Monthly Reports 2010-10 (Oct)
MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
October 2010
Current Strong Schools Bond
Capital Improvement Projects
Prepared by
O’Connor Construction Management, Inc.
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Capital Projects
High School Master Plan page 7
Gunn High School – New Classroom Buildings A & B page 8
Gunn High School – Parking and Drop‐off Sitework Improvement page 9
Gunn High School – New Gymnasium page 10
Gunn High School – Air Conditioning of Existing Buildings page 11
Palo Alto High School – Athletic Stadium Improvements page 12
Palo Alto High School – Multi‐use Field page 13
Palo Alto High School – Classroom Building and Media Arts page 14
Palo Alto High School – Theater and Associated Site Improvements page 15
Jordan Middle School page 16
J.L. Stanford Middle School page 17
Terman Middle School page 18
Fairmeadow Elementary School page 19
Ohlone Elementary School page 20
Hoover Elementary School page 21
Duveneck Elementary School page 22
Elementary Classroom Improvements page 23
Technology page 24
Completed Capital Projects
Gunn High School – Industrial Arts Renovation page 25
Gunn High School – Aquatic Center page 26
Middle School Pre‐Design page 27
Middle School Interim Classrooms page 28
Inactive Capital Projects
Garland Elementary School page 29
Elementary School Teaching Walls – Phase 1 Schools page 30
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
CAPITAL PROJECTS
High School Master Plan
The Board of Education (BOE) approved the Palo Alto high school updated master plan project list on October 9,
2010.
Gunn High School – New Classroom Buildings A & B
DLM submitted construction documents to the Division of State Architect (DSA) on August 4, 2010, which will
remain under review until spring 2011. Constructability reviews & interdisciplinary document coordination (IDC)
backchecks are being completed, while strategies to reduce cost are being evaluated.
Gunn High School – Parking and Drop‐off Sitework Improvement
The new parking and drop‐off layout and the updated construction site plan will be presented at the next facilities
steering committee (FSC) meeting on November 3, 2010. These plans will also be reviewed with the city school
traffic safety committee (CSTSC) on November 18, 2010.
Gunn High School – New Gymnasium
DLM submitted construction documents to DSA on August 4, 2010 and are anticipated to remain under review
until spring 2011. Constructability reviews & IDC backchecks are being completed.
Gunn High School – Air Conditioning of Existing Buildings
DLM met with facilities and maintenance to confirm the design and operation for the new air conditioning units.
Additional site coordination was completed to confirm roofing scope of work and mechanical operation.
Construction documents for buildings L, S, MS, A and IA were submitted to DSA on October 20, 2010. Additional
estimating efforts and constructability review to begin in mid‐November 2010.
Palo Alto High School – Athletics Field Renovation
The BOE approved DLM’s contract amendment to proceed with schematic design on October 26, 2010. A kick‐off
meeting is scheduled for November 3, 2010.
Palo Alto High School – Multi‐use Field
Valley Crest Landscape Development completed the installation of the natural turf and began preparing for the
installation of the artificial turf. Paving for the dugouts and artificial turf installation is anticipated to be complete
in mid‐November 2010. The field is scheduled to be complete and ready for sport play by February 15, 2011.
Palo Alto High School – Classroom Building and Media Arts Building
DLM submitted construction documents to DSA on August 3, 2010, which will remain under review until spring
2011. A budget augmentation was approved on October 26, 2010 to accommodate additional campus
infrastructure work. Constructability reviews & IDC backchecks are being completed.
Palo Alto High School – Performing Arts Center (PAC)
The schematic design estimate provided by DLM was higher than the conceptual design budget. DLM modified
the design to try to realign the budget and design without impacting program goals, but the project is still over
budget. They will continue to work on cost reductions with the subcommittee and FSC in November, 2010 to bring
the project back within budget.
Page | 4
Jordan Middle School
Estimates are being prepared and will be updated based on the 50% CD’s that AEDIS submitted on October 28,
2010. Efforts continue to find creative cost saving opportunities. DSA submission is anticipated for mid‐December
2010.
