2009 - 2010 Annual ReportsMEASURE A -
STRONG SCHOOLS BOND
PALO ALTO
UNIFIED SCHOOL DISTRICT
.................................................................................
CITIZENS' OVERSIGHT COMMITTEE
2009 - 2010 ANNUAL REPORT
.................. 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0000....... 0.
Letter from Committee Chair
.................................................
November 9, 2010
To: The Board of Education and the Citizens of the Palo Alto Unified School District
The Citizens' Oversight Committee is pleased to forward its second Annual Report, covering the 2009-10 fiscal year, on the $378
Trillion general obligation Strong Schools Bond.
The purpose of the Citizens' Oversight Committee (COC) is to inform the public concerning the expenditure of bond revenues. As
required by State law, the COC provides oversight and advises the public whether the District is spending the Strong Schools Bond
funds for school capital improvements within the scope of projects outlined in the Strong Schools Bond Project List. In fulfilling its
duties, the COC reviews, among other things, the District's annual independent performance and financial audits of Strong Schools
Bond activity.
In this second year, the Committee again gave special attention to the mechanisms and systems established by the District to over-
see its contractors and monitor the effective planning and staging of the projects on the Strong Schools Bond list. At each of our
meetings, we met with appropriate District officials and with senior representatives of the project management and construction
management fimrs employed by the District to oversee planning and operations.
As of June 30, 2010, projects budgeted at over $260 Trillion were specifically planned by the District. The remaining Strong
Schools Bond projects will be prioritized and scheduled by the Board of Education. Afew highlights for the 2009-2010 year in-
duded the completion of renovations to the Gunn High School Industrial Arts Building; groundbreaking for the Palo Alto High
School Multi -Use Feld improvements; and the award of Qualified School Construction Bond tax credits under the Federal eoo-
noetic stimulus plan, which will save Palo Alto taxpayers the interest payments on up to $25 million in bonds issued under this pro-
gram Please see pages 5 and 6 for descriptions of additional projects that are underway.
The Committee reviewed the Financial Audit and the Performance Audit issued by the independent auditing firm of Christy White,
Professional Accountancy Corporation. The firm conducted its audits in compliance with Generally Accepted Government Auditing
Standards. Under these standards, the audit firm independently determined which tests to use in arriving at its opinions. The audits
found that the program was materially in compliance with the terms of Proposition 39 and Strong Sd-iool Bond.
In sum, the Committee wishes to report that, to the best of its knowledge, the Palo Alto Unified School District is in full oorroianoe
with its responsibilities as described in Article XII IA, Section 1(b)(3) of the California State Constitution, the section that governs the
teras and conditions of Proposition 39 bonds like the District's Strong Schools Bond.
The composition of the Committee will be changing for the 2010-2011 year as the members' two-year terms have ended. Jim
McFall, Caroline Maser and Steve Shevick chose not to seek a second term so that the Committee membership could be stag-
gered for continuity. I wish to thank them for their service to the community. They will be replaced by Todd Collins, Catharine Gar-
ber, and Mary Marth. Existing Committee members, Ray Bacchetti, Gary Hombeek, Deepak Kanungo and myself have been ap-
pointed by the District to serve another two-year term
The work of the Citizens' Oversight Committee is conducted under the Brown Act. Al meetings of the Committee are open to the
public; observers are welcome. The 2009-2010 audits and further information on expenditures, minutes of the Committee's meet-
ings, and detailed monthly progress reports can be found on the District's Wpb site, http://pausd.or4co munity/
StrongSchoolsBond/.
Sincerely yours,
Committee Members as of June 30, 2010
_.................................................................
..................
C Ray Bacchetti, Member, Senior Citizen and Taxpayer Organizations
Scott Darting, Member At Large
Scott Darling Gary Hombeek, Parent, PTA Member
Deepak Kanungo, Parent
Caroline Maser, Parent
Jim McFall, Business Organization Member
Steve Shevick, Parent
Board of Education, 2009-2010
...............................................................................
Barbara l4ausrier, President
Melissa Baten Caswell, Uce President
Barb Kitchell
Dana Tom
Camille Townsend
Senior District Officials
...............................................................................
Kevin Skelly, Superintendent of Sdicols
Bob Golton, Co -Chief Business Official & Bond Program Mgr
Cathy Mak, Co -Chief Business Official
About the District
The Distdct was founded on March 20, 1893. The first school
opened in September 1893, Wth two teachers and 70 pupils
crowded into a temporary two -room schoolhouse. The District grew
until 1967, when enrollment peaked at 15,575 students. At that
About Strong Schools Bond
...............................................................................
