Monthly Reports 2011-05 (May) MMOONNTTHHLLYY  PPRROOGGRREESSSS  RREEPPOORRTT     Through  May 2011      Current Strong Schools Bond  Capital Improvement Projects  Prepared by     O’Connor Construction Management, Inc.  &  Gilbane Building Company  Page | 2   TABLE OF CONTENTS    Executive Summary         page 3   Attachment 1 – Consolidated Expenditure Report          Attachment 2 – Master Program Schedule Summary         Capital Projects     Gunn High School – New Classroom Buildings A & B     page 6    Gunn High School – Parking and Drop‐off Sitework Improvement    page 7    Gunn High School – New Gymnasium       page 8    Gunn High School – Air Conditioning of Existing Buildings    page 9    Palo Alto High School – Athletic Stadium Improvements    page 10    Palo Alto High School – Classroom Building and Media Arts    page 11    Palo Alto High School – Performing Arts Center     page 12    Jordan Middle School        page 13    J.L. Stanford Middle School       page 14    Terman Middle School        page 15    Middle Schools Interim Classrooms – Jordan and J.L. Stanford    page 16    Fairmeadow Elementary School       page 17    Fairmeadow Elementary School – Portable Relocation    page 18    Ohlone Elementary School        page 19    Duveneck Elementary School       page 20    Technology          page 21    Completed Capital Projects    Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 22    Palo Alto High School – Multi‐use Field      page 23    Gunn High School – Industrial Arts Renovation     page 24    Gunn High School – Aquatic Center       page 25    Middle School Pre‐Design        page 26    Inactive Capital Projects    Garland Elementary School       page 27    Elementary School Teaching Walls – Phase 1 Schools     page 28    High School Master Plan        page 29    Hoover Elementary School        page 30    Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo page 31      Appendix  Exhibit A – Bond Project List    Page | 3   EXECUTIVE SUMMARY    CAPITAL PROJECTS     Gunn High School – New Classroom Buildings A & B  Final approval from Division of State Architect (DSA) was received May 19, 2011.  Bidding is scheduled to begin  June 13, 2011 and bids are due July 13, 2011.  Alternates have been developed to mitigate a potential budget  shortfall.  Construction will commence in August, 2011.     Gunn High School – Parking and Drop‐off Sitework Improvement  Design for the parking and drop‐off improvements will recommence in conjunction with the planning of group 2  projects in fall 2011.     Gunn High School – New Gymnasium  DSA approval was received May 17, 2011.  Bidding is scheduled to begin June 3, 2011, with bids due on July 7,  2011. Construction is anticipated to commence in August 2011.  This project is currently within budget.    Gunn High School – Air Conditioning of Existing Buildings  Best Contracting Services, Inc. commenced early work by surveying existing systems and ductwork, and laying out  routing and supports for new condensing units, piping and electrical work.  Installation will commence after school  is dismissed for summer break on June 9, 2011.  Palo Alto High School – Athletics Stadium Improvements  Both the Bleachers and Concessions Building and Site Improvements packages are being reviewed by DSA, with  approval anticipated to occur in October 2011.  Construction of the concessions building and site improvements is  anticipated to start in November 2011.  Portable buildings located where the new concessions building will be are  being relocated during the summer 2011.  The bleacher portion of work will commence upon completion of the  2011 football season in December 2011.    Palo Alto High School – Classroom Building and Media Arts Building  This project went out to bid on May 20, 2011, with bids due on June 20, 2011. Construction is anticipated to  commence in mid‐July 2011.    Palo Alto High School – Performing Arts Center (PAC)  DLM has studied several layouts for the PAC to maximize the seating capacity on the selected site. The PAC  subcommittee and FSC are recommending the 466‐seat, single story layout as the design that best meets program  needs and also is within the budget for this project. This recommendation will be discussed with the BOE on June  14, 2011.       Jordan Middle School  DSA continues review of the plans with approval anticipated in the fall of 2011.  District and site staff continue to  review strategies for prioritizing scope and identifying alternates.  Final constructability and coordination reviews  will continue through June 2011.     J.L. Stanford Middle School  AEDIS submitted drawings of the main new construction and renovation project to DSA on May 6, 2011, with an  anticipated approval date in early 2012.  The project is currently within budget.    Terman Middle School  DSA continues to review the plans, with approval anticipated in the fall of 2011.  Final constructability and  coordination reviews will continue through June 2011. The project is currently within budget.     Page | 4   Middle Schools Interim Classrooms – Jordan and J.L. Stanford  A new portable was installed at Jordan and four new portables were installed at Stanford during the summer of  2009.  The projects will now also fund the relocation of two 6th grade portable classrooms at Stanford, and the  installation of six new portables at Jordan.  The relocation of the portables at Stanford went out to bid on April 29,  2011, with bids due on June 1, 2011.  The relocation is expected to start in late June 2011 and be complete by  August 1, 2011. The Jordan portables will go out to bid mid‐June, with bids due on July 14, 2011. The installation of  these portables will occur in August 2011.    Fairmeadow Elementary School – New Classroom Building and Modernization  Gelfand conducted a site committee meeting on May 2, 2011 to finalize the landscape and site plan design.   Gelfand also conducted a series of meetings with their consultants to review constructability and to perform  quality assurance.  The 90% CD drawings were submitted to the district on May 27, 2011 for a final estimate and  constructability review.    Fairmeadow Elementary School – Portable Relocation  Bids were opened on May 2, 2011, however the bid results were higher than anticipated.  Therefore, the project  was submitted to the BOE for authorization to bid on May 24, 2011, with a new bid opening scheduled for June 14,  2011.  The JLS project is funding the relocation of this portable to provide access for the construction site for JLS’  new 2‐story classroom building.  Ohlone Elementary School – New Classroom Building and Modernization  Jeff Luchetti Construction continued installation of, mechanical, electrical, plumbing, and fire protection systems.  The installation of exterior lath and plaster, flashing, door frames, and windows are also underway. The roofing  system is being installed, and the steel framing for the exterior canopy is installed. Insulation and drywall  installation for the interior walls has also begun.    