J.L. Stanford Middle School
Constructability reviews and estimates based on 100% design development documents prepared by AEDIS are
underway.
Terman Middle School
Estimates are being prepared and will be updated based on the 50% CD’s that AEDIS submitted on October 28,
2010. Efforts continue to find creative cost saving opportunities. DSA submission is anticipated for mid‐December
2010.
Fairmeadow Elementary School – New Classroom Building and Modernization
Gelfand Partners continued design efforts through October. Gelfand is expected to submit 100% design
development drawings to the district on November 22, 2010.
Ohlone Elementary School – New Classroom Building and Modernization
Jeff Luchetti Construction continued site clearing, existing utility demolition, and grubbing. Temporary power for
construction was installed and site utility connections are underway. Rough grading and earthwork for the new
building is complete. Under slab plumbing and electrical were also installed in preparation for the structural
footings and slab construction in November, 2010.
Hoover Elementary School – Pre‐Design
Gelfand presented the final conceptual design to the campus steering committee on October 4, 2010. Gelfand also
presented the design to the CSTSC on October 21, 2010, and during a community meeting October 26, 2010. The
project scope of work and budget increase will be presented to the elementary school principals, prior to
presenting the recommended design to the BOE on November 9, 2010.
Duveneck Elementary School – Pre‐Design
Gelfand presented to CSTSC on October 21, 2010 for feedback, and met with the steering committee on October
27, 2010 to finalize the conceptual design, discuss scope of work, budget and next steps. Gelfand will host a
community meeting on November 4, 2010 to present the recommended design for feedback. The steering
committees’ recommended design is planned to be presented to the BOE in December.
Elementary Classroom Improvements
Gelfand prepared cost estimates based on the scope of work determined by the discussions with site staff. Project
scope of work is to include new casework, new indirect lighting, adding operable windows and coverings, vents,
and replacement of ceiling tiles for the least renovated classrooms at Barron Park and El Carmelo. This project is
also funding installation of new interactive whiteboards (IWB) and sound assist systems (SAS). Coulter
Construction has completed the installation of IWB and SAS at Addison, Escondido and Hays Elementary Schools.
Phase 2 and 3 schools IWB and SAS projects went out to bid on October 15, 2010.
Technology
Approximately 80% of the computer purchases planned for the 2010/11 school year have been made. The district
continues to purchase about 90% Apple products. In addition to traditional desktops and laptops, schools have
purchased iPod touches, iPads and netbooks for pilot projects. Most printer purchases are made from the general
fund, however a handful of printers were purchased for schools.
Page | 5
COMPLETED CAPITAL PROJECTS
Gunn High School – Industrial Arts Addition & Renovation
Of the $5,511,500 project budget, 90.5% or $4,997,072 was expended. Approved change orders were $207,033,
approximately 41.6% of the $349,000 construction contingency. This project will be closed pending final closeout
of the project by DSA.
Gunn High School – Aquatic Center
Of the $5,013,750 project budget, 96.9%, or $4,860,823 was expended. Approved change orders were $194,739,
approximately 49.9% of the $389,887 construction contingency. This project will be closed pending final closeout
of the project by DSA.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for
discussion and received approval on September 8 by the Board of Education to move into schematic design. This
project is now closed, and funds will soon be transferred to program contingency.
Middle Schools Interim Housing – Jordan and J.L. Stanford
Contractors completed the installation of these new portables on August 3, 2009 at Jordan and August 12, 2009 at
Stanford. Of the $1,047,186 project budget, 48.9%, or $488,536 was expended. Pending Change Orders were
estimated to be $26,381, which is approximately 49.6% of the $52,379 construction contingency. These projects
will be closed pending final closeout of the projects by DSA.
INACTIVE CAPITAL PROJECTS
Garland Elementary School Renovation
The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.
Therefore, the district has placed the project on hold.
