Monthly Reports 2011-07 (Jul)
MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
July 2011
Current Strong Schools Bond
Capital Improvement Projects
Prepared by
O’Connor Construction Management, Inc.
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Attachment 2 – Master Program Schedule Summary
Capital Projects
Gunn High School – New Classroom Buildings A & B page 7
Gunn High School – Parking and Drop‐off Sitework Improvement page 8
Gunn High School – New Gymnasium page 9
Gunn High School – Air Conditioning of Existing Buildings page 10
Palo Alto High School – Athletic Stadium Improvements page 11
Palo Alto High School – Classroom Building and Media Arts page 12
Palo Alto High School – Performing Arts Center page 13
Jordan Middle School page 14
Jordan Middle School – Interim Classrooms page 15
J.L. Stanford Middle School page 16
J.L. Stanford Middle School – Interim Classrooms page 17
Terman Middle School page 18
Fairmeadow Elementary School page 19
Fairmeadow Elementary School – Portable Relocation page 20
Ohlone Elementary School page 21
Duveneck Elementary School page 22
Technology page 23
Completed Capital Projects
Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 24
Palo Alto High School – Multi‐use Field page 25
Gunn High School – Industrial Arts Renovation page 26
Gunn High School – Aquatic Center page 27
Middle School Pre‐Design page 28
Inactive Capital Projects
Garland Elementary School page 29
Elementary School Teaching Walls – Phase 1 Schools page 30
High School Master Plan page 31
Hoover Elementary School page 32
Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo page 33
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
Gunn High School – New Classroom Buildings A & B
Six bids were received from prequalified contractors on July 14, 2011, with BRCO Constructors being the lowest
responsive bidder at $17.6M. As anticipated, the project bids were over budget, therefore District staff
recommended the acceptance of a budget augmentation to the classroom project from the savings received from
the gymnasium project bid. The contract was awarded to BRCO Constructors at the July 22, 2011 BOE meeting,
along with the budget augmentation. A construction kick‐off meeting is scheduled for August 2, 2011 and BRCO is
anticipated to begin mobilization August 1, 2011.
Gunn High School – Parking and Drop‐off Sitework Improvement
Design for the parking and drop‐off improvements will recommence in conjunction with the planning of group 2
projects in fall 2011.
Gunn High School – New Gymnasium
Six bids were opened July 13, 2011, with SJ Amoroso Construction being the lowest responsive bidder. The project
bid at $9.2M which is under the original construction budget of $10.4M. The contract was awarded to SJ Amoroso
Construction at the July 20, 2011 BOE meeting, and a construction kick‐off meeting is scheduled for August 2,
2011.
Gunn High School – Air Conditioning of Existing Buildings
Best Contracting Services Inc. is nearing completion on the installation of air conditioning units and cool roof
coating. Testing of the installed units was completed on July 29, 2011 and punchlist items are expected to be
completed before August 8, 2011.
Palo Alto High School – Athletics Stadium Improvements
The bleacher project received initial DSA Approval on July 8, 2011. The Bleacher project is currently bidding with
bids due on August 18, 2011. A contract award is scheduled for August 23, 2011, followed by formal design of the
bleachers by a bleacher manufacturer to submit to DSA for final approval. Fabrication and installation of bleachers
is anticipated in late spring 2012.
The Concessions and Site Improvements package received DSA Approval on July 26, 2011. The concessions project
estimates are being finalized, and are anticipated to be over budget. Bidding is anticipated to occur in September,
followed by award and construction in November 2011.
Palo Alto High School – Classroom Building and Media Arts Building
A contract was awarded to Taisei Construction on July 12, 2011. Staff issued a notice to proceed on July 27, 2011.
A construction kick‐off meeting occurred on July 27, 2011, and Taisei Construction is anticipated to begin
mobilization August 1, 2011.
Palo Alto High School – Performing Arts Center (PAC)
During a discussion with site staff and the BOE during the June 28, 2011 meeting, the BOE requested that DLM and
staff consider a facility to accommodate at least 100 more seats above the 466 seat scheme recommended by
staff. DLM has developed a design that meets this request, with a total of 575 seats. OCMI is conducting an
estimate before reviewing this design scheme with staff at the next FSC meeting in September.
Jordan Middle School
DSA approval is anticipated in late August 2011. AEDIS and staff met July 27, 2011 to discuss strategies to identify
potential alternates. DSA is requiring campus‐wide ADA compliance improvements, which will add cost to the
project. Prequalification of contractors is underway, and the project is scheduled to bid in September 2011, with
construction to commence in November 2011.
Page | 4
Jordan Middle School ‐ Interim Classrooms
Bids were opened on July 14, 2011, and Coulter Construction was awarded the project at the July 20, 2011 BOE
meeting. A construction kick‐off meeting was conducted on July 26, 2011 and Coulter began work on July 28,
2011. The portables are anticipated to be complete by September 30, 2011. The project is funded by bond funds
and impact fees.
J.L. Stanford Middle School
Approval from DSA is anticipated in early 2012. The project is currently within budget. Final estimates, and
constructability reviews will occur in fall 2011.
