Monthly Reports 2011-03 (Mar)
MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
March 2011
Current Strong Schools Bond
Capital Improvement Projects
Prepared by
O’Connor Construction Management, Inc.
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Attachment 2 – Master Program Schedule Summary
Capital Projects
Gunn High School – New Classroom Buildings A & B page 7
Gunn High School – Parking and Drop‐off Sitework Improvement page 8
Gunn High School – New Gymnasium page 9
Gunn High School – Air Conditioning of Existing Buildings page 10
Palo Alto High School – Athletic Stadium Improvements page 11
Palo Alto High School – Classroom Building and Media Arts page 12
Palo Alto High School – Performing Arts Center page 13
Jordan Middle School page 14
J.L. Stanford Middle School page 15
Terman Middle School page 16
Fairmeadow Elementary School page 17
Fairmeadow Elementary School – Portable Relocation page 18
Ohlone Elementary School page 19
Duveneck Elementary School page 20
Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 21
Technology page 22
Completed Capital Projects
Palo Alto High School – Multi‐use Field page 23
Gunn High School – Industrial Arts Renovation page 24
Gunn High School – Aquatic Center page 25
Middle School Pre‐Design page 26
Middle School Interim Classrooms page 27
Inactive Capital Projects
Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo page 28
Garland Elementary School page 29
Elementary School Teaching Walls – Phase 1 Schools page 30
High School Master Plan page 31
Hoover Elementary School page 32
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
CAPITAL PROJECTS
Gunn High School – New Classroom Buildings A & B
The Division of State Architect (DSA) backcheck appointment is secured for April 13, 2011, with final approval
expected shortly after. Alternates are being developed to mitigate a potential budget shortfall. The project is
anticipated to go out to bid in early May 2011.
Gunn High School – Parking and Drop‐off Sitework Improvement
No further action occurred on this project. Design for the parking and drop‐off improvements will recommence
with the planning of group 2 projects.
Gunn High School – New Gymnasium
The DSA backcheck appointment is scheduled for April 19, 2011, with final approval expected shortly after.
Prequalification of contractors is complete and the project is anticipated to go out for bid in May 2011.
Gunn High School – Air Conditioning of Existing Buildings
Bids were opened on March 28, 2011 and Best Contracting Services, Inc. was the low bidder. Staff will seek
authorization to award from BOE on April 5, 2011.
Palo Alto High School – Athletics Stadium Improvements
The BOE approved the schematic design on March 8, 2011. The bleacher design was submitted to DSA, and the
concession stand design package will be submitted to DSA on April 4, 2011. DLM continues refining the design
documents for landscape and tree protection.
Palo Alto High School – Classroom Building and Media Arts Building
The DSA backcheck appointment is scheduled for April 13, 2011, with final approval expected shortly after.
Alternates are being developed to mitigate the potential for bids coming in over budget. The project is anticipated
to go out for bid in May 2011.
Palo Alto High School – Performing Arts Center (PAC)
After further review of an option for a smaller capacity facility, DLM is reviewing additional PAC studies for a 575
seat capacity in a single‐level configuration. DLM and district representatives toured McAfee Theater in Saratoga
to review the floor plan and program layout. Schematic design work is currently on hold pending a decision from
site staff and administration on the PAC seating capacity and respective design.
Jordan Middle School
DSA continues to review the submitted plans with approval anticipated in fall 2011. AEDIS and Gilbane reconciled
cost estimates, confirming that the project remains over budget. The Jordan bond advisory committee met on
March 16, 2011 to review budget information and to discuss options for prioritizing scope to identify as alternate
bid packages. Final constructability and coordination reviews will occur in April 2011.
J.L. Stanford Middle School
AEDIS submitted 50% construction documents to the District and intends to submit drawings to DSA in late April
2011. The project design is currently within budget. AEDIS also anticipates submitting an over‐the‐counter
package to DSA in April for the relocation of the two existing portable classrooms that are currently located in the
designed area of the new 2‐story building.
Page | 4
Terman Middle School
DSA continues to review the submitted plans and approval is anticipated in fall 2011. AEDIS and Gilbane
reconciled cost estimates, confirming that the project is within budget. Final constructability and coordination
reviews will occur in April 2011.
Fairmeadow Elementary School – New Classroom Building and Modernization
Gelfand conducted landscape meetings with the site committee on March 3 and March 21, 2011. On March 10,
2011, a City of Palo Alto traffic engineer conducted a site visit to observe the existing drop‐off routine and parking
needs for the school. Gelfand continues to work on construction documents to meet an anticipated DSA submittal
date of April 18, 2011.