Elementary School Teaching Walls – Phase 1 Schools
The district placed this project on hold after review of the implementation of other classroom improvements, as
recommended by the elementary school principals. This project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
Board Actions in October
October 12, 2010
Action 9 – Updated Master Plan Project List for Palo Alto High School
October 26, 2010
Consent 8 – Approval of Budget Augmentation to Math and History/Social Sciences and Media Arts Project
Consent 9 – Authorization to Issue Addendum No. 9 to Deems Lewis McKinley Architecture (DLM) for Palo Alto
High School Athletic Field Stadium Design Services
Action 15 – Resolution 2010‐11.09: Authorizing the Completion and Submission of an Application for Qualified
School Construction Bond Allocation from the California Department of Education
Action 20 – Contract with O’Connor Construction Management, Inc. (OCMI) for Project/Construction Management
Services for the Fairmeadow Elementary School Project
A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 132,391 117,359 80.9% 15,032 88.65% 12,609Gunn High School 1 - Aquatic Center 5,013,750 4,865,424 4,860,823 96.9% 4,601 99.91% 148,326Gunn High School 2 - I.A Building 5,511,500 5,045,704 4,997,072 90.7% 48,632 99.04% 465,796Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 24,120,000 3,963,032 2,277,881 9.4% 1,685,151 57.48% 20,156,968Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 4,041 0.1% 213,729 1.86% 3,722,230Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 1,593,953 697,057 5.0% 896,896 43.73% 12,236,047Gunn High School 7- A/C 2,600,000 319,199 56,894 0.0% 262,305 17.82% 2,280,801Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.00% 20,945,045Palo Alto High Schools - High School Master Plan 145,000 132,997 119,107 82.1% 13,890 89.56% 12,003Palo Alto High School 1 - Stadium Field 1,358,437 351,184 168,449 12.4% 182,735 47.97% 1,007,253Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,988,139 1,959,061 65.3% 1,029,078 65.56% 13,924Palo Alto high School 3 - New classroom & Media Art Building 34,220,000 4,985,146 2,440,087 7.1% 2,545,059 48.95% 29,234,854Palo Alto High School 4 - New Theater 17,720,000 1,034,610 76,814 0.4% 957,796 7.42% 16,685,390Palo Alto High School - Reserved 42,348,045 0 0 0.0% 0 0.00% 42,348,045Jordan Middle School -Program Management- MS Pre-Design 33,665 18,890 17,826 53.0% 1,064 94.37% 14,775Jordan Middle Schools 1- Interim Classrooms 600,342 171,101 162,245 27.0% 8,856 94.82% 429,241Jordan Middle School 2- Improvements 17,943,194 2,538,284 534,675 3.0% 2,003,609 21.06% 15,404,910J.L.S Middle School - Program Management- MS Pre-Design 33,669 18,799 18,408 54.7% 391 97.92% 14,870J.L.S Middle School 1 - Interim Classrooms 446,844 337,590 326,291 73.0% 11,299 96.65% 109,254 J.L.S Middle School 2- Improvements 17,184,699 2,348,311 438,113 2.5% 1,910,198 18.66% 14,836,388Terman Middle School - Program Management- MS Pre-Design 33,666 18,799 18,423 54.7% 376 98.00% 14,867Terman Middle School 1- Improvements 12,850,071 1,859,787 396,431 3.1% 1,463,356 21.32% 10,990,284PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 55,560 55,560 38.3% 0 100.00% 89,440Addison Elementary School 1-Phase I 5,199,727 0 0 0.0% 0 0.00% 5,199,727Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 7,019,083 49,351 10,176 0.1% 39,175 20.62% 6,969,732Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 780,460 125,557 1.3% 654,903 16.09% 8,547,040Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 69,351 17,373 0.2% 51,978 25.05% 8,506,038Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 10,302,215 1,510,141 12.9% 8,792,074 14.66% 1,365,750Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 840,725 480,504 5.4% 360,221 57.15% 8,046,797Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.00% 8,410,862PAUSD - Program Management 5,042,021 3,807,824 2,638,639 52.3% 1,169,185 69.30% 1,234,197PAUSD - Technology 7,080,712 3,421,567 3,417,805 48.3% 3,762 99.89% 3,659,145PAUSD - Technology -Reserved 6,826,653 0 0 0.0% 0 0.00% 6,826,653PAUSD - Reserved 7,185,694 0 0 0.0% 0 0.00% 7,185,694Bond Issuance Cost 1,840,700 1,840,700 1,840,700 100.0% 0 100.00% 0Total350,684,826 54,395,919 30,069,402 24,326,517 296,288,907Prepared by: Business Services Department based on QSS accounting SystemBudget BalanceCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond10/31/2010Percent of ExpendedContract BalanceExpenditures
Page | 6
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
The Board of Education (BOE) approved the Palo Alto high
school updated master plan project list on October 9, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
• Paly’s updated master plan project list approved by BOE on October 9, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $290,000
Other Funding $0
Total $290,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $286,826
Construction & Equipment $0
Soft Costs Contingency $2,174
Total $290,000
Percent of Budget Expended 81.5%
Current Phase: Master Planning
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010
Paly MP Revision Approval (2) October 9, 2010
Gunn MP Revision Approval (2) October 12, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 7
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
DLM submitted construction documents to the Division of State
Architect (DSA) on August 4, 2010, which will remain under review
until spring 2011. Constructability reviews & interdisciplinary
document coordination (IDC) backchecks are being completed,
while strategies to reduce cost are being evaluated.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule. Budget estimates are currently high and will be evaluated at
bid time.