J.L. Stanford Middle School ‐ Interim Classrooms
Coulter Construction relocated the two portables to the new location. Underground utilities for the portables and
the future building were installed. Completion and move‐in are scheduled for mid‐ August for the beginning of
school.
Terman Middle School
DSA approval is anticipated in August 2011. Prequalification of contractors is underway, and the project is
scheduled to bid in September 2011, with construction to commence in November 2011. The project is currently
within budget.
Fairmeadow Elementary School – New Classroom Building and Modernization
Gelfand implemented cost savings measures to bring the project back within budget. Additional structural plans
were submitted to DSA for review, and comments are anticipated to be received by August 19, 2011. Bidding is
scheduled to occur in November 2011, with construction planned to begin in January 2012.
Fairmeadow Elementary School – Portable Relocation
Guerra Construction Group commenced work on July 5, 2011. The portable was relocated to the new location July
22, 2011 and work within the building will be complete by August 1, 2011. The JLS project is funding the relocation
of this portable to provide the required setback for the construction of JLS’ new 2‐story classroom building.
Ohlone Elementary School – New Classroom Building and Modernization
Jeff Luchetti Construction continued work on the new building, modernization of the existing buildings, and the
front parking and drop‐off area. For the new building, mechanical, electrical, plumbing and fire sprinkler rough‐ins
are nearly complete. Interior finishes including painting, T‐bar ceiling, casework, and ceramic tile installation work
continues. Exterior doors are hung and the pavers for the green roof are scheduled to be installed next month.
For the modernization, new light fixtures have been installed and installation of new windows, interactive white
boards, and sound assist systems are nearly complete. Final cleaning will occur in August, prior to the beginning of
classes on August 23, 2011.
Duveneck Elementary School – New Classroom Buildings and Modernization
Gelfand commenced design development. Anticipated meetings with district and site staff will be scheduled in
August 2011.
Technology
The District purchased computers, utilizing bond funds, throughout the 2010/11 school year. During the year
there was a notable shift from desktops and laptops to handheld devices, primarily at the elementary school level.
At the end of the school year, orders were placed for equipment to be used in the 2011/12 school year.
Implementation of the Voice over IP (VoIP) telephone system began in July 2011, starting at the district office. A
major upgrade to the District's network is currently out to bid with bids opening in August 2011.
Page | 5
COMPLETED CAPITAL PROJECTS
Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems
Coulter Construction installed SmartBoards and Lightspeed sound assist systems, and completed the installation
April 29, 2011. Phase 4 and 5 schools were the final elementary schools to receive interactive whiteboards and
sound assist systems.
Palo Alto High School – Multi‐use Field
The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9,
2011.
Gunn High School – Industrial Arts Addition & Renovation
This facility was available for instruction in January 2010. DSA closeout is anticipated to occur by the end of August
2011.
Gunn High School – Aquatic Center
This facility was available for use in July 2009, and has been closed out with DSA.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education for approval on
September 8, which became the program documents for the new projects at each campus. These projects for pre‐
design work have been closed, and funds will be transferred to the program contingency on June 14, 2011.
INACTIVE CAPITAL PROJECTS
Garland Elementary School Renovation
The Board of Education has put new development for Garland on hold until a growth plan is established for the
elementary schools. The board voted to terminate the lease with Stratford School in June 2011, so that future
plans for growth at the elementary schools can begin on this campus as early as June 2014.
Elementary School Teaching Walls – Phase 1 Schools
The district placed this project on hold after review of the implementation of other classroom improvements, as
recommended by the elementary school principals. This project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary below).
High School Master Plan
The Board of Education (BOE) approved the master plans for both high schools, and these projects have been
closed, with funds transferred to the respective campus reserve funds.
Hoover Elementary School – Pre‐Design
This project has been put on hold until a growth plan is established for the elementary schools.
Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo
DSA comments were returned to Gelfand for Phase 1 plans that include new lighting, adding operable windows
and coverings, ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo
elementary schools. The authorization to bid has been placed on hold pending further discussions with the BOE
about elementary growth planning
Page | 6
Board Actions in July
July 12, 2011
Action 1 – Authorization to Award a Contract to Taisei Construction, Inc. for Construction of a New Classroom
Building, a Central Utility Plant, and a New Media Arts Center at Palo Alto High School
July 20, 2011
Consent 1 – Authorization to Bid Strong Schools Bond Projects for Jordan and Terman Middle Schools
Consent 2 – Authorization to Bid for Palo Alto High School Stadium Field
Action 5 – Authorization to Award a Contract to S.J. Amoroso Construction Co., Inc. for Construction of the Gunn
High School New Gymnasium Project
Action 6 – Authorization to Award a Contract to Coulter Construction, Inc. for Installation of Six Modular Classroom
Buildings at Jordan Middle School
July 22, 2011
Action 1 – Authorization to Award a Contract for the Gun High School New Classroom Buildings A & B Project and
Adjust the Gunn Strong Schools Bond Budget
A B C C / A B - C C / B A - BGunn High School - High School Master Plan 142,389 136,009 117,416 82.5% 18,593 86.33% 6,381Gunn High School 1 - Aquatic Center 4,865,423 4,862,530 4,862,530 99.9% 0 100.00% 2,893Gunn High School 2 - I.A Building 5,082,402 5,049,540 5,044,731 99.3% 4,809 99.90% 32,862Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 24,120,000 4,154,519 2,809,440 11.6% 1,345,079 67.62% 19,965,481Gunn High School 5 - Parking & Drop Off improvements 3,940,000 310,125 22,063 0.6% 288,062 7.11% 3,629,875Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 1,701,857 828,343 6.0% 873,514 48.67% 12,128,143Gunn High School 7- A/C 2,600,000 2,140,632 645,172 24.8% 1,495,460 30.14% 459,368Gunn High School - Reserved 21,525,081 0 0 0.0% 0 0.00% 21,525,081Palo Alto High Schools - High School Master Plan 142,998 137,757 128,442 89.8% 9,315 93.24% 5,240Palo Alto High School 1 - Stadium Field 3,626,101 802,087 510,242 14.1% 291,845 63.61% 2,824,014Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,615,016 2,604,765 99.8% 10,251 99.61% -5,336Palo Alto high School 3 - New classroom & Media Art Building 37,140,000 33,032,862 3,228,938 8.7% 29,803,924 9.77% 4,107,138Palo Alto High School 4 - New Theater 17,720,000 1,364,138 219,893 1.2% 1,144,245 16.12% 16,355,862Palo Alto High School - Reserved 37,554,766 0 0 0.0% 0 0.00% 37,554,766Jordan Middle School -Program Management- MS Pre-Design 18,890 18,890 17,826 94.4% 1,064 94.37% 0Jordan Middle Schools 1- Interim Classrooms 600,342 289,547 171,289 28.5% 118,258 59.16% 310,795Jordan Middle School 2- Improvements 17,943,194 2,788,304 1,306,095 7.3% 1,482,209 46.84% 15,154,890J.L.S Middle School - Program Management- MS Pre-Design 18,799 18,799 18,408 97.9% 391 97.92% 0J.L.S Middle School 1 - Interim Classrooms 446,844 377,993 356,969 79.9% 21,024 94.44% 68,851 J.L.S Middle School 2- Improvements 17,184,699 3,061,792 1,470,891 8.6% 1,590,901 48.04% 14,122,907Terman Middle School - Program Management- MS Pre-Design 18,799 18,799 18,423 98.0% 376 98.00% 0Terman Middle School 1- Improvements 12,850,071 1,999,163 969,791 7.5% 1,029,372 48.51% 10,850,908PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 98,480 83,550 57.6% 14,930 84.84% 46,520Addison Elementary School 1-Phase I 5,199,727 21,267 21,267 0.4% 0 100.00% 5,178,460Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 11,088,757 246,281 183,281 1.7% 63,000 74.42% 10,842,476Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 1,549,538 786,496 8.4% 763,042 50.76% 7,777,962Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 70,550 57,165 0.7% 13,385 81.03% 8,504,839Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 11,288,079 5,980,990 51.3% 5,307,090 52.99% 379,886Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,153,022 2,004,891 1,863,784 22.9% 141,107 92.96% 6,148,131Elementary Schools - Reserved 5,075,688 0 0 0.0% 0 0.00% 5,075,688PAUSD - Program Management 6,651,992 3,953,835 3,543,665 53.3% 410,170 89.63% 2,698,156PAUSD - Technology 7,101,063 4,966,983 3,729,463 52.5% 1,237,519 75.09% 2,134,080PAUSD - Technology -Reserved 6,806,302 0 0 0.0% 0 0.00% 6,806,302PAUSD - Reserved 7,230,205 0 0 0.0% 0 0.00% 7,230,205Bond Issuance Cost 1,840,700 1,840,700 1,840,700 100.0% 0 100.00% 0Total352,294,796 91,208,020 43,727,918 47,480,102 261,086,776Prepared by: Business Services Department based on QSS accounting SystemBudget BalanceCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond7/31/2011Percent of ExpendedContract BalanceExpenditures