Duveneck Elementary School – New Classroom Buildings and Modernization  Gelfand submitted schematic design plans to the district in May for plan review and estimating. The initial estimate   was over budget, so a value engineering meeting was conducted on May 24, 2011.  The final estimate  reconciliation is due on June 3, 2011, so the schematic design can be presented to the BOE for approval on June  14, 2011.    Technology  Computer purchases planned for the 2010/11 school year were made.   The district continues to purchase more  Apple products than PC products.  In addition to traditional desktops and laptops, schools will purchase iPod  touches, iPads and netbooks for future use.    COMPLETED CAPITAL PROJECTS   Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems  Coulter Construction installed SmartBoards and Lightspeed sound assist systems, and completed the installation  April 29, 2011.  Phase 4 and 5 schools were the final elementary schools to receive interactive whiteboards and  sound assist systems.      Palo Alto High School – Multi‐use Field  The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9,  2011.    Gunn High School – Industrial Arts Addition & Renovation  This facility was available for instruction in January 2010. DSA closeout is anticipated to occur by the end of August  2011.      Page | 5   Gunn High School – Aquatic Center   This facility was available for use in July 2009, and has been closed out with DSA.    Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman  AEDIS presented recommended concept plans for each campus to the Board of Education for approval on  September 8, which became the program documents for the new projects at each campus.  These projects for pre‐ design work have been closed, and funds will be transferred to the program contingency on June 14, 2011.    INACTIVE CAPITAL PROJECTS     Garland Elementary School Renovation  The Board of Education has put new development for Garland on hold until a growth plan is established for the  elementary schools.  The board will discuss terminating the lease to Stratford School in June 2011, so that future  plans for growth at the elementary schools can begin on this campus as early as June 2014.    Elementary School Teaching Walls – Phase 1 Schools  The district placed this project on hold after review of the implementation of other classroom improvements, as  recommended by the elementary school principals.  This project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).     High School Master Plan  The Board of Education (BOE) approved the master plans for both high schools, and these projects will be closed,  with funds transferred to the respective campus reserve funds.   Hoover Elementary School – Pre‐Design  This project has been put on hold until a growth plan is established for the elementary schools.      Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo  DSA continues reviewing Phase 1 plans for work that includes new lighting, adding operable windows and  coverings, ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo elementary  schools.  The authorization to bid has been placed on hold pending further discussions with the BOE about  elementary growth planning.        Board Actions in May  May 10, 2011  Consent 6 – Authorization to Issue Addendum No. 11 to Deem Lewis McKinley Architects    Consent 7 – Authorization to Issue Addendum No. 5 to AEDIS Architecture and Planning for Additional Services at  Jordan and J.L. Stanford Middle Schools    May 24, 2011  Consent 5 – Authorization to Bid Summer Modular Building Relocations and Installations    Consent 6 – Approval of Inspector of Record (IOR) Services Firm    Consent 7 – Approval of Project Budget and Authorization to Solicit Bids for the Palo Alto High School Haymarket  and Tower Boiler Replacement Project    A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 143,011 117,416 81.0% 25,595 82.10% 1,989Gunn High School 1 - Aquatic Center 5,013,750 4,862,530 4,862,530 97.0% 0 100.00% 151,220Gunn High School 2 - I.A Building 5,511,500 5,048,363 5,030,097 91.3% 18,266 99.64% 463,137Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 24,120,000 4,050,462 2,713,005 11.2% 1,337,457 66.98% 20,069,538Gunn High School 5 - Parking & Drop Off improvements 3,940,000 219,460 5,731 0.1% 213,729 2.61% 3,720,540Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 1,649,703 776,736 5.6% 872,967 47.08% 12,180,297Gunn High School 7- A/C 2,600,000 2,255,745 138,153 5.3% 2,117,592 6.12% 344,255Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.00% 20,945,045Palo Alto High Schools - High School Master Plan 145,000 142,997 128,442 88.6% 14,555 89.82% 2,003Palo Alto High School 1 - Stadium Field 3,626,101 627,140 343,133 9.5% 284,007 54.71% 2,998,961Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,988,139 2,967,636 98.9% 20,503 99.31% 13,924Palo Alto high School 3 - New classroom & Media Art Building 37,140,000 5,201,006 2,975,910 8.0% 2,225,096 57.22% 31,938,994Palo Alto High School 4 - New Theater 17,720,000 1,364,138 210,019 1.2% 1,154,119 15.40% 16,355,862Palo Alto High School - Reserved 37,160,381 0 0 0.0% 0 0.00% 37,160,381Jordan Middle School -Program Management- MS Pre-Design 33,665 18,890 17,826 53.0% 1,064 94.37% 14,775Jordan Middle Schools 1- Interim Classrooms 600,342 176,573 165,893 27.6% 10,680 93.95% 423,769Jordan Middle School 2- Improvements 17,943,194 2,655,812 1,122,990 6.3% 1,532,822 42.28% 15,287,382J.L.S Middle School - Program Management- MS Pre-Design 33,669 18,799 18,408 54.7% 391 97.92% 14,870J.L.S Middle School 1 - Interim Classrooms 446,844 365,502 348,385 78.0% 17,117 95.32% 81,342 J.L.S Middle School 2- Improvements 17,184,699 2,866,951 1,387,599 8.1% 1,479,352 48.40% 14,317,748Terman Middle School - Program Management- MS Pre-Design 33,666 18,799 18,423 54.7% 376 98.00% 14,867Terman Middle School 1- Improvements 12,850,071 1,985,911 843,785 6.6% 1,142,126 42.49% 10,864,160PAUSD Elementary Schools - Program Management- Elem Growth Plan145 00098 48075 85552 3%22 62577 03%46 520Percent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond5/31/2011Percent of ExpendedContract BalanceExpenditures Budget BalanceCommittedBudgetSchool Name - Project NamePAUSD Elementary Schools - Program Management- Elem. Growth Plan145,00098,48075,85552.3%22,62577.03%46,520Addison Elementary School 1-Phase I 5,199,727 21,017 21,017 0.4% 0 100.00% 5,178,710Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 7,019,083 183,281 119,138 1.7% 64,143 65.00% 6,835,802Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 1,542,535 732,758 7.9% 809,777 47.50% 7,784,965Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 70,910 57,165 0.7% 13,745 80.62% 8,504,479Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 10,570,905 4,700,534 40.3% 5,870,371 44.47% 1,097,060Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 2,036,364 1,863,784 21.0% 172,580 91.53% 