Monthly Reports 2011-02 (Feb) MMOONNTTHHLLYY  PPRROOGGRREESSSS  RREEPPOORRTT     Through  February 2011      Current Strong Schools Bond  Capital Improvement Projects  Prepared by     O’Connor Construction Management, Inc.  &  Gilbane Building Company  Page | 2   TABLE OF CONTENTS    Executive Summary         page 3      Attachment 1 – Consolidated Expenditure Report          Attachment 2 – Master Program Schedule Summary         Capital Projects     Gunn High School – New Classroom Buildings A & B     page 6    Gunn High School – Parking and Drop‐off Sitework Improvement    page 7    Gunn High School – New Gymnasium       page 8    Gunn High School – Air Conditioning of Existing Buildings    page 9    Palo Alto High School – Athletic Stadium Improvements    page 10    Palo Alto High School – Multi‐use Field      page 11    Palo Alto High School – Classroom Building and Media Arts    page 12    Palo Alto High School – Theater and Associated Site Improvements    page 13    Jordan Middle School        page 14    J.L. Stanford Middle School       page 15    Terman Middle School        page 16    Fairmeadow Elementary School       page 17    Ohlone Elementary School        page 18    Duveneck Elementary School       page 19    Elementary Classroom Improvements      page 20    Technology          page 21    Completed Capital Projects    Gunn High School – Industrial Arts Renovation     page 22    Gunn High School – Aquatic Center       page 23    Middle School Pre‐Design        page 24    Middle School Interim Classrooms       page 25    Inactive Capital Projects    Garland Elementary School       page 26    Elementary School Teaching Walls – Phase 1 Schools     page 27    High School Master Plan        page 28    Hoover Elementary School        page 29    Appendix  Exhibit A – Bond Project List    Page | 3   EXECUTIVE SUMMARY    CAPITAL PROJECTS     Gunn High School – New Classroom Buildings A & B  The Division of State Architect (DSA) completed their plan review and final approval is anticipated in March  2011. Current estimates are over budget, so alternate packages are being developed to mitigate this potential  budget shortfall.  Prequalification of contractors is underway, as the project is anticipated to bid in April 2011.    Gunn High School – Parking and Drop‐off Sitework Improvement  No further action occurred on this project.  Design for the parking and drop‐off improvements will recommence  with the planning of group 2 projects.     Gunn High School – New Gymnasium  DLM has received all review comments from DSA and are expected to receive approval in March 2011. Prequalification of contractors is underway, as the project is anticipated to bid in April 2011.    Gunn High School – Air Conditioning of Existing Buildings  DSA approval was received on February 10, 2011 and estimates show that the project is within budget.  Staff asked  the BOE for authorization to bid on February 22, 2011 and the bid opening is scheduled for March 28, 2011.    Palo Alto High School – Athletics Stadium Improvements  DLM presented and received approval of the schematic design from the FSC on February 2, 2011.  The schematic  design was also presented to the BOE on February 22, 2011, with approval anticipated on March 8, 2011.  DLM will  submit the bleacher design and the concession stand design as separate projects to DSA in March 2011.    Palo Alto High School – Multi‐use Field  The fields were available for play on February 1, 2011, and final change order negotiations are expected to be  complete in March 2011.    Palo Alto High School – Classroom Building and Media Arts Building  DSA complete their plan review and provided comments to DLM, with final approval anticipated in March 2011.   Prequalification of contractors is underway, as the project is anticipated to bid in April 2011.    Palo Alto High School – Performing Arts Center (PAC)  DLM presented the alternate schematic design for the single story, 472‐seat facility to the FSC on February 2, 2011.  The design was recommended to staff for approval, since it is in line with the campus master project budget.   Estimating of this alternate design was completed on February 18, 2011 and DLM is anticipated to present  schematic design to the BOE in April 2011, pending review of the reduced seating capacity.    Jordan Middle School  DSA continues to review the submitted plans and approval is anticipated in late summer 2011.  Concurrent with  DSA’s review, Gilbane will perform cost estimating and constructability reviews for the project.  A value  engineering (VE), alternate bid strategy and phasing session with staff and AEDIS is also planned to occur in March  2011. The goal will be to prioritize alternates and maximize flexibility in order to remain within the budget.     J.L. Stanford Middle School  Cost estimating, constructability reviews, and VE efforts continued through February 2011 on the design  development package.  AEDIS will submit 50% construction documents and an estimate update to the district for  review in March 2011.      Page | 4     Terman Middle School  DSA continues to review the submitted plans and approval is anticipated in late summer 2011.  During DSA’s  review, Gilbane is performing cost estimating and constructability reviews for the project.  In order to ensure this  project remains within budget, alternate bid strategies and phasing options are being considered.    Fairmeadow Elementary School – New Classroom Building and Modernization  Gelfand presented an updated site plan to the site committee on February 28, 2011, and is continuing with  construction documents for the 50% CD submittal on March 14, 2011.  Construction documents will include  recommendations based on the VE session completed in January 2011.  DSA submittal is anticipated on April 8,  2011.     Ohlone Elementary School – New Classroom Building and Modernization  Jeff Luchetti Construction continues steel and wood framing of the building.  These activities will continue into  March 2011, with MEP rough‐in to commence shortly after.    Duveneck Elementary School – New Classroom Buildings and Modernization  Gelfand commenced schematic design with the user groups on February 9, 2011 and February 23, 2011.  Design  meetings will continue with users in March 2011, with a community meeting and presentation to the BOE  anticipated for April 2011.    Elementary Classroom Improvements  DSA is reviewing Phase 1 plans for work that includes new lighting, adding operable windows and coverings,  ventilation, and replacement of ceiling tiles for classrooms at Barron Park and El Carmelo elementary schools.  