Activity IDActivity NameOriginalDurationemainingDurationchedule %ompleteStartFinishTotalFloatGunn ACGunn AC4441010%01-Jan-10 A19-Dec-11-3Gunn - PGunn - Parking and Drop Off10595600%01-Sep-09 A20-Sep-130ClassrooClassroom Improvements16900%02-Sep-10 A22-Apr-11 APaly - AtPaly - Athletic Stadium Renovation Project9003990%17-Aug-09 A07-Feb-130New PerfNew Performing Arts Center (PAC)15309160%09-Sep-09 A02-Feb-15-708Garland Garland School Modernization16800%03-Nov-08 A24-Jun-09 AFairmeadFairmeadow Elementary School11945140%14-Dec-09 A01-Aug-13-316DuvenecDuveneck Elementary School11027850%13-May-10 A01-Aug-14-577Hoover EHoover Elementary School14600%12-May-10 A01-Dec-10 ATeachingTeaching Walls Casework17200%06-Apr-09 A28-Sep-09 AGunn- InGunn- Industrial Arts Renovation45100%01-Oct-08 A24-Jun-10 AJordan NJordan New Classroom Wing & Modernization12415210%03-Nov-08 A29-Jul-13-313Gunn NeGunn New Gym9433490%21-Apr-09 A30-Nov-12-141Gunn NeGunn New Classroom Buildings A and B10414460%20-Apr-09 A16-Apr-13-238Paly NewPaly New Media Arts and Classroom Building11045090%20-Apr-09 A12-Jul-13-301StanfordStanford New Classroom Wing12665560%03-Nov-08 A16-Sep-13-348Terman ATerman Admin Wing Addition & Modernization12275160%03-Nov-08 A23-Jul-13-308Paly - MuPaly - Multi Use Field Improvements72510%03-Nov-08 A01-Aug-11207Ohlone EOhlone Elementary School8481330%03-Nov-08 A02-Feb-1275JJASNJFAJJASNJFAJJASDJFAJJASDJFAJJASDJFAJJASDJAJJASDJFAJJA19-Dec-11, Gunn AC20-Sep-13, Gunn - Parking and Drop Off22-Apr-11 A, Classroom Improvements07-Feb-13, Paly - Athletic Stadium Renovation Project02-Feb-15, 24-Jun-09 A, Garland School Modernization01-Aug-13, Fairmeadow Elementary School01-Aug-14, Duveneck E01-Dec-10 A, Hoover Elementary School28-Sep-09 A, Teaching Walls Casework24-Jun-10 A, Gunn- Industrial Arts Renovation29-Jul-13, Jordan New Classroom Wing & Mod30-Nov-12, Gunn New Gym16-Apr-13, Gunn New Classroom Buildings A and B12-Jul-13, Paly New Media Arts and Classroom 16-Sep-13, Stanford New Classroom Wing23-Jul-13, Terman Admin Wing Addition & Mod01-Aug-11, Paly - Multi Use Field Improvements02-Feb-12, Ohlone Elementary SchoolPAUSD Strong Schools Bond - Program Master ScheduleClassic WBS Layout24-Aug-11 17:16Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryPage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc.
Page | 7
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
Six bids were received from prequalified contractors on July 14, 2011,
with BRCO Constructors being the lowest responsive bidder at $17.6M.
As anticipated, the project bids were over budget, therefore District
staff recommended the acceptance of a budget augmentation to the
classroom project from the savings received from the gymnasium
project bid. The contract was awarded to BRCO Constructors at the July
22, 2011 BOE meeting, along with the budget augmentation. A
construction kick‐off meeting is scheduled for August 2, 2011 and BRCO
is anticipated to begin mobilization August 1, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
• Bids were opened on July 14, 2011 and BRCO was awarded the contract at the July 22, 2011 BOE meeting.
Funding
State Funds $0
Strong Schools Bond Funds $24,120,000
Other Funding $0
Total $24,120,000
Budget
Salaries and Benefits $13,253
Supplies $0
Contracts & Services $4,462,881
Construction & Equipment $19,567,102
Soft Costs Contingency $76,764
Total $24,120,000
Percent of Budget Expended 11.6%
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 22, 2011
Notice to Proceed August 1, 2011*
Substantial Completion February 23, 2013*
Planned Occupancy April 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
Design for the parking and drop‐off improvements will
recommence in conjunction with the planning of group 2 projects
in fall 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
• Design will recommence with the planning of group 2 projects.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $898,978
Construction & Equipment $2,919,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 0.6%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) October 25, 2011*
BOE Approval November 8, 2011*
Schematic Design (2) February 14, 2012*
BOE Approval February 28, 2012*
Submit to DSA June 1, 2012*
Approval by DSA November 30, 2012*
Authorize to Bid (2) November 19, 2012*
BOE Approval November 30, 2012*
Bid Opening January 11, 2013*
Award of Contract (1) February 15, 2013*
Notice to Proceed February 25, 2013*
Substantial Completion August 12, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Gunn High School
New Gymnasium
A. PROJECT STATUS
Six bids were opened July 13, 2011, with SJ Amoroso
Construction being the lowest responsive bidder. The project
bid at $9.2M which is under the original construction budget of
$10.4M. The contract was awarded to SJ Amoroso
Construction at the July 20, 2011 BOE meeting, and a
construction kick‐off meeting is scheduled for August 2, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
• Bids were received on July 13, 2011.
• SJ Amoroso was awarded the contract at the July 20, 2011 BOE meeting.