Funding
State Funds $0
Strong Schools Bond Funds $24,120,000
Other Funding $0
Total $24,120,000
Budget
Salaries and Benefits $11,661
Supplies $0
Contracts & Services $4,376,965
Construction & Equipment $19,567,102
Soft Costs Contingency $164,272
Total $24,120,000
Percent of Budget Expended 9.4%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Approval by DSA March 24, 2011*
Bid Opening May 5, 2011*
Award of Contract (1) May 24, 2011*
Notice to Proceed June 13, 2011*
Substantial Completion July 15, 2013*
Planned Occupancy July 30, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
The new parking and drop‐off layout and the updated
construction site plan will be presented at the next facilities
steering committee (FSC) meeting on November 3, 2010.
These plans will also be reviewed with the city school traffic
safety committee (CSTSC) on November 18, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
• Updated parking and drop‐off layout will be reviewed with FSC on November 3, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $898,978
Construction & Equipment $2,919,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) January 25, 2011*
BOE Approval February 8, 2011*
Schematic Design (2) June 6, 2011*
BOE Approval June 13, 2011*
Submit to DSA April 18, 2012*
Approval by DSA November 20, 2012*
Authorize to Bid (2) November 21, 2012*
BOE Approval December 4, 2012*
Bid Opening March 5, 2013*
Award of Contract (1) April 9, 2013*
Notice to Proceed May 1, 2013*
Substantial Completion November 20, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Gunn High School
New Gymnasium
A. PROJECT STATUS
DLM submitted construction documents to DSA on August 4,
2010 and are anticipated to remain under review until spring
2011. Constructability reviews & IDC backchecks are being
completed.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,830,000
Other Funding $0
Total $13,830,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,651,521
Construction & Equipment $11,094,450
Soft Costs Contingency $84,029
Total $13,830,000
Percent of Budget Expended 5.0%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Approval by DSA March 18, 2011*
Bid Opening April 19, 2011*
Award of Contract (1) April 27, 2011*
Notice to Proceed May 10, 2011*
Substantial Completion July 12, 2012*
Planned Occupancy August 6, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
DLM met with facilities and maintenance to confirm the
design and operation for the new air conditioning units.
Additional site coordination was completed to confirm
roofing scope of work and mechanical operation.
