Planning & Design Meetings 11/1/2011 - Agenda
25 Churchill Avenue, Building ‘D’ ● Palo Alto, CA 94306 ● Phone 650.329.3935 ● Fax 650.327.3588 ● www.pausd.org
STRONG SCHOOLS BOND
Palo Alto High School
Facilities Steering Committee
Agenda
November 1, 2011
3:30 pm to 4:30 pm
Library, ERC Room
1. Performing Arts Center
Action 20 min
2. Athletic Stadium Update
Information 5 min
3. Construction Update (Gilbane)
a. Media Arts Center
b. Classroom Building
Information 15 min
4. Next Meetings
a. Paly FSC – Dec. 7, 2011
Information 5 min
5. Public Comments Discussion 5 min
Palo Alto HS PAC SUB-COMMITTEE MEETING
Palo Alto Unified School District
2 November 2011
P. 1
PALO ALTO HIGH SCHOOL
Palo Alto Unified School District
PERFORMING ARTS CENTER (PAC) SUBCOMMITTEE MEETING
DATE: 1 November 2011, 12:15 pm-1:30 pm
SUBJECT: PAC Plan Options
ATTENDEES: See attached sign-up sheet
The purpose of the meeting was to review the newest revisions to the PAC scheme
responding to recent FSC and Board comments, discuss current design option, and
come to consensus on a recommendation to the FSC at the 03 November 2011
meeting.
The following are the highlights of the meeting:
1. Brad Gunkel (BG) of DLM began the discussion by walking the committee
through a set of plans documenting the newest scheme.
• The balcony has been removed and the PAC has been increased in
width by a couple feet and in length by approximately 12 feet.
• The increase in the length of the house and the need to maintain
sightlines opened up an exciting opportunity – to provide upper side
boxes above the side aisles that can be accessed from the now higher
back row, and a possibility of placing program space under the control
booth. Side box seats could be removable or closed off to reduce seat
count for performances.
• Scheme shows 570+ seats (some of which are contingency in case they
need to be deleted while moving forward with design development.
Possibilities for removable seats include side boxes (24 upper, 8 lower),
orchestra pit (25) and numerous seats in the center aisle and back row.
• Instead of catwalks running under a coffered ceiling (as had previously
been shown), new scheme has catwalks running above a false arched
ceiling, hiding the clutter, maintaining the functionality and creating a
greater sense of intimacy in the space.
• Building has been pulled back a little more to maintain 30+ foot setback
from curb at drop-off area.
2. A conversation ensued regarding the new scheme:
• Michael Najar (MN) questioned the reason the current design is now
being represented as a 570+ seat scheme when the direction coming out
Palo Alto HS PAC SUB-COMMITTEE MEETING
Palo Alto Unified School District
2 November 2011
P. 2
of the last meeting with Kevin Skelly regarding this topic had 540 seats
as a target. JDL stated that the 570+ seats shown were meant as a
contingency to get to 540 seats since seats will likely be lost as the
design development moves forward.
• Tom Hodges (TH) gave a brief history of the conversations that have
been occurring behind the scenes regarding the Board’s concerns about
the seating capacity of PAC. The board had misinterpreted the seating
count of the new scheme and the actual seats shown (570 +) were
counted. The Board was responding more positively to the new scheme
but was not satisfied with 540 seats.
• MN stated that, in his mind, 570 is not 30 seats more than the previously
approved direction because he never wanted 540 seats. He stated that
the ideal maximum seating capacity would be in the mid 400s so 570
seats is 130 seats (not 30) more than makes sense. He stated concerns
about a house feeling half empty for performances and sited recent
performance numbers as examples. Holly Ward (HW) expressed similar
concerns stating that the 570 seating capacity would rarely be used and
would compromise the use of the space for performing arts.
• Phil Winston (PW) did a quick calculation based on projected future
enrollment and the fact that approximately 10% of a class are generally
not in attendance at full-class assemblies to determine that an assembly
space would only need to accommodate around 520 students to house
an entire class.
• BG pointed out that the current scheme can address the Board’s desires
that the PAC accommodate an entire class for assemblies while
addressing the PAC Subcommittee’s desire for a space that does not
feel half empty during performances. BG and JD revisited the locations
and numbers of possible removable seats and noted that these seats
could be taken out with little impact to the seating capacity that is not
being utilized.
• MN stated that, even though the current scheme is still not ideal, he
believes it is the best it is going to be considering the numerous parties
involved in the approval process. MN stated that, overall, he thinks the
new plan is a good plan. He and others stated that they’re concerned
that, if this moves forward, the elements that make this plan work as a
performing arts center are not lost. BG stated that DLM’s intention is to
continue working with the Subcommittee to make sure that those
elements are preserved as the design moves forward.
