Monthly Report 2017-11 (Nov) 1        MONTHLY PROGRESS REPORT    Through  November 2017      Strong Schools Bond  Capital Improvement Projects  Prepared by     fs3|Hodges     2    TABLE OF CONTENTS    Executive Summary         page 3   Attachment 1 – Consolidated Expenditure Report        Capital Projects     Gunn High School – Central Building Project      page 7  Palo Alto High School – Building 500 Renovation     page 8  Palo Alto High School – Science Building Addition     page 9  Addison Elementary School – New Library, Administration and Multipurpose Building  page 10  El Carmelo Elementary School – New Multipurpose Building    page 11  Escondido Elementary School – New Multipurpose Building    page 12  Hays Elementary School – New Multipurpose Building    page 13  Hoover Elementary School – New Library, Administration and Multipurpose Building  page 14    Completed Capital Projects    Gunn High School – Aquatic Center       page 15  Gunn High School – Industrial Arts Renovation      page 16  Gunn High School – New Classroom Building and World Languages Building    page 17  Gunn High School – New Gymnasium       page 18  Gunn High School – Air Conditioning of Existing Buildings     page 19  Gunn High School – Existing Gymnasium Modernization    page 20  Gunn High School – E and K (L31 and MS) Buildings Renovation     page 21  Gunn High School – Traffic Signal Replacement (Phase I‐ Improvements)    page 22  Palo Alto High School – Athletic Stadium Improvements    page 23  Palo Alto High School – Multi‐use Field       page 24  Palo Alto High School – Haymarket and Tower Building Improvements   page 25  Palo Alto High School – New Classroom Building and Media Arts     page 26  Palo Alto High School – Performing Arts Center     page 27  Palo Alto High School – Indoor PE and Athletic Facilities     page 28  Jordan Middle School        page 29  Jordan Middle School – Interim Classrooms       page 30  J.L. Stanford Middle School       page 31  J.L. Stanford Middle School – Landscape and Site Improvements     page 32  J.L. Stanford Middle School – Interim Classrooms      page 33  Terman Middle School        page 34  Duveneck Elementary School – New Classroom Buildings and Modernization    page 35  Fairmeadow Elementary School – New Classroom Buildings and Modernization   page 36  Fairmeadow Elementary School – Portable Relocation    page 37  Ohlone Elementary School        page 38  Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System  page 39  Property Acquisition – 525 San Antonio Rd       page 40  Middle School Pre‐Design        page 41  Technology          page 42    Inactive Capital Projects    Garland Elementary School       page 43  High School Master Plan        page 44      3  EXECUTIVE SUMMARY    CURRENT CAPITAL PROJECTS   Gunn High School – Central Building Project  Alten has completed steel erection at the Spangenberg Theater addition, and has begun erecting steel columns at  the Central Building. Stem walls are being formed at Spangenberg, and under‐slab plumbing and electrical work is  underway at in preparation for pouring the slab on grade. Steel framing erection for the Central Building will  continue through November.    Palo Alto High School – Building 500 Renovation (Library)  Sausal Corp has installed the under‐slab plumbing and electrical work, and is preparing for re‐pouring the slab on  grade. Roof demolition and cutting in new skylights is halfway complete, with the 2nd half of the roof work in  progress. Foundations have been dug inside the building for the mezzanine framing.    Palo Alto High School – Science Building Addition   Construction documents were submitted to DSA on November 22nd, and DSA has accepted the submittal as  complete. They will continue their review for the next several months. Staff is also completing a constructability  review and will update estimates on this plan set as well, which should be completed in December.    