Construction documents for buildings L, S, MS, A and IA
were submitted to DSA on October 20, 2010. Additional
estimating efforts and constructability review to begin in
mid‐November 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $454,610
Construction & Equipment $2,120,580
Soft Costs Contingency $24,810
Total $2,600,000
Percent of Budget Expended 0.0%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA October 20, 2010
Approval by DSA March 15, 2011*
Authorize to Bid (2) February 8, 2011*
BOE Approval February 22, 2011*
Bid Opening April 15, 2011*
Award of Contract (1) April 26, 2011*
Notice to Proceed April 28, 2011*
Substantial Completion August 10, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Athletic Stadium Improvements
A. PROJECT STATUS
The BOE approved DLM’s contract amendment to proceed
with schematic design on October 26, 2010. A kick‐off
meeting is scheduled for November 3, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
• BOE approved DLM addendum on October 26, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $1,358,473
Other Funding $0
Total $1,358,437
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $259,847
Construction & Equipment $1,098,590
Soft Costs Contingency $0
Total $1,358,437
Percent of Budget Expended 12.4%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) January 11, 2011*
BOE Approval January 25, 2011*
Submit to DSA August 25, 2011*
Approval by DSA March 20, 2012*
Authorize to Bid (2) March 13, 2012*
BOE Approval March 27, 2012*
Bid Opening May 30, 2012*
Award of Contract (1) June 11, 2012*
Notice to Proceed June 14, 2012*
Substantial Completion March 22, 2013*
Planned Occupancy August 14, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 12
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
Valley Crest Landscape Development completed the installation of the
natural turf and began preparing for the installation of the artificial turf.
Paving for the dugouts and artificial turf installation is anticipated to be
complete in mid‐November 2010. The field is scheduled to be complete and
ready for sport play by February 15, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
• Project currently within budget. Due to the unavailability of special equipment the project has been
delayed by 2 weeks, however is not anticipated to delay the planned occupancy date.
Funding
State Funds $0
Strong Schools Bond Funds $3,002,063
Other Funding $1,075,991
Total $4,078,054
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $678,295
Construction & Equipment $3,380,258
Soft Costs Contingency $19,501
Total $4,078,054
Percent of Budget Expended 65.3%
Change Order Contingency
• Starting Contingency Balance $269,300
• Remaining Contingency Balance $218,885
• Percent of Changes 0.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 18, 2008
BOE Approval December 09, 2008
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) February 24, 2009
BOE Approval March 17, 2009
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion February 10, 2011*
Planned Occupancy February 1, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
DLM submitted construction documents to DSA on August 3, 2010,
which will remain under review until spring 2011. A budget
augmentation was approved on October 26, 2010 to accommodate
additional campus infrastructure work. Constructability reviews & IDC
backchecks are being completed.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule. A budget augmentation was approved by the BOE on
October 26, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $34,220,000
Other Funding $0
Total $34,220,000
Budget
Salaries and Benefits $14,721
Supplies $0
Contracts & Services $6,238,275
Construction & Equipment $27,741,384
Soft Costs Contingency $225,620
Total $34,220,000
Percent of Budget Expended 7.1%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Approval by DSA March 24, 2011*
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Bid Opening March 15, 2011*
Award of Contract (1) March 23, 2011*
Notice to Proceed April 1, 2011*
Substantial Completion May 13, 2013*
Planned Occupancy July 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Palo Alto High School
Performing Arts Center (PAC)
A. PROJECT STATUS
The schematic design estimate provided by DLM was higher than the
conceptual design budget. DLM modified the design to try to realign the
budget and design without impacting program goals, but the project is still
over budget. They will continue to work on cost reductions with the
subcommittee and FSC in November, 2010 to bring the project back within
budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
• Project is progressing through the schematic design phase.
Funding
State Funds $0
Strong Schools Bond Funds $17,720,000
Other Funding $0
Total $17,720,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,451,077
Construction & Equipment $14,159,700
Soft Costs Contingency $109,223
Total $17,720,000
Percent of Budget Expended 0.4%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) December 7, 2010*
BOE Approval December 14, 2010*
Submit to DSA May 13, 2011*
Approval by DSA December 12, 2011*
Authorize to Bid (2) March 1, 2012*
BOE Approval March 14, 2012*
Bid Opening May 31, 2012*
Award of Contract (1) June 19, 2012*
Notice to Proceed July 16, 2013*
Substantial Completion August 26, 2015*
Planned Occupancy August, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
Jordan Middle School
A. PROJECT STATUS
Estimates are being prepared and will be updated based on the 50%
CD’s that AEDIS submitted on October 28, 2010. Efforts continue to
find creative cost saving opportunities. DSA submission is
anticipated for mid‐December 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule. Estimates will be updated based on 50% CDs.
