,775,176Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 70,550 57,165 0.7% 13,385 81.03% 8,504,839Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 10,646,936 6,136,869 52.6% 4,510,067 57.64% 1,021,029Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,153,022 2,004,891 1,863,784 22.9% 141,107 92.96% 6,148,131Elementary Schools - Reserved 5,075,688 0 0 0.0% 0 0.00% 5,075,688PAUSD - Program Management 6,651,992 4,967,433 3,633,940 54.6% 1,333,494 73.16% 1,684,558PAUSD - Technology 7,101,063 5,052,383 3,730,111 52.5% 1,322,272 73.83% 2,048,680PAUSD - Technology -Reserved 6,806,302 0 0 0.0% 0 0.00% 6,806,302PAUSD - Reserved 7,230,205 0 0 0.0% 0 0.00% 7,230,205Bond Issuance Cost 1,840,700 1,840,700 1,840,700 100.0% 0 100.00% 0Total352,294,796 120,988,733 45,458,181 75,530,552 231,306,063Prepared by: Business Services Department based on QSS accounting SystemExpenditures Budget BalanceCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond8/31/2011Percent of ExpendedContract Balance Page | 7   Gunn High School  New Classroom Buildings A & B  A. PROJECT STATUS     Six bids were received on July 14, 2011 and the contract was  awarded for $17.6M to BRCO Constructors at the July 22, 2011  BOE meeting.  A kick‐off meeting was conducted on August 2,  2011 and the notice to proceed was issued on August 24, 2011.   BRCO mobilized, temporary construction site fencing is installed,  and grading efforts have commenced.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4    D. PROJECT OVERVIEW:  • Notice to proceed issued on August 24, 2011.  •  BRCO mobilized, temporary construction site fencing is installed, and demolition efforts commenced.    Funding  State Funds $0  Strong Schools Bond Funds $25,035,200  Other Funding $0  Total $25,035,200    Budget  Salaries and Benefits $13,253  Supplies $0  Contracts & Services $4,462,881  Construction & Equipment $20,482,302  Soft Costs Contingency $76,764  Total $25,035,200    Percent of Budget Expended 11.4%    Change Order Contingency  • Starting Contingency Balance $ 1,763,200  • Remaining Contingency Balance $ 1,763,200  • Percent of Changes 0.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010     Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA May 27, 2011    Bid Opening July 13, 2011    Award of Contract (1) July 22, 2011    Notice to Proceed August 24, 2011    Substantial Completion February 23, 2013*    Planned Occupancy April 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 8   Gunn High School  Parking and Drop‐off Sitework Improvement  A. PROJECT STATUS    Design for the parking and drop‐off improvements will  recommence in conjunction with the planning of group 2 projects  in fall 2011.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:  • Design will recommence with the planning of group 2 projects.     Funding  State Funds $0  Strong Schools Bond Funds $3,940,000  Other Funding $0  Total $3,940,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $898,978  Construction & Equipment $2,919,840  Soft Costs Contingency $121,182  Total $3,940,000    Percent of Budget Expended 2.4%  Current Phase: Conceptual Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 9   Gunn High School  New Gymnasium  A. PROJECT STATUS     Six bids were opened July 13, 2011 and the contract was awarded  for $8.35M to SJ Amoroso Construction at the July 20, 2011 BOE  meeting.  Contracts were executed and a construction kick‐off  meeting was conducted on August 2, 2011.  SJ Amoroso has  mobilized, temporary construction site fencing is installed and  demolition efforts are underway.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:  • Notice to proceed issued on August 1, 2011.  • SJ Amoroso has mobilized, temporary construction site fencing is installed and demolition efforts are  underway.  Funding  State Funds $0  Strong Schools Bond Funds $12,914,800  Other Funding $0  Total $12,914,800    Budget  Salaries and Benefits $0  Supplies $1,001  Contracts & Services $2,671,560  Construction & Equipment $10,158,210  Soft Costs Contingency $84,029  Total $12,914,800    Percent of Budget Expended 6.2%    Change Order Contingency  • Starting Contingency Balance $834,700  • Remaining Contingency Balance $834,700  • Percent of Changes 0.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA May 27, 2011    Bid Opening July 13, 2011    Award of Contract (1) July 20, 2011    Notice to Proceed August 1, 2011    Substantial Completion September 11, 2012*    Planned Occupancy November 15, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 10   Palo Alto High School  Athletic Stadium Improvements  A. PROJECT STATUS    Four bids were received for the bleacher project on August 18,  2011 and the low bid was significantly over budget. The  Concessions and Site Improvements project estimate was also over  budget, so it was determined to reject all the bleacher bids and  consolidate the two projects into one bid package.  A budget  augmentation and/or de‐scoping of the project will be discussed with the Stadium subcommittee and facilities  steering committee (FSC) in early September.  If the FSC approves a budget increase, the project is anticipated  to bid in November 2011 and construction on the concessions building would likely commence in January  2012.  