6,851,158Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.00% 8,410,862PAUSD - Program Management 5,042,021 3,879,318 3,342,594 66.3% 536,724 86.16% 1,162,703PAUSD - Technology 7,101,063 3,681,401 3,645,893 51.3% 35,508 99.04% 3,419,662PAUSD - Technology -Reserved 6,806,302 0 0 0.0% 0 0.00% 6,806,302PAUSD - Reserved 7,185,694 0 0 0.0% 0 0.00% 7,185,694Bond Issuance Cost 1,840,700 1,840,700 1,840,700 100.0% 0 100.00% 0Total350,684,826 60,871,898 40,877,445 19,994,453 289,812,927Prepared by: Business Services Department based on QSS accounting System Activity IDActivity NameOriginalDurationemainingDurationchedule %ompleteStartFinishTotalFloatGunn ACGunn AC4091100%01-Jan-10 A31-Oct-1132Gunn - PGunn - Parking and Drop Off12898340%01-Sep-09 A08-Aug-140ClassrooClassroom Improvements16900%02-Sep-10 A22-Apr-11 APaly - AtPaly - Athletic Stadium Renovation Project8543990%17-Aug-09 A05-Dec-120Paly - NePaly - New Performing Arts Center (PAC)15309600%09-Sep-09 A02-Feb-15-708Garland Garland School Modernization16800%03-Nov-08 A24-Jun-09 AFairmeadFairmeadow Elementary School12235970%14-Dec-09 A11-Sep-13-345DuvenecDuveneck Elementary School10307570%13-May-10 A23-Apr-14-505Hoover EHoover Elementary School14600%12-May-10 A01-Dec-10 ATeachingTeaching Walls Casework17200%06-Apr-09 A28-Sep-09 AGunn- InGunn- Industrial Arts Renovation45100%01-Oct-08 A24-Jun-10 AJordan NJordan New Classroom Wing & Modernization12315570%03-Nov-08 A15-Jul-13-303Gunn NeGunn New Gym8583100%21-Apr-09 A03-Aug-12-56Gunn NeGunn New Classroom Buildings A and B9453960%20-Apr-09 A03-Dec-12-142Paly NewPaly New Media Arts and Classroom Building11205710%20-Apr-09 A05-Aug-13-317StanfordStanford New Classroom Wing12375730%03-Nov-08 A06-Aug-13-319Terman ATerman Admin Wing Addition & Modernization12275620%03-Nov-08 A23-Jul-13-308Paly - MuPaly - Multi Use Field Improvements68110%03-Nov-08 A31-May-11251Ohlone EOhlone Elementary School8261550%03-Nov-08 A03-Jan-1297SNDJFAJJASONDJFAMJJASNDJFMAJJASNDJFAMJJASONDJFAMJJASNDJFMAJJASNDJFMAJ31-Oct-11, Gunn AC08-Aug-14, Gunn - P22-Apr-11 A, Classroom Improvements05-Dec-12, Paly - Athletic Stadium Renovation Project02-Feb-124-Jun-09 A, Garland School Modernization11-Sep-13, Fairmeadow Elementary Schoo23-Apr-14, Duveneck Eleme01-Dec-10 A, Hoover Elementary School28-Sep-09 A, Teaching Walls Casework24-Jun-10 A, Gunn- Industrial Arts Renovation15-Jul-13, Jordan New Classroom Wing & Mode03-Aug-12, Gunn New Gym03-Dec-12, Gunn New Classroom Buildings A and B05-Aug-13, Paly New Media Arts and Classroo06-Aug-13, Stanford New Classroom Wing23-Jul-13, Terman Admin Wing Addition & Mod31-May-11, Paly - Multi Use Field Improvements03-Jan-12, Ohlone Elementary SchoolPAUSD Strong Schools Bond - Program Master ScheduleClassic WBS Layout08-Jun-11 12:50Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryPage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc. Page | 6   Gunn High School  New Classroom Buildings A & B  A. PROJECT STATUS    Final approval from Division of State Architect (DSA) was received May  19, 2011.  Bidding is scheduled to begin June 13, 2011 and bids are due  July 13, 2011.  Alternates have been developed to mitigate a potential  budget shortfall.  Construction will commence in August, 2011.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4    D. PROJECT OVERVIEW:  • DSA approved documents on May 19, 2011.  Budget estimates are currently over budget, which will be  evaluated at bid time.           Funding  State Funds $0  Strong Schools Bond Funds $24,120,000  Other Funding $0  Total $24,120,000    Budget  Salaries and Benefits $12,193  Supplies $0  Contracts & Services $4,463,941  Construction & Equipment $19,567,102  Soft Costs Contingency $76,764  Total $24,120,000    Percent of Budget Expended 11.2%  Current Phase: Bid & Award   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010     Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA May 19, 2011    Bid Opening June 10, 2011*    Award of Contract (1) July 12, 2011*    Notice to Proceed August 1, 2011*    Substantial Completion October 11, 2012*    Planned Occupancy December 3, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 7   Gunn High School  Parking and Drop‐off Sitework Improvement  A. PROJECT STATUS    Design for the parking and drop‐off improvements will  recommence in conjunction with the planning of group 2 projects  in fall 2011.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:  • Design will recommence with the planning of group 2 projects.     Funding  State Funds $0  Strong Schools Bond Funds $3,940,000  Other Funding $0  Total $3,940,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $898,978  Construction & Equipment $2,919,840  Soft Costs Contingency $121,182  Total $3,940,000    Percent of Budget Expended 0.1%  Current Phase: Conceptual Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) October 25, 2011*  BOE Approval November 8, 2011*    Schematic Design (2) January 25, 2012*  BOE Approval February 1, 2012*    Submit to DSA December 7, 2012*     Approval by DSA June 20, 2013*    Authorize to Bid (2) June 21, 2013*  BOE Approval July 5, 2013*    Bid Opening September 27, 2013*    Award of Contract (1) November 1, 2013*    Notice to Proceed November 29, 2013*    Substantial Completion June 22, 2014*      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 8   Gunn High School  New Gymnasium  A. PROJECT STATUS    DSA approval was received May 17, 2011.  Bidding is scheduled  to begin June 3, 2011, with bids due on July 7, 2011.  Construction is anticipated to commence in August 2011.  This  project is currently within budget.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:  • DSA approval received on May 19, 2011.      Funding  State Funds $0  Strong Schools Bond Funds $13,830,000  Other Funding $0  Total $13,830,000    Budget  Salaries and Benefits $0  Supplies $1,001  Contracts & Services $2,650,520  Construction & Equipment $11,094,450  Soft Costs Contingency $84,029  Total $13,830,000    Percent of Budget Expended 5.6%  Current Phase: Bid & Award   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA May 17, 2011*    Bid Opening July 7, 2011*    Award of Contract (1) July 19, 2011*    Notice to Proceed August 1, 2011*    Substantial Completion July 13, 2012*    Planned Occupancy August 3, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 9   Gunn High School  Air Conditioning of Existing Buildings  A. PROJECT STATUS    Best Contracting Services, Inc. commenced early work by surveying  existing systems and ductwork, and laying out routing and supports  for new condensing units, piping and electrical work.  Installation  will commence after school is dismissed for summer break on June  9, 2011.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.7    D. PROJECT OVERVIEW:  • Best Contracting Services, Inc.  to commence work on the campus once school dismisses for summer  break.    