Monthly Reports 2010-08 (Aug)
MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
August 2010
Current Strong Schools Bond
Capital Improvement Projects
Prepared by
O’Connor Construction Management, Inc.
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Attachment 2 – Master Project Schedule
Capital Projects
High School Master Plan page 7
Gunn High School – New Classroom Buildings A & B page 8
Gunn High School – Parking and Drop‐off Sitework Improvement page 9
Gunn High School – New Gymnasium page 10
Gunn High School – Air Conditioning of Existing Buildings page 11
Palo Alto High School – Stadium Field Renovation page 12
Palo Alto High School – Multi‐use Field page 13
Palo Alto High School – Classroom Building and Media Arts page 14
Palo Alto High School – Theater and Associated Site Improvements page 15
Jordan Middle School page 16
J.L. Stanford Middle School page 17
Terman Middle School page 18
Fairmeadow Elementary School page 19
Ohlone Elementary School page 20
Hoover Elementary School page 21
Duveneck Elementary School page 22
Elementary Classroom Improvements page 23
Technology page 24
Completed Capital Projects
Gunn High School – Industrial Arts Renovation page 25
Gunn High School – Aquatic Center page 26
Middle School Pre‐Design page 27
Middle School Interim Classrooms page 28
Inactive Capital Projects
Garland Elementary School page 29
Elementary School Teaching Walls – Phase 1 Schools page 30
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
CAPITAL PROJECTS
High School Master Plan
The facilities steering committees (FSC) will reconvene in September to proceed with coordination for final
approval of the updated master plans.
Gunn High School – New Classroom Buildings A & B
DLM submitted construction documents to the Division of State Architect (DSA) on August 3, 2010, which will
remain under review until spring 2011. Estimates are currently being reconciled, and strategies to reduce cost are
being evaluated in the event the reconciled estimate is over budget. Constructability reviews and document
coordination efforts are underway. The portable relocation is complete and classes began on August 24, 2010.
Gunn High School – Parking and Drop‐off Sitework Improvement
DLM will continue meeting with City School Traffic Safety Committee (CSTSC) in September to review plans for the
new parking / drop‐off layout and site logistics during construction. A meeting was held in August with a City of
Palo Alto traffic engineer to review planning options during construction of the new classroom buildings and the
gymnasium.
Gunn High School – New Gymnasium
DLM submitted construction documents to DSA on August 3, 2010 and are anticipated to remain under review
until spring 2011. Estimates are currently being reconciled and are within the established construction budget.
Constructability reviews and document coordination efforts are underway.
Gunn High School – Air Conditioning of Existing Buildings
DLM continued design efforts on the air conditioning project. A 50% construction documents set was submitted in
August for estimating and constructability review.
Palo Alto High School – Stadium Field Renovation
Planning will resume after the FSC reviews the revised master plan project list and determines the final scope and
budget for this project.
Palo Alto High School – Multi‐use Field
Valley Crest Landscape Development substantially completed the parking lot on August 13, 2010. Construction
fencing was relocated to allow parking lot use by students and staff for the beginning of school year. Work
continues on the fields with installation of fencing poles, lighting bases, drainage piping and dugouts in progress.
The project remains on schedule for completion by January 31, 2011, which includes a 90 day establishment period
for the new turf.
Palo Alto High School – Classroom Building and Media Arts Building
DLM submitted construction documents to DSA on August 3, 2010 which will remain under review until spring
2011. Estimates are currently being reconciled and show a need for a budget augmentation to accommodate
additional campus infrastructure work being done during this phase. Constructability reviews and document
coordination efforts are underway. The portable relocation is complete and classes began on August 24, 2010.
Palo Alto High School – Theater and Associated Site Improvements
DLM and their theater and acoustic consultants met with the theater subcommittee on August 26, 2010 to review
programming and design progress since June. A reservation of funds for the Career Technical Education (CTE)
grant for this project is still anticipated, and will require an accelerated design schedule to achieve DSA approval
within the 12 months of receiving this reservation, which should occur in October.
Page | 4
Jordan Middle School
AEDIS submitted 100% design development drawings on August 11, 2010. Cost estimates are currently being
prepared and drawings are being reviewed for constructability.