The  authorization to bid has been placed on hold pending further discussions with the BOE about elementary growth  planning.  The project is also funding the installation of new interactive whiteboards and sound assist systems.   Phases 4 and 5 bids for installation at Duveneck, El Carmelo, Hoover and Nixon were opened on February 28, 2011.   Staff will seek authorization to award from the BOE on March 8, 2011.   Technology  80% of the computer purchases planned for the 2010/11 school year have been made.   The district continues to  purchase more Apple products than PC products.  In addition to traditional desktops and laptops, schools have  purchased iPod touches, iPads and netbooks for pilot projects.      COMPLETED CAPITAL PROJECTS   Gunn High School – Industrial Arts Addition & Renovation  Of the $5,511,500 project budget, 90.5% or $4,987,908 was expended.  Approved change orders were $145,184,  approximately 41.6% of the $349,000 construction contingency, or 5.7% of the construction contract.  This project  will be closed pending final closeout of the project by DSA.    Gunn High School – Aquatic Center   Of the $5,013,750 project budget, 96.9%, or $4,858,324 was expended.  Approved change orders were $194,554,  approximately 49.9% of the $389,887 construction contingency, or 5.0% of the construction contract. This project  will be closed pending final closeout of the project by DSA.    Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman  AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for  discussion and received approval on September 8 by the Board of Education to move into schematic design.  This  project is now closed, and funds will soon be transferred to program contingency.    Page | 5   Middle Schools Interim Housing – Jordan and J.L. Stanford  Contractors completed the installation of these new portables on August 3, 2009 at Jordan and August 12, 2009 at  Stanford.  Of the $1,047,186 project budget, 48.9%, or $512,074 was expended. Change Orders were $25,980,  which is approximately 49.6% of the $52,379 construction contingency or 5% of the construction contracts. These  projects will be closed pending final closeout of the projects by DSA.    INACTIVE CAPITAL PROJECTS     Garland Elementary School Renovation  The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.   Therefore, the district has placed the project on hold.    Elementary School Teaching Walls – Phase 1 Schools  The district placed this project on hold after review of the implementation of other classroom improvements, as  recommended by the elementary school principals.  This project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).     High School Master Plan  The Board of Education (BOE) approved the Palo Alto high school updated master plan project list on October 9,  2010 and no further action on the high school master plans is planned.   Hoover Elementary School – Pre‐Design  Staff has put this project on hold until growth projections are reviewed and a growth plan is established for the  elementary schools.         No Board Actions in February  A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 142,391 117,416 81.0% 24,975 82.46% 2,609Gunn High School 1 - Aquatic Center 5,013,750 4,865,424 4,860,823 96.9% 4,601 99.91% 148,326Gunn High School 2 - I.A Building 5,511,500 5,055,070 5,016,404 91.0% 38,666 99.24% 456,430Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 24,120,000 4,015,328 2,492,314 10.3% 1,523,014 62.07% 20,104,672Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 4,041 0.1% 213,729 1.86% 3,722,230Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 1,617,196 741,645 5.4% 875,551 45.86% 12,212,804Gunn High School 7- A/C 2,600,000 319,199 130,061 0.0% 189,138 40.75% 2,280,801Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.00% 20,945,045Palo Alto High Schools - High School Master Plan 145,000 142,997 128,442 88.6% 14,555 89.82% 2,003Palo Alto High School 1 - Stadium Field 1,358,437 592,540 204,400 15.0% 388,140 34.50% 765,897Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,988,139 2,804,292 93.4% 183,847 93.85% 13,924Palo Alto high School 3 - New classroom & Media Art Building 37,140,000 5,125,106 2,668,944 7.2% 2,456,162 52.08% 32,014,894Palo Alto High School 4 - New Theater 17,720,000 1,364,138 146,441 0.8% 1,217,697 10.74% 16,355,862Palo Alto High School - Reserved 39,428,045 0 0 0.0% 0 0.00% 39,428,045Jordan Middle School -Program Management- MS Pre-Design 33,665 18,890 17,826 53.0% 1,064 94.37% 14,775Jordan Middle Schools 1- Interim Classrooms 600,342 176,573 164,525 27.4% 12,048 93.18% 423,769Jordan Middle School 2- Improvements 17,943,194 2,655,813 1,056,117 5.9% 1,599,696 39.77% 15,287,381J.L.S Middle School - Program Management- MS Pre-Design 33,669 18,799 18,408 54.7% 391 97.92% 14,870J.L.S Middle School 1 - Interim Classrooms 446,844 364,654 336,929 75.4% 27,725 92.40% 82,190 J.L.S Middle School 2- Improvements 17,184,699 2,774,572 859,090 5.0% 1,915,482 30.96% 14,410,127Terman Middle School - Program Management- MS Pre-Design 33,666 18,799 18,423 54.7% 376 98.00% 14,867Terman Middle School 1- Improvements 12,850,071 1,937,074 790,718 6.2% 1,146,356 40.82% 10,912,997PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 55,560 55,560 38.3% 0 100.00% 89,440Addison Elementary School 1-Phase I 5,199,727 21,017 2,373 0.0% 18,644 11.29% 5,178,710Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 7,019,083 49,351 46,851 0.7% 2,500 94.93% 6,969,732Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 1,517,932 444,770 4.8% 1,073,162 29.30% 7,809,568Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 70,910 57,165 0.7% 13,745 80.62% 8,504,479Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 10,559,873 2,605,120 22.3% 7,954,753 24.67% 1,108,092Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 1,344,046 1,005,017 11.3% 339,029 74.78% 7,543,476Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.00% 8,410,862PAUSD - Program Management 5,042,021 3,842,118 3,042,100 60.3% 800,018 79.18% 1,199,903PAUSD - Technology 7,101,063 3,611,695 3,562,059 50.2% 49,636 98.63% 3,489,368PAUSD - Technology -Reserved 6,806,302 0 0 0.0% 0 0.00% 6,806,302PAUSD - Reserved 7,185,694 0 0 0.0% 0 0.00% 7,185,694Bond Issuance Cost 1,840,700 1,840,700 1,840,700 100.0% 0 100.00% 0Total350,684,826 57,610,730 35,524,864 22,085,866 293,074,095Prepared by: Business Services Department based on QSS accounting SystemExpenditures Budget BalanceCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond2/28/2011Percent of ExpendedContract Balance Activity IDActivity NameOriginalDurationemainingDurationchedule %ompleteStartFinishTotalFloatGunn ACGunn AC4091760%01-Jan-10 A31-Oct-1132Gunn - PGunn - Parking and Drop Off12238340%01-Sep-09 A08-May-140ClassrooClassroom Improvements7806530%02-Sep-10 A28-Aug-130Paly - AtPaly - Athletic Stadium Renovation Project8064150%17-Aug-09 A28-Sep-120Paly - NePaly - New Performing Arts Center (PAC)153010260%09-Sep-09 A02-Feb-15-708Garland Garland School Modernization16800%03-Nov-08 A24-Jun-09 AFairmeadFairmeadow Elementary School11946340%14-Dec-09 A01-Aug-13-316DuvenecDuveneck Elementary School9867790%13-May-10 A20-Feb-14-461Hoover EHoover Elementary School14600%12-May-10 A01-Dec-10 ATeachingTeaching Walls Casework17200%06-Apr-09 A28-Sep-09 AGunn- InGunn- Industrial Arts Renovation45100%01-Oct-08 A24-Jun-10 AJordan NJordan New Classroom Wing & Modernization12516420%03-Nov-08 A12-Aug-13-323Gunn NeGunn New Gym8613780%21-Apr-09 A07-Aug-12-59Gunn NeGunn New Classroom Buildings A and B11216370%20-Apr-09 A06-Aug-13-318Paly NewPaly New Media Arts and Classroom Building11216370%20-Apr-09 A06-Aug-13-318StanfordStanford New Classroom Wing12406410%03-Nov-08 A09-Aug-13-322Terman ATerman Admin Wing Addition & Modernization12406400%03-Nov-08 A09-Aug-13-321Paly - MuPaly - Multi Use Field Improvements652220%03-Nov-08 A29-Mar-11296Ohlone EOhlone Elementary School8232180%03-Nov-08 A29-Dec-11100SNDJFAJJASONDJFAMJJASNDJFMAJJASNDJFAMJJASONDJFAMJJASNDJFMAJJASNDJFMAJ31-Oct-11, Gunn AC08-May-14, Gunn - Parking28-Aug-13, Classroom Improvements28-Sep-12, Paly - Athletic Stadium Renovation Project02-Feb-124-Jun-09 A, Garland School Modernization01-Aug-13, Fairmeadow Elementary School20-Feb-14, Duveneck Elementar01-Dec-10 A, Hoover Elementary School28-Sep-09 A, Teaching Walls Casework24-Jun-10 A, Gunn- Industrial Arts Renovation12-Aug-13, Jordan New Classroom Wing & M07-Aug-12, Gunn New Gym06-Aug-13, Gunn New Classroom Buildings A06-Aug-13, Paly New Media Arts and Classroo09-Aug-13, Stanford New Classroom Wing09-Aug-13, Terman Admin Wing Addition & M29-Mar-11, Paly - Multi Use Field Improvements29-Dec-11, Ohlone Elementary SchoolPAUSD Strong Schools Bond Master ScheduleClassic WBS Layout10-Mar-11 16:18Actual WorkRemaining WorkCritical Remaining WorkMilestoneSummaryPage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc. Page | 6   Gunn High School  New Classroom Buildings A & B  A. PROJECT STATUS    The Division of State Architect (DSA) completed their plan review and  final approval is anticipated in March 2011. Current estimates are over  budget, so alternate packages are being developed to mitigate this  potential budget shortfall.  Prequalification of contractors is underway,  as the project is anticipated to bid in April 2011.            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule under DSA’s anticipated review time.  Budget estimates are  currently over budget, which will be evaluated at bid time.               Funding  State Funds $0  Strong Schools Bond Funds $24,120,000  Other Funding $0  Total $24,120,000    Budget  Salaries and Benefits $12,192  Supplies $0  Contracts & Services $4,451,369  Construction & Equipment $19,567,102  Soft Costs Contingency $125,336  Total $24,120,000    Percent of Budget Expended 10.3%  Current Phase: DSA Review   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010     Authorize to Bid (2) March 8, 2011*  BOE Approval March 22, 2011*    Approval by DSA March 30, 2011*    Bid Opening April 28, 2011*    Award of Contract (1) May 4, 2011*    Notice to Proceed June 6, 2011*    Substantial Completion June 14, 2013*    Planned Occupancy August 6, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 7   Gunn High School  Parking and Drop‐off Sitework Improvement  A. PROJECT STATUS    No further action occurred on this project.  Design for the parking  and drop‐off improvements will recommence with the planning of  group 2 projects.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:  • Design will recommence with the planning of group 2 projects.     Funding  State Funds $0  Strong Schools Bond Funds $3,940,000  Other Funding $0  Total $3,940,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $898,978  Construction & Equipment $2,919,840  Soft Costs Contingency $121,182  Total $3,940,000    Percent of Budget Expended 0.1%  Current Phase: Conceptual Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 1, 2011*  BOE Approval June 15, 2011*    Schematic Design (2) September 27, 2011*  BOE Approval October 4, 2011*    Submit to DSA August 9, 2012*     Approval by DSA March 13, 2013*    Authorize to Bid (2) March 14, 2013*  BOE Approval March 27, 2013*    Bid Opening June 26, 2013*    Award of Contract (1) July 31, 2013*    Notice to Proceed September 4, 2013*    Substantial Completion March 13, 2014*      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 8   Gunn High School  New Gymnasium  A. PROJECT STATUS    DLM has received all review comments from DSA and are  expected to receive approval in March 2011. Prequalification of  contractors is underway, as the project is anticipated to bid in  April 2011.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule under DSA’s anticipated review time and within budget.        Funding  State Funds $0  Strong Schools Bond Funds $13,830,000  Other Funding $0  Total $13,830,000    Budget  Salaries and Benefits $0  Supplies $1,001  Contracts & Services $2,650,520  Construction & Equipment $11,094,450  Soft Costs Contingency $84,029  Total $13,830,000    Percent of Budget Expended 5.4%  Current Phase: DSA Review   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011*  BOE Approval March 22, 2011*    Approval by DSA April 4, 2011*    Bid Opening May 5, 2011*    Award of Contract (1) May 13, 2011*    Notice to Proceed June 1, 2011*    Substantial Completion July 18, 2012*    Planned Occupancy August 7, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 9   Gunn High School  Air Conditioning of Existing Buildings  A. PROJECT STATUS    DSA approval was received on February 10, 2011 and estimates  show that the project is within budget.  Staff asked the BOE for  authorization to bid on February 22, 2011 and the bid opening is  scheduled for March 28, 2011.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.7    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.  DSA approval received February 10, 2011.    