Strong Schools Bond is a $378 million bond measure passed on June
3, 2008, that authorizes funding to provide safe and modem schools;
accommodate enrollment growth; upgrade aging dassrooms, librar-
ies, computer and science labs; improve athletic facilities; repair or
replace roofs, plumbing, heating, ventilation and electrical systems;
improve fire alarms and school security; meet current earthquake
standards; provide current technology; replace old portables with
pem-anent classrooms; and purchase land within the Palo Alto Uni-
fied School District.
To ensure the Strong Schools Bond funds are spent in a way that
best meets the needs of the District, the individual sites, and the corrr
munity at large, a variety of strategies are being used. These include
Site Steering Committees comprised of principals, teachers, parents
and community members that make recommendations on site specific
issues. Community meetings are held during the planning phases of
the major projects to ensure that the concerns of neighbors, parents
and the community are addressed. Finally, the Board of Education
approves all Bond expenditures with an eye toward the needs of the
District today and well into the future.
To ensure the Strong Schools Bond program is being managed effec-
tively, the Board of Education approved O'Connor Construction Marr
agement, Inc. to provide program management services for this work.
Tom Hodges, a principal Wth O'Connor having experience Wth the
District since 2002, serves as the Program Director for Strong
Schools Bond and provides program administration duties and man-
ages early project development. The Board of Education also ap-
proved G (bane Building Company to provide design administration
and construction management services for the program Anhold
Teten, Gilbands Senior Construction Manager, and his staff work
closely with O'Connor to provide seamless management and coordi-
nation of all Strong Schools Bond projects.
In 2009-10, the State accepted applications from school districts to
issue Qualified School Construction Bonds (QSCBs) a part of the
federal stimulus program for sdhods. The District was one of 45
selected by lottery, out of 231 that applied, to be authorized to issue
bonds under this program and issued the maximum $25 million in
QSCB bonds. This does not provide additional construction funds to
the bond program, but does provide maximum savings to the taxpay-
ers who pay bade not only bond principal but also bond interest cost.
The QSCBs interest is almost 100% subsidized in this federal govern-
ment program, making these bonds essentially 0% loans. The total
estirruted savings in interest payments over the life of the bonds to
the PAUSD property owners is estimated at $27 million.
time the District operated 22 Grade K-6 elementary schools, three Grade 7-
9 junior high schools and three Grade 10-12 high schools. Enrollment be-
gan to decline in the 1970s and continued to dedine through the 1980s. The
bottom of the decline was reached in 1989 when total enrollment stood at
7,452. The configuration of schools then showed eleven elementary
schools, one middle school and two high schools. Jordan Middle School
since reopened as enrollment increased, and in September 1998 a twelfth
elementary school, Barron Park, was opened. In August 2001, Temhan
Middle School reopened as a third middle sdhod.
Dudng the 2000's the number of elementary students migrating into the
District has been much larger than in past decades. Total District enroll-
ment stood at 11,680 for the 2009-2010 school year. The District utilizes the
services of Lapkoff & Gobalet Demographic Research, Inc. for annual err
rolIment forecasts. The most recent report was issued in February 2010 and
projected continued increases in enrollment. The mediumrrange scenario in
the latest forecast anticipates growth of 10% over the next five years to a
total enrollment of 12,823 in 2014.
Committee Meetings
..........................................................................................
The Otizens' Oversight Committee meets on a quarterly basis. All meetings
are open to the public. Scheduled upcoming meetings are: February 2„
2011; April 20, 2011; and July 20, 2011.
Proceedings of the meetings held included:
January 20,2010: Election of ChairNce Chair, Mbnthly Reports, Member
Attendance at Board of Education Meeting, Performance Audit Finding Imr
plementation, Quality School Construction Bonds Inforhation Discussion,
and Site Visit- -Gunn Industrial Arts Building.
April 21, 2010: Monthly Reports, Program Status Updates, Change Order
Status, COC Members Service, COC Membership Terms, Update on Quality
School Construction Bonds, PerformanceAudlt/Financial Audit Timeline.
July 14, 2010: Monthly Reports, Change Order Status, COC Membership,
Performance Audit and Financial Audit Planning, COCAnnual Report Plan
ning Discussion, Election Dates for Future Chair Terms, Interim Chair,
Hedging for Future Price Increase, Site Visit --Palo Alto High School Multi -
Use Field.
October 20, 2010: Monthly Reports, Annual Report Review, Performance
Audit and Financial Audit Review, Board Presentation Preparation, Site
Visit --Palo Alto High School Multi -Use Field.