Fairmeadow Elementary School – Portable Relocation
ATI Architects and Engineers were contracted to provide the design documents for the relocation of portable
classroom (Rm. 19) at Fairmeadow. The JLS project budget is funding relocating this classroom since it is currently
located in the construction location of JLS’ new 2‐story classroom building. ATI submitted an over the counter
package to DSA and received approval on March 3, 2011. The project is anticipated to bid in April 2011.
Ohlone Elementary School – New Classroom Building and Modernization
Jeff Luchetti Construction continues structural steel and wood framing of the building. Interior and exterior
framing are well underway, with both first and second floor walls in progress. Rough‐in is also underway for
plumbing, mechanical and electrical systems. Roofing is scheduled to begin on March 30, 2011.
Duveneck Elementary School – New Classroom Buildings and Modernization
Gelfand continued meeting with staff and faculty and presented an update to the steering committee on March
16, 2011, and a follow up meeting is scheduled to occur in April. A community meeting will be scheduled in early
May, with a presentation to the BOE anticipated for late May 2011.
Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems
On March 8, 2011, the BOE authorized the award for installation of new interactive whiteboards and sound assist
systems at Phase 4 and 5 schools, Duveneck, El Carmelo, Escondido, Hoover and Nixon, to Coulter Construction.
Installation of sound assist systems commenced on March 24, 2011 and SmartBoard units are anticipated to arrive
in early April, 2011.
Technology
80% of the computer purchases planned for the 2010/11 school year have been made. The district continues to
purchase more Apple products than PC products. In addition to traditional desktops and laptops, schools have
purchased iPod touches, iPads and netbooks for pilot projects.
COMPLETED CAPITAL PROJECTS
Palo Alto High School – Multi‐use Field
The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9,
2011.
Gunn High School – Industrial Arts Addition & Renovation
Of the $5,511,500 project budget, 90.5% or $4,987,908 was expended. Approved change orders were $145,184,
approximately 41.6% of the $349,000 construction contingency, or 5.7% of the construction contract. This project
will be closed pending final closeout of the project by DSA.
Page | 5
Gunn High School – Aquatic Center
Of the $5,013,750 project budget, 96.9%, or $4,858,324 was expended. Approved change orders were $194,554,
approximately 49.9% of the $389,887 construction contingency, or 5.0% of the construction contract. This project
will be closed pending final closeout of the project by DSA.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for
discussion and received approval on September 8 by the Board of Education to move into schematic design. This
project is now closed, and funds will soon be transferred to program contingency.
Middle Schools Interim Housing – Jordan and J.L. Stanford
Contractors completed the installation of these new portables on August 3, 2009 at Jordan and August 12, 2009 at
Stanford. Of the $1,047,186 project budget, 48.9%, or $512,074 was expended. Change Orders were $25,980,
which is approximately 49.6% of the $52,379 construction contingency or 5% of the construction contracts. These
projects will be closed pending final closeout of the projects by DSA.
INACTIVE CAPITAL PROJECTS
Garland Elementary School Renovation
The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.
Therefore, the district has placed the project on hold.
Elementary School Teaching Walls – Phase 1 Schools
The district placed this project on hold after review of the implementation of other classroom improvements, as
recommended by the elementary school principals. This project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
High School Master Plan
The Board of Education (BOE) approved the Palo Alto high school updated master plan project list on October 9,
2010 and no further action on the high school master plans is planned.
Hoover Elementary School – Pre‐Design
Staff has put this project on hold until growth projections are reviewed and a growth plan is established for the
elementary schools.
Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo
DSA continues reviewing Phase 1 plans for work that includes new lighting, adding operable windows and
coverings, ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo elementary
schools. The authorization to bid has been placed on hold pending further discussions with the BOE about
elementary growth planning.