Funding
State Funds $0
Strong Schools Bond Funds $13,830,000
Other Funding $0
Total $13,830,000
Budget
Salaries and Benefits $0
Supplies $1,001
Contracts & Services $2,650,520
Construction & Equipment $11,094,450
Soft Costs Contingency $84,029
Total $13,830,000
Percent of Budget Expended 6.0%
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed August 8, 2011*
Substantial Completion September 11, 2012*
Planned Occupancy November 15, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
Best Contracting Services Inc. is nearing completion on the installation
of air conditioning units and cool roof coating. Testing of the installed
units was completed on July 29, 2011 and punchlist items are
expected to be completed before August 8, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
• Best Contracting Services, Inc. anticipated completion date is August 8, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $454,610
Construction & Equipment $2,120,580
Soft Costs Contingency $24,810
Total $2,600,000
Percent of Budget Expended 24.8%
Current Phase: Construction
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA October 20, 2010
Approval by DSA February 10, 2011
Authorize to Bid (2) February 22, 2011
BOE Approval March 8, 2011
Bid Opening March 28, 2011
Award of Contract (1) April 8, 2011
Notice to Proceed April 11, 2011
Substantial Completion August 8, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Athletic Stadium Improvements
A. PROJECT STATUS
The bleacher project received initial DSA Approval on July 8, 2011.
The Bleacher project is currently bidding with bids due on August
18, 2011. A contract award is scheduled for August 23, 2011,
followed by formal design of the bleachers by a bleacher
manufacturer to submit to DSA for final approval. Fabrication and
installation of bleachers is anticipated in late spring 2012.
The Concessions and Site Improvements package received DSA
approval on July 26, 2011. The concessions project estimates are
being finalized, and are anticipated to be over budget. Bidding is
anticipated to occur in September, followed by award and
construction in November 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
• Bleacher project is out to bid with bids due on August 18, 2011. The Concessions and Site Improvements
project was approved by DSA on July 26, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $3,626,101
Other Funding $0
Total $3,626,101
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $788,406
Construction & Equipment $2,795,621
Soft Costs Contingency $42,074
Total $3,626,101
Percent of Budget Expended 14.1%
Current Phase: Bid & Award (Bleachers)/DSA Review
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) February 22, 2011
BOE Approval March 8, 2011
Submit to DSA April 4, 2011
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA (Bleachers) January 17, 2012*
Approval by DSA (Concessions) December 9, 2011*
Bid Opening October 18, 2011*
Award of Contract (1) October 26, 2011*
Notice to Proceed November 11, 2011*
Substantial Completion August 1, 2012*
Planned Occupancy August 31, 2012*
* Anticipated Dates – Subject to Change
Page | 12
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
A contract was awarded to Taisei Construction on July 12, 2011. Staff
issued a notice to proceed on July 27, 2011. A construction kick‐off
meeting occurred on July 27, 2011, and Taisei Construction is
anticipated to begin mobilization August 1, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• BOE awarded to Taisei Construction on July 12, 2011 and a construction kick‐off meeting held on July 27,
2011.
Funding
State Funds $0
Strong Schools Bond Funds $37,140,000
Other Funding $0
Total $37,140,000
Budget
Salaries and Benefits $14,721
Supplies $0
Contracts & Services $7,001,769
Construction & Equipment $29,740,000
Soft Costs Contingency $383,510
Total $37,140,000
Percent of Budget Expended 8.7%
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA April 28, 2011
Bid Opening June 30, 2011
Award of Contract (1) July 12, 2011
Notice to Proceed August 1, 2011*
Substantial Completion June 20, 2013*
Planned Occupancy July 20, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Palo Alto High School
Performing Arts Center (PAC)
A. PROJECT STATUS
During a discussion with site staff and the BOE during the June 28, 2011
meeting, the BOE requested that DLM and staff consider a facility to
accommodate at least 100 more seats above the 466 seat scheme
recommended by staff. DLM has developed a design that meets this
request, with a total of 575 seats. OCMI is conducting an estimate before
reviewing this design scheme with staff at the next FSC meeting in
September.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
• Project schematic design is being reviewed and will now be submitted for BOE approval in the fall.
Funding
State Funds $0
Strong Schools Bond Funds $17,720,000
Other Funding $0
Total $17,720,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,684,187
Construction & Equipment $13,926,590
Soft Costs Contingency $109,223
Total $17,720,000
Percent of Budget Expended 1.2%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) June 14, 2011
BOE Approval September 27, 2011*
Submit to DSA May 18, 2012*
Approval by DSA December 11, 2012*
Authorize to Bid (2) December 12, 2012*
BOE Approval December 25, 2012*
Bid Opening February 19, 2012*
Award of Contract (1) March 8, 2013*
Notice to Proceed April 4, 2013*
Substantial Completion December 1, 2014*
Planned Occupancy January, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Jordan Middle School
A. PROJECT STATUS
DSA approval is anticipated in late August 2011. AEDIS and staff met
July 27, 2011 to discuss strategies to identify potential alternates.
DSA is requiring campus‐wide ADA compliance improvements,
which will add cost to the project. Prequalification of contractors is
underway, and the project is scheduled to bid in September 2011,
with construction to commence in November 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time. Budget estimates are
currently over budget.