Addison Elementary School – (Donor Funded Project)  Gelfand Partners has submitted construction documents to DSA for review on September 5th, and has begun to  receive comments back already from their review, which is ahead of schedule. Staff has also completed updating  estimates and performing constructability reviews. Estimates are reflecting the project is over budget, due mostly  to increasing construction costs in the Bay Area. Constructability review comments will be picked up in December.  Staff is hopeful that DSA will provide their remaining structural comments by the end of December as well.    El Carmelo Elementary School – New MP Building  The conceptual design was presented to the Board of Education on October 24. The Board decided to defer any  decision to move forward until staff can provide a project list of other potential projects for their review, prior to  committing funds to this project.    Escondido Elementary School – New MP Building  The conceptual design was presented to the Board of Education on October 24. The Board decided to defer any  decision to move forward until staff can provide a project list of other potential projects for their review, prior to  committing funds to this project.    Hays Elementary School – New MP Building  The conceptual design was presented to the Board of Education on October 24. The Board decided to defer any  decision to move forward until staff can provide a project list of other potential projects for their review, prior to  committing funds to this project.    Hoover Elementary School  The Board of Education approved the schematic design for Hoover on October 24th, and Gelfand is working on  design development drawings. Staff continued to hold several DD design meetings with Hoover staff in November  to lay out specific needs in individual spaces. Gelfand is scheduled to submit plans to DSA next spring.      4    COMPLETED CAPITAL PROJECTS   Gunn High School – Aquatic Center   This facility was available for use in July 2009, and has been closed out with DSA.    Gunn High School – Industrial Arts Addition & Renovation  This facility was available for instruction in January 2010. DSA closeout received on July 18, 2011.    Gunn High School – New Classroom Building and World Languages Building  The new Math and English Building was occupied by staff and students on August 15, 2013.  World Language Building  classrooms were occupied in February 2013.    Gunn High School – New Gymnasium  The new gymnasium was occupied on June 7, 2013 and PE classes were held in the new gym on August 15, 2013.   The tennis courts were completed August 27, 2013.    Gunn High School – Air Conditioning of Existing Buildings  Best Contracting Services Inc. completed the installation of air conditioning units and roofing in the summer 2011.    Gunn High School – Existing Gymnasium Modernization  The modernized Bow gym was occupied by the campus on November 4, 2013.    Gunn High School – E and K (L‐31 and MS) Buildings Renovation  Students occupied E and K buildings on August 13, 2014, and building E was occupied on September 15, 2014.    Gunn High School –Traffic Signal Replacement (Phase I ‐ Parking and Drop‐Off Improvements)  All improvements were completed in August 2015, and the first phase of this project is complete.    Palo Alto High School – Athletics Stadium Improvements  The concessions building, track re‐surfacing, new ornamental fence, signage and entry lighting were completed for  the 2013 football season.    Palo Alto High School – Multi‐use Field  The fields were available for play on February 1, 2011, and the project was completed on March 9, 2011.    Palo Alto High School – Haymarket and Tower Building Improvements  All Trusty Builders completed the installation of the new windows on August 9, 2013.    Palo Alto High School – New Math/Social Sciences Building and Media Arts Building  Move in and occupancy of both buildings occurred in July 2014. Contract and DSA closeout are complete.      