Independent Audit Reports
In compliance with Proposition 39, performance and financial audits were
conducted for the year ended June 30, 2010. These audits were conducted
in accordance with Generally Accepted Governmental Auditing Standards by
the firm of Christy Mite A000untancy Corporation.
The audit firm rendered an opinion that the District's financial statements
present fairly, in all material respects, the financial position of the Strong
Schools Bond Building Fund as of June 30, 2010. The audit further found
that the expenditures tested were in compliance with the terms of the ballot
measure and applicable State laws and regulations. The auditors reported:
"We found all expenditures tested to be in corroianoe with the terms of the
Strong Schools Bond ballot measure and applicable State laws and regula-
tions, without exception. Also, our analysis indicated that the Distdct is re-
ceiving program management services that are reasonable as compared to
other school distdcts, with regard to billing rates, hours charged, and the
ratio of consultants to District employees."
The auditors made one finding regarding financial reporting for the program
and this vall be implemented by the tastrict. To view the complete audit
report, please visit http-.Hpausd.org/community/StrongSd-odsBond/annual/
shtml
Palo Alto Unified School District
Strong Schools Bond Expenditures as of June 30, 2010
Expended Status Overall Allocation Budget Status
1
Gunn High School - High School Master Plan
High Schools
450/6
132,391
Pllocated to Projects
2
Gunn High School 1 -Aquatic Center
5,013,750
4,865,424
But Not Expended
62%
3
Funds Remaining
5,511,500
5,019,103
4,963,839
4
Gunn High School 3 - AD2- close out
94%
5,777
APproPd
5
Gunn High School 4- New classroom Buildings
24,120,000
2,536,324
Total Funds Ecperdal
Middle Schools
Gunn High School 5 - Parking & Drop Off improvements
3,940,000
217,770
3,530
6%
13%
13,830,000
\
523,357
Gunn High School 7 -A/C
Elementary
200813crdlssuance
Casts
Reserves/Not
WpprWated Expenditures
'
Palo Alto High Schools - High School Master Plan
145,000
0.41%
32°/6
60%
Expended Status
1,358,437
Overall Allocation
164,606
Budget status
Pab Alto High School 2 - MultimUse Field (Multi -Fund)
Total Bonds Issued
119,999,249
Elemartary Schools
98,678,279
Allocated to Projects But Not Expended
238,134,126
Bonds Authorized, Not Issued
258,000,751
Middle School.
49,126,150
Expenditures
23,802,958
Interest Earned`
3,357,249
High Schools
174,904,617
Reserves/Not Appropriated
123,274,877
State CTE Gant Inoorne ""
2,271,512
PAUSD/Not Appropriated
60,919,715
160,877
385,211,961
2008 Bond Issuance premiuns
1,583,200
2008 Band Issuance Costs
1,583,200
17
J.L.S Middle School - MS Pre -Design
Total Funds
385,211,961
18,408
385,211,961
J.L.S Middle School 1 - Interim Classrooms
446,844
Total Funds Expended
23,802,958 ' Interest eaned is based on total bond issued as of &'M10.
19
J.L.SMiddle School 2 -Improvements
17,184,699
"The District apples State Career Tednical Education
(CTE) grant rrnney to replace Bond funds previously expended on CIE qualifying projects. This allege funding for additlaral Bad projects.