Page | 6
Board Actions in March
March 8, 2011
Consent 5 – Approval of Schematic Design and Project Budget for the Athletic Stadium Improvements Project at
Palo Alto High School
Consent 6 – Authorization to Bid the Air Conditioning of Existing Classroom Buildings at Gunn High School
Consent 7 – Authorization to Bid Classroom Buildings A and B for Gunn High School
Consent 8 – Authorization to Bid the Gunn High School Gymnasium Project
Consent 9 – Authorization to Bid the Math and History/Social Sciences and Media Arts Buildings at Palo Alto High
School
Consent 10 – Authorization to Execute Agreements for Labor Compliance Services with The Labor Compliance
Managers
Consent 11 – Addendum #1 to Agreement with Verde Design Inc. for Palo Alto High School Multi‐Use Field
Improvement Project ($13,527)
Action 18 – Authorization to Award Interactive Whiteboards and Sound Assist Devices, Phase 4 & 5
March 22, 2011
Consent 5 – Approval of Change Orders
Consent 6 – Appointment of Independent Auditors for 2010 ‐ 11
A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 142,391 117,416 81.0% 24,975 82.46% 2,609Gunn High School 1 - Aquatic Center 5,013,750 4,865,425 4,862,530 97.0% 2,895 99.94% 148,325Gunn High School 2 - I.A Building 5,511,500 5,067,398 5,016,404 91.0% 50,994 98.99% 444,102Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 24,120,000 4,035,923 2,555,547 10.6% 1,480,376 63.32% 20,084,077Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 4,041 0.1% 213,729 1.86% 3,722,230Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 1,617,303 759,025 5.5% 858,278 46.93% 12,212,697Gunn High School 7- A/C 2,600,000 320,786 134,621 5.2% 186,165 41.97% 2,279,214Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.00% 20,945,045Palo Alto High Schools - High School Master Plan 145,000 142,997 128,442 88.6% 14,555 89.82% 2,003Palo Alto High School 1 - Stadium Field 3,626,101 607,540 338,057 9.3% 269,483 55.64% 3,018,561Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,974,612 2,957,299 98.5% 17,313 99.42% 27,451Palo Alto high School 3 - New classroom & Media Art Building 37,140,000 5,156,866 2,810,898 7.6% 2,345,968 54.51% 31,983,134Palo Alto High School 4 - New Theater 17,720,000 1,364,138 207,087 1.2% 1,157,051 15.18% 16,355,862Palo Alto High School - Reserved 37,160,381 0 0 0.0% 0 0.00% 37,160,381Jordan Middle School -Program Management- MS Pre-Design 33,665 18,890 17,826 53.0% 1,064 94.37% 14,775Jordan Middle Schools 1- Interim Classrooms 600,342 176,573 164,525 27.4% 12,048 93.18% 423,769Jordan Middle School 2- Improvements 17,943,194 2,655,812 1,101,277 6.1% 1,554,535 41.47% 15,287,382J.L.S Middle School - Program Management- MS Pre-Design 33,669 18,799 18,408 54.7% 391 97.92% 14,870J.L.S Middle School 1 - Interim Classrooms 446,844 364,654 338,753 75.8% 25,901 92.90% 82,190 J.L.S Middle School 2- Improvements 17,184,699 2,774,949 1,206,061 7.0% 1,568,888 43.46% 14,409,750Terman Middle School - Program Management- MS Pre-Design 33,666 18,799 18,423 54.7% 376 98.00% 14,867Terman Middle School 1- Improvements 12,850,071 1,937,075 825,533 6.4% 1,111,542 42.62% 10,912,996PAUSD Elementary Schools-Program Management-Elem Growth Plan145 00055 56055 56038 3%0100 00%89 440CommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond3/31/2011Percent of ExpendedContract BalanceExpenditures Budget BalancePAUSD Elementary Schools - Program Management- Elem. Growth Plan145,00055,56055,56038.3%0100.00%89,440Addison Elementary School 1-Phase I 5,199,727 21,017 21,017 0.4% 0 100.00% 5,178,710Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 7,019,083 60,781 46,851 0.7% 13,930 77.08% 6,958,302Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 1,507,425 485,975 5.2% 1,021,450 32.24% 7,820,075Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 70,910 57,165 0.7% 13,745 80.62% 8,504,479Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 10,483,424 3,332,261 28.6% 7,151,163 31.79% 1,184,541Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 2,169,932 1,050,282 11.8% 1,119,650 48.40% 6,717,590Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.00% 8,410,862PAUSD - Program Management 5,042,021 3,859,518 3,146,745 62.4% 712,773 81.53% 1,182,503PAUSD - Technology 7,101,063 3,644,013 3,612,318 50.9% 31,695 99.13% 3,457,050PAUSD - Technology -Reserved 6,806,302 0 0 0.0% 0 0.00% 6,806,302PAUSD - Reserved 7,185,694 0 0 0.0% 0 0.00% 7,185,694Bond Issuance Cost 1,840,700 1,840,700 1,840,700 100.0% 0 100.00% 0Total350,684,826 58,479,036 37,516,937 20,962,099 292,205,789Prepared by: Business Services Department based on QSS accounting System