Funding
State Funds $0
Strong Schools Bond Funds $17,943,194
Other Funding $0
Total $17,943,194
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,564,530
Construction & Equipment $13,949,500
Soft Costs Contingency $429,164
Total $17,943,194
Percent of Budget Expended 7.3%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA September 1, 2011*
Bid Opening October 18, 2011*
Award of Contract (1) October 25, 2011*
Notice to Proceed November 7, 2011*
Substantial Completion July 1, 2013*
Planned Occupancy August 15, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
Jordan Middle Schools ‐ Interim Classrooms
A. PROJECT STATUS
Bids were opened on July 14, 2011, and Coulter Construction
was awarded the project at the July 20, 2011 BOE meeting. A
construction kick‐off meeting was conducted on July 26, 2011
and Coulter began work on July 28, 2011. The portables are
anticipated to be complete by September 30, 2011. The project
is funded by bond funds and impact fees.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $300,171
Other Funding $300,171
Total $600,342
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $171,558
Construction & Equipment $428,020
Soft Costs Contingency $764
Total $600,342
Percent of Budget Expended 28.5%*
*Budget previously expended
Current Phase: Construction
Schedule:
Approval by DSA June 16, 2011
Authorize to Bid (2) June 14, 2011
BOE Approval June 28, 2011
Bid Opening July 14, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed July 27, 2011
Substantial Completion September 20, 2011*
Planned Occupancy October 1, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
J.L. Stanford Middle School
A. PROJECT STATUS
Approval from DSA is anticipated in early 2012. The
project is currently within budget. Final estimates, and
constructability reviews will occur in fall 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,699
Other Funding $0
Total $17,184,699
Budget
Salaries and Benefits $0
Supplies $3,458
Contracts & Services $3,408,170
Construction & Equipment $13,421,500
Soft Costs Contingency $351,571
Total $17,184,699
Percent of Budget Expended 8.6%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28, 2010
Submit to DSA May 6, 2011
Approval by DSA January 6, 2012*
Authorize to Bid (2) December 20, 2012*
BOE Approval January 10, 2012*
Bid Opening February 14, 2012*
Award of Contract (1) February 22, 2012*
Notice to Proceed March 5, 2012*
Substantial Completion June 24, 2013*
Planned Occupancy August 6, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
J.L. Stanford Middle School ‐ Interim Classrooms
A. PROJECT STATUS
Coulter Construction relocated the two portables to the new location.
Underground utilities for the portables and the future building were
installed. Completion and move‐in are scheduled for mid‐ August for
the beginning of school.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project on schedule. Anticipated completion date is August 8, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,699
Other Funding $0
Total $17,184,699
Budget
Salaries and Benefits $0
Supplies $3,458
Contracts & Services $3,408,170
Construction & Equipment $13,421,500
Soft Costs Contingency $351,571
Total $17,184,699
Percent of Budget Expended 8.6%
This portable relocation project funded by main JLS
project.
Current Phase: Construction
Schedule:
Approval by DSA April 19, 2011
Jordan Project June 16, 2011*
Authorize to Bid (2) May 10, 2011
BOE Approval May 24, 2011
Bid Opening June 1, 2011
Award of Contract (1) June 13, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 8, 2011*
Planned Occupancy August 15, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Terman Middle School
A. PROJECT STATUS
DSA approval is anticipated in August 2011. Prequalification of
contractors is underway, and the project is scheduled to bid in
September 2011, with construction to commence in November 2011.
The project is currently within budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $12,850,071
Other Funding $0
Total $12,850,071
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,533,760
Construction & Equipment $10,031,569
Soft Costs Contingency $284,742
Total $12,850,071
Percent of Budget Expended 7.5%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA August 19, 2011*
Bid Opening October 6, 2011*
Award of Contract (1) October 12, 2011*
Notice to Proceed October 27, 2011*
Substantial Completion June 24, 2013*
Planned Occupancy July 23, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Gelfand implemented cost savings measures to bring the project
back within budget. Additional structural plans were submitted to
DSA for review, and comments are anticipated to be received by
August 19, 2011. Bidding is scheduled to occur in November 2011,
with construction planned to begin in January 2012.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $9,327,500
Other Funding $0
Total $9,327,500
Budget
Salaries and Benefits $0
Supplies $7,697
Contracts & Services $1,831,019
Construction & Equipment $7,443,000
Soft Costs Contingency $45,784
Total $9,327,500
Percent of Budget Expended 8.4%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010
BOE Approval September 28, 2010
Submit to DSA April 18, 2011
Approval by DSA October 17, 2011*
Authorize to Bid (2) November 8, 2011*
BOE Approval November 22, 2011*
Bid Opening December 21, 2011*
Award of Contract (1) December 28, 2011*
Notice to Proceed January 3, 2012*
Substantial Completion May 8, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Fairmeadow Elementary School
Portable Relocation Project
A. PROJECT STATUS
Guerra Construction Group commenced work on July 5, 2011. The
portable was relocated to the new location July 22, 2011 and work
within the building will be complete by August 1, 2011. The JLS project
is funding the relocation of this portable to provide the required setback
for the construction of JLS’ new 2‐story classroom building.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 6.4
D. PROJECT OVERVIEW:
• Guerra Construction Group commenced work on July 5, 2011, and anticipated completion time is
August 1, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,699
Other Funding $0
Total $17,184,699
Budget
Salaries and Benefits $0
Supplies $3,458
Contracts & Services $3,408,170
Construction & Equipment $13,421,500
Soft Costs Contingency $351,571
Total $17,184,699
Percent of Budget Expended 8.6%
This portable relocation project funded by main JLS
project.