J.L. Stanford Middle School
AEDIS proceeded into design development for the classroom buildings. They also continued to refine the
expanded areas of exterior site work and landscape, and will meet with the advisory committee and interested
community members in early September 2010. The additional areas of site and landscaping design for the JLS
project will be presented to the BOE in late September 2010.
Terman Middle School
AEDIS submitted 100% design development drawings on August 11, 2010. Cost estimates are currently being
prepared and the drawings are being reviewed for constructability.
Fairmeadow Elementary School – New Classroom Building and Modernization
Gelfand Partners submitted schematic design drawings on August 20, 2010 for district review and to prepare cost
estimates. Gelfand will meet with the site committee, the PTA and community in early September before
presenting the schematic design plans to the BOE on September 14, 2010.
Ohlone Elementary School – New Classroom Building and Modernization
The modernization and new construction project was awarded and contractor mobilization began in late August.
Site fencing and tree protection was installed, allowing for earth work to begin in September. Coulter Construction
completed the relocation of two existing portables and two new portables for occupancy on August 24, 2010.
Hoover Elementary School – Pre‐Design
Gelfand completed a building and site conditions assessment for architectural, structural and engineering
evaluation and will submit a draft report in September 2010. Gelfand will reconvene campus planning discussions
in September 2010 with the site steering committee.
Duveneck Elementary School – Pre‐Design
Gelfand is scheduled to recommence campus planning efforts in September 2010 with the site steering committee.
Elementary Classroom Improvements
Gelfand will meet with site staff in early September to review project scope and schedule. The classroom
improvements project is planned to include new casework, new indirect lighting, adding operable windows, vents
and shading, and replacement of ceiling tiles. The project is also funding installation of new interactive
whiteboards. Bids were received on August 10, 2010 for installation of these interactive whiteboards at Addison,
Escondido and Hays Elementary. Authorization to award the contract to Coulter Construction for phase one was
approved by the BOE on August 24, 2010. Construction will begin in September.
Technology
Approximately 80% of the computer purchases planned for the 2010/11 school year have been made. Computers
were delivered to classrooms and teachers in August 2010. The district continues to purchase about 90% Apple
products. In addition to traditional desktops and laptops, schools have purchased ipod touches, ipads and
netbooks for pilot projects. Most printer purchases are made from the general fund, however a handful of printers
were purchased for schools.
Page | 5
COMPLETED CAPITAL PROJECTS
Gunn High School – Industrial Arts Addition & Renovation
Of the $5,576,500 project budget, 84.6% or $4,720,037 was expended. Approved change orders were $208,756,
approximately 59.8% of the $349,000 construction contingency. This project will be closed pending final closeout
of the project by DSA.
Gunn High School – Aquatic Center
Of the $5,013,750 project budget, 96.6%, or $4,844,070 was expended. Approved change orders were $194,739,
approximately 49.9% of the $389,887 construction contingency. This project will be closed pending final closeout
of the project by DSA.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for
discussion and received approval on September 8 by the Board of Education to move into schematic design. This
project is now closed, and funds will soon be transferred to program contingency.
Middle Schools Interim Housing – Jordan and J.L. Stanford
Contractors completed the installation of these new portables on August 3, 2009 at Jordan and August 12, 2009 at
Stanford. Of the $1,047,186 project budget, 25%, or $236,696 was expended. Pending Change Orders are
currently estimated to be a credit of ($10,331), which is approximately ‐30% of the $30,698 construction
contingency. These projects will be closed pending final closeout of the projects by DSA.
INACTIVE CAPITAL PROJECTS
Garland Elementary School Renovation
The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.
Therefore, the district has placed the project on hold.