Funding  State Funds $0  Strong Schools Bond Funds $2,600,000  Other Funding $0  Total $2,600,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $454,610  Construction & Equipment $2,120,580  Soft Costs Contingency $24,810  Total $2,600,000    Percent of Budget Expended 5.3%  Current Phase: Construction   Schedule:  Architect Contract (2) March 27, 2010  BOE Approval April 6, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA October 20, 2010    Approval by DSA February 10, 2011    Authorize to Bid (2) February 22, 2011  BOE Approval March 8, 2011    Bid Opening March 28, 2011    Award of Contract (1) April 8, 2011    Notice to Proceed April 15, 2011    Substantial Completion August 8, 2011*      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 10   Palo Alto High School  Athletic Stadium Improvements  A. PROJECT STATUS     Both the Bleachers and Concessions Building and Site  Improvements packages are being reviewed by DSA, with approval  anticipated to occur in October 2011.  Construction of the  concessions building and site improvements is anticipated to start  in November 2011.  Portable buildings located where the new  concessions building will be are being relocated during the summer  2011.  The bleacher portion of work will commence upon  completion of the 2011 football season in December 2011.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.13    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule under DSA’s anticipated review time.  Funding  State Funds $0  Strong Schools Bond Funds $3,626,101  Other Funding $0  Total $3,626,101    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $793,026  Construction & Equipment $2,791,001  Soft Costs Contingency $42,074  Total $3,626,101    Percent of Budget Expended 9.5%  Current Phase: DSA Review   Schedule:  Architect Contract (2) January 26, 2010  BOE Approval February 9, 2010    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) February 22, 2011  BOE Approval March 8, 2011    Submit to DSA April 4, 2011    Approval by DSA November 10, 2011*    Authorize to Bid (2) August 22, 2011*  BOE Approval September 5, 2011*    Bid Opening December 14, 2011*    Award of Contract (1) December 22, 2011*    Notice to Proceed December 29, 2011*    Substantial Completion October 26, 2012*    Planned Occupancy December 3, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 11   Palo Alto High School  Classroom Building and Media Arts  A. PROJECT STATUS     This project went out to bid on May 20, 2011, with bids due on June  20, 2011. Construction is anticipated to commence in mid‐July 2011.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:  • Project out to bid on May 20, 2011.   Funding  State Funds $0  Strong Schools Bond Funds $37,140,000  Other Funding $0  Total $37,140,000    Budget  Salaries and Benefits $14,721  Supplies $0  Contracts & Services $7,001,769  Construction & Equipment $29,740,000  Soft Costs Contingency $383,510  Total $37,140,000    Percent of Budget Expended 8.0%  Current Phase: Bid & Award   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011  BOE Approval March 22, 2011    Approval by DSA April 28, 2011    Bid Opening June 20, 2011*    Award of Contract (1) June 28, 2011*    Notice to Proceed July 11, 2011*    Substantial Completion July 11, 2013*    Planned Occupancy August 5, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 12   Palo Alto High School  Performing Arts Center (PAC)  A. PROJECT STATUS     DLM has studied several layouts for the PAC to maximize the seating  capacity on the selected site. The PAC subcommittee and FSC are  recommending the 466‐seat, single story layout as the design that best  meets program needs and also is within the budget for this project. This  recommendation will be discussed with the BOE on June 14, 2011.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.11    D. PROJECT OVERVIEW:  • Project schematic design to be presented to BOE on June 14, 2011.  Funding  State Funds $0  Strong Schools Bond Funds $17,720,000  Other Funding $0  Total $17,720,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,451,077  Construction & Equipment $14,159,700  Soft Costs Contingency $109,223  Total $17,720,000    Percent of Budget Expended 1.2%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) June 14, 2011*  BOE Approval June 28, 2011*    Submit to DSA February 20, 2012*    Approval by DSA September 12, 2012*    Authorize to Bid (2) September 13, 2012*  BOE Approval September 26, 2012*    Bid Opening November 15, 2012*    Award of Contract (1) December 10, 2012*    Notice to Proceed February 11, 2013*    Substantial Completion December 1, 2014*    Planned Occupancy January, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 13   Jordan Middle School  A. PROJECT STATUS    DSA continues review of the plans with approval anticipated in the  fall of 2011.  District and site staff continue to review strategies for  prioritizing scope and identifying alternates.  Final constructability  and coordination reviews will continue through June 2011.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule under DSA’s anticipated review time.  Budget estimates are  currently over budget. Funding  State Funds $0  Strong Schools Bond Funds $17,943,194  Other Funding $0  Total $17,943,194    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,522,530  Construction & Equipment $13,949,500  Soft Costs Contingency $471,164  Total $17,943,194    Percent of Budget Expended 6.3%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) March 23, 2010  BOE Approval April 27, 2010    Submit to DSA December 21, 2010     Authorize to Bid (2) June 14, 2011*  BOE Approval June 28, 2011*    Approval by DSA September 1, 2011*    Bid Opening October 4, 2011*    Award of Contract (1) October 12, 2011*    Notice to Proceed October 31, 2011*    Substantial Completion June 17, 2013*    Planned Occupancy July 10, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 14   J.L. Stanford Middle School  A. PROJECT STATUS    AEDIS submitted drawings of the main new construction  and renovation project to DSA on May 6, 2011, with an  anticipated approval date in early 2012.  The project is  currently within budget.                           B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:  • Project plans submitted to DSA on May 6, 2011. Funding  State Funds $0  Strong Schools Bond Funds $17,184,699  Other Funding $0  Total $17,184,699    Budget  Salaries and Benefits $0  Supplies $3,458  Contracts & Services $3,376,270  Construction & Equipment $13,341,000  Soft Costs Contingency $463,971  Total $17,184,699    Percent of Budget Expended 8.1%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (3) June 1, 2010  BOE Approval June 22, 2010  BOE Approval (Sitework) September 28, 2010    Submit to DSA May 6, 2011     Approval by DSA January 6, 2012*    Authorize to Bid (2) January 10, 2012*  BOE Approval January 24, 2012*    Bid Opening February 28, 2012*    Award of Contract (1) February 29, 2012*    Notice to Proceed March 15, 2012*    Substantial Completion June 21, 2013*    Planned Occupancy August 6, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings Page | 15   Terman Middle School  A. PROJECT STATUS    DSA continues to review the plans, with approval anticipated in  the fall of 2011.  