Current Phase: Construction
Schedule:
Architect Contract (2) February 15, 2011
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA March 3, 2011
Approval by DSA March 3, 2011
Authorize to Bid (2) May 11, 2011
BOE Approval May 24, 2011
Bid Opening June 14, 2011
Award of Contract (1) June 14, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 1, 2011*
Planned Occupancy August 10, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Jeff Luchetti Construction continued work on the new building,
modernization of the existing buildings, and the front parking and drop‐off
area. For the new building, mechanical, electrical, plumbing and fire
sprinkler rough‐ins are nearly complete. Interior finishes including
painting, T‐bar ceiling, casework, and ceramic tile installation work
continues. Exterior doors are hung and the pavers for the green roof are
scheduled to be installed next month. For the modernization, new light
fixtures have been installed and installation of new windows, interactive
white boards, and sound assist systems are nearly complete. Final cleaning
will occur in August, prior to the beginning of classes on August 23, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $0
Supplies $5,467
Contracts & Services $2,348,367
Construction & Equipment $9,169,121
Soft Costs Contingency $145,010
Total $11,667,965
Percent of Budget Expended 51.3%
Change Order Contingency
• Starting Contingency Balance $748,400
• Remaining Contingency Balance $690,961
• Percent of Changes 0.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010
Award of Contract (1) August 3, 2010
Notice to Proceed August 19, 2010
Substantial Completion November 7, 2011*
Planned Occupancy January 3, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Duveneck Elementary School
New Classroom Buildings and Modernization
A. PROJECT STATUS
Gelfand commenced design development. Anticipated meetings
with district and site staff will be scheduled in August 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand Parnters proceeding with design development.
Funding
State Funds $0
Strong Schools Bond Funds $11,088,757
Other Funding $0
Total $11,088,757
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,129,387
Construction & Equipment $8,803,087
Soft Costs Contingency $156,283
Total $11,088,757
Percent of Budget Expended 1.7%
Current Phase: Design Development
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) December 14, 2010
BOE Approval January 11, 2011
Schematic Design (2) June 14, 2011
BOE Approval June 28, 2011
Submit to DSA December 19, 2011*
Approval by DSA August 6, 2012*
Authorize to Bid (2) September 28, 2012*
BOE Approval October 9, 2012*
Bid Opening November 22, 2012*
Award of Contract (1) November 27, 2012*
Notice to Proceed December 5, 2012*
Substantial Completion April 16, 2014*
Planned Occupancy August 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Technology Improvements
A. PROJECT STATUS
The District purchased computers, utilizing bond funds, throughout the
2010/11 school year. During the year there was a notable shift from
desktops and laptops to handheld devices, primarily at the elementary
school level. At the end of the school year, orders were placed for
equipment to be used in the 2011/12 school year. Implementation of the Voice over
IP (VoIP) telephone system began in July 2011, starting at the district office. A
major upgrade to the District's network is currently out to bid with bids opening in
August 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• New computers for 2011/12 school year being delivered to school sites.
Funding
State Funds $0
Strong Schools Bond Funds $7,101,063
Other Funding $0
Total $7,101,063
Budget
Salaries and Benefits $0
Supplies & Computers $6,718,468
Contracts & Services $180,173
Construction & Equipment $202,422
Soft Costs Contingency $0
Total $7,101,063
Percent of Budget Expended 52.5%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Elementary Classroom Improvements
Interactive Whiteboards and Sound Assist System Installation
A. PROJECT STATUS
Coulter Construction installed SmartBoards and Lightspeed sound assist systems, and completed the
installation April 29, 2011. Phase 4 and 5 schools were the final elementary schools to receive interactive
whiteboards and sound assist systems.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• All SmartBoards and Lightspeed sound systems installed.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,195,880
Construction & Equipment $7,488,707
Soft Costs Contingency $202,935
Total $8,887,522
Percent of Budget Expended 22..9%
Current Phase: Complete ‐May 15, 2011
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) November 9, 2010
BOE Approval November 23, 2010
Bid Opening February 25, 2011
Award of Contract (1) March 8, 2011
Notice to Proceed March 9, 2011
Completion May 15, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
The fields were available for play on February 1, 2011, and final change
order negotiations completed on March 9, 2011.
Budget re‐alignment, approved by BOE on June 28, 2011, was performed
and reflected to this project budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
• Field was open for use on February 1, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $2,609,680
Other Funding $984,063
Total $3,593,743
Budget
Salaries and Benefits $0
Supplies $1,506
Contracts & Services $729,418
Construction & Equipment $2,860,125
Soft Costs Contingency $2,694
Total $3,593,743
Percent of Budget Expended 99.8%
Change Order Contingency
• Starting Contingency Balance $269,300
• Remaining Contingency Balance $230,579
• Percent of Changes 1.7%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –February 1, 2011
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 18, 2008
BOE Approval December 09, 2008
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) February 24, 2009
BOE Approval March 17, 2009
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion January 31, 2011
Planned Occupancy February 1, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
This facility was available for instruction in January 2010. DSA
closeout is anticipated to occur by the end of August 2011.