Elementary School Teaching Walls – Phase 1 Schools
The district placed this project on hold after review of the implementation of other classroom improvements, as
recommended by the elementary school principals. This project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
Board Actions in August
August 24, 2010
Consent 6 – Authorization to Enter into a Contract with DSA School Inspections, LLC for Inspector of Record (IOR)
Services on the Classroom Building Construction and Modernization of Existing Classrooms at Ohlone Elementary
School
Action 9 – Appointment of Three Members to the Citizens’ Oversight Committee for the Strong Schools Bond
Action 13 – Appointment of Christy White Accountancy Corporation as Strong Schools Bond Independent Auditor
for 2009 – 10
Action 16 – Authorization to Award a Contract to Coulter Construction to Install Interactive Whiteboards and
Sound Assist Devices
A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 132,391 115,845 79.9% 16,546 87.50% 12,609Gunn High School 1 - Aquatic Center 5,013,750 4,865,424 4,860,823 96.9% 4,601 99.91% 148,326Gunn High School 2 - I.A Building 5,511,500 5,020,638 4,987,204 90.5% 33,434 99.33% 490,862Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 24,120,000 2,843,143 1,916,240 7.9% 926,903 67.40% 21,276,857Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 3,530 0.1% 214,240 1.62% 3,722,230Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 989,849 582,437 4.2% 407,412 58.84% 12,840,151Gunn High School 7- A/C 2,600,000 161,050 1,781 0.0% 159,269 1.11% 2,438,950Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.00% 20,945,045Palo Alto High Schools - High School Master Plan 145,000 132,773 117,739 81.2% 15,034 88.68% 12,227Palo Alto High School 1 - Stadium Field 1,358,437 168,449 164,607 12.1% 3,842 97.72% 1,189,988Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,908,082 1,092,760 36.4% 1,815,322 37.58% 93,981Palo Alto high School 3 - New classroom & Media Art Building 34,220,000 3,340,638 1,684,466 4.9% 1,656,172 50.42% 30,879,362Palo Alto High School 4 - New Theater 17,720,000 1,026,210 48,867 0.3% 977,343 4.76% 16,693,790Palo Alto High School - Reserved 42,348,045 0 0 0.0% 0 0.00% 42,348,045Jordan Middle School -Program Management- MS Pre-Design 33,665 18,890 17,826 53.0% 1,064 94.37% 14,775Jordan Middle Schools 1- Interim Classrooms 600,342 171,101 161,333 26.9% 9,768 94.29% 429,241Jordan Middle School 2- Improvements 17,943,194 1,547,169 303,399 1.7% 1,243,770 19.61% 16,396,025J.L.S Middle School - Program Management- MS Pre-Design 33,669 18,799 18,408 54.7% 391 97.92% 14,870J.L.S Middle School 1 - Interim Classrooms 446,844 337,590 320,819 71.8% 16,771 95.03% 109,254 J.L.S Middle School 2- Improvements 17,184,699 1,395,712 219,057 1.3% 1,176,655 15.70% 15,788,987Terman Middle School - Program Management- MS Pre-Design 33,666 18,799 18,423 54.7% 376 98.00% 14,867Terman Middle School 1- Improvements 12,850,071 1,151,225 214,478 1.7% 936,747 18.63% 11,698,846PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 55,560 55,560 38.3% 0 100.00% 89,440Addison Elementary School 1-Phase I 5,199,727 0 0 0.0% 0 0.00% 5,199,727Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 7,019,083 27,501 8,048 0.1% 19,453 29.26% 6,991,582Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 780,409 118,909 1.3% 661,500 15.24% 8,547,091Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 47,500 4,630 0.1% 42,870 9.75% 8,527,889Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 9,789,040 1,115,808 9.6% 8,673,232 11.40% 1,878,925Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 106,788 106,788 1.2% 0 100.00% 8,780,734Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.00% 8,410,862PAUSD - Program Management 5,299,521 4,105,666 2,752,299 51.9% 1,353,367 67.04% 1,193,855PAUSD - Technology 7,080,712 3,413,664 3,390,705 47.9% 22,959 99.33% 3,667,048PAUSD - Technology -Reserved 6,826,653 0 0 0.0% 0 0.00% 6,826,653PAUSD - Reserved 7,185,694 0 0 0.0% 0 0.00% 7,185,694Total349,101,626 45,078,886 24,688,679 20,390,207 304,022,740Prepared by: Business Services Department based on QSS accounting SystemSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond8/31/2010Percent of ExpendedContract BalanceExpenditures Budget BalanceCommittedBudget