Funding  State Funds $0  Strong Schools Bond Funds $2,600,000  Other Funding $0  Total $2,600,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $454,610  Construction & Equipment $2,120,580  Soft Costs Contingency $24,810  Total $2,600,000    Percent of Budget Expended 0.0%  Current Phase: Bid & Award   Schedule:  Architect Contract (2) March 27, 2010  BOE Approval April 6, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA October 20, 2010    Approval by DSA February 10, 2011    Authorize to Bid (2) February 22, 2011  BOE Approval March 8, 2011*    Bid Opening March 28, 2011*    Award of Contract (1) April 5, 2011*    Notice to Proceed April 8, 2011*    Substantial Completion August 8, 2011*      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 10   Palo Alto High School  Athletic Stadium Improvements  A. PROJECT STATUS    DLM presented and received approval of the schematic design from  the FSC on February 2, 2011.  The schematic design was also  presented to the BOE on February 22, 2011, with approval  anticipated on March 8, 2011.  DLM will submit the bleacher design  and the concession stand design as separate projects to DSA in  March 2011.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.13    D. PROJECT OVERVIEW:  • Project presented to BOE on February 22, 2011.  Funding  State Funds $0  Strong Schools Bond Funds $1,358,437  Other Funding $0  Total $1,358,437    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $259,847  Construction & Equipment $1,098,590  Soft Costs Contingency $0  Total $1,358,437    Percent of Budget Expended 15.0%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) January 26, 2010  BOE Approval February 9, 2010    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) February 22, 2011  BOE Approval March 8, 2011*    Submit to DSA March 7, 2011*    Approval by DSA September 2, 2011*    Authorize to Bid (2) July 25, 2011*  BOE Approval August 8, 2011*    Bid Opening October 6, 2011*    Award of Contract (1) October 4, 2011*    Notice to Proceed October 21, 2011*    Substantial Completion August 20, 2012*    Planned Occupancy September 15, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 11   Palo Alto High School   Multi‐Use Field  A. PROJECT STATUS     The fields were available for play on February 1, 2011, and final change  order negotiations are expected to be complete in March 2011.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.14    D. PROJECT OVERVIEW:  • Field was open for use on February 1, 2011.  Funding  State Funds $0  Strong Schools Bond Funds $3,002,063  Other Funding $1,075,991  Total $4,078,054    Budget  Salaries and Benefits $0  Supplies $6  Contracts & Services $678,289  Construction & Equipment $3,380,258  Soft Costs Contingency $19,501  Total $4,078,054     Percent of Budget Expended 93.4%    Change Order Contingency  • Starting Contingency Balance $269,300  • Remaining Contingency Balance $230,579  • Percent of Changes 1.7%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –February 1, 2011    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 18, 2008  BOE Approval December 09, 2008    Submit to DSA March 19, 2009     Approval by DSA September 30, 2009    Authorize to Bid (2) February 24, 2009  BOE Approval March 17, 2009    Bid Opening March 16, 2010    Award of Contract (1) April 7, 2010    Notice to Proceed June 1, 2010    Substantial Completion January 31, 2011    Planned Occupancy February 1, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 12   Palo Alto High School  Classroom Building and Media Arts  A. PROJECT STATUS    DSA complete their plan review and provided comments to DLM, with  final approval anticipated in March 2011.  Prequalification of  contractors is underway, as the project is anticipated to bid in April  2011.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule under DSA’s anticipated review time. Funding  State Funds $0  Strong Schools Bond Funds $37,140,000  Other Funding $0  Total $37,140,000    Budget  Salaries and Benefits $14,721  Supplies $0  Contracts & Services $6,955,269  Construction & Equipment $29,740,000  Soft Costs Contingency $430,010  Total $37,140,000    Percent of Budget Expended 7.2%  Current Phase: DSA Review   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 4, 2010    Authorize to Bid (2) March 8, 2011*  BOE Approval March 22, 2011*    Approval by DSA April 4, 2011*    Bid Opening May 12, 2011*    Award of Contract (1) May 20, 2011*    Notice to Proceed June 20, 2011*    Substantial Completion July 15, 2013*    Planned Occupancy August 6, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 13   Palo Alto High School  Performing Arts Center (PAC)  A. PROJECT STATUS    DLM presented the alternate schematic design for the single story, 472‐seat  facility to the FSC on February 2, 2011. The design was recommended to  staff for approval, since it is in line with the campus master project budget.   Estimating of this alternate design was completed on February 18, 2011 and  DLM is anticipated to present schematic design to the BOE in April 2011,  pending review of the reduced seating capacity.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.11    D. PROJECT OVERVIEW:  • Project is progressing through the schematic design phase.  Funding  State Funds $0  Strong Schools Bond Funds $17,720,000  Other Funding $0  Total $17,720,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,451,077  Construction & Equipment $14,159,700  Soft Costs Contingency $109,223  Total $17,720,000    Percent of Budget Expended 0.8%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) March 8, 2011*  BOE Approval March 22, 2011*    Submit to DSA November 14, 2011*    Approval by DSA June 6, 2012*    Authorize to Bid (2) June 7, 2012*  BOE Approval June 20, 2012*    Bid Opening August 15, 2012*    Award of Contract (1) September 3, 2012*    Notice to Proceed February 11, 2013*    Substantial Completion December 1, 2014*    Planned Occupancy January, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 14   Jordan Middle School  A. PROJECT STATUS    DSA continues to review the submitted plans and approval is  anticipated in late summer 2011.  Concurrent with DSA’s review,  Gilbane will perform cost estimating and constructability reviews for  the project.  A value engineering (VE), alternate bid strategy and  phasing session with staff and AEDIS is also planned to occur  in March 2011. The goal will be to prioritize alternates and maximize  flexibility in order to remain within the budget.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule under DSA’s anticipated review time.  