The structural design for the bleachers will be submitted by the successful bidder for DSA approval.            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.13    D. PROJECT OVERVIEW:  • FSC will review scope and potential budget increase to allow project to be re‐bid in October as one  package.    Funding  State Funds $0  Strong Schools Bond Funds $3,626,101  Other Funding $0  Total $3,626,101    Budget  Salaries and Benefits $882  Supplies $0  Contracts & Services $757,619  Construction & Equipment $2,827,317  Soft Costs Contingency $40,283  Total $3,626,101    Percent of Budget Expended 15.6%  Current Phase: Bid & Award   Schedule:  Architect Contract (2) January 26, 2010  BOE Approval February 9, 2010    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) February 22, 2011  BOE Approval March 8, 2011    Submit to DSA April 4, 2011    Authorize to Bid (2) June 28, 2011  BOE Approval July 19, 2011    Approval by DSA July 26, 2011     Bid Opening December 8, 2011*    Award of Contract (1) December 13, 2011*    Notice to Proceed January 3, 2012*    Substantial Completion March 1, 2012*    Planned Occupancy March 15, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 11   Palo Alto High School  Classroom Building and Media Arts  A. PROJECT STATUS      A contract was awarded to Taisei Construction Corporation (TCC)  on July 12, 2011.  Staff issued a notice to proceed on July 27, 2011  and TCC began tree protection and installing construction fencing  on August 1, 2011.  Existing asphalt paving was demolished, which  has been ground up for reuse on site. The rest of the material is being  shipped offsite for recycling.  Utility demolition commenced and will  continue into next month.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:  • TCC began mobilizing with tree protection and temporary construction site fencing on August 1, 2011. Funding  State Funds $0  Strong Schools Bond Funds $37,140,000  Other Funding $0  Total $37,140,000    Budget  Salaries and Benefits $14,721  Supplies $0  Contracts & Services $7,051,769  Construction & Equipment $29,740,000  Soft Costs Contingency $333,510  Total $37,140,000    Percent of Budget Expended 8.9%    Change Order Contingency  • Starting Contingency Balance $2,515,000  • Remaining Contingency Balance $2,515,000  • Percent of Changes 0.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA April 28, 2011    Bid Opening June 30, 2011    Award of Contract (1) July 12, 2011    Notice to Proceed August 4, 2011    Substantial Completion June 20, 2013*    Planned Occupancy July 20, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 12   Palo Alto High School  Performing Arts Center (PAC)  A. PROJECT STATUS    On June 28, 2011 the BOE requested that DLM and staff consider a facility  to accommodate at least 100 more seats above the 466 seat scheme  recommended by staff.  DLM completed a design that meets this request,  which includes a small balcony that accommodates 175 seats, for a total of  575 seats.  The design and estimate will be presented to the FSC on  September 7, 2011.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.11    D. PROJECT OVERVIEW:  • Project schematic design is anticipated to be submitted for BOE approval on December 13, 2011.  Funding  State Funds $0  Strong Schools Bond Funds $17,720,000  Other Funding $0  Total $17,720,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,684,187  Construction & Equipment $13,926,590  Soft Costs Contingency $109,223  Total $17,720,000    Percent of Budget Expended 1.3%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) June 14, 2011  BOE Approval December 13, 2011*    Submit to DSA August 13, 2012*    Approval by DSA March 26, 2013*    Authorize to Bid (2) March 12, 2013*  BOE Approval March 27, 2013*    Bid Opening June 4, 2013*    Award of Contract (1) June 19, 2013*    Notice to Proceed July 10, 2013*    Substantial Completion January 15, 2015*    Planned Occupancy February 15, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 13   Jordan Middle School  A. PROJECT STATUS    DSA is requiring campus‐wide ADA compliance improvements,  therefore DSA approval is not expected until October 2011, which  will also add cost to the project.  The project is now scheduled to go  out to bid in October 2011, with construction to commence in  January 2012.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5    D. PROJECT OVERVIEW:  • DSA’s anticipated review time has extended due to DSA access compliance requirements with approval  expected in October 2011.  Budget estimates are currently over budget. Funding  State Funds $0  Strong Schools Bond Funds $17,943,194  Other Funding $0  Total $17,943,194    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,564,530  Construction & Equipment $13,949,500  Soft Costs Contingency $429,164  Total $17,943,194    Percent of Budget Expended 7.8%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) March 23, 2010  BOE Approval April 27, 2010    Submit to DSA December 21, 2010     Authorize to Bid (2) June 28, 2011  BOE Approval July 19, 2011    Approval by DSA October 5, 2011*    Bid Opening November 29, 2011*    Award of Contract (1) December 13, 2011*    Notice to Proceed January 3, 2012*    Substantial Completion July 1, 2013*    Planned Occupancy August 15, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 14   Jordan Middle Schools ‐ Interim Classrooms  A. PROJECT STATUS    Coulter Construction was awarded the project at the July 20, 2011  BOE meeting and commenced work on July 28, 2011. Coulter  installed underground utilities and prepared the foundation pad on  schedule for installation of the portables on August 15 and 16,  2011.  