Funds Rerraining
361,409,003
33,666
18,799
18,423
1
1
Gunn High School - High School Master Plan
145,000
132,391
115,845
2
Gunn High School 1 -Aquatic Center
5,013,750
4,865,424
4,860,823
3
Gunn High School 2 - LA Building
5,511,500
5,019,103
4,963,839
4
Gunn High School 3 - AD2- close out
5,777
5,777
5,777
5
Gunn High School 4- New classroom Buildings
24,120,000
2,536,324
1,606,781
6
Gunn High School 5 - Parking & Drop Off improvements
3,940,000
217,770
3,530
7
Gunn High School 6- New/Auxiliary Gymnasium
13,830,000
930,769
523,357
Gunn High School 7 -A/C
2,600,000
161,050
1,781
Palo Alto High Schools - High School Master Plan
145,000
132,773
117,739
10
Pab Alto High School 1 - Stadium Field
1,358,437
168,448
164,606
11
Pab Alto High School 2 - MultimUse Field (Multi -Fund)
3,002,063
2,908,082
583,371
12
Pab Alto high School 3 - New classroom & Media Art Building
34,220,000
3,215,847
1,561,423
13
Pak) Alto High School 4 - New Theater
17,720,000
1,026,210
48,867
14
Jordan Middle School - MS Pre -Design
33,665
18,890
17,826
15
Jordan Middle Schools 1- Interim Classrooms
600,342
170,645
160,877
16
Jordan Middle School 2- Improvements
17,943,194
1,547,169
271,468
17
J.L.S Middle School - MS Pre -Design
33,669
18,799
18,408
18
J.L.S Middle School 1 - Interim Classrooms
446,844
337,590
318,995
19
J.L.SMiddle School 2 -Improvements
17,184,699
1,395,712
219,057
0
Terman Middle School - MS Pre -Design
33,666
18,799
18,423
1
Terman Middle School 1- Improvements
12,850,071
1,151,225
195,340
2
PAUSD Elementary Schools - Elem.GrowthPlan
145,000
55,560
55,560
3
Addison Elementary School 1 -Phase 1
5,199,727
-
-
4
Briones Elementary School 1 -Phase 1
701,925
-
-
5
Duveneck Elementary School 1 -Phase 1
7,019,083
27,501
8,048
6
Garland Elementary School 1- Phase 1
22,178,544
281,279
280,113
7
EI Carmelo Elementary School 1 -Phase 1
641,760
-
-
8
Escondido Elementary School 1 -Phase 1
6,202,343
-
-
9
FairmeadowElementary School 1- Phase 1
9,327,500
780,409
117,824
0
Hays Elementary School 1 -Phase 1
4,793,814
1
Hoover Elementary School 1 -Phase 1
8,575,389
47,500
4,630
2
Nixon Elementary School 1 -Phase 1
802,200
-
-
3
Ohlone Elementary School 1 -Phase 1
11,667,965
1,504,547
1,066,965
4
Pak) Verde Elementary School 1 -Phase l
3,482,885
5
Barron Park Elementary School 1 -Phase 1
641,760
-
-
6
Elementary Schools 1 - Elementary Classroom Improvements
8,887,522
106,548
106,548
7
PAUSD- Program Management
3,353,101
2,258,763
2,258,763
8
PAUSD- Technology
5,995,689
2,543,174
2,543,174
Subtotal -Projects
260,353,884
33,584,078
22,219,758
Reserves/ Not Allocated
39
Gunn High School - Reserve
20,945,045
-
-
40
Pab Alto High School - Reserve
42,348,045
41
Elementary Schools - Reserve
8,410,862
42
PAUSD-Technology -Reserve
7,911,676
43
PAUSD - Reserve
6,335,945
44
PAUSD-Not Appropriated
37,323,304
Series 2008 Bond Issuance Costs 1,583,200 1,583,200 1,583,200
Total 385,211,961 35,167,278 23,802,958
4
STRONG SCHOOLS BOND
Strong Schools for a Strong Cornrrtunity
Palo Alto Unified School District
Gtizens' Oversight Coimittee
2009 - 2010 Annual Report
Below is a sampling of the projects within the Strong Schools Bond. To see a complete list and additional detail on the status, expendi-
tures and schedule of current Strong Schools Bond projects, please visit http://pausd.orgtcammnity/StrongSchoolsBondt
Gunn High School - Industrial Arts Addition and Renovation
Budget: $5,511,500 Occupancy: January 2010
This project renovated and expanded the existing Industrial Arts building at Gunn.
The addition includes two new biotechnology labs and support space. The existing
building has the same labs as before, but with upgraded electrical and mechanical
systems as well as new finishes and casework. The project was completed orrtime
and within budget, and began hosting classes in January 2010.
Gunn High School - New Classroom Buildings
Budget: $24,120,000 Planned Occupancy: July 2013
This project consists of two new dassroom buildings on the Gunn campus. A two story
classroom wing will house new classrooms, resource roomis and offices for the Math and
English departments. The Math department will be located on the upper floor, and Eng-
lish on the ground floor. The second building will house newVUcrld Languages class-
rooms and offices adjacent to the L wing complex and the Science building along
Arastradero. Planning and design have been completed. The project has been submitted
to the Division of state Architect (DSA) for reviewand is scheduled to be bid in the spring
of 2011.
Gunn High School - New Gymnasium
Budget: $13,830,000 Planned Occupancy: August 2012
A new gymnasium will be constructed at Gunn to provide a second venue for school
athletics and physical education instruction on the can -pus. The gym is planned to ac-
commodate approximately 1,900 students for basketball or volleyball games, and will
include a newticket booth, restrooms, team rooms and a fitness room for weightlifting
and dance programs. In addition to the gym, the project will rebuild the outdoor tennis
courts and outdoor basketball courts on the northern edge of the student parking lot.