Final constructability and coordination reviews will  continue through June 2011. The project is currently within budget.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule under DSA’s anticipated review time and within budget.      Funding  State Funds $0  Strong Schools Bond Funds $12,850,071  Other Funding $0  Total $12,850,071    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,533,760  Construction & Equipment $10,031,569  Soft Costs Contingency $284,742  Total $12,850,071    Percent of Budget Expended 6.6%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) May 11, 2010  BOE Approval May 25, 2010    Submit to DSA December 21, 2010    Authorize to Bid (2) June 14, 2011*  BOE Approval June 28, 2011*    Approval by DSA August 26, 2011*    Bid Opening October 4, 2011*    Award of Contract (1) October 12, 2011*    Notice to Proceed October 27,  2011*    Substantial Completion June 24, 2013*    Planned Occupancy July 23, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 16   Middle Schools Interim Classrooms  Jordan and J.L. Stanford  A. PROJECT STATUS    A new portable was installed at Jordan and four new portables were installed at Stanford during the summer  of 2009.  The projects will now also fund the relocation of two 6th grade portable classrooms at Stanford, and  the installation of six new portables at Jordan.  The relocation of the portables at Stanford went out to bid on  April 29, 2011, with bids due on June 1, 2011.  The relocation is expected to start in late June 2011 and be  complete by August 1, 2011. The Jordan portables will go out to bid mid‐June, with bids due on July 14, 2011.  The installation of these portables will occur in August 2011.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:  • This project was completed under budget and on schedule. Funding  State Funds $0  Strong Schools Bond Funds $1,047,186  Other Funding $0  Total $1,047,186    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $353,148  Construction & Equipment $691,490  Soft Costs Contingency $2,548  Total $1,047,186    Percent of Budget Expended 48.9%*    *Budget previously expended       Current Phase: DSA Review / Bid & Award    Schedule:  Approval by DSA April 19, 2011  Jordan Project June 16, 2011*     Authorize to Bid (2) May 10, 2011  BOE Approval May 24, 2011    Bid Opening June 1, 2011*  Jordan Project July 14, 2011*    Award of Contract (1) June 13, 2011*  Jordan Project July 19, 2011*    Notice to Proceed June 20, 2011*  Jordan Project July 27, 2011*    Substantial Completion August 1, 2011*  Jordan Project September 20, 2011*    Planned Occupancy August 15, 2011*  Jordan Project October 1, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 17   Fairmeadow Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS      Gelfand conducted a site committee meeting on May 2, 2011 to  finalize the landscape and site plan design.  Gelfand also conducted  a series of meetings with their consultants to review constructability  and to perform quality assurance.  The 90% CD drawings were  submitted to the district on May 27, 2011 for a final estimate and  constructability review.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule under DSA’s anticipated review time and within budget.   Funding  State Funds $0  Strong Schools Bond Funds $9,327,500  Other Funding $0  Total $9,327,500    Budget  Salaries and Benefits $0  Supplies $7,697  Contracts & Services $1,831,019  Construction & Equipment $7,443,000  Soft Costs Contingency $45,784  Total $9,327,500    Percent of Budget Expended 7.9%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 13, 2009  BOE Approval October 27, 2009    Conceptual Design (2) March 23, 2010  BOE Approval April 6, 2010    Schematic Design (2) September 14, 2010  BOE Approval September 28, 2010    Submit to DSA April 18, 2011     Approval by DSA February 14, 2012*    Authorize to Bid (2) February 21, 2012*  BOE Approval March 8, 2012*    Bid Opening April 12, 2012*    Award of Contract (1) April 23, 2012*    Notice to Proceed April 27, 2012*    Substantial Completion July 25, 2013*    Planned Occupancy August 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 18   Fairmeadow Elementary School  Portable Relocation Project  A. PROJECT STATUS     Bids were opened on May 2, 2011, however the bid results  were higher than anticipated.  Therefore, the project was  submitted to the BOE for authorization to bid on May 24, 2011,  with a new bid opening scheduled for June 14, 2011.  The JLS  project is funding the relocation of this portable to provide  access for the construction site for JLS’ new 2‐story classroom  building.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 6.4    D. PROJECT OVERVIEW:  • Project is currently out to bid and bids are scheduled to be opened on June 14, 2011.     Funding  State Funds $0  Strong Schools Bond Funds $161,507  Other Funding $0  Total $161,507    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $15,690  Construction & Equipment $132,317  Soft Costs Contingency $13,500  Total $161,507    Percent of Budget Expended 0.6%  Current Phase: Bid & Award   Schedule:  Architect Contract (2) February 15, 2011  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA March 3, 2011     Approval by DSA March 3, 2011    Authorize to Bid (2) May 11, 2011  BOE Approval May 24, 2011    Bid Opening June 14, 2011*    Award of Contract (1) June 14, 2011*    Notice to Proceed June 20, 2011*    Substantial Completion August 1, 2011*    Planned Occupancy August 10, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 19   Ohlone Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS     Jeff Luchetti Construction continued installation of, mechanical, electrical,  plumbing, and fire protection systems. The installation of exterior lath and  plaster, flashing, door frames, and windows are also underway. The roofing  system is being installed, and the steel framing for the exterior canopy is  installed. Insulation and drywall installation for the interior walls has also  begun.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.    Funding  State Funds $0  Strong Schools Bond Funds $11,667,965  Other Funding $0  Total $11,667,965    Budget  Salaries and Benefits $0  Supplies $5,467  Contracts & Services $2,348,367  Construction & Equipment $9,169,121  Soft Costs Contingency $145,010  Total $11,667,965    Percent of Budget Expended 40.3%    Change Order Contingency  • Starting Contingency Balance $748,400  • Remaining Contingency Balance $690,961  • Percent of Changes 0.8%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) March 3, 2009  BOE Approval March 17, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA November 24, 2009    Authorize to Bid (2) April 27, 2010  BOE Approval May 11, 2010    Approval by DSA May 18, 2010    Bid Opening July 13, 2010    Award of Contract (1) August 3, 2010    Notice to Proceed August 11, 2010    Substantial Completion November 7, 2011*    Planned Occupancy January 3, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 20   Duveneck Elementary School  New Classroom Buildings and Modernization  A. PROJECT STATUS    Gelfand submitted schematic design plans to the district in May  for plan review and estimating. The initial estimate was over  budget, so a value engineering meeting was conducted on May  24, 2011.  