Activity IDPhaseActivity NameOriginalDurationStartFinishDuration %CompleteGunn- IndusGunn- Industrial AGunn- Industrial Arts Renovation45101-Oct-08 A23-Jun-10 A100%Gunn - New Gunn - New ClassrGunn - New Classroom Building109520-Apr-09 A01-Jul-1328.49%Gunn - ParkiGunn - Parking andGunn - Parking and Drop Off119401-Sep-09 A28-Mar-1420.02%Gunn New GGunn New GymnasGunn New Gymnasium94021-Apr-09 A27-Nov-1233.09%Gunn Air CoGunn Air ConditionGunn Air Conditioning Project52801-Jan-10 A23-Sep-1143.37%Paly - StadiuPaly - Stadium FielPaly - Stadium Field Renovation Project83817-Aug-09 A13-Nov-1228.76%Paly - Multi UPaly - Multi Use FiePaly - Multi Use Field Improvements58703-Nov-08 A01-Feb-1173.59%Paly - New CPaly - New ClassroPaly - New Classroom Building & Media Arts113820-Apr-09 A29-Aug-1327.42%Paly - New TPaly - New TheaterPaly - New Theater and Sitework157609-Sep-09 A14-Sep-1515.23%Jordan New Jordan New ClassrJordan New Classroom Wing & Modernization124103-Nov-08 A05-Aug-1336.58%Stanford NewStanford New ClasStanford New Classroom Wing123603-Nov-08 A05-Aug-1334.55%Terman AdmTerman Admin WinTerman Admin Wing Addition & Modernization121303-Nov-08 A03-Jul-1337.1%Garland SchGarland School MoGarland School Modernization48003-Nov-08 A24-Jun-09 A100%FairmeadowFairmeadow ElemeFairmeadow Elementary School119414-Dec-09 A01-Aug-1334.34%Duveneck ElDuveneck ElementDuveneck Elementary School85313-May-10 A19-Aug-136.57%Hoover ElemHoover ElementaryHoover Elementary School85412-May-10 A19-Aug-136.67%Ohlone New Ohlone New ClassOhlone New Classroom Wing97703-Nov-08 A01-Aug-1246.37%Teaching WaTeaching Walls CaTeaching Walls Casework17206-Apr-09 A28-Sep-09 A100%NDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASON2009201020112012201320142015PALO ALTO UNIFIED SCHOOL DISTRICTSTRONG SCHOOLS BOND PROGRAMMASTER SCHEDULE SUMMARY DesignPlanningBid and AwardConstructionDSACloseoutMilestonePage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc.
Page | 6
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
The facilities steering committees (FSC) will reconvene in
September to proceed with coordination for final approval of
the updated master plans.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
• Landscape master plans for each campus to the BOE in June as information. FSC for Gunn and Paly to
meet in September.
Funding
State Funds $0
Strong Schools Bond Funds $290,000
Other Funding $0
Total $290,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $279,521
Construction & Equipment $0
Soft Costs Contingency $9,479
Total $290,000
Percent of Budget Expended 80.6%
Current Phase: Master Planning
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) October 12, 2010*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 7
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
DLM submitted construction documents to the Division of State
Architect (DSA) on August 3, 2010 and are anticipated to remain
under review until spring 2011. Estimates are currently being
reconciled. Strategies to reduce cost are being evaluated, in the
event the reconciled estimate is over budget. Constructability
reviews and document coordination efforts are underway. The 26
relocated portables were completed by August 24, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $24,120,000
Other Funding $0
Total $24,120,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $4,315,728
Construction & Equipment $19,590,000
Soft Costs Contingency $164,272
Total $24,120,000
Percent of Budget Expended 7.9%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Approval by DSA March 24, 2011*
Bid Opening May 5, 2011*
Award of Contract (1) May 25, 2011*
Notice to Proceed June 13, 2011*
Substantial Completion July 15, 2013*
Planned Occupancy July 30, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
DLM will continue meetings with City School Traffic Safety
Committee (CSTSC) in September to review working plans for
the new parking / drop‐off layout and site logistics during
construction. A meeting was held in August with a City of
Palo Alto traffic engineer to review planning options during
construction.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
• Project commenced over summer break and will be discussed with FSC in the fall.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $883,978
Construction & Equipment $2,934,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) January 25, 2011*
BOE Approval February 8, 2011*
Schematic Design (2) August 9, 2011*
BOE Approval August 23, 2011*
Submit to DSA July 26, 2012*
Approval by DSA April 3, 2013*
Authorize to Bid (2) February 12, 2013*
BOE Approval February 26, 2013*
Bid Opening June 6, 2013*
Award of Contract (1) June 18, 2013*
Notice to Proceed July 3, 2013*
Substantial Completion February 7, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Gunn High School
New Gymnasium
A. PROJECT STATUS
DLM submitted construction documents to DSA on August 3,
2010 and are anticipated to remain under review until spring
2011. Estimates are currently being reconciled and are within
the established budget. Constructability reviews and document
coordination efforts are underway.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,830,000
Other Funding $0
Total $13,830,000
Budget
Salaries and Benefits $0
Supplies $40,000
Contracts & Services $2,596,521
Construction & Equipment $11,109,450
Soft Costs Contingency $84,029
Total $13,830,000
Percent of Budget Expended 4.2%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Approval by DSA March 24, 2011*