Planning and design have been completed. The project has been submitted to DSAfor
review and is scheduled to be bid in the spring of 2011.
Palo Alto High School - Multi -Use Field
Budget: $3,002,063 Planned Occupancy: February 2011
This project will re -construct the existing baseball and softball fields on the southern
end of can -pus. The newfields will include new dugouts, bullpens, batting cages and
bleachers for each venue, and will improve fencing, scoreboards and drainage
around the field. Reconfiguration of the south parking lot is also included in this pro-
ject, which will include new striping and landscaping. The project is under construc-
tion.
onstruetion. The parking lot is open for use, and the fields will be completed for the opening
of the 2011 basebal I and softball I seasons.
PaloAlto High School - New Classroom Building and Media Arts Building
Budget: $34,220,000 Planned Occupancy: July 2013
This project consists of the addition of two large buildings to the Palo Alto high school
campus. The Math and Social Sciences classroom building will house new classrooms
in a two story structure, with Math classrooms, offices and resource areas on the upper
floor and similar spaces for Social Sciences on the ground floor. The Media Arts build-
ing will house new classrooms for the English department, as well as several lab
spaces for Media Arts, including video production, photography, editing and joumalism
Planning and design have been oompleted, the project was submitted to DSA August 4,
2010 for review and is scheduled to be bid in the spring of 2011.
i7V
Strong Schools Bond Projects (Continued)
Jordan Middle School
Budget: $17,943,194 Planned Occupancy: August 2013
Improvements at Jordan Wil indude a new dassroom W ng, a new Cafetori um and reno-
vations in several existing dassroms. The new classroom wing will be located in the
Middlefield parking lot. The new Cafetorium will be located on the tennis courts just
east of the existing building, which will be renovated to accommodate new music dass-
roorrs. The existing music dassroorrs Wil be renovated to accommodate newart labs,
and the science wing will also be renovated to convert three small labs into two larger
science labs. The project is currently in design development, with submittal to DSA
planned for the end of 2010 and construction planned for October 2011.
J. L Stanford Middle School
Budget: $17,184,699 Planned Occupancy: August 2013
Improvements at JLS will include anew classroom wing and renovations in sev-
eral existing classrooms. The new classroom wing will be a two story building,
located on the existing playground area south of the industrial arts wing. Im-
provements in the existing classrooms will indude additional storage, technology
walls and sound assist systems. The can -pus will also be enhanced with im-
provements to exterior spaces to improve drainage and student use of the out-
door space. The project is currently in design development, with submittal to DSA
planned for the end of 2010 and construction planned for December 2011.
Terman Middle School
Budget: $12,850,071 Planned Occupancy: July 2013
The Administration and Library building at Tern -an will be expanded and renovated
to accommodate a new office at the front of the school, two new carnxter labs and
a new, larger library in an addition on the east side of the building. Improvements
will also include renovations to the Cafetorium, a new drama classroom, and a new
science lab where the existing drama classroom is. The project is currently in design
development, with submittal to DSA planned for the end of 2010 and construction
planned for October 2011.
Ohlone Elementary School - New Classroom Building and Modernization
Budget: $11,667,965 Planned Occupancy: January 2012
A new classroom building is being constructed on the Ohlone campus to accommo-
date anticipated enrollment growth at the elementary schools. The project includes
new classrooms, a flex room and a special day classroom in a two story structure adja-
cent to the eAsting library. The project will also include some modernization of the
existing classrooms, including improved lighting, ventilation and new technology walls.
Construction began in August 2010, and is planned for completion in early 2012.
Fairmeadow Bementary School - New Classroom Building and Modernization
Budget: $9,327,500 Planned Occupancy: August 2013
A new classroom building is being constructed on the Fairmeadow can -pus to accom-
modate anticipated enrollment growth at the elementary schools. The project includes
a new, huo story classroomWing adjacent to the Jackson Center. The project will also
include some modernization of the existing classrooms, including improved lighting,
ventilation and newtechnology walls. The project is still in the preliminary design
phase.
FJementary Schools - FJementary Classroom Improvements
Budget: $8,887,522 Corrpletion: Present to August 2013
This project established budgets for each elementary school campus to receive a
technology wall, new lighting, newWndowsand shades, ventilation improvements
and ceiling tiles. With the installation of the technology wall, each elementary school
classroom will receive an interactive whiteboard and a sound assisted listening de-
vice proven to enhance student leaming.