Planning & Design Meetings Meeting #4 6/1/2010 - PresentationConceptual Design
Stadium Improvements
P A L O A L T O DLM H I G H S C H O O L
Palo Alto Unified School District
1 J ne 2010
DLM
A R C H I T E C T U R E
1 June 2010
Football Stadium ImprovementsFootball Stadium Improvements
Program Elements:
•New home and visitors bleachers with approximate seating capacity of
2,524 with 1,730 at home side and 794 at visitors side
•New press box and filming platform
•Concession and Restroom Facility with athletic storageyg
•Entry gates and ticket control
•Pedestrian path to visitors bleachers
•Trees to block views to “white”corporation yard warehouseTrees to block views to white corporation yard warehouse
•New long jump pits
•Upgrade picnic and gathering areas under existing trees
R l t t l t bl b ildi i ti d•Relocate two relocatable buildings in corporation yard
Construction Cost: approx $3 mPalo Alto High School
D e e m s L e w i s M c K i n l e y
Visitor Bleacher
Jump Pit
Pedestrian Path
Visitor Bleacher
Landscape Screen
Pedestrian Path
H 1 730
Home Bleachers
Concession/
iiA
Jump Pit
Home 1,730
Visitor 794
Total 2,524
Restrooms Picnic Area
Campus
Entry Plaza
Palo Alto High School Football Stadium Improvements
Entry Plaza
D e e m s L e w i s M c K i n l e y
Visitors
seating capacity 794
Palo Alto High School Home
seating capacity 1730D e e m s L e w i s M c K i n l e y seating capacity 1730
Palo Alto High School Home Sight Lines
D e e m s L e w i s M c K i n l e y
g
Before
Palo Alto High School
After
D e e m s L e w i s M c K i n l e y
New Bleachers
Picnic AreaConcession
Campus Stadium
Et
Restroom
Entry PlazaEntry
Turn-around
Bikes
Turn around
Drop-off/Pick-upKiosk
Palo Alto High School Campus Entry and Vehicular Drop-off
D e e m s L e w i s M c K i n l e y
Palo Alto High School Concession / Restroom Facility Floor Plan
D e e m s L e w i s M c K i n l e y
Concession / Restroom Facility Floor Plan
Palo Alto High School Concession / Restroom Facility
D e e m s L e w i s M c K i n l e y
Concession / Restroom Facility
Palo Alto High School Concession / Restroom Facility
D e e m s L e w i s M c K i n l e y
Concession / Restroom Facility
Project Milestones:Project Milestones:
Sequence of work
•Relocate existing relocatable buildings
•Jump pits
•Concession /Restroom Facility
•Visitors Bleachers
•Demolition of existing restroom and concession buildings
•Home Bleachers
•Submit to DSA : December 2010
•DSA Review: June 2011
Ctti J /J l 2011•Construction:June/July 2011
Palo Alto High School
D e e m s L e w i s M c K i n l e y
Next Steps:
•Meet with the user groups to begin schematic design levelMeet with the user groups to begin schematic design level
discussions
•Fine tune budget and program scope
•C ltthL d M t Pl d di t ithidiid l•Complete the Landscape Master Plan and coordinate with individual
landscape projects
•Meet with traffic consultant and schedule coordination meetings with
the Traffic and Safety group
Palo Alto High School
D e e m s L e w i s M c K i n l e y
A R C H I T E C T U R E