Budget estimates are  currently over budget. Funding  State Funds $0  Strong Schools Bond Funds $17,943,194  Other Funding $0  Total $17,943,194    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,522,530  Construction & Equipment $13,949,500  Soft Costs Contingency $471,164  Total $17,943,194    Percent of Budget Expended 5.9%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) March 23, 2010  BOE Approval April 27, 2010    Submit to DSA December 21, 2010     Approval by DSA August 22, 2011*    Authorize to Bid (2) July 26, 2011*  BOE Approval August 23, 2011*    Bid Opening September 27, 2011*    Award of Contract (1) October 12, 2011*    Notice to Proceed October 31, 2011*    Substantial Completion July 13, 2013*    Planned Occupancy August 9, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 15   J.L. Stanford Middle School  A. PROJECT STATUS    Cost estimating, constructability reviews, and VE efforts  continued through February 2011 on the design  development package.  AEDIS will submit 50%  construction documents and an estimate update to the  district for review in March 2011.                           B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:  • Project currently proceeding within budget and anticipate to submit to DSA in April, 2011. Funding  State Funds $0  Strong Schools Bond Funds $17,184,699  Other Funding $0  Total $17,184,699    Budget  Salaries and Benefits $0  Supplies $3,458  Contracts & Services $3,354,000  Construction & Equipment $13,341,000  Soft Costs Contingency $486,241  Total $17,184,699    Percent of Budget Expended 5.0%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (3) June 1, 2010  BOE Approval June 22, 2010  BOE Approval (Sitework) September 28, 2010    Submit to DSA April 12, 2011*     Approval by DSA December 12, 2011*    Authorize to Bid (2) December 13, 2011*  BOE Approval December 27, 2011*    Bid Opening January 31, 2012*    Award of Contract (1) January 25, 2012*    Notice to Proceed February 9, 2012*    Substantial Completion June 26, 2013*    Planned Occupancy August 9, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings Page | 16   Terman Middle School  A. PROJECT STATUS    DSA continues to review the submitted plans and approval is  anticipated in late summer 2011.  During DSA’s review, Gilbane is  performing cost estimating and constructability reviews for the  project.  In order to ensure this project remains within budget,  alternate bid strategies and phasing options are being considered.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule under DSA’s anticipated review time and within budget. Funding  State Funds $0  Strong Schools Bond Funds $12,850,071  Other Funding $0  Total $12,850,071    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,492,860  Construction & Equipment $10,031,569  Soft Costs Contingency $325,642  Total $12,850,071    Percent of Budget Expended 6.2%  Current Phase: DSA Review   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) May 11, 2010  BOE Approval May 25, 2010    Submit to DSA December 21, 2010    Approval by DSA August 23, 2011*    Authorize to Bid (2) July 26, 2011*  BOE Approval August 23, 2011*    Bid Opening September 27, 2011*    Award of Contract (1) October 12, 2011*    Notice to Proceed October 27, 2011*    Substantial Completion July 11, 2013*    Planned Occupancy August 9, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 17   Fairmeadow Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    Gelfand presented an updated site plan to the site committee on  February 28, 2011, and is continuing with construction documents for  the 50% CD submittal on March 14, 2011.  Construction documents will  include recommendations based on the VE session completed in  January 2011.  DSA submittal is anticipated on April 8, 2011.                   B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.   Funding  State Funds $0  Strong Schools Bond Funds $9,327,500  Other Funding $0  Total $9,327,500    Budget  Salaries and Benefits $0  Supplies $7,697  Contracts & Services $1,831,019  Construction & Equipment $7,443,000  Soft Costs Contingency $45,784  Total $9,327,500    Percent of Budget Expended 4.8%  Current Phase: Design Development    Schedule:  Architect Contract (2) October 13, 2009  BOE Approval October 27, 2009    Conceptual Design (2) March 23, 2010  BOE Approval April 6, 2010    Schematic Design (2) September 14, 2010  BOE Approval September 28, 2010    Submit to DSA April 27, 2011*     Approval by DSA December 21, 2011*    Authorize to Bid (2) December 28, 2011*  BOE Approval January 13, 2012*    Bid Opening February 12, 2012*    Award of Contract (1) February 17, 2012*    Notice to Proceed March 12, 2012*    Substantial Completion June 21, 2013*    Planned Occupancy August 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 18   Ohlone Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    Jeff Luchetti Construction continues steel and wood framing of the  building.  These activities will continue into March 2011, with MEP rough‐ in to commence shortly after.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.      Funding  State Funds $0  Strong Schools Bond Funds $11,667,965  Other Funding $0  Total $11,667,965    Budget  Salaries and Benefits $0  Supplies $5,467  Contracts & Services $2,348,367  Construction & Equipment $9,169,121  Soft Costs Contingency $145,010  Total $11,667,965    Percent of Budget Expended 22.3%    Change Order Contingency  • Starting Contingency Balance $748,400  • Remaining Contingency Balance $748,400  • Percent of Changes 0.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Construction   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) March 3, 2009  BOE Approval March 17, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA November 24, 2009    Authorize to Bid (2) April 27, 2010  BOE Approval May 11, 2010    Approval by DSA May 18, 2010    Bid Opening July 13, 2010    Award of Contract (1) August 3, 2010    Notice to Proceed August 11, 2010    Substantial Completion October 19, 2011*    Planned Occupancy December 29, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 19   Duveneck Elementary School  New Classroom Buildings and Modernization  A. PROJECT STATUS    Gelfand commenced schematic design with the user groups on February 9,  2011 and February 23, 2011.  Design meetings will continue with users in  March 2011, with a community meeting and presentation to the BOE  anticipated for April 2011.