Funding
State Funds $0
Strong Schools Bond Funds $17,943,191
Other Funding $0
Total $17,943,191
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,501,930
Construction & Equipment $13,949,500
Soft Costs Contingency $491,764
Total $17,943,194
Percent of Budget Expended 3.0%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA December 13, 2010*
Approval by DSA August 17, 2011*
Authorize to Bid (2) August 11, 2011*
BOE Approval August 24, 2011*
Bid Opening September 26, 2011*
Award of Contract (1) October 11, 2011*
Notice to Proceed November 7, 2011*
Substantial Completion May 7, 2013*
Planned Occupancy August 5, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
J.L. Stanford Middle School
A. PROJECT STATUS
Constructability reviews and estimates based on 100%
design development documents prepared by AEDIS are
underway.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
• Project currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,697
Other Funding $0
Total $17,184,697
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,354,000
Construction & Equipment $13,341,000
Soft Costs Contingency $489,699
Total $17,184,699
Percent of Budget Expended 2.5%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28. 2010
Submit to DSA February 16, 2011*
Approval by DSA October 18, 2011*
Authorize to Bid (2) October 25, 2011*
BOE Approval November 8, 2011*
Bid Opening December 13, 2011*
Award of Contract (1) December 27, 2011*
Notice to Proceed December 30, 2011*
Substantial Completion February 12, 2013*
Planned Occupancy August 5, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Terman Middle School
A. PROJECT STATUS
Estimates are being prepared and will be updated based on the 50%
CD’s that AEDIS submitted on October 28, 2010. Efforts continue to
find creative cost saving opportunities. DSA submission is anticipated
for mid‐December 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule. Estimates will be updated based on 50% CDs.
Funding
State Funds $0
Strong Schools Bond Funds $12,850,071
Other Funding $0
Total $12,850,071
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,477,950
Construction & Equipment $10,031,569
Soft Costs Contingency $340,552
Total $12,850,071
Percent of Budget Expended 3.1%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA December 6, 2010*
Approval by DSA August 2, 2011*
Authorize to Bid (2) August 3, 2011*
BOE Approval August 10, 2011*
Bid Opening September 19, 2011*
Award of Contract (1) October 4, 2011*
Notice to Proceed October 5, 2011*
Substantial Completion March 26, 2013*
Planned Occupancy July 3, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Gelfand Partners continued design efforts through October. Gelfand
is expected to submit 100% design development drawings to the
district on November 22, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand continued design efforts and will meet with site committee in November to review design
development progress.
Funding
State Funds $0
Strong Schools Bond Funds $9,327,500
Other Funding $0
Total $9,327,500
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,805,519
Construction & Equipment $7,443,000
Soft Costs Contingency $78,981
Total $9,327,500
Percent of Budget Expended 1.3%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010
BOE Approval September 28, 2010
Submit to DSA February 24, 2011*
Approval by DSA October 20, 2011*
Authorize to Bid (2) November 9, 2011*
BOE Approval November 23, 2012*
Bid Opening January 9, 2012*
Award of Contract (1) February 27, 2012*
Notice to Proceed March 12, 2012*
Substantial Completion May 13, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Jeff Luchetti Construction continued site clearing, existing utility
demolition, and grubbing. Temporary power for construction was
installed and site utility connections are underway. Rough grading
and earthwork for the new building is complete. Under slab
plumbing and electrical were also installed in preparation for the
structural footings and slab construction in November, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,322,677
Construction & Equipment $9,167,001
Soft Costs Contingency $178,287
Total $11,667,965
Percent of Budget Expended 12.9%
Change Order Contingency
• Starting Contingency Balance $748,400
• Remaining Contingency Balance $748,400
• Percent of Changes 0.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010
Award of Contract (1) August 3, 2010
Notice to Proceed August 11, 2010
Substantial Completion December 1, 2011*
Planned Occupancy January 4, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
Gelfand presented the final conceptual design to the campus steering
committee on October 4, 2010. Gelfand also presented the design to the