Budget re‐alignment, approved by BOE on June 28, 2011, was
performed and reflected to this project budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
• The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,082,402
Other Funding $0
Total $5,082,402
Budget
Salaries and Benefits $1,061
Supplies $88,985
Contracts & Services $1,000,861
Construction & Equipment $3,991,495
Soft Costs Contingency $0
Total $5,082,402
Percent of Budget Expended 99.3%
Change Order Contingency
• Starting Contingency Balance $349,000
• Remaining Contingency Balance $141,967
• Percent of Changes 41.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
Gunn High School
Aquatic Center
A. PROJECT STATUS
This facility was available for use in July 2009, and has been closed
out with DSA.
Budget re‐alignment, approved by BOE on June 28, 2011, was
performed and reflected to this project budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
• This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $4,865,423
Other Funding $0
Total $4,865,423
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $647,169
Construction & Equipment $4,218,253
Soft Costs Contingency $0
Total $4,865,423
Percent of Budget Expended 99.9%
Change Order Contingency
• Starting Contingency Balance $389,887
• Remaining Contingency Balance $195,148
• Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education for approval on September 8, which became the
program documents for the new projects at each campus. These
projects for pre‐design work have been closed, and funds will be
transferred to the program contingency on June 14, 2011.
Budget re‐alignment, approved by BOE on June 28, 2011, was
performed and reflected to this project budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
• This project has been completed. Board approval received on September 8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $56,489
Other Funding $0
Total $56,489
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $56,489
Construction & Equipment $0
Soft Costs Contingency $0
Total $56,489
Percent of Budget Expended 96.8%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 29
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education has put new development for Garland on
hold until a growth plan is established for the elementary schools.
The board will discuss terminating the lease to Stratford School in
June 2011, so that future plans for growth at the elementary
schools can begin on this campus as early as June 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,915,789
Construction & Equipment $17,400,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: On Hold
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 30
Elementary School Teaching Walls
Phase 1 Schools
A. PROJECT STATUS
The district placed this project on hold after review of the
implementation of other classroom improvements, as
recommended by the elementary school principals. This
project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.9
D. PROJECT OVERVIEW:
• This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary
above).
Funding
State Funds $0
Strong Schools Bond Funds $7,044,987
Other Funding $0
Total $7,044,987
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,341,394
Construction & Equipment $5,498,498
Soft Costs Contingency $205,095
Total $7,044,987
Percent of Budget Expended 1.6%
Current Phase: Project Renamed. See Classroom
Improvements Project
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates –Subject to Change
Page | 31
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
The Board of Education (BOE) approved the master plans for both
high schools, and these projects will be closed, with funds
transferred to the respective campus reserve funds.
Budget re‐alignment, approved by BOE on June 28, 2011, was
performed and reflected to this project budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
• Group 2 project planning at the high schools will re‐commence in fall 2011.
Funding
State Funds $0
Strong Schools Bond Funds $285,387
Other Funding $0
Total $285,387
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $285,387
Construction & Equipment $0
Soft Costs Contingency $0
Total $285,387
Percent of Budget Expended 86.2%
Current Phase: Master Planning
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010
Paly MP Revision Approval (2) October 9, 2010
Gunn MP Revision Approval (2) October 12, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 32
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
This project has been put on hold until a growth plan is established for the
elementary schools.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently on hold.
Funding
State Funds $0
Strong Schools Bond Funds $8,575,389
Other Funding $0
Total $8,575,389
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,643,477
Construction & Equipment $6,831,912
Soft Costs Contingency $100,000
Total $8,575,389
Percent of Budget Expended 0.4%
Current Phase: On Hold
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) November 9, 2010
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 33
Elementary Classroom Improvements
Phase 1 – Barron Park and El Carmelo
A. PROJECT STATUS
DSA comments were returned to Gelfand for Phase 1 plans that
include new lighting, adding operable windows and coverings,
ventilation, and replacement of ceiling tiles for classrooms at Barron
Park and El Carmelo elementary schools. The authorization to bid has
been placed on hold pending further discussions with the BOE about
elementary growth planning.
Budget re‐alignment, approved by BOE on June 28, 2011, was
performed and reflected to this project budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $8,153,022
Other Funding $0
Total $8,153,022
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,195,880
Construction & Equipment $6,754,207
Soft Costs Contingency $202,935
Total $8,153,022
Percent of Budget Expended 22.9%
Phase 1 Schools: Barron Park and El Carmelo
Current Phase: On Hold
Schedule:
Architect Contract (2) June 8, 2010
BOE Approval June 22, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 9, 2010
BOE Approval December 7, 2010
Submit to DSA December 23, 2010
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.