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Schematic design meetings commenced on February 9, 2011. Funding  State Funds $0  Strong Schools Bond Funds $7,019,083  Other Funding $0  Total $7,019,083    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,368,869  Construction & Equipment $5,559,683  Soft Costs Contingency $90,531  Total $7,019,083    Percent of Budget Expended 0.7%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) December 14, 2010  BOE Approval January 11, 2011    Schematic Design (2) April 26, 2011*  BOE Approval May 10, 2011*    Submit to DSA October 21, 2011*     Approval by DSA June 15, 2012*    Authorize to Bid (2) July 27, 2012*  BOE Approval August 15, 2012*    Bid Opening September 18, 2012*    Award of Contract (1) September 26, 2012*    Notice to Proceed September 30, 2012*    Substantial Completion January 1, 2014*    Planned Occupancy January, 2014*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 20   Elementary Classroom Improvements  Phase 1 – Barron Park and El Carmelo  A. PROJECT STATUS    DSA is reviewing Phase 1 plans for work that includes new lighting,  adding operable windows and coverings, ventilation, and replacement  of ceiling tiles for classrooms at Barron Park and El Carmelo  elementary schools.  The authorization to bid has been placed on hold  pending further discussions with the BOE about elementary growth  planning.  The project is also funding the installation of new  interactive whiteboards and sound assist systems.  Phases 4 and 5 bids  for installation at Duveneck, El Carmelo, Hoover and Nixon were  opened on February 28, 2011.  Staff will seek authorization to award  from the BOE on March 8, 2011.          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • Bids opened for Phase 4 and 5 on February 25, 2011.        Funding  State Funds $0  Strong Schools Bond Funds $8,887,522  Other Funding $0  Total $8,887,522    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,194,920  Construction & Equipment $7,488,707  Soft Costs Contingency $203,895  Total $8,887,522    Percent of Budget Expended 11.3%    Phase 1 Schools: Barron Park and El Carmelo  Current Phase:  DSA Review    Schedule:  Architect Contract (2) June 8, 2010  BOE Approval June 22, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) November 9, 2010  BOE Approval December 7, 2010    Submit to DSA December 23, 2010     Approval by DSA May 9, 2011*    Authorize to Bid (2) April 15, 2011*  BOE Approval April 30, 2011*    Bid Opening May 12, 2011*    Award of Contract (1) May 24, 2011*    Notice to Proceed June 1, 2011*    Substantial Completion August 1, 2011*    Planned Occupancy August 10, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 21     Technology Improvements  A. PROJECT STATUS     80% of the computer purchases planned for the 2010/11 school year have  been made.   The district continues to purchase more Apple products than  PC products.  In addition to traditional desktops and laptops, schools have  purchased iPod touches, iPads and netbooks for pilot projects.           B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • New computers delivered to schools.      Funding  State Funds $0  Strong Schools Bond Funds $7,101,063  Other Funding $0  Total $7,101,063    Budget  Salaries and Benefits $0  Supplies & Computers $6,718,468  Contracts & Services $180,173  Construction & Equipment $202,422  Soft Costs Contingency $0  Total $7,101,063    Percent of Budget Expended 50.2%    Current Phase: N/A   Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 22     Gunn High School  Industrial Arts Addition and Renovation  A. PROJECT STATUS    Of the $5,511,500 project budget, 90.5% or $4,987,908 was  expended.  Approved change orders were $145,184, approximately  41.6% of the $349,000 construction contingency, or 5.7% of the  construction contract.  This project will be closed pending final  closeout of the project by DSA.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11    D. PROJECT OVERVIEW:  • The building occupied as scheduled, and the project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,511,500  Other Funding $0  Total $5,511,500    Budget  Salaries and Benefits $1,063  Supplies $76,657  Contracts & Services $1,225,866  Construction & Equipment $4,207,322  Soft Costs Contingency $592  Total $5,511,500    Percent of Budget Expended 91.0%    Change Order Contingency  • Starting Contingency Balance $349,000  • Remaining Contingency Balance $141,967  • Percent of Changes 41.6%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –January 4, 2010    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA June 17, 2008     Approval by DSA December 24, 2008    Authorize to Bid (2) October 14, 2008  BOE Approval October 28, 2008    Bid Opening December 16, 2008    Award of Contract (1) December 24, 2008    Notice to Proceed January 6, 2009    Substantial Completion November 25, 2009    Planned Occupancy January 4, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 23   Gunn High School  Aquatic Center  A. PROJECT STATUS    Of the $5,013,750 project budget, 96.9%, or $4,858,324 was  expended.  Approved change orders were $194,554, approximately  49.9% of the $389,887 construction contingency, or 5.0% of the  construction contract. This project will be closed pending final  closeout of the project by DSA.          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.12    D. PROJECT OVERVIEW:  • This project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,013,750  Other Funding $0  Total $5,013,750    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $692,797  Construction & Equipment $4,318,858  Soft Costs Contingency $1,095  Total $5,013,750    Percent of Budget Expended 96.9%    Change Order Contingency  • Starting Contingency Balance $389,887  • Remaining Contingency Balance $195,148  • Percent of Changes 49.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –June 15, 2009    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA December 11, 2007     Approval by DSA April 24, 2008    Authorize to Bid (2) April 8, 2008  BOE Approval April 22, 2008    Bid Opening May 28, 2008    Award of Contract (1) June 4, 2008    Notice to Proceed December 6, 2008    Substantial Completion June 15, 2009    Planned Occupancy June 15, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 24   Middle School Pre‐Design  Jordan, J.L. Stanford and Terman  A. PROJECT STATUS    AEDIS presented recommended concept plans for each campus to the  Board of Education on June 23 for discussion and received approval  on September 8 by the Board of Education to move into schematic  design.