Once the portables were placed, the remaining electrical,  data, plumbing and fire alarm installation work began and will  continue through September 2011.  The portables are anticipated  to be complete and ready for occupancy by September 30, 2011.   The project is co‐funded with bond funds and impact fees.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:  • This project is proceeding on schedule and within budget.  • Anticipated occupancy is September 30, 2011.  Funding  State Funds $0  Strong Schools Bond Funds $392,120  Other Funding $208,222  Total $600,342    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $173,566  Construction & Equipment $426,012  Soft Costs Contingency $764  Total $600,342    Percent of Budget Expended 28.6%*    *Budget previously expended       Current Phase: Construction   Schedule:  Approval by DSA June 16, 2011    Authorize to Bid (2) June 14, 2011  BOE Approval June 28, 2011    Bid Opening July 14, 2011    Award of Contract (1) July 20, 2011    Notice to Proceed July 27, 2011    Substantial Completion September 20, 2011*    Planned Occupancy October 1, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 15   J.L. Stanford Middle School  A. PROJECT STATUS    Approval from DSA is anticipated in early 2012.  The  project is currently within budget.  Final estimates, and  constructability reviews will occur in fall 2011.                               B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule per DSA’s anticipated review time and is within budget.    Funding  State Funds $0  Strong Schools Bond Funds $17,184,699  Other Funding $0  Total $17,184,699    Budget  Salaries and Benefits $0  Supplies $3,458  Contracts & Services $3,413,770  Construction & Equipment $13,421,500  Soft Costs Contingency $345,971  Total $17,184,699    Percent of Budget Expended 9.7%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (3) June 1, 2010  BOE Approval June 22, 2010  BOE Approval (Sitework) September 28, 2010    Submit to DSA May 6, 2011     Approval by DSA January 6, 2012*    Authorize to Bid (2) December 20, 2012*  BOE Approval January 10, 2012*    Bid Opening February 21, 2012*    Award of Contract (1) February 28, 2012*    Notice to Proceed March 12, 2012*    Substantial Completion June 24, 2013*    Planned Occupancy August 6, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings Page | 16   Terman Middle School  A. PROJECT STATUS    DSA approval is anticipated in early September 2011, and anticipating  going out to bid in late October/early November 2011 and  construction commencing in January 2013.  Prequalification of  approximately 19 contractors is almost complete.  The project is  currently within budget.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule per DSA’s anticipated review time, and is within budget.  • DSA approval expected on September 1, 2011.  Funding  State Funds $0  Strong Schools Bond Funds $12,850,071  Other Funding $0  Total $12,850,071    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,533,760  Construction & Equipment $10,031,569  Soft Costs Contingency $284,742  Total $12,850,071    Percent of Budget Expended 8.0%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) May 11, 2010  BOE Approval May 25, 2010    Submit to DSA December 21, 2010    Authorize to Bid (2) June 28, 2011  BOE Approval July 19, 2011    Approval by DSA September 1, 2011*    Bid Opening December 6, 2011*    Award of Contract (1) December 13, 2011*    Notice to Proceed January 3, 2012*    Substantial Completion June 24, 2013*    Planned Occupancy August 2, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 17     Fairmeadow Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    Gelfand received all DSA comments on August 29, 2011, and they  have scheduled backcheck appointments for October 25 ‐ 27.  O’Connor is concurrently performing site verification and  backchecking constructability review comments with Gelfand, and  finalizing front end documents. Prequalification of contractors will  commence in September. Bidding is anticipated to occur in  November 2011, with construction planned to begin in January  2012.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule per DSA’s anticipated review time, and is within budget.   Funding  State Funds $0  Strong Schools Bond Funds $9,327,500  Other Funding $0  Total $9,327,500    Budget  Salaries and Benefits $0  Supplies $7,697  Contracts & Services $1,831,019  Construction & Equipment $7,443,000  Soft Costs Contingency $45,784  Total $9,327,500    Percent of Budget Expended 8.5%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 13, 2009  BOE Approval October 27, 2009    Conceptual Design (2) March 23, 2010  BOE Approval April 6, 2010    Schematic Design (2) September 14, 2010  BOE Approval September 28, 2010    Submit to DSA April 18, 2011     Authorize to Bid (2) October 11, 2011*  BOE Approval October 25, 2011*    Approval by DSA October 27, 2011*    Bid Opening December 13, 2011*    Award of Contract (1) January 10, 2012*    Notice to Proceed January 24, 2012*    Substantial Completion May 8, 2013*    Planned Occupancy August 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 18   Ohlone Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    Jeff Luchetti Construction completed the modernization portion  of the work prior to the beginning of classes on August 23, 2011.  