• The Subcommittee voted to recommend the revised scheme to the FSC.
3. BG showed the Subcommittee the presentation intended for the FSC:
• The slideshow presented the information that had been discussed.
• The Subcommittee requested that slides emphasizing the numerous
schemes previously considered not be presented.
Palo Alto HS PAC SUB-COMMITTEE MEETING
Palo Alto Unified School District
2 November 2011
P. 3
• Carolyn Williams (CW) asked about sightlines to the Haymarket Theater.
BG showed that a 30+ setback from the drop-off curb was being
maintained to preserve those sightlines.
• Next FSC meeting will be scheduled for Thursday, 03 November 2011 at 3:30 PM.
END
Prepared by Brad Gunkel of Deems Lewis McKinley. Please advise if you feel that any of the above items
are inaccurate or need further clarification or detail.
cc: Attendees
File
P A L O A L T O
H I G H S C H O O L
P l Al U ifi d S h l Di iPaloAltoUnifiedSchoolDistrict
Facility Site Committee
2 November 2011
PERFORMING ARTS CENTERPERFORMING ARTS CENTER
Vi h i d
Palo Alto High School
Various schemes were reviewed
and discussed.
D e e m s L e w i s M c K i n l e y
Reduced Scheme
575 seat max. theater with side boxes, 1 classroom,
basement/ orchestra pit& full fly tower
7
Schematic Design:
Program Elements:Program Elements:
Program remains same as 575 scheme with the deletion of balcony seating
•Lobby with restrooms, tickets, concession and gallery/display area
idfbd h h l dh•Stage sizedfor band, orchestra, choral, and theater
•Full fly loft
•Orchestra pit and trap room (now part of base contract – not an alternate)
•Control room and tech equipment support rooms
•Green Rooms with adjacent toilet and dressing rooms
•Scene,prop and costume storage, front of house storage,p p g,g
•Performing Arts Classroom
•Performing Arts Center office
TotalArea: approx 26 000 SFTotalArea: approx 26,000 SF
PaloAlto High SchoolPaloAlto High School
D e e m s L e w i s M c K i n l e y
SdFl Fi t Fl
Palo Alto High School Previous Scheme
SecondFloor FirstFloor
Presented 5 Oct 2010Approx. 38,000 SF
D e e m s L e w i s M c K i n l e y
Palo Alto High School First Floor Plans
550 Seats with Balcony 575 Max. Seats with Side Boxes
Previous Scheme Current Scheme
D e e m s L e w i s M c K i n l e y
First Floor Plan Upper Side Box Plan
2 November 2011
Palo Alto High School
D e e m s L e w i s M c K i n l e y Revised Floor Plan - Single Story with Basement
East-West Section
Palo Alto High School
D e e m s L e w i s M c K i n l e y North-South Section
Palo Alto High School Example of Catwalks Above False Arches
D e e m s L e w i s M c K i n l e y
p
Palo Alto High School
D e e m s L e w i s M c K i n l e y Site Plan
Palo Alto High School Tree Mitigation Strategy
xxx
XXX
D e e m s L e w i s M c K i n l e y
ggy
•Trees to be removed:
Total 7Total 7.
•Trees to be relocated:
Total 31
l•Replacement trees
per landscape plan:
Total 53
Palo Alto High School
D e e m s L e w i s M c K i n l e y
Tree Status Remains Same Tree Inventory Plan
View from El Camino
575 seat max.
Palo Alto High School
View from El Camino 2 November 2011
D e e m s L e w i s M c K i n l e y
View from El Camino
575 seat max.
2 N b 2011View from El Camino 2November 2011
Aerial View
Remains Similar
Remains Similar
View from El Camino
540 seats plus
Palo Alto High School
View from El Camino
p
2 November 2011
D e e m s L e w i s M c K i n l e y Remains Similar
Performing Arts Center g
Schedule
1. BOE Presentation November 29, 2011 OR,
Schematic Design December 13, 2011
2. DSA submittal July 2012
3. Bid / Award April 2013
5 SC i J 20135.Start Construction June 2013
6. Planned Occupancy August 2015
Palo Alto High School
D e e m s L e w i s M c K i n l e y
Proposed Schematic Design BudgetProposed Schematic Design Budget
Estimated Construction Cost $17,350,000
Change Order Contingency $ 1,735,000
Total Construction Budget $19,085,000
Soft Costs (Architect, CM, Inspection, Other fees)$ 5,310,049 (p)
Total Proposed Project Budget $24,395,049
Palo Alto High School
D e e m s L e w i s M c K i n l e y
ARCHITECTUREARCHITECTURE