Activity IDActivity NameOriginalDurationemainingDurationchedule %ompleteStartFinishTotalFloatGunn ACGunn AC4091530%01-Jan-10 A31-Oct-1132Gunn - PGunn - Parking and Drop Off12468340%01-Sep-09 A10-Jun-140ClassrooClassroom Improvements7806300%02-Sep-10 A28-Aug-130Paly - AtPaly - Athletic Stadium Renovation Project8184040%17-Aug-09 A16-Oct-120Paly - NePaly - New Performing Arts Center (PAC)153010030%09-Sep-09 A02-Feb-15-708Garland Garland School Modernization16800%03-Nov-08 A24-Jun-09 AFairmeadFairmeadow Elementary School11946110%14-Dec-09 A01-Aug-13-316DuvenecDuveneck Elementary School9967660%13-May-10 A06-Mar-14-471Hoover EHoover Elementary School14600%12-May-10 A01-Dec-10 ATeachingTeaching Walls Casework17200%06-Apr-09 A28-Sep-09 AGunn- InGunn- Industrial Arts Renovation45100%01-Oct-08 A24-Jun-10 AJordan NJordan New Classroom Wing & Modernization12516220%03-Nov-08 A12-Aug-13-323Gunn NeGunn New Gym8803770%21-Apr-09 A04-Sep-12-78Gunn NeGunn New Classroom Buildings A and B11216170%20-Apr-09 A06-Aug-13-318Paly NewPaly New Media Arts and Classroom Building11296250%20-Apr-09 A16-Aug-13-326StanfordStanford New Classroom Wing12376180%03-Nov-08 A06-Aug-13-319Terman ATerman Admin Wing Addition & Modernization12406200%03-Nov-08 A09-Aug-13-321Paly - MuPaly - Multi Use Field Improvements65210%03-Nov-08 A31-Mar-11294Ohlone EOhlone Elementary School8422180%03-Nov-08 A25-Jan-1281NDJFAJJASONDJFAMJJASNDJFMAJJASNDJFAMJJASONDJFAMJJASNDJFMAJJASNDJFMAJJA31-Oct-11, Gunn AC10-Jun-14, Gunn - Parking a28-Aug-13, Classroom Improvements16-Oct-12, Paly - Athletic Stadium Renovation Project02-Feb-15, 24-Jun-09 A, Garland School Modernization01-Aug-13, Fairmeadow Elementary School06-Mar-14, Duveneck Elementary 01-Dec-10 A, Hoover Elementary School28-Sep-09 A, Teaching Walls Casework24-Jun-10 A, Gunn- Industrial Arts Renovation12-Aug-13, Jordan New Classroom Wing & Mode04-Sep-12, Gunn New Gym06-Aug-13, Gunn New Classroom Buildings A and16-Aug-13, Paly New Media Arts and Classroom06-Aug-13, Stanford New Classroom Wing09-Aug-13, Terman Admin Wing Addition & Mode31-Mar-11, Paly - Multi Use Field Improvements25-Jan-12, Ohlone Elementary SchoolPAUSD Strong Schools Bond Master ScheduleClassic WBS Layout11-Apr-11 16:00Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryPage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc.
Page | 7
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
The Division of State Architect (DSA) backcheck appointment is secured
for April 13, 2011, with final approval expected shortly after. Alternates
are being developed to mitigate a potential budget shortfall. The
project is anticipated to go out to bid in early May 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time. Budget estimates are
currently over budget, which will be evaluated at bid time.
Funding
State Funds $0
Strong Schools Bond Funds $24,120,000
Other Funding $0
Total $24,120,000
Budget
Salaries and Benefits $12,193
Supplies $0
Contracts & Services $4,463,941
Construction & Equipment $19,567,102
Soft Costs Contingency $76,764
Total $24,120,000
Percent of Budget Expended 10.6%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA April 13, 2011*
Bid Opening May 24, 2011*
Award of Contract (1) June 15, 2011*
Notice to Proceed June 29, 2011*
Substantial Completion June 14, 2013*
Planned Occupancy August 6, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
No further action occurred on this project. Design for the parking
and drop‐off improvements will recommence with the planning of
group 2 projects.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
• Design will recommence with the planning of group 2 projects.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $898,978
Construction & Equipment $2,919,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2011*
BOE Approval June 15, 2011*
Schematic Design (2) September 27, 2011*
BOE Approval October 4, 2011*
Submit to DSA August 9, 2012*
Approval by DSA March 13, 2013*
Authorize to Bid (2) March 14, 2013*
BOE Approval March 27, 2013*
Bid Opening June 26, 2013*
Award of Contract (1) July 31, 2013*
Notice to Proceed September 4, 2013*
Substantial Completion March 13, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Gunn High School
New Gymnasium
A. PROJECT STATUS
The DSA backcheck appointment is scheduled for April 19,
2011, with final approval expected shortly after.