CSTSC on October 21, 2010, and during a community meeting October 26,
2010. The project scope of work and budget increase will be presented to
the elementary school principals, prior to presenting the recommended
design to the BOE on November 9, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Conceptual design to be presented to the BOE on November 9, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $8,575,389
Other Funding $0
Total $8,575,389
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,643,477
Construction & Equipment $6,831,912
Soft Costs Contingency $100,000
Total $8,575,389
Percent of Budget Expended 0.2%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) November 9, 2010*
BOE Approval December 7, 2010*
Schematic Design (2) February 9, 2011*
BOE Approval February 22, 2011*
Submit to DSA July 19, 2011*
Approval by DSA March 13, 2012*
Authorize to Bid (2) April 24, 2012*
BOE Approval May 6, 2012*
Bid Opening June 14, 2012*
Award of Contract (1) June 30, 2012*
Notice to Proceed July 6, 2012*
Substantial Completion November 4, 2013*
Planned Occupancy January 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Duveneck Elementary School
Pre‐Design
A. PROJECT STATUS
Gelfand presented to CSTSC on October 21, 2010 for feedback, and met
with the steering committee on October 27, 2010 to finalize the
conceptual design, discuss scope of work, budget and next steps.
Gelfand will host a community meeting on November 4, 2010 to present
the recommended design for feedback. The steering committees’
recommended design is planned to be presented to the BOE in
December.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand met with the steering committee on October 27, 2010 and will host a community meeting on
November 4, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $7,019,083
Other Funding $0
Total $7,019,083
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,368,869
Construction & Equipment $5,559,683
Soft Costs Contingency $90,531
Total $7,019,083
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) December 7 2010*
BOE Approval December 14, 2010*
Schematic Design (2) February 22, 2011*
BOE Approval March 8, 2011*
Submit to DSA August 19, 2011*
Approval by DSA April 13, 2012*
Authorize to Bid (2) May 25, 2012*
BOE Approval June 6, 2012*
Bid Opening July 7, 2012*
Award of Contract (1) July 17, 2012*
Notice to Proceed July 24, 2012*
Substantial Completion November 19, 2013*
Planned Occupancy January 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Elementary Classroom Improvements
Phase 1 – Barron Park and El Carmelo
A. PROJECT STATUS
Gelfand prepared cost estimates based on the scope of work
determined by the discussions with site staff. Project scope of work is
to include new casework, new indirect lighting, adding operable
windows and coverings, vents, and replacement of ceiling tiles for the
least renovated classrooms at Barron Park and El Carmelo. This
project is also funding installation of new interactive whiteboards
(IWB) and sound assist systems (SAS). Coulter Construction has
completed the installation of IWB and SAS at Addison, Escondido and
Hays Elementary Schools. Phase 2 and 3 schools IWB and SAS projects
went out to bid on October 15, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• Gelfand will present design for phase 1 schools to BOE on November 9, 2010. Installation of technology
wall underway.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,193,960
Construction & Equipment $7,488,707
Soft Costs Contingency $204,855
Total $8,887,522
Percent of Budget Expended 5.4%
Phase 1 Schools: Barron Park and El Carmelo
Current Phase: Schematic Design
Schedule:
Architect Contract (2) June 8, 2010
BOE Approval June 22, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 9, 2010*
BOE Approval December 7, 2010*
Submit to DSA November 22, 2010*
Approval by DSA May 9, 2011*
Authorize to Bid (2) April 15, 2011*
BOE Approval April 30, 2011*
Bid Opening May 12, 2011*
Award of Contract (1) May 24, 2011*
Notice to Proceed June 1, 2011*
Substantial Completion August 15, 2011*
Planned Occupancy August 17, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Technology Improvements
A. PROJECT STATUS
Approximately 80% of the computer purchases planned for the 2010/11
school year have been made. The district continues to purchase about 90%
Apple products. In addition to traditional desktops and laptops, schools
have purchased iPod touches, iPads and netbooks for pilot projects. Most
printer purchases are made from the general fund, however a handful of
printers were purchased for schools.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• New computers delivered to schools.