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12    D. PROJECT OVERVIEW:  • This project has been completed on schedule and under budget. Board approval received on September  8, 2009. Funding  State Funds $0  Strong Schools Bond Funds $101,000  Other Funding $0  Total $101,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $85,000  Construction & Equipment $0  Soft Costs Contingency $15,000  Total $101,000    Percent of Budget Expended 52.9%    Current Phase: Complete   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 25   Middle Schools Interim Classrooms  Jordan and J.L. Stanford  A. PROJECT STATUS    Contractors completed the installation of these new portables on  August 3, 2009 at Jordan and August 12, 2009 at Stanford.  Of the  $1,047,186 project budget, 48.9%, or $512,074 was expended.  Change Orders were $25,980, which is approximately 49.6% of the  $52,379 construction contingency or 5% of the construction  contracts. These projects will be closed pending final closeout of  the projects by DSA.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:  • This project was completed under budget and on schedule. Funding  State Funds $0  Strong Schools Bond Funds $1,047,186  Other Funding $0  Total $1,047,186    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $353,148  Construction & Equipment $691,490  Soft Costs Contingency $2,548  Total $1,047,186    Percent of Budget Expended 48.9%    Change Order Contingency  • Starting Contingency Balance $52,379  • Remaining Contingency Balance $25,998  • Percent of Changes 49.6%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –August 25, 2009    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA April 14, 2009     Approval by DSA April 22, 2009    Authorize to Bid (2) March 31, 2009  BOE Approval April 14, 2009    Bid Opening May 14, 2009    Award of Contract (1) May 26, 2009    Notice to Proceed June 1, 2009    Substantial Completion August 12, 2009    Planned Occupancy August 25, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 26   Garland Elementary School  Campus Modernization  A. PROJECT STATUS    The Board of Education voted on August 25, 2009 to approve the  amendment to Garland lease to Stratford School.  Therefore, the  district has placed the project on hold.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10    D. PROJECT OVERVIEW:  • This project has been placed on hold. Funding  State Funds $0  Strong Schools Bond Funds $22,178,544  Other Funding $0  Total $22,178,544    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,915,789  Construction & Equipment $17,400,000  Soft Costs Contingency $862,755  Total $22,178,544    Percent of Budget Expended 1.3%  Current Phase: On Hold   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) February 10, 2009  BOE Approval February 24, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 27   Elementary School Teaching Walls  Phase 1 Schools  A. PROJECT STATUS    The district placed this project on hold after review of the  implementation of other classroom improvements, as  recommended by the elementary school principals.  This  project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.9    D. PROJECT OVERVIEW:  • This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary  above).            Funding  State Funds $0  Strong Schools Bond Funds $7,044,987  Other Funding $0  Total $7,044,987    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,341,394  Construction & Equipment $5,498,498  Soft Costs Contingency $205,095  Total $7,044,987    Percent of Budget Expended 1.6%  Current Phase: Project Renamed. See Classroom      Improvements Project    Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates –Subject to Change Page | 28   High School Master Plan  Palo Alto HS and Gunn HS  A. PROJECT STATUS    The Board of Education (BOE) approved the Palo Alto high  school updated master plan project list on October 9, 2010 and  no further action on the high school master plans is planned.                  B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14    D. PROJECT OVERVIEW:  • No further action since Paly’s updated master plan project list was approved by BOE on October 9, 2010.                  Funding  State Funds $0  Strong Schools Bond Funds $290,000  Other Funding $0  Total $290,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $288,565  Construction & Equipment $0  Soft Costs Contingency $435  Total $290,000    Percent of Budget Expended 81.5%  Current Phase: Master Planning    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Initial Master Plan Approval (2) September 8, 2009  BOE Approval September 22, 2009    Paly CEQA Approval (2) February 9, 2010  BOE Approval February 23, 2010    Gunn Master Plan Update (2) March 23, 2010  BOE Approval April 6, 2010    Gunn CEQA Approval (2) April 27, 2010   BOE Approval May 11, 2010     Master Plan Revision Approval (2) September 14, 2010  Paly MP Revision Approval (2) October 9, 2010  Gunn MP Revision Approval (2) October 12, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 29   Hoover Elementary School  Pre‐Design  A. PROJECT STATUS    Staff has put this project on hold until growth projections are reviewed  and a growth plan is established for the elementary schools.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Project is currently on hold.    Funding  State Funds $0  Strong Schools Bond Funds $8,575,389  Other Funding $0  Total $8,575,389    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,643,477  Construction & Equipment $6,831,912  Soft Costs Contingency $100,000  Total $8,575,389    Percent of Budget Expended 0.4%  Current Phase: On Hold   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) November 9, 2010  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A  Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  OHS WEST:260388860.1 A-1 EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. Numbers Added A-2 OHS WEST:260388860.1 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. A-3 OHS WEST:260388860.1 3. GUNN HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Demolish old library building. 3. Replace temporary classrooms with permanent classrooms. 4. Construct additional restrooms. 5. Construct second gymnasium. 6. Construct new soccer field. 7. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 9. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 10. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 11. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 12. Replace swimming pool with new 35-meter pool, pool equipment and support structures, pool decking, bleachers, storage, restrooms, showers, associated equipment. 