Prequalification of contractors is complete and the project is
anticipated to go out for bid in May 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,830,000
Other Funding $0
Total $13,830,000
Budget
Salaries and Benefits $0
Supplies $1,001
Contracts & Services $2,650,520
Construction & Equipment $11,094,450
Soft Costs Contingency $84,029
Total $13,830,000
Percent of Budget Expended 5.5%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA April 19, 2011*
Bid Opening May 31, 2011*
Award of Contract (1) June 14, 2011*
Notice to Proceed June 29, 2011*
Substantial Completion August 14, 2012*
Planned Occupancy August 22, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
Bids were opened on March 28, 2011 and Best Contracting
Services, Inc. was the low bidder. Staff will seek authorization to
award from BOE on April 5, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
• Project bids received within budget. Award of Contract to be issued on schedule.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $454,610
Construction & Equipment $2,120,580
Soft Costs Contingency $24,810
Total $2,600,000
Percent of Budget Expended 5.2%
Current Phase: Bid &Award
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA October 20, 2010
Approval by DSA February 10, 2011
Authorize to Bid (2) February 22, 2011
BOE Approval March 8, 2011
Bid Opening March 28, 2011
Award of Contract (1) April 8, 2011*
Notice to Proceed April 15, 2011*
Substantial Completion August 8, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Athletic Stadium Improvements
A. PROJECT STATUS
The BOE approved the schematic design on March 8, 2011. The
bleacher design was submitted to DSA, and the concession stand
design package will be submitted to DSA on April 4, 2011. DLM
continues refining the design documents for landscape and tree
protection.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
• BOE approved schematic design on March 8, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $3,626,101
Other Funding $0
Total $3,626,101
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $793,026
Construction & Equipment $2,828,218
Soft Costs Contingency $4,857
Total $3,626,101
Percent of Budget Expended 9.3%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) February 22, 2011
BOE Approval March 8, 2011
Submit to DSA April 4, 2011*
Approval by DSA September 21, 2011*
Authorize to Bid (2) August 11, 2011*
BOE Approval August 25, 2011*
Bid Opening October 25, 2011*
Award of Contract (1) November 2, 2011*
Notice to Proceed November 9, 2011*
Substantial Completion September 6, 2012*
Planned Occupancy October 12, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 12
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
The DSA backcheck appointment is scheduled for April 13, 2011, with
final approval expected shortly after. Alternates are being developed to
mitigate the potential for bids coming in over budget. The project is
anticipated to go out for bid in May 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time.
Funding
State Funds $0
Strong Schools Bond Funds $37,140,000
Other Funding $0
Total $37,140,000
Budget
Salaries and Benefits $14,721
Supplies $0
Contracts & Services $6,955,269
Construction & Equipment $29,740,000
Soft Costs Contingency $430,010
Total $37,140,000
Percent of Budget Expended 7.6%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA April 13, 2011*
Bid Opening May 24, 2011*
Award of Contract (1) June 1, 2011*
Notice to Proceed June 30, 2011*
Substantial Completion July 25, 2013*
Planned Occupancy August 16, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Palo Alto High School
Performing Arts Center (PAC)
A. PROJECT STATUS
After further review of an option for a smaller capacity facility, DLM is
reviewing additional PAC studies for a 575 seat capacity in a single‐level
configuration. DLM and district representatives toured McAfee Theater in
Saratoga to review the floor plan and program layout. Schematic design
work is currently on hold pending a decision from site staff and
administration on the PAC seating capacity and respective design.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
• Project schematic design phase is on hold pending decision on seating capacity for this facility.
Funding
State Funds $0
Strong Schools Bond Funds $17,720,000
Other Funding $0
Total $17,720,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,451,077
Construction & Equipment $14,159,700
Soft Costs Contingency $109,223
Total $17,720,000
Percent of Budget Expended 1.2%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) May 24, 2011*
BOE Approval June 10, 2011*
Submit to DSA January 16, 2012*
Approval by DSA August 12, 2012*
Authorize to Bid (2) August 9, 2012*
BOE Approval August 22, 2012*
Bid Opening October 17, 2012*
Award of Contract (1) November 5, 2012*
Notice to Proceed February 11, 2013*
Substantial Completion December 1, 2014*
Planned Occupancy January, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Jordan Middle School
A. PROJECT STATUS
DSA continues to review the submitted plans with approval
anticipated in fall 2011. AEDIS and Gilbane reconciled cost
estimates, confirming that the project remains over budget. The
Jordan bond advisory committee met on March 16, 2011 to review
budget information and to discuss options for prioritizing scope to
identify as alternate bid packages. Final constructability and
coordination reviews will occur in April 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time. Budget estimates are
currently over budget.