This included the front parking and drop‐off area and the  installation of Smartboards, sound assist systems, ventilation  improvements, and lighting systems.  The kindergarten bathrooms  were also remodeled with new ceramic tile, plumbing fixtures,  flooring and ADA improvements.  Current work on the new two‐story  building is focused on casework installation, tackable surface wall  covering, and t‐bar ceiling installation. Exterior pavers, sealant on the  green roof, and concrete flatwork around the building are also  underway.            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $11,667,965  Other Funding $0  Total $11,667,965    Budget  Salaries and Benefits $0  Supplies $5,467  Contracts & Services $2,364,267  Construction & Equipment $9,169,121  Soft Costs Contingency $129,110  Total $11,667,965    Percent of Budget Expended 52.6%    Change Order Contingency  • Starting Contingency Balance $748,400  • Remaining Contingency Balance $687,595  • Percent of Changes 0.8%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) March 3, 2009  BOE Approval March 17, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA November 24, 2009    Authorize to Bid (2) April 27, 2010  BOE Approval May 11, 2010    Approval by DSA May 18, 2010    Bid Opening July 13, 2010    Award of Contract (1) August 3, 2010    Notice to Proceed August 19, 2010    Substantial Completion November 7, 2011*    Planned Occupancy January 3, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 19   Duveneck Elementary School  New Classroom Buildings and Modernization  A. PROJECT STATUS    Gelfand conducted a pre‐submission meeting with DSA on  August 22, 2011 and met the new principal to review the scope  of the project on August 25, 2011.  The master plan was on  display at the Duveneck back‐to‐school night on August 30, 2011  to promote project awareness and answer any questions.   Gelfand continues design development documents and  anticipates submitting a package for district review in  early October 2011.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Gelfand Partners proceeding with design development.  • Project plans on display during Duveneck’s Back‐to‐School night. Funding  State Funds $0  Strong Schools Bond Funds $11,088,757  Other Funding $0  Total $11,088,757    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,129,387  Construction & Equipment $8,803,087  Soft Costs Contingency $156,283  Total $11,088,757    Percent of Budget Expended 1.7%  Current Phase: Design Development    Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) December 14, 2010  BOE Approval January 11, 2011    Schematic Design (2) June 14, 2011  BOE Approval June 28, 2011    Submit to DSA January 19, 2012*     Approval by DSA September 6, 2012*    Authorize to Bid (2) September 28, 2012*  BOE Approval October 9, 2012*    Bid Opening November 22, 2012*    Award of Contract (1) November 27, 2012*    Notice to Proceed December 5, 2012*    Substantial Completion April 16, 2014*    Planned Occupancy August 1, 2014*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 20   Technology Improvements  A. PROJECT STATUS     The District purchased computers, utilizing bond funds, throughout the  2010/11 school year.  During the year there was a notable shift from  desktops and laptops to handheld devices, primarily at the elementary  school level. At the end of the 2010/11 school year, orders were placed for  equipment to be used in the 2011/12 school year.  Implementation of the Voice‐over‐ IP (VoIP) telephone system is scheduled to begin at the district office this fall.   A  major upgrade to the District's network is currently out for re‐bid, with bids opening  in September 2011.       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • New computers for 2011/12 school year being delivered to school sites.    Funding  State Funds $0  Strong Schools Bond Funds $7,101,063  Other Funding $0  Total $7,101,063    Budget  Salaries and Benefits $0  Supplies & Computers $6,718,468  Contracts & Services $180,173  Construction & Equipment $202,422  Soft Costs Contingency $0  Total $7,101,063    Percent of Budget Expended 52.5%    Current Phase: N/A   Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 21   Gunn High School  Air Conditioning of Existing Buildings  A. PROJECT STATUS    Best Contracting Services Inc. completed the installation of air  conditioning units and cool roof coating.  Remaining punchlist items  and EMS programming continues, though the units are functioning  and in use.  The final change order is negotiated and will be executed  after all equipment is commissioned.  Project close‐out has  commenced.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.7    D. PROJECT OVERVIEW:  • Project in close‐out.    