Funding
State Funds $0
Strong Schools Bond Funds $7,080,712
Other Funding $0
Total $7,080,712
Budget
Salaries and Benefits $0
Supplies & Computers $6,698,117
Contracts & Services $180,173
Construction & Equipment $202,422
Soft Costs Contingency $0
Total $7,080,712
Percent of Budget Expended 48.3%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
Of the $5,511,500 project budget, 90.5% or $4,997,072 was
expended. Approved change orders were $207,033, approximately
41.6% of the $349,000 construction contingency. This project will be
closed pending final closeout of the project by DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
• The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,511,500
Other Funding $0
Total $5,511,500
Budget
Salaries and Benefits $1,063
Supplies $76,657
Contracts & Services $1,232,253
Construction & Equipment $4,200,322
Soft Costs Contingency $1,205
Total $5,511,500
Percent of Budget Expended 90.5%
Change Order Contingency
• Starting Contingency Balance $349,000
• Remaining Contingency Balance $141,967
• Percent of Changes 41.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Gunn High School
Aquatic Center
A. PROJECT STATUS
Of the $5,013,750 project budget, 96.9%, or $4,860,823 was
expended. Approved change orders were $194,739, approximately
49.9% of the $389,887 construction contingency. This project will be
closed pending final closeout of the project by DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
• This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,013,750
Other Funding $0
Total $5,013,750
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $692,797
Construction & Equipment $4,318,858
Soft Costs Contingency $1,095
Total $5,013,750
Percent of Budget Expended 96.9%
Change Order Contingency
• Starting Contingency Balance $389,887
• Remaining Contingency Balance $195,148
• Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education on June 23 for discussion and received approval
on September 8 by the Board of Education to move into schematic
design.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
• This project has been completed on schedule and under budget. Board approval received on September
8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $101,000
Other Funding $0
Total $101,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $85,000
Construction & Equipment $0
Soft Costs Contingency $15,000
Total $101,000
Percent of Budget Expended 52.9%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
Middle Schools Interim Classrooms
Jordan and J.L. Stanford
A. PROJECT STATUS
Contractors completed the installation of these new portables on
August 3, 2009 at Jordan and August 12, 2009 at Stanford. Of the
$1,047,186 project budget, 48.9%, or $488,536 was expended.
Pending Change Orders were estimated to be $26,381, which is
approximately 49.6% of the $52,379 construction contingency.
These projects will be closed pending final closeout of the projects
by DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project was completed under budget and on schedule.
Funding
State Funds $0
Strong Schools Bond Funds $1,047,186
Other Funding $0
Total $1,047,186
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $346,148
Construction & Equipment $698,490
Soft Costs Contingency $2,548
Total $1,047,186
Percent of Budget Expended 48.9%
Change Order Contingency
• Starting Contingency Balance $52,379
• Remaining Contingency Balance $25,998
• Percent of Changes 49.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –August 25, 2009
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA April 14, 2009
Approval by DSA April 22, 2009
Authorize to Bid (2) March 31, 2009
BOE Approval April 14, 2009
Bid Opening May 14, 2009
Award of Contract (1) May 26, 2009
Notice to Proceed June 1, 2009
Substantial Completion August 12, 2009
Planned Occupancy August 25, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education voted on August 25, 2009 to approve the
amendment to Garland lease to Stratford School. Therefore, the
district has placed the project on hold.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,915,789
Construction & Equipment $17,400,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: On Hold
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 29
Elementary School Teaching Walls
Phase 1 Schools
A. PROJECT STATUS
The district placed this project on hold after review of the
implementation of other classroom improvements, as
recommended by the elementary school principals. This
project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.9
D. PROJECT OVERVIEW:
• This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary
above).
Funding
State Funds $0
Strong Schools Bond Funds $7,044,987
Other Funding $0
Total $7,044,987
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,341,394
Construction & Equipment $5,498,498
Soft Costs Contingency $205,095
Total $7,044,987
Percent of Budget Expended 1.6%
Current Phase: Project Renamed. See Classroom
Improvements Project
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates –Subject to Change
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.