Funding
State Funds $0
Strong Schools Bond Funds $17,943,194
Other Funding $0
Total $17,943,194
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,522,530
Construction & Equipment $13,949,500
Soft Costs Contingency $471,164
Total $17,943,194
Percent of Budget Expended 6.1%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA December 21, 2010
Approval by DSA September 7, 2011*
Authorize to Bid (2) August 23, 2011*
BOE Approval September 13, 2011*
Bid Opening October 18, 2011*
Award of Contract (1) November 9, 2011*
Notice to Proceed November 28, 2011*
Substantial Completion July 13, 2013*
Planned Occupancy August 7, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
J.L. Stanford Middle School
A. PROJECT STATUS
AEDIS submitted 50% construction documents to the
District and intends to submit drawings to DSA in late April
2011. The project design is currently within budget. AEDIS
also anticipates submitting an over‐the‐counter package to
DSA in April for the relocation of the two existing portable
classrooms that are currently located in the designed area
of the new 2‐story building.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
• Project currently proceeding within budget and anticipate to submit to DSA in April, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,699
Other Funding $0
Total $17,184,699
Budget
Salaries and Benefits $0
Supplies $3,458
Contracts & Services $3,360,750
Construction & Equipment $13,341,000
Soft Costs Contingency $479,491
Total $17,184,699
Percent of Budget Expended 7.0%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28, 2010
Submit to DSA April 26, 2011*
Approval by DSA December 26, 2011*
Authorize to Bid (2) December 27, 2011*
BOE Approval January 10, 2012*
Bid Opening February 14, 2012*
Award of Contract (1) February 25, 2012*
Notice to Proceed March 1, 2012*
Substantial Completion June 21, 2013*
Planned Occupancy August 5, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
Terman Middle School
A. PROJECT STATUS
DSA continues to review the submitted plans and approval is
anticipated in fall 2011. AEDIS and Gilbane reconciled cost estimates,
confirming that the project is within budget. Final constructability
and coordination reviews will occur in April 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $12,850,071
Other Funding $0
Total $12,850,071
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,492,860
Construction & Equipment $10,031,569
Soft Costs Contingency $325,642
Total $12,850,071
Percent of Budget Expended 6.4%
Current Phase: DSA Review
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA December 21, 2010
Approval by DSA August 23, 2011*
Authorize to Bid (2) August 23, 2011*
BOE Approval September 13, 2011*
Bid Opening October 18, 2011*
Award of Contract (1) October 26, 2011*
Notice to Proceed November 10, 2011*
Substantial Completion July 11, 2013*
Planned Occupancy August 9, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Gelfand conducted landscape meetings with the site committee on
March 3 and March 21, 2011. On March 10, 2011, a City of Palo
Alto traffic engineer conducted a site visit to observe the existing
drop‐off routine and parking needs for the school. Gelfand
continues to work on construction documents to meet an
anticipated DSA submittal date of April 18, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $9,327,500
Other Funding $0
Total $9,327,500
Budget
Salaries and Benefits $0
Supplies $7,697
Contracts & Services $1,831,019
Construction & Equipment $7,443,000
Soft Costs Contingency $45,784
Total $9,327,500
Percent of Budget Expended 5.2%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010
BOE Approval September 28, 2010
Submit to DSA April 18, 2011*
Approval by DSA December 29, 2011*
Authorize to Bid (2) January 5, 2012*
BOE Approval January 23, 2012*
Bid Opening February 27, 2012*
Award of Contract (1) March 3, 2012*
Notice to Proceed March 12, 2012*
Substantial Completion June 28, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Fairmeadow Elementary School
Portable Relocation Project
A. PROJECT STATUS
ATI Architects and Engineers were contracted to provide the
design documents for the relocation of portable classroom (Rm.
19) at Fairmeadow. The JLS project budget is funding relocating
this classroom since it is currently located in the construction
location of JLS’ new 2‐story classroom building. ATI submitted
an over the counter package to DSA and received approval on
March 3, 2011. The project is anticipated to bid in April 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 6.4
D. PROJECT OVERVIEW:
• Project is currently out to bid.
Funding
State Funds $0
Strong Schools Bond Funds $85,650
Other Funding $0
Total $85,650
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $17,650
Construction & Equipment $62,000
Soft Costs Contingency $6,000
Total $85,650
Percent of Budget Expended 0.6%
Current Phase: Bid & Award
Schedule:
Architect Contract (2) February 15, 2011
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA March 3, 2011
Approval by DSA March 3, 2011
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening May 2, 2011*
Award of Contract (1) May 10, 2011*
Notice to Proceed May 16, 2011*
Substantial Completion August 1, 2011*
Planned Occupancy August 10, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Jeff Luchetti Construction continues structural steel and wood framing of
the building. Interior and exterior framing are well underway, with both
first and second floor walls in progress. Rough‐in is also underway for
plumbing, mechanical and electrical systems. Roofing is scheduled to
begin on March 30, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $0
Supplies $5,467
Contracts & Services $2,348,367
Construction & Equipment $9,169,121
Soft Costs Contingency $145,010
Total $11,667,965
Percent of Budget Expended 28.6%
Change Order Contingency
• Starting Contingency Balance $748,400
• Remaining Contingency Balance $748,400
• Percent of Changes 0.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010
Award of Contract (1) August 3, 2010
Notice to Proceed August 11, 2010
Substantial Completion November 15, 2011*
Planned Occupancy January 25, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Duveneck Elementary School
New Classroom Buildings and Modernization
A. PROJECT STATUS
Gelfand continued meeting with staff and faculty and presented an update to the
steering committee on March 16, 2011, and a follow up meeting is scheduled to
occur in April. A community meeting will be scheduled in early May, with a
presentation to the BOE anticipated for late May 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is progressing through the schematic design phase.