Bid Opening May 5, 2011*
Award of Contract (1) May 24, 2011*
Notice to Proceed June 13, 2011*
Substantial Completion July 12, 2012*
Planned Occupancy August 6, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
DLM continued design efforts on the air conditioning
project. A 50% CD was submitted in August for estimating
and constructability review.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $447,110
Construction & Equipment $2,128,080
Soft Costs Contingency $24,810
Total $2,600,000
Percent of Budget Expended 0.0%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA September 28, 2010*
Approval by DSA March 23, 2011*
Authorize to Bid (2) February 8, 2011*
BOE Approval February 22, 2011*
Bid Opening March 29, 2011*
Award of Contract (1) April 5, 2011*
Notice to Proceed April 13, 2011*
Substantial Completion August 12, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Football Stadium Renovation
A. PROJECT STATUS
Planning will resume after the FSC reviews the
revised master plan project list and determines the
scope of this project.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
• Conceptual design was approved BOE on June 22, 2010. However, the project budget approval is being
deferred until a new master plan is approved for the campus.
Funding
State Funds $0
Strong Schools Bond Funds $1,358,473
Other Funding $0
Total $1,358,437
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $127,622
Construction & Equipment $1,230,815
Soft Costs Contingency $0
Total $1,358,437
Percent of Budget Expended 12.1%
Current Phase: Programming
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) December 7, 2010*
BOE Approval December 14, 2010*
Submit to DSA June 9, 2011*
Approval by DSA January 11, 2012*
Authorize to Bid (2) December 29, 2012*
BOE Approval January 19, 2012*
Bid Opening March 20, 2012*
Award of Contract (1) March 29, 2012*
Notice to Proceed April 5, 2012*
Substantial Completion November 27, 2012*
Planned Occupancy December 31, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 12
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
Valley Crest Landscape Development substantially completed the
parking lot on August 13, 2010. Construction fencing was relocated to
allow parking lot use by students and staff for the beginning of school
year. Work continues on the fields with installation of fencing poles,
lighting bases, drainage piping and dugouts. The project remains on
schedule for completion by January 31, 2011, which includes a 90 day
grow in period for the new turf.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
• Project currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $3,002,063
Other Funding $1,075,991
Total $4,078,054
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $656,970
Construction & Equipment $3,312,683
Soft Costs Contingency $108,401
Total $4,078,054
Percent of Budget Expended 36.4%
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 18, 2008
BOE Approval December 09, 2008
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) February 24, 2009
BOE Approval March 17, 2009
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion January 31, 2011*
Planned Occupancy February 1, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
DLM submitted construction documents to DSA on August 3, 2010
and are anticipated to remain under review until spring 2011.
Estimates are currently being reconciled and are aligned with
previous estimates that indicated a need for a budget augmentation
to accommodate additional infrastructure work that benefits the
entire campus. Constructability reviews and document coordination
efforts are underway. The 16 relocated portables were completed
for occupation on August 24, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $34,220,000
Other Funding $0
Total $34,220,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $6,067,996
Construction & Equipment $27,876,384
Soft Costs Contingency $225,620
Total $34,220,000
Percent of Budget Expended 4.9%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Approval by DSA March 24, 2011*
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Bid Opening March 16, 2011*
Award of Contract (1) April 4, 2011*
Notice to Proceed April 13, 2011*
Substantial Completion March 1, 2013*
Planned Occupancy July 10, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Palo Alto High School
Theater and Associated Site Improvements
A. PROJECT STATUS
DLM and theater specialty consultants met with the theater
subcommittee on August 26, 2010 to discuss programming and
design progress. The subcommittee was notified of the Career
Technical Education (CTE) grant status and requirement for an
accelerated deign schedule to meet these grant needs.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
• Project is currently under schematic design phase.