Palo Alto High School – Performing Arts Center (PAC)  Students and staff occupied the new building in July, and DSA closeout was completed in September 2016.    Palo Alto High School – Indoor PE and Athletic Facilities   The new facility was occupied for the fall quarter of 2017. Some remaining furnishing items and equipment remain  to be installed, and new gates will be installed by Vance Brown for the pool in October. DSA closeout will be  completed by November 17th.    5  Jordan Middle School  Students occupied all new and modernized buildings in fall 2013.    Jordan Middle School ‐ Interim Classrooms  The portables were installed and moved into for fall 2011.  DSA closeout received November 19, 2012.    J.L. Stanford Middle School  Students occupied all new and modernized buildings in fall 2013.    J.L. Stanford Middle School – Landscape and Sitework Improvements    Scapes completed the project on schedule in the fall 2013.    J.L. Stanford Middle School ‐ Interim Classrooms  Coulter Construction completed the work on the relocated portables in August 2011.      Terman Middle School  Students  occupied  the  new  instructional  spaces  and  modernized  buildings  in  fall  2013.    The  cafetorium  modernization was completed in October 2013.    Duveneck Elementary School – New Classroom Buildings and Modernization  All buildings were substantially complete and occupied on August 11, 2014.     Fairmeadow Elementary School – New Classroom Building and Modernization   Students occupied all new and modernized buildings in fall 2013.    Fairmeadow Elementary School – Portable Relocation  Relocation of the portable was complete and occupied on August 8, 2011.    Ohlone Elementary School – New Classroom Building and Modernization  Students occupied the new building on January 3, 2012.      Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems  Installation  of  SmartBoards  and  Lightspeed  sound  assist  systems  were  completed  for  all  elementary  school  classrooms and libraries in April 2011.      525 San Antonio Road – Site Acquisition  This site has been leased to Athena Academy.     Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman  These projects for pre‐design work have been closed.    Technology  Equipment orders have arrived and were deployed to the various campuses for use during the 2014/15 school year.     6    INACTIVE CAPITAL PROJECTS     Garland Elementary School Renovation  The Board of Education has put new development for Garland on hold until a growth plan is established for the  elementary schools.      High School Master Plan  The Board of Education (BOE) approved the master plans for both high schools, and these projects have been closed.   Board Items in November  November 14, 2017:   No Strong Schools Bond items         A B C C / A B - C C / B A - B Measure A Fund Gunn High School - High School Master Plan 172,390 166,328 147,706 86% 18,622 88.80% 6,062 Gunn High School 1 - Aquatic Center 4,862,530 4,862,530 4,862,530 100% 0 100.00% 0 Gunn High School 2 - I.A Building 5,065,128 5,065,128 5,065,128 100% 0 100.00% 0 Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100% 0 100.00% 0 Gunn High School 4 - New classroom Buildings 24,808,489 24,779,698 24,779,698 100% 0 100.00% 28,791 Gunn High School 5 - Parking & Drop Off improvements 3,939,998 2,070,855 1,855,723 47% 215,132 89.61% 1,869,143 Gunn High School 6- New/Auxiliary Gymnasium 12,450,948 12,440,998 12,440,998 100% 0 100.00% 9,950 Gunn High School 7- A/C 2,092,366 2,092,366 2,092,366 100% 0 100.00% 0 Gunn High School 8 - MS & L-31 Buildings 1,629,176 1,623,174 1,623,174 100% 0 100.00% 6,002 Gunn High School 9 - Central building 24,887,216 24,263,477 4,863,689 20% 19,399,788 20.05% 623,739 Gunn High School - Reserved 3,390,796 0 0 0% 0 0.00% 3,390,796 Palo Alto High Schools - High School Master Plan 172,999 167,759 161,616 93% 6,143 96.34% 5,240 Palo Alto High School 1 - Stadium Field 4,758,037 4,758,037 4,758,037 100% 0 100.00% 0 Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,609,680 