Funding
State Funds $0
Strong Schools Bond Funds $7,019,083
Other Funding $0
Total $7,019,083
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,368,869
Construction & Equipment $5,559,683
Soft Costs Contingency $90,531
Total $7,019,083
Percent of Budget Expended 0.7%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) December 14, 2010
BOE Approval January 11, 2011
Schematic Design (2) May 10, 2011*
BOE Approval May 25, 2011*
Submit to DSA November 4, 2011*
Approval by DSA June 29, 2012*
Authorize to Bid (2) August 10, 2012*
BOE Approval August 25, 2012*
Bid Opening October 2, 2012*
Award of Contract (1) October 16, 2012*
Notice to Proceed October 30, 2012*
Substantial Completion February 7, 2014*
Planned Occupancy August 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Elementary Classroom Improvements
Interactive Whiteboards and Sound Assist System Installation
A. PROJECT STATUS
On March 8, 2011, the BOE authorized the award for installation of new interactive whiteboards and sound
assist systems at Phase 4 and 5 schools, Duveneck, El Carmelo, Escondido, Hoover and Nixon, to Coulter
Construction. Installation of sound assist systems commenced on March 24, 2011 and SmartBoard units are
anticipated to arrive in early April, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• BOE authorized award of contract to Coulter Construction on March 8, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,195,880
Construction & Equipment $7,488,707
Soft Costs Contingency $202,935
Total $8,887,522
Percent of Budget Expended 11.8%
Phase 4 & 5 Schools: Duveneck, El Carmelo, Hoover & Nixon
Current Phase: Construction
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) November 9, 2010
BOE Approval November 23, 2010
Bid Opening February 25, 2011
Award of Contract (1) March 8, 2011
Notice to Proceed March 9, 2011
Completion May 15, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Technology Improvements
A. PROJECT STATUS
80% of the computer purchases planned for the 2010/11 school year have
been made. The district continues to purchase more Apple products than
PC products. In addition to traditional desktops and laptops, schools have
purchased iPod touches, iPads and netbooks for pilot projects.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• New computers delivered to schools.
Funding
State Funds $0
Strong Schools Bond Funds $7,101,063
Other Funding $0
Total $7,101,063
Budget
Salaries and Benefits $0
Supplies & Computers $6,718,468
Contracts & Services $180,173
Construction & Equipment $202,422
Soft Costs Contingency $0
Total $7,101,063
Percent of Budget Expended 50.9%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
The fields were available for play on February 1, 2011, and final change
order negotiations were completed on March 9, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
• Field was open for use on February 1, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $3,002,063
Other Funding $1,075,991
Total $4,078,054
Budget
Salaries and Benefits $0
Supplies $6
Contracts & Services $727,165
Construction & Equipment $3,348,189
Soft Costs Contingency $2,694
Total $4,078,054
Percent of Budget Expended 98.5%
Change Order Contingency
• Starting Contingency Balance $269,300
• Remaining Contingency Balance $230,579
• Percent of Changes 1.7%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –February 1, 2011
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 18, 2008
BOE Approval December 09, 2008
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) February 24, 2009
BOE Approval March 17, 2009
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion January 31, 2011
Planned Occupancy February 1, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
Of the $5,511,500 project budget, 90.5% or $4,987,908 was
expended. Approved change orders were $145,184, approximately
41.6% of the $349,000 construction contingency, or 5.7% of the
construction contract. This project will be closed pending final
closeout of the project by DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
• The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,511,500
Other Funding $0
Total $5,511,500
Budget
Salaries and Benefits $1,063
Supplies $88,985
Contracts & Services $1,213,538
Construction & Equipment $4,207,322
Soft Costs Contingency $592
Total $5,511,500
Percent of Budget Expended 91.0%
Change Order Contingency
• Starting Contingency Balance $349,000
• Remaining Contingency Balance $141,967
• Percent of Changes 41.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Gunn High School
Aquatic Center
A. PROJECT STATUS
Of the $5,013,750 project budget, 96.9%, or $4,858,324 was
expended. Approved change orders were $194,554, approximately
49.9% of the $389,887 construction contingency, or 5.0% of the
construction contract. This project will be closed pending final
closeout of the project by DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
• This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,013,750
Other Funding $0
Total $5,013,750
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $692,797
Construction & Equipment $4,318,858
Soft Costs Contingency $1,095
Total $5,013,750
Percent of Budget Expended 96.9%
Change Order Contingency
• Starting Contingency Balance $389,887
• Remaining Contingency Balance $195,148
• Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education on June 23 for discussion and received approval
on September 8 by the Board of Education to move into schematic
design.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
• This project has been completed on schedule and under budget. Board approval received on September
8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $101,000
Other Funding $0
Total $101,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $85,000
Construction & Equipment $0
Soft Costs Contingency $15,000
Total $101,000
Percent of Budget Expended 52.9%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
Middle Schools Interim Classrooms
Jordan and J.L. Stanford
A. PROJECT STATUS
Contractors completed the installation of these new portables on
August 3, 2009 at Jordan and August 12, 2009 at Stanford. Of the
$1,047,186 project budget, 48.9%, or $512,074 was expended.