13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace athletic equipment. 14. Modernize football stadium, including new bathrooms and concession stands. A-4 OHS WEST:260388860.1 4. PALO ALTO HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Construct additional restrooms. 4. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 6. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 7. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 8. Library modernization and building interior improvements, including infrastructure and major building system upgrades. 9. Renovation or replacement of the Tower Building to accommodate administration, classroom and program support space. 10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility improvements; construction of new restrooms; install new roofing; replace doors and windows; replace gymnasium floors and athletic equipment, bleachers and renovation of interior. Renovation or replacement of weight training facility. 11. Construct new theater building. 12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing and storage. 13. Modernize football stadium, including replace bleachers; new bathrooms and concession stands. 14. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. A-5 OHS WEST:260388860.1 5. OTHER DISTRICT-WIDE PROJECTS Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and equipment for all classrooms, athletic facilities and other facilities, as needed. 1. Replace existing or acquire new computers, technology and related equipment on an ongoing basis. 2. Establish a planned maintenance fund to address maintenance work expected to be needed to all District facilities on an ongoing basis (other than as may be necessary for current maintenance, operation or repairs), in order to implement the District’s comprehensive facilities maintenance plan. 3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease- purchase arrangements, or execute purchase option under a lease for any of these authorized facilities. 4. If and as opportunities become available, and to the extent the Board of Education determines that bond funds are available for the purpose, acquisition of land and other interests in real property for future school buildings and other District facilities, and construction of such facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise listed. 5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field equipment and facilities (including nets, basketball standards, goals and goalposts, backstops), field lighting, etc. 6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS 1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead, etc., where necessary. 2. Address unforeseen conditions revealed by construction/modernization (including plumbing or gas line breaks, dry rot, seismic, structural, etc.). 3. Other improvements required to comply with existing building codes, including the Field Act, and access requirements of the Americans with Disabilities Act (ADA). 4. Site preparation/restoration in connection with new construction, renovation or remodeling, or installation or removal of relocatable classrooms, including ingress and egress, demolition of existing structures, removing, replacing, or installing irrigation and drainage, utility lines (such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any necessary easements, licenses, or rights of way to the property. 5. Rental or construction of storage facilities and other space on an interim basis, as needed to accommodate construction materials, equipment, and personnel, and interim classrooms (including relocatables) for students and school functions or other storage for classroom materials displaced during construction. A-6 OHS WEST:260388860.1 7. RENOVATION/MODERNIZATION (DEFINED) For purposes of the Bond Project List, renovation and modernization projects are intended to restore the building systems and infrastructure, weather protections, finishes, and technology, or reallocate and reorganize space, to a condition that will provide a sustainable, functional educational and administrative environment for future years, comparable to new construction. Renovation projects may include, but are not limited to nor necessarily encompass, all of the following, depending upon the age, condition and needs of each particular school facility: 1. upgrade electrical, communication, fire alarm, and similar building systems as well as main power service and distribution, which may include active and passive solar power and heating system acquisition, installation and construction 2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply, meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within buildings and sites and to connect with city supply and drainage systems 3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient heating and air cooling systems (HVAC), including installing energy management systems (EMS); 4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and fixtures, as necessary; 5. Repair, modify and construct structural elements of the existing structure as necessary; 6. Replace or repair aging roofs with similar materials or District standard materials; 7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes, doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces (including white boards, marker boards, tack boards, television mounts, scoreboards, fire extinguishers, kitchen cabinets/equipment, etc.); 8. Upgrade, modify and construct restroom facilities; 9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24 requirements; 10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood siding, paint, etc.); replace doors and windows 11. Modify, expand, separate, convert and construct school support areas; staff work and lunch areas; and educational areas to provide adequate, functional environments; 12. Modify, replace and construct functional components of altered or replaced building components (including rainwater leaders, fascias, mansards, etc.); ™ For any project involving renovation, modernization, remodeling or rehabilitation of a building or the major portion of a building, the District may proceed with new replacement construction instead (including any necessary demolition), if the Board of Education determines that replacement and new construction is more practical than rehabilitation and renovation, considering the building’s age, condition, expected remaining life, comparative cost, and other relevant factors.