The final estimate reconciliation is due on June 3,  2011, so the schematic design can be presented to the BOE for  approval on June 14, 2011.                         B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Schematic design to be presented to BOE on June 14, 2011. Funding  State Funds $0  Strong Schools Bond Funds $7,019,083  Other Funding $0  Total $7,019,083    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,380,299  Construction & Equipment $5,559,683  Soft Costs Contingency $79,101  Total $7,019,083    Percent of Budget Expended 1.7%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) December 14, 2010  BOE Approval January 11, 2011    Schematic Design (2) June 14, 2011*  BOE Approval June 28, 2011*    Submit to DSA December 16, 2011*     Approval by DSA August 3, 2012*    Authorize to Bid (2) September 14, 2012*  BOE Approval September 28, 2012*    Bid Opening November 5, 2012*    Award of Contract (1) November 14, 2012*    Notice to Proceed November 30, 2012*    Substantial Completion March 27, 2014*    Planned Occupancy August 1, 2014*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 21   Technology Improvements  A. PROJECT STATUS      Computer purchases planned for the 2010/11 school year were made.   The  district continues to purchase more Apple products than PC products.  In  addition to traditional desktops and laptops, schools will purchase iPod  touches, iPads and netbooks for future use.           B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • New computers under evaluation for 2011/12 school year.      Funding  State Funds $0  Strong Schools Bond Funds $7,101,063  Other Funding $0  Total $7,101,063    Budget  Salaries and Benefits $0  Supplies & Computers $6,718,468  Contracts & Services $180,173  Construction & Equipment $202,422  Soft Costs Contingency $0  Total $7,101,063    Percent of Budget Expended 51.3%    Current Phase: N/A   Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 22   Elementary Classroom Improvements  Interactive Whiteboards and Sound Assist System Installation  A. PROJECT STATUS    Coulter Construction installed SmartBoards and Lightspeed sound assist systems, and completed the  installation April 29, 2011.  Phase 4 and 5 schools were the final elementary schools to receive interactive  whiteboards and sound assist systems.          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • All SmartBoards and Lightspeed sound systems installed.           Funding  State Funds $0  Strong Schools Bond Funds $8,887,522  Other Funding $0  Total $8,887,522    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,195,880  Construction & Equipment $7,488,707  Soft Costs Contingency $202,935  Total $8,887,522    Percent of Budget Expended 19.7%    Current Phase: Complete ‐May 15, 2011    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) November 9, 2010  BOE Approval November 23, 2010    Bid Opening February 25, 2011    Award of Contract (1) March 8, 2011    Notice to Proceed March 9, 2011    Completion May 15, 2011      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 23   Palo Alto High School   Multi‐Use Field  A. PROJECT STATUS    The fields were available for play on February 1, 2011, and final change  order negotiations completed on March 9, 2011.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.14    D. PROJECT OVERVIEW:  • Field was open for use on February 1, 2011.     Funding  State Funds $0  Strong Schools Bond Funds $3,002,063  Other Funding $1,075,991  Total $4,078,054    Budget  Salaries and Benefits $0  Supplies $1,506  Contracts & Services $747,165  Construction & Equipment $3,326,689  Soft Costs Contingency $2,694  Total $4,078,054     Percent of Budget Expended 98.5%    Change Order Contingency  • Starting Contingency Balance $269,300  • Remaining Contingency Balance $230,579  • Percent of Changes 1.7%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –February 1, 2011    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 18, 2008  BOE Approval December 09, 2008    Submit to DSA March 19, 2009     Approval by DSA September 30, 2009    Authorize to Bid (2) February 24, 2009  BOE Approval March 17, 2009    Bid Opening March 16, 2010    Award of Contract (1) April 7, 2010    Notice to Proceed June 1, 2010    Substantial Completion January 31, 2011    Planned Occupancy February 1, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 24   Gunn High School  Industrial Arts Addition and Renovation  A. PROJECT STATUS    This facility was available for instruction in January 2010. DSA  closeout is anticipated to occur by the end of August 2011.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11    D. PROJECT OVERVIEW:  • The building occupied as scheduled, and the project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,511,500  Other Funding $0  Total $5,511,500    Budget  Salaries and Benefits $1,063  Supplies $88,985  Contracts & Services $1,213,538  Construction & Equipment $4,207,322  Soft Costs Contingency $592  Total $5,511,500    Percent of Budget Expended 91.0%    Change Order Contingency  • Starting Contingency Balance $349,000  • Remaining Contingency Balance $141,967  • Percent of Changes 41.6%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –January 4, 2010    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA June 17, 2008     Approval by DSA December 24, 2008    Authorize to Bid (2) October 14, 2008  BOE Approval October 28, 2008    Bid Opening December 16, 2008    Award of Contract (1) December 24, 2008    Notice to Proceed January 6, 2009    Substantial Completion November 25, 2009    Planned Occupancy January 4, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 25   Gunn High School  Aquatic Center  A. PROJECT STATUS    This facility was available for use in July 2009, and has been closed  out with DSA.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.12    D. PROJECT OVERVIEW:  • This project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,013,750  Other Funding $0  Total $5,013,750    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $691,797  Construction & Equipment $4,318,858  Soft Costs Contingency $2,095  Total $5,013,750    Percent of Budget Expended 96.9%    Change Order Contingency  • Starting Contingency Balance $389,887  • Remaining Contingency Balance $195,148  • Percent of Changes 49.