Funding
State Funds $0
Strong Schools Bond Funds $17,720,000
Other Funding $0
Total $17,720,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $3,276,077
Construction & Equipment $14,284,700
Soft Costs Contingency $109,223
Total $17,720,000
Percent of Budget Expended 0.3%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) October 19, 2010*
BOE Approval November 2, 2010*
Submit to DSA March 15, 2011*
Approval by DSA September 6, 2011*
Authorize to Bid (2) February 7, 2012*
BOE Approval February 21, 2012*
Bid Opening May 9, 2012*
Award of Contract (1) May 28, 2012*
Notice to Proceed February 11, 2013*
Substantial Completion July 13, 2015*
Planned Occupancy August, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
Jordan Middle School
A. PROJECT STATUS
AEDIS submitted 100% design development drawings on
August 11, 2010. Cost estimates are currently being prepared
and drawings are being reviewed for constructability.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $17,943,191
Other Funding $0
Total $17,943,191
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,432,480
Construction & Equipment $14,014,500
Soft Costs Contingency $496,214
Total $17,943,194
Percent of Budget Expended 1.7%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA December 13, 2010*
Approval by DSA August 17, 2011*
Authorize to Bid (2) August 11, 2011*
BOE Approval August 24, 2011*
Bid Opening September 26, 2011*
Award of Contract (1) October 11, 2011*
Notice to Proceed November 7, 2011*
Substantial Completion May 7, 2013*
Planned Occupancy August 5, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
J.L. Stanford Middle School
A. PROJECT STATUS
AEDIS proceeded into design development for the
classroom buildings. They also continued to refine the
expanded areas of exterior site work and landscape,
and plan to meet with the advisory committee and
interested community members in early September
2010. The exterior design and landscaping portion of
the JLS project will be presented to the BOE in
September 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
• Exterior site schematic design to be discussed at September 28, 2010 BOE meeting.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,697
Other Funding $0
Total $17,184,697
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,281,600
Construction & Equipment $13,406,000
Soft Costs Contingency $497,099
Total $17,184,699
Percent of Budget Expended 1.3%
Current Phase: Schematic Design/Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) June 1, 2010*
BOE Approval June 22, 2010*
Submit to DSA January 20, 2011*
Approval by DSA October 8, 2011*
Authorize to Bid (2) September 2, 2011*
BOE Approval September 15, 2011*
Bid Opening November 4, 2011*
Award of Contract (1) November 21, 2011*
Notice to Proceed December 15, 2011*
Substantial Completion April 6, 2013*
Planned Occupancy August 15, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Terman Middle School
A. PROJECT STATUS
AEDIS submitted 100% design development drawings on August
11, 2010. Cost estimates are currently being prepared and the
drawings are being reviewed for constructability.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $12,850,071
Other Funding $0
Total $12,850,071
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,411,150
Construction & Equipment $10,096,569
Soft Costs Contingency $342,352
Total $12,850,071
Percent of Budget Expended 1.7%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA December 6, 2010*
Approval by DSA August 2, 2011*
Authorize to Bid (2) August 3, 2011*
BOE Approval August 10, 2011*
Bid Opening September 19, 2011*
Award of Contract (1) October 4, 2011*
Notice to Proceed October 5, 2011*
Substantial Completion March 26, 2013*
Planned Occupancy July 3, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Gelfand Partners submitted schematic design drawings on August 20,
2010 for district review and estimating efforts. Gelfand will meet with
the site committee, the PTA and community in early September
before presenting the schematic design plans to the BOE on
September 14, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Anticipate schematic design to be presented to BOE at September 14, 2010 meeting.