Change Orders were $25,980, which is approximately 49.6% of the
$52,379 construction contingency or 5% of the construction
contracts. These projects will be closed pending final closeout of
the projects by DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project was completed under budget and on schedule.
Funding
State Funds $0
Strong Schools Bond Funds $1,047,186
Other Funding $0
Total $1,047,186
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $353,148
Construction & Equipment $691,490
Soft Costs Contingency $2,548
Total $1,047,186
Percent of Budget Expended 48.9%
Change Order Contingency
• Starting Contingency Balance $52,379
• Remaining Contingency Balance $25,998
• Percent of Changes 49.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –August 25, 2009
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA April 14, 2009
Approval by DSA April 22, 2009
Authorize to Bid (2) March 31, 2009
BOE Approval April 14, 2009
Bid Opening May 14, 2009
Award of Contract (1) May 26, 2009
Notice to Proceed June 1, 2009
Substantial Completion August 12, 2009
Planned Occupancy August 25, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Elementary Classroom Improvements
Phase 1 – Barron Park and El Carmelo
A. PROJECT STATUS
DSA continues reviewing Phase 1 plans for work that includes new
lighting, adding operable windows and coverings, ventilation, and
replacement of ceiling tiles for classrooms at Barron Park and El
Carmelo elementary schools. The authorization to bid has been
placed on hold pending further discussions with the BOE about
elementary growth planning.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,195,880
Construction & Equipment $7,488,707
Soft Costs Contingency $202,935
Total $8,887,522
Percent of Budget Expended 11.8%
Phase 1 Schools: Barron Park and El Carmelo
Current Phase: DSA Review
Schedule:
Architect Contract (2) June 8, 2010
BOE Approval June 22, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 9, 2010
BOE Approval December 7, 2010
Submit to DSA December 23, 2010
Approval by DSA May 9, 2011*
Authorize to Bid (2) April 15, 2011*
BOE Approval April 30, 2011*
Bid Opening May 12, 2011*
Award of Contract (1) May 24, 2011*
Notice to Proceed June 1, 2011*
Substantial Completion August 1, 2011*
Planned Occupancy August 10, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 29
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education voted on August 25, 2009 to approve the
amendment to Garland lease to Stratford School. Therefore, the
district has placed the project on hold.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,915,789
Construction & Equipment $17,400,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: On Hold
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotesnumber of Board of Education Readings
Page | 30
Elementary School Teaching Walls
Phase 1 Schools
A. PROJECT STATUS
The district placed this project on hold after review of the
implementation of other classroom improvements, as
recommended by the elementary school principals. This
project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.9
D. PROJECT OVERVIEW:
• This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary
above).
Funding
State Funds $0
Strong Schools Bond Funds $7,044,987
Other Funding $0
Total $7,044,987
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,341,394
Construction & Equipment $5,498,498
Soft Costs Contingency $205,095
Total $7,044,987
Percent of Budget Expended 1.6%
Current Phase: Project Renamed. See Classroom
Improvements Project
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates –Subject to Change
Page | 31
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
The Board of Education (BOE) approved the Palo Alto high
school updated master plan project list on October 9, 2010 and
no further action on the high school master plans is planned.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
• No further action since Paly’s updated master plan project list was approved by BOE on October 9, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $290,000
Other Funding $0
Total $290,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $288,565
Construction & Equipment $0
Soft Costs Contingency $435
Total $290,000
Percent of Budget Expended 81.5%
Current Phase: Master Planning
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010
Paly MP Revision Approval (2) October 9, 2010
Gunn MP Revision Approval (2) October 12, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 32
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
Staff has put this project on hold until growth projections are reviewed
and a growth plan is established for the elementary schools.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently on hold.
Funding
State Funds $0
Strong Schools Bond Funds $8,575,389
Other Funding $0
Total $8,575,389
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,643,477
Construction & Equipment $6,831,912
Soft Costs Contingency $100,000
Total $8,575,389
Percent of Budget Expended 0.4%
Current Phase: On Hold
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) November 9, 2010
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.