Funding  State Funds $0  Strong Schools Bond Funds $2,600,000  Other Funding $0  Total $2,600,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $455,010  Construction & Equipment $2,120,580  Soft Costs Contingency $24,410  Total $2,600,000    Percent of Budget Expended 58.1%  Current Phase: Close‐out   Schedule:  Architect Contract (2) March 27, 2010  BOE Approval April 6, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA October 20, 2010    Approval by DSA February 10, 2011    Authorize to Bid (2) February 22, 2011  BOE Approval March 8, 2011    Bid Opening March 28, 2011    Award of Contract (1) April 8, 2011    Notice to Proceed April 11, 2011    Substantial Completion August 8, 2011      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 22   J.L. Stanford Middle School ‐ Interim Classrooms  A. PROJECT STATUS    Coulter Construction completed the work on the relocated  portables.  Project close‐out has commenced.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:  • Project completed on schedule and is currently in close‐out.      Funding  State Funds $0  Strong Schools Bond Funds $17,184,699  Other Funding $0  Total $17,184,699    Budget  Salaries and Benefits $0  Supplies $3,458  Contracts & Services $3,408,170  Construction & Equipment $13,421,500  Soft Costs Contingency $351,571  Total $17,184,699    Percent of Budget Expended 80.5%    This portable relocation project funded by main JLS  project.    Current Phase: Occupancy ‐August 11, 2011    Schedule:  Approval by DSA April 19, 2011  Jordan Project June 16, 2011*     Authorize to Bid (2) May 10, 2011  BOE Approval May 24, 2011    Bid Opening June 1, 2011    Award of Contract (1) June 13, 2011    Notice to Proceed June 20, 2011    Substantial Completion August 8, 2011    Planned Occupancy August 15, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 23   Fairmeadow Elementary School  Portable Relocation Project  A. PROJECT STATUS     Guerra Construction Group completed the work on the relocated  portable on August 8, 2011.  The JLS project is funding the relocation of  this portable for the construction of JLS’ new 2‐story classroom building.   Project close‐out has commenced.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 6.4    D. PROJECT OVERVIEW:  • Project completed ahead of schedule on August 8, 2011.       Funding  State Funds $0  Strong Schools Bond Funds $17,184,699  Other Funding $0  Total $17,184,699    Budget  Salaries and Benefits $0  Supplies $3,458  Contracts & Services $3,408,170  Construction & Equipment $13,421,500  Soft Costs Contingency $351,571  Total $17,184,699    Percent of Budget Expended 9.7%    This portable relocation project funded by main JLS  project.  Current Phase: Occupancy ‐August 8, 2011    Schedule:  Architect Contract (2) February 15, 2011  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA March 3, 2011     Approval by DSA March 3, 2011    Authorize to Bid (2) May 11, 2011  BOE Approval May 24, 2011    Bid Opening June 14, 2011    Award of Contract (1) June 14, 2011    Notice to Proceed June 20, 2011    Substantial Completion August 1, 2011    Planned Occupancy August 8, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 24   Elementary Classroom Improvements  Interactive Whiteboards and Sound Assist System Installation  A. PROJECT STATUS    Coulter Construction installed SmartBoards and Lightspeed sound assist systems, and completed the  installation April 29, 2011.  Phase 4 and 5 schools were the final elementary schools to receive interactive  whiteboards and sound assist systems.          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • All SmartBoards and Lightspeed sound systems installed.           Funding  State Funds $0  Strong Schools Bond Funds $8,887,522  Other Funding $0  Total $8,887,522    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,195,880  Construction & Equipment $7,488,707  Soft Costs Contingency $202,935  Total $8,887,522    Percent of Budget Expended 22.9%    Current Phase: Complete ‐May 15, 2011    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) November 9, 2010  BOE Approval November 23, 2010    Bid Opening February 25, 2011    Award of Contract (1) March 8, 2011    Notice to Proceed March 9, 2011    Completion May 15, 2011      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 25   Palo Alto High School   Multi‐Use Field  A. PROJECT STATUS    The fields were available for play on February 1, 2011, and final change  order negotiations completed on March 9, 2011.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.14    D. PROJECT OVERVIEW:  • Field was open for use on February 1, 2011.     Funding  State Funds $0  Strong Schools Bond Funds $2,609,680  Other Funding $984,063  Total $3,593,743    Budget  Salaries and Benefits $0  Supplies $1,506  Contracts & Services $729,418  Construction & Equipment $2,860,125  Soft Costs Contingency $2,694  Total $3,593,743     Percent of Budget Expended 99.8%    Change Order Contingency  • Starting Contingency Balance $269,300  • Remaining Contingency Balance $230,579  • Percent of Changes 1.7%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –February 1, 2011    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 18, 2008  BOE Approval December 09, 2008    Submit to DSA March 19, 2009     Approval by DSA September 30, 2009    Authorize to Bid (2) February 24, 2009  BOE Approval March 17, 2009    Bid Opening March 16, 2010    Award of Contract (1) April 7, 2010    Notice to Proceed June 1, 2010    Substantial Completion January 31, 2011    Planned Occupancy February 1, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 26   Gunn High School  Industrial Arts Addition and Renovation  A. PROJECT STATUS    This facility was available for instruction in January 2010. DSA  closeout is anticipated to occur by the end of August 2011.