Funding
State Funds $0
Strong Schools Bond Funds $9,327,500
Other Funding $0
Total $9,327,500
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,770,519
Construction & Equipment $7,478,000
Soft Costs Contingency $78,981
Total $9,327,500
Percent of Budget Expended 1.3%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010*
BOE Approval September 28, 2010*
Submit to DSA February 23, 2011*
Approval by DSA October 19, 2011*
Authorize to Bid (2) November 9, 2011*
BOE Approval November 23, 2012*
Bid Opening January 13, 2012*
Award of Contract (1) February 27, 2012*
Notice to Proceed March 12, 2012*
Substantial Completion July 8, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
The modernization and new construction project was awarded
and the contractor started to mobilize in late August. Site fencing
and tree protection was installed, allowing for earth work to begin
in September. Coulter Construction completed the relocation of
two existing portables and two new portables for occupancy on
August 24, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• BOE to authorize the award of contract on August 3, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,221,535
Construction & Equipment $9,181,991
Soft Costs Contingency $264,439
Total $11,667,965
Percent of Budget Expended 9.6%
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010
Award of Contract (1) August 3, 2010
Notice to Proceed August 11, 2010
Substantial Completion December 1, 2011*
Planned Occupancy January 4, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
Gelfand completed a building and site conditions
assessment for architectural, structural and engineering
evaluation and will submit a draft report in September 2010.
Gelfand will reconvene campus planning discussions in
September 2010 with the site steering committee.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand to meet with the site steering committee in September.
Funding
State Funds $0
Strong Schools Bond Funds $8,575,389
Other Funding $0
Total $8,575,389
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,608,477
Construction & Equipment $6,866,912
Soft Costs Contingency $100,000
Total $8,575,389
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) October 26, 2010*
BOE Approval November 9, 2010*
Schematic Design (2) January 11, 2011*
BOE Approval January 25, 2011*
Submit to DSA June 2, 2011*
Approval by DSA January 26, 2012*
Authorize to Bid (2) March 8, 2012*
BOE Approval March 24, 2012*
Bid Opening April 30, 2012*
Award of Contract (1) May 15, 2012*
Notice to Proceed May 21, 2012*
Substantial Completion September 17, 2013*
Planned Occupancy December 23, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Duveneck Elementary School
Pre‐Design
A. PROJECT STATUS
Gelfand is scheduled to recommence campus planning efforts in
September 2010 with the site steering committee.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand to meet with the site steering committee in September.
Funding
State Funds $0
Strong Schools Bond Funds $7,019,083
Other Funding $0
Total $7,019,083
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,332,019
Construction & Equipment $5,594,683
Soft Costs Contingency $92,381
Total $7,019,083
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) September 28, 2010*
BOE Approval October 12, 2010*
Schematic Design (2) December 9, 2010*
BOE Approval December 14, 2010*
Submit to DSA June 2, 2011*
Approval by DSA January 26, 2012*
Authorize to Bid (2) March 8, 2012*
BOE Approval March 24, 2012*
Bid Opening April 30, 2012*
Award of Contract (1) May 15, 2012*
Notice to Proceed May 21, 2012*
Substantial Completion September 17, 2013*
Planned Occupancy December 23, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Elementary Classroom Improvements
Phase 1 – Barron Park, Duveneck, El Carmelo, Hoover
A. PROJECT STATUS
Gelfand will meet with site staff in early September to review project scope and schedule. The classroom
improvements project is planned to include new lighting, windows and shades, ventilation improvements and
ceiling tiles. Also part of the project is the implementation of a technology wall. Bids were received on August
10, 2010 for installation of technology walls at Addison, Escondido and Hays Elementary. Authorization to
award the contract to Coulter Construction for phase one technology wall installation was approved by the
BOE on August 24, 2010. Construction will begin in September.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• Gelfand commenced design for phase 1 schools. Installation of technology wall awarded to Coulter
Construction on August 24, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,193,721
Construction & Equipment $7,488,706
Soft Costs Contingency $205,095
Total $8,887,522
Percent of Budget Expended 1.2%
Phase 1 Schools:Barron Park, Duveneck, El Carmelo, Hoover
Current Phase: Planning
Schedule:
Architect Contract (2) June 8, 2010
BOE Approval June 22, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) October 26, 2010*
BOE Approval November 9, 2010*
Submit to DSA November 10, 2010*
Approval by DSA April 1, 2011*
Authorize to Bid (2) April 15, 2011*
BOE Approval April 30, 2011*
Bid Opening May 23, 2011*
Award of Contract (1) May 31, 2011*
Notice to Proceed June 1, 2011*
Substantial Completion August 15, 2011*
Planned Occupancy August 20, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Technology Improvements
A. PROJECT STATUS
Approximately 80% of the computer purchases planned for the 2010/11
school year has been made. Computers were delivered to classrooms and
teachers in August 2010. The district continues to purchase about 90%
Apple products. In addition to traditional desktops and laptops, schools
have purchased ipod touches, ipads and netbooks for pilot projects. Most
printer purchases are made from the general fund, however a handful of printers
were purchased for schools.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• New computers delivered to schools before start of school year.