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –June 15, 2009    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA December 11, 2007     Approval by DSA April 24, 2008    Authorize to Bid (2) April 8, 2008  BOE Approval April 22, 2008    Bid Opening May 28, 2008    Award of Contract (1) June 4, 2008    Notice to Proceed December 6, 2008    Substantial Completion June 15, 2009    Planned Occupancy June 15, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 26   Middle School Pre‐Design  Jordan, J.L. Stanford and Terman  A. PROJECT STATUS    AEDIS presented recommended concept plans for each campus to the  Board of Education for approval on September 8, which became the  program documents for the new projects at each campus.  These  projects for pre‐design work have been closed, and funds will be  transferred to the program contingency on June 14, 2011.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12    D. PROJECT OVERVIEW:  • This project has been completed on schedule and under budget. Board approval received on September  8, 2009. Funding  State Funds $0  Strong Schools Bond Funds $101,000  Other Funding $0  Total $101,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $85,000  Construction & Equipment $0  Soft Costs Contingency $15,000  Total $101,000    Percent of Budget Expended 52.9%    Current Phase: Complete   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 27   Garland Elementary School  Campus Modernization  A. PROJECT STATUS    The Board of Education has put new development for Garland on  hold until a growth plan is established for the elementary schools.   The board will discuss terminating the lease to Stratford School in  June 2011, so that future plans for growth at the elementary  schools can begin on this campus as early as June 2014.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10    D. PROJECT OVERVIEW:  • This project has been placed on hold. Funding  State Funds $0  Strong Schools Bond Funds $22,178,544  Other Funding $0  Total $22,178,544    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,915,789  Construction & Equipment $17,400,000  Soft Costs Contingency $862,755  Total $22,178,544    Percent of Budget Expended 1.3%  Current Phase: On Hold   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) February 10, 2009  BOE Approval February 24, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 28   Elementary School Teaching Walls  Phase 1 Schools  A. PROJECT STATUS    The district placed this project on hold after review of the  implementation of other classroom improvements, as  recommended by the elementary school principals.  This  project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.9    D. PROJECT OVERVIEW:  • This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary  above).            Funding  State Funds $0  Strong Schools Bond Funds $7,044,987  Other Funding $0  Total $7,044,987    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,341,394  Construction & Equipment $5,498,498  Soft Costs Contingency $205,095  Total $7,044,987    Percent of Budget Expended 1.6%  Current Phase: Project Renamed. See Classroom      Improvements Project    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates –Subject to Change Page | 29   High School Master Plan  Palo Alto HS and Gunn HS  A. PROJECT STATUS    The Board of Education (BOE) approved the master plans for  both high schools, and these projects will be closed, with funds  transferred to the respective campus reserve funds.                  B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14    D. PROJECT OVERVIEW:  • No further action since Paly’s updated master plan project list was approved by BOE on October 9, 2010.                  Funding  State Funds $0  Strong Schools Bond Funds $290,000  Other Funding $0  Total $290,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $288,565  Construction & Equipment $0  Soft Costs Contingency $435  Total $290,000    Percent of Budget Expended 81.5%  Current Phase: Master Planning    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Initial Master Plan Approval (2) September 8, 2009  BOE Approval September 22, 2009    Paly CEQA Approval (2) February 9, 2010  BOE Approval February 23, 2010    Gunn Master Plan Update (2) March 23, 2010  BOE Approval April 6, 2010    Gunn CEQA Approval (2) April 27, 2010   BOE Approval May 11, 2010     Master Plan Revision Approval (2) September 14, 2010  Paly MP Revision Approval (2) October 9, 2010  Gunn MP Revision Approval (2) October 12, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 30   Hoover Elementary School  Pre‐Design  A. PROJECT STATUS    This project has been put on hold until a growth plan is established for the  elementary schools.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Project is currently on hold.                Funding  State Funds $0  Strong Schools Bond Funds $8,575,389  Other Funding $0  Total $8,575,389    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,643,477  Construction & Equipment $6,831,912  Soft Costs Contingency $100,000  Total $8,575,389    Percent of Budget Expended 0.4%  Current Phase: On Hold   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) November 9, 2010  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A  Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 31   Elementary Classroom Improvements  Phase 1 – Barron Park and El Carmelo  A. PROJECT STATUS    DSA continues reviewing Phase 1 plans for work that includes new  lighting, adding operable windows and coverings, ventilation, and  replacement of ceiling tiles for classrooms at Barron Park and El  Carmelo elementary schools.  The authorization to bid has been  placed on hold pending further discussions with the BOE about  elementary growth planning.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • This project has been placed on hold.        Funding  State Funds $0  Strong Schools Bond Funds $8,887,522  Other Funding $0  Total $8,887,522    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,195,880  Construction & Equipment $7,488,707  Soft Costs Contingency $202,935  Total $8,887,522    Percent of Budget Expended 11.8%    Phase 1 Schools: Barron Park and El Carmelo  Current Phase:  DSA Review    Schedule:  Architect Contract (2) June 8, 2010  BOE Approval June 22, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 9, 2010  BOE Approval December 7, 2010    Submit to DSA December 23, 2010     Approval by DSA May 9, 2011*    Authorize to Bid (2) April 15, 2011*  BOE Approval April 30, 2011*    Bid Opening May 12, 2011*    Award of Contract (1) May 24, 2011*    Notice to Proceed June 1, 2011*    Substantial Completion August 1, 2011*    Planned Occupancy August 10, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  OHS WEST:260388860.1 A-1 EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. Numbers Added A-2 OHS WEST:260388860.1 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. A-3 OHS WEST:260388860.1 3. GUNN HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Demolish old library building. 