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11    D. PROJECT OVERVIEW:  • The building occupied as scheduled, and the project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,082,402  Other Funding $0  Total $5,082,402    Budget  Salaries and Benefits $1,061  Supplies $88,985  Contracts & Services $1,000,861  Construction & Equipment $3,991,495  Soft Costs Contingency $0  Total $5,082,402    Percent of Budget Expended 99.3%    Change Order Contingency  • Starting Contingency Balance $349,000  • Remaining Contingency Balance $141,967  • Percent of Changes 41.6%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –January 4, 2010    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA June 17, 2008     Approval by DSA December 24, 2008    Authorize to Bid (2) October 14, 2008  BOE Approval October 28, 2008    Bid Opening December 16, 2008    Award of Contract (1) December 24, 2008    Notice to Proceed January 6, 2009    Substantial Completion November 25, 2009    Planned Occupancy January 4, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 27   Gunn High School  Aquatic Center  A. PROJECT STATUS    This facility was available for use in July 2009, and has been closed  out with DSA.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.12    D. PROJECT OVERVIEW:  • This project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $4,865,423  Other Funding $0  Total $4,865,423    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $647,169  Construction & Equipment $4,218,253  Soft Costs Contingency $0  Total $4,865,423    Percent of Budget Expended 99.9%    Change Order Contingency  • Starting Contingency Balance $389,887  • Remaining Contingency Balance $195,148  • Percent of Changes 49.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –June 15, 2009    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA December 11, 2007     Approval by DSA April 24, 2008    Authorize to Bid (2) April 8, 2008  BOE Approval April 22, 2008    Bid Opening May 28, 2008    Award of Contract (1) June 4, 2008    Notice to Proceed December 6, 2008    Substantial Completion June 15, 2009    Planned Occupancy June 15, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 28   Middle School Pre‐Design  Jordan, J.L. Stanford and Terman  A. PROJECT STATUS    AEDIS presented recommended concept plans for each campus to the  Board of Education for approval on September 8, which became the  program documents for the new projects at each campus.  These  projects for pre‐design work have been closed, and funds will be  transferred to the program contingency on June 14, 2011.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12    D. PROJECT OVERVIEW:  • This project has been completed. Board approval received on September 8, 2009. Funding  State Funds $0  Strong Schools Bond Funds $56,489  Other Funding $0  Total $56,489    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $56,489  Construction & Equipment $0  Soft Costs Contingency $0  Total $56,489    Percent of Budget Expended 96.8%    Current Phase: Complete   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 29   Garland Elementary School  Campus Modernization  A. PROJECT STATUS    The Board of Education has put new development for Garland on  hold until a growth plan is established for the elementary schools.   The board voted to terminate the lease with Stratford School in  June 2011, so that future plans for growth at the elementary  schools can begin on this campus as early as June 2014.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10    D. PROJECT OVERVIEW:  • This project has been placed on hold. Funding  State Funds $0  Strong Schools Bond Funds $22,178,544  Other Funding $0  Total $22,178,544    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,915,789  Construction & Equipment $17,400,000  Soft Costs Contingency $862,755  Total $22,178,544    Percent of Budget Expended 1.3%  Current Phase: On Hold   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) February 10, 2009  BOE Approval February 24, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 30   Elementary School Teaching Walls  Phase 1 Schools  A. PROJECT STATUS    The district placed this project on hold after review of the  implementation of other classroom improvements, as  recommended by the elementary school principals.  This  project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary below).              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.9    D. PROJECT OVERVIEW:  • This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary  above).            