Funding
State Funds $0
Strong Schools Bond Funds $5,995,689
Other Funding $0
Total $5,995,689
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $177,798
Construction & Equipment $5,817,891
Soft Costs Contingency $0
Total $5,995,689
Percent of Budget Expended 47.9%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
Of the $5,576,500 project budget, 84.6% or $4,720,037 was
expended. Approved change orders were $208,756, which is
approximately 59.8% of the $349,000 construction contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
• The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,576,500
Other Funding $0
Total $5,576,500
Budget
Salaries and Benefits $0
Supplies $10,358
Contracts & Services $1,216,066
Construction & Equipment $4,300,350
Soft Costs Contingency $49,726
Total $5,576,500
Percent of Budget Expended 90.5%
Change Order Contingency
• Starting Contingency Balance $349,000
• Remaining Contingency Balance $140,244
• Percent of Changes 59.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Gunn High School
Aquatic Center
A. PROJECT STATUS
Of the $5,013,750 project budget, 96.6%, or $4,844,070 was
expended. Approved change orders were $194,739, which is
approximately 49.9% of the $389,887 construction contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
• This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,013,750
Other Funding $0
Total $5,013,750
Budget
Salaries and Benefits $0
Supplies $7,684
Contracts & Services $679,284
Construction & Equipment $4,323,742
Soft Costs Contingency $3,040
Total $5,013,750
Percent of Budget Expended 96.9%
Change Order Contingency
• Starting Contingency Balance $389,887
• Remaining Contingency Balance $195,148
• Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education on June 23 for discussion and received approval
on September 8 by the Board of Education to move into schematic
design.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
• This project has been completed on schedule and under budget. Board approval received on September
8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $101,000
Other Funding $0
Total $101,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $85,000
Construction & Equipment $0
Soft Costs Contingency $15,000
Total $101,000
Percent of Budget Expended 52.9%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
Middle Schools Interim Classrooms
Jordan and J.L. Stanford
A. PROJECT STATUS
Contracts were awarded to Coulter Construction for Jordan Middle
School and Mark Electric for Stanford Middle School following
Board of Education approval on May 26, 2009. Both contractors
started work on June 15, 2009 and were completed on August 3,
2009 at Jordan and August 12, 2009 at Stanford. Of the $1,047,186
project budget, 25%, or $236,696 has been expended. Pending
Change Orders are currently estimated to be a deduct of ($10,331),
which is approximately 0% of the $30,698 construction
contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project was completed under budget and on schedule.
Funding
State Funds $0
Strong Schools Bond Funds $1,047,186
Other Funding $0
Total $1,047,186
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $308,648
Construction & Equipment $707,840
Soft Costs Contingency $30,698
Total $1,047,186
Percent of Budget Expended 48.9%
Change Order Contingency
• Starting Contingency Balance $30,698
• Remaining Contingency Balance $30,698
• Percent of Changes 0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –August 25, 2009
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA April 14, 2009
Approval by DSA April 22, 2009
Authorize to Bid (2) March 31, 2009
BOE Approval April 14, 2009
Bid Opening May 14, 2009
Award of Contract (1) May 26, 2009
Notice to Proceed June 1, 2009
Substantial Completion August 12, 2009
Planned Occupancy August 25, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education voted on August 25, 2009 to approve the
amendment to Garland lease to Stratford School. Therefore, the
district has placed the project on hold.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,830,789
Construction & Equipment $17,485,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: On Hold
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 29
Elementary School Teaching Walls
Phase 1 Schools
A. PROJECT STATUS
The district placed this project on hold after review of the
implementation of other classroom improvements, as
recommended by the elementary school principals. This
project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.9
D. PROJECT OVERVIEW:
• This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary
above).
Funding
State Funds $0
Strong Schools Bond Funds $7,044,987
Other Funding $0
Total $7,044,987
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,341,394
Construction & Equipment $5,498,498
Soft Costs Contingency $205,095
Total $7,044,987
Percent of Budget Expended 1.6%
Current Phase: Project Renamed. See Classroom
Improvements Project
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates –Subject to Change
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.