3. Replace temporary classrooms with permanent classrooms. 4. Construct additional restrooms. 5. Construct second gymnasium. 6. Construct new soccer field. 7. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 9. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 10. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 11. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 12. Replace swimming pool with new 35-meter pool, pool equipment and support structures, pool decking, bleachers, storage, restrooms, showers, associated equipment. 13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace athletic equipment. 14. Modernize football stadium, including new bathrooms and concession stands. A-4 OHS WEST:260388860.1 4. PALO ALTO HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Construct additional restrooms. 4. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 6. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 7. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 8. Library modernization and building interior improvements, including infrastructure and major building system upgrades. 9. Renovation or replacement of the Tower Building to accommodate administration, classroom and program support space. 10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility improvements; construction of new restrooms; install new roofing; replace doors and windows; replace gymnasium floors and athletic equipment, bleachers and renovation of interior. Renovation or replacement of weight training facility. 11. Construct new theater building. 12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing and storage. 13. Modernize football stadium, including replace bleachers; new bathrooms and concession stands. 14. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. A-5 OHS WEST:260388860.1 5. OTHER DISTRICT-WIDE PROJECTS Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and equipment for all classrooms, athletic facilities and other facilities, as needed. 1. Replace existing or acquire new computers, technology and related equipment on an ongoing basis. 2. Establish a planned maintenance fund to address maintenance work expected to be needed to all District facilities on an ongoing basis (other than as may be necessary for current maintenance, operation or repairs), in order to implement the District’s comprehensive facilities maintenance plan. 3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease- purchase arrangements, or execute purchase option under a lease for any of these authorized facilities. 4. If and as opportunities become available, and to the extent the Board of Education determines that bond funds are available for the purpose, acquisition of land and other interests in real property for future school buildings and other District facilities, and construction of such facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise listed. 5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field equipment and facilities (including nets, basketball standards, goals and goalposts, backstops), field lighting, etc. 6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS 1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead, etc., where necessary. 2. Address unforeseen conditions revealed by construction/modernization (including plumbing or gas line breaks, dry rot, seismic, structural, etc.). 3. Other improvements required to comply with existing building codes, including the Field Act, and access requirements of the Americans with Disabilities Act (ADA). 4. Site preparation/restoration in connection with new construction, renovation or remodeling, or installation or removal of relocatable classrooms, including ingress and egress, demolition of existing structures, removing, replacing, or installing irrigation and drainage, utility lines (such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any necessary easements, licenses, or rights of way to the property. 5. Rental or construction of storage facilities and other space on an interim basis, as needed to accommodate construction materials, equipment, and personnel, and interim classrooms (including relocatables) for students and school functions or other storage for classroom materials displaced during construction. A-6 OHS WEST:260388860.1 7. RENOVATION/MODERNIZATION (DEFINED) For purposes of the Bond Project List, renovation and modernization projects are intended to restore the building systems and infrastructure, weather protections, finishes, and technology, or reallocate and reorganize space, to a condition that will provide a sustainable, functional educational and administrative environment for future years, comparable to new construction. Renovation projects may include, but are not limited to nor necessarily encompass, all of the following, depending upon the age, condition and needs of each particular school facility: 1. upgrade electrical, communication, fire alarm, and similar building systems as well as main power service and distribution, which may include active and passive solar power and heating system acquisition, installation and construction 2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply, meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within buildings and sites and to connect with city supply and drainage systems 3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient heating and air cooling systems (HVAC), including installing energy management systems (EMS); 4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and fixtures, as necessary; 5. Repair, modify and construct structural elements of the existing structure as necessary; 6. Replace or repair aging roofs with similar materials or District standard materials; 7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes, doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces (including white boards, marker boards, tack boards, television mounts, scoreboards, fire extinguishers, kitchen cabinets/equipment, etc.); 8. Upgrade, modify and construct restroom facilities; 9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24 requirements; 10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood siding, paint, etc.); replace doors and windows 11. Modify, expand, separate, convert and construct school support areas; staff work and lunch areas; and educational areas to provide adequate, functional environments; 12. Modify, replace and construct functional components of altered or replaced building components (including rainwater leaders, fascias, mansards, etc.); ™ For any project involving renovation, modernization, remodeling or rehabilitation of a building or the major portion of a building, the District may proceed with new replacement construction instead (including any necessary demolition), if the Board of Education determines that replacement and new construction is more practical than rehabilitation and renovation, considering the building’s age, condition, expected remaining life, comparative cost, and other relevant factors.