Funding  State Funds $0  Strong Schools Bond Funds $7,044,987  Other Funding $0  Total $7,044,987    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,341,394  Construction & Equipment $5,498,498  Soft Costs Contingency $205,095  Total $7,044,987    Percent of Budget Expended 1.6%  Current Phase: Project Renamed. See Classroom      Improvements Project    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates –Subject to Change Page | 31   High School Master Plan  Palo Alto HS and Gunn HS  A. PROJECT STATUS    The Board of Education (BOE) approved the master plans for both  high schools, and these projects have been closed, with funds  transferred to the respective campus reserve funds.                    B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14    D. PROJECT OVERVIEW:  • Group 2 project planning at the high schools will re‐commence in fall 2011.                Funding  State Funds $0  Strong Schools Bond Funds $285,387  Other Funding $0  Total $285,387    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $285,387  Construction & Equipment $0  Soft Costs Contingency $0  Total $285,387    Percent of Budget Expended 86.2%  Current Phase: Master Planning    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Initial Master Plan Approval (2) September 8, 2009  BOE Approval September 22, 2009    Paly CEQA Approval (2) February 9, 2010  BOE Approval February 23, 2010    Gunn Master Plan Update (2) March 23, 2010  BOE Approval April 6, 2010    Gunn CEQA Approval (2) April 27, 2010   BOE Approval May 11, 2010     Master Plan Revision Approval (2) September 14, 2010  Paly MP Revision Approval (2) October 9, 2010  Gunn MP Revision Approval (2) October 12, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 32   Hoover Elementary School  Pre‐Design  A. PROJECT STATUS    This project has been put on hold until a growth plan is established for the  elementary schools.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Project is currently on hold.                Funding  State Funds $0  Strong Schools Bond Funds $8,575,389  Other Funding $0  Total $8,575,389    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,643,477  Construction & Equipment $6,831,912  Soft Costs Contingency $100,000  Total $8,575,389    Percent of Budget Expended 0.4%  Current Phase: On Hold   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) November 9, 2010  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A  Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 33   Elementary Classroom Improvements  Phase 1 – Barron Park and El Carmelo  A. PROJECT STATUS    DSA comments were returned to Gelfand for Phase 1 plans that  include new lighting, adding operable windows and coverings,  ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo elementary schools.   The authorization to bid has been placed on hold pending further discussions with the BOE about elementary  growth planning.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • This project has been placed on hold.        Funding  State Funds $0  Strong Schools Bond Funds $8,153,022  Other Funding $0  Total $8,153,022    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,195,880  Construction & Equipment $6,754,207  Soft Costs Contingency $202,935  Total $8,153,022    Percent of Budget Expended 22.9%    Phase 1 Schools: Barron Park and El Carmelo  Current Phase:  On Hold    Schedule:  Architect Contract (2) June 8, 2010  BOE Approval June 22, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 9, 2010  BOE Approval December 7, 2010    Submit to DSA December 23, 2010     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  OHS WEST:260388860.1 A-1 EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. Numbers Added A-2 OHS WEST:260388860.1 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. A-3 OHS WEST:260388860.1 3. GUNN HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Demolish old library building. 3. Replace temporary classrooms with permanent classrooms. 4. Construct additional restrooms. 5. Construct second gymnasium. 6. Construct new soccer field. 7. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 9. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 10. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 11. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 12. Replace swimming pool with new 35-meter pool, pool equipment and support structures, pool decking, bleachers, storage, restrooms, showers, associated equipment. 13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace athletic equipment. 14. Modernize football stadium, including new bathrooms and concession stands. A-4 OHS WEST:260388860.1 4. PALO ALTO HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Construct additional restrooms. 4. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 6. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 7. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 8. Library modernization and building interior improvements, including infrastructure and major building system upgrades. 9. Renovation or replacement of the Tower Building to accommodate administration, classroom and program support space. 10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility improvements; construction of new restrooms; install new roofing; replace doors and windows; replace gymnasium floors and athletic equipment, bleachers and renovation of interior. Renovation or replacement of weight training facility. 11. Construct new theater building. 12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing and storage. 13. Modernize football stadium, including replace bleachers; new bathrooms and concession stands. 14. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. A-5 OHS WEST:260388860.1 5. OTHER DISTRICT-WIDE PROJECTS Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and equipment for all classrooms, athletic facilities and other facilities, as needed. 1. Replace existing or acquire new computers, technology and related equipment on an ongoing basis. 2. Establish a planned maintenance fund to address maintenance work expected to be needed to all District facilities on an ongoing basis (other than as may be necessary for current maintenance, operation or repairs), in order to implement the District’s comprehensive facilities maintenance plan. 3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease- purchase arrangements, or execute purchase option under a lease for any of these authorized facilities. 4. If and as opportunities become available, and to the extent the Board of Education determines that bond funds are available for the purpose, acquisition of land and other interests in real property for future school buildings and other District facilities, and construction of such facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise listed. 5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field equipment and facilities (including nets, basketball standards, goals and goalposts, backstops), field lighting, etc. 6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS 1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead, etc., where necessary. 2. Address unforeseen conditions revealed by construction/modernization (including plumbing or gas line breaks, dry rot, seismic, structural, etc.). 3. Other improvements required to comply with existing building codes, including the Field Act, and access requirements of the Americans with Disabilities Act (ADA). 4. Site preparation/restoration in connection with new construction, renovation or remodeling, or installation or removal of relocatable classrooms, including ingress and egress, demolition of existing structures, removing, replacing, or installing irrigation and drainage, utility lines (such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any necessary easements, licenses, or rights of way to the property. 5. Rental or construction of storage facilities and other space on an interim basis, as needed to accommodate construction materials, equipment, and personnel, and interim classrooms (including relocatables) for students and school functions or other storage for classroom materials displaced during construction. A-6 OHS WEST:260388860.1 7. RENOVATION/MODERNIZATION (DEFINED) For purposes of the Bond Project List, renovation and modernization projects are intended to restore the building systems and infrastructure, weather protections, finishes, and technology, or reallocate and reorganize space, to a condition that will provide a sustainable, functional educational and administrative environment for future years, comparable to new construction. Renovation projects may include, but are not limited to nor necessarily encompass, all of the following, depending upon the age, condition and needs of each particular school facility: 1. upgrade electrical, communication, fire alarm, and similar building systems as well as main power service and distribution, which may include active and passive solar power and heating system acquisition, installation and construction 2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply, meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within buildings and sites and to connect with city supply and drainage systems 3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient heating and air cooling systems (HVAC), including installing energy management systems (EMS); 4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and fixtures, as necessary; 5. Repair, modify and construct structural elements of the existing structure as necessary; 6. Replace or repair aging roofs with similar materials or District standard materials; 7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes, doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces (including white boards, marker boards, tack boards, television mounts, scoreboards, fire extinguishers, kitchen cabinets/equipment, etc.); 8. Upgrade, modify and construct restroom facilities; 9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24 requirements; 10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood siding, paint, etc.); replace doors and windows 11. Modify, expand, separate, convert and construct school support areas; staff work and lunch areas; and educational areas to provide adequate, functional environments; 12. Modify, replace and construct functional components of altered or replaced building components (including rainwater leaders, fascias, mansards, etc.); ™ For any project involving renovation, modernization, remodeling or rehabilitation of a building or the major portion of a building, the District may proceed with new replacement construction instead (including any necessary demolition), if the Board of Education determines that replacement and new construction is more practical than rehabilitation and renovation, considering the building’s age, condition, expected remaining life, comparative cost, and other relevant factors.