100% 0 100.00% 0 Palo Alto high School 3 - New classroom & Media Art Building 36,938,516 36,819,195 36,819,195 100% 0 100.00% 119,321 Palo Alto High School 4 - New Theater 27,481,465 27,125,133 27,117,763 99% 7,370 99.97% 356,332 Palo Alto High School 5 - Haymarket and Tower Admin. Building 1,260,933 1,260,933 1,260,933 100% 0 100.00% 0 Palo Alto High School 6- Science Addition 5,532,205 979,919 840,984 15% 138,935 85.82% 4,552,286 Paly 7- Paly Athletic Center (Two Funds) 18,234,222 18,057,173 17,530,730 96% 526,443 97.08% 177,049 Paly 8-Library 14,161,140 13,510,894 3,065,816 22% 10,445,078 22.69% 650,246 Palo Alto High School - Reserved 558,921 0 0 0% 0 0.00% 558,921 Jordan Middle School -Program Management- MS Pre-Design 17,826 17,826 17,826 100% 0 100.00% 0 Jordan Middle Schools 1- Interim Classrooms 488,033 488,033 488,033 100% 0 100.00% 0 Jordan Middle School 2- Improvements 19,109,345 18,947,062 18,947,062 99% 0 100.00% 162,283 Jordan Middle School - Reserved 0 0 0 0% 0 0.00% 0 J.L.S Middle School - Program Management- MS Pre-Design 18,408 18,408 18,408 100% 0 100.00% 0 J.L.S Middle School 1 - Interim Classrooms 422,500 422,500 422,500 100% 0 100.00% 0 J.L.S Middle School 2- Improvements 15,670,128 15,535,784 15,535,784 99% 0 100.00% 134,344 J.L.S Middle School - Reserved 0 0 0 0% 0 0.00% 0 Terman Middle School - Program Management- MS Pre-Design 18,423 18,423 18,423 100% 0 100.00% 0 Terman Middle School 1- Improvements 13,051,488 13,003,128 13,003,128 100% 0 100.00% 48,360 Terman Middle School - Reserved 0 0 0 0% 0 0.00% 0 PAUSD Elementary Schools - Program Management- Elem. Growth Plan 308,000 93,480 89,000 29% 4,480 95.21% 214,520 Addison Elementary School 1-Phase I 21,267 21,267 21,267 100% 0 100.00% 0 El Carmelo Multi-Use Building 10,898,835 28,555 26,555 0% 2,000 93.00% 10,870,280 Escondido Multi-Use Building 15,891,036 26,514 24,514 0% 2,000 92.46%15,864,522 Walter Hays Multi-Use Building 1,646,435 53,983 24,453 1% 29,530 45.30% 1,592,452 Hoover Elementary School 1-Phase I 23,207,165 2,834,275 461,553 2% 2,372,722 16.28% 20,372,890 Duveneck Elementary School 1-Phase I 9,230,464 9,229,952 9,229,952 100% 0 100.00% 512 Fairmeadow Elementary School 1- Phase I 7,590,515 7,584,495 7,584,495 100% 0 100.00% 6,020 Ohlone Elementary School 1- Phase I 10,528,254 10,528,254 10,528,254 100% 0 100.00% 0 Garland Elementary School 1- Phase I 280,113 280,113 280,113 100% 0 100.00% 0 Elementary Schools 1 - Elementary Classroom Improvements 1,879,695 1,879,695 1,879,695 100% 0 100.00% 0 Multi-Use Builindg - Reserved 8,696,502 0 0 0% 0 0.00% 8,696,502 PAUSD - Program Management 16,163,405 14,426,178 13,587,284 84% 838,894 94.18% 1,737,227 PAUSD - Technology 12,885,056 11,597,263 11,529,097 89% 68,166 99.41% 1,287,793 PAUSD - Technology -Reserved 1,022,312 0 0 0% 0 0.00% 1,022,312 PAUSD - Reserved 0 0 0 0% 0 0.00% 0 525 San Antonio -Property Acquisition 8,500,000 8,500,000 8,500,000 100% 0 100.00% 0 Transfer out to Planned Maintenance Fund* 17,758,557 8,604,510 8,604,510 48% 0 100.00% 9,154,047 Bond Issuance Cost 3,043,618 2,972,933 2,972,933 98% 0 100.00% 70,685 Measure A Fund Total 393,360,312 309,771,684 275,696,381 34,075,303 83,588,628 * Planned Maintenance Fund Total 8,604,511 8,159,574 6,569,249 76% 1,590,325 444,937 *$17,758,557 from Measure A fund to Planned Maintenance fund was approved. The budget for Planned maintenance fund will be increased about $2 M every year in 9 years. Prepared by: Business Services Department based on QSS accounting System School Name - Project Name Percent of Budget Expended Palo Alto Unified School District Strong Schools Bond 11/30/2017 Percent of Expended Contract BalanceExpenditures Budget BalanceCommittedBudget 7  Gunn High School  Central Building Project  A. PROJECT STATUS    Alten has completed steel erection at the  Spangenberg Theater addition, and has begun  erecting steel columns and beams at the Central  Building. Stem walls are being formed at  Spangenberg, and under‐slab plumbing and electrical  work is underway at in preparation for pouring the  slab on grade. Steel framing erection for the Central  Building will continue through November.            B. BUDGET & SCHEDULE SUMMARY                                                C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:   Foundation work is in progress.       Funding  State Funds  $0  Strong Schools Bond Funds  $ 24,887,216  Other Funding  $0  Total  $24,887,216    Budget  Salaries and Benefits  $4,098  Supplies  $421  Contracts & Services  $3,811,130  Construction & Equipment  $21,010,351  Soft Costs Contingency  $61,216  Total  $24,887,216    Percent of Budget Expended  20%    Change Order Contingency   Starting Contingency Balance  $1,966,300   Remaining Contingency Balance  $1,854,153   Percent of Changes  0.57%  (Change Orders + Construction Change Directives.  Original Contract)    Current Phase:  Construction    Schedule:  Architect Contract (2)  March 31, 2009  BOE Approval  April 14, 2009    Conceptual Design (2)  February 25, 2014  BOE Approval  March 11, 2014    Schematic Design (2)  June 3, 2014  BOE Approval  June 17, 2014  BOE Approval of Program Change  December 9, 2014    Submit to DSA  February 15, 2016    Authorize to Bid (2)  September 27, 2016  BOE Approval  October 18, 2016     Approval by DSA  February 7, 2017    Bid Opening  March 21, 2017    Award of Contract (1)  March 28, 2017    Notice to Proceed  May 15, 2017    Substantial Completion  December 15, 2018*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  8  Palo Alto High School   Building 500 Renovation (Library)    A. PROJECT STATUS     Sausal Corp has installed the under‐slab plumbing and  electrical work, and is preparing for re‐pouring the slab  on grade. Roof demolition and cutting in new skylights is  halfway complete, with the 2nd half of the roof work in  progress. Foundations have been dug inside the building  for the mezzanine framing.                      B. BUDGET & SCHEDULE SUMMARY                                                C. BOND PROJECT LIST REFERENCE: 4.8    D. PROJECT OVERVIEW:   Sausal completed underground plumbing and electrical work in November.     Funding  State Funds  $0  Strong Schools Bond Funds  $14,161,140  Other Funding  $0  Total  $14,161,140    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $2,283,420  Construction & Equipment  $11,728,800  Soft Costs Contingency  $148,920  Total  $14,161,140    Percent of Budget Expended  22%    Change Order Contingency   Starting Contingency Balance  $978,750   Remaining Contingency Balance  $946,537   Percent of Changes  0.33%  (Change Orders + Construction Change Directives.  Original Contract)    Current Phase: Construction    Schedule:  Architect Contract (2)  N/A  BOE Approval  N/A    Conceptual Design (2)  September 23, 2014  BOE Approval  October 14, 2014    Schematic Design (2)  March 24, 2015  BOE Approval  April 21, 2015    Submit to DSA  December 15, 2015    Approval by DSA  March 14, 2017*    Authorize to Bid (1)  February 28, 2017    Award of Contract (1)  May 23, 2017    Construction Start  August 1, 2017    Substantial Completion  November 15, 2018*    Planned Occupancy  January 2019*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  9    Palo Alto High School  Science Building Addition    A. PROJECT STATUS   Construction documents were submitted to DSA on  November 22nd, and DSA has accepted the submittal as  complete. They will continue their review for the next  several months. Staff is also completing a constructability  review and will update estimates on this plan set as well,  which should be completed in December.            B. BUDGET & SCHEDULE SUMMARY                                                    C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   DLM submitted construction documents to DSA for review on November 22, 2017.     Funding  State Funds  $0  Strong Schools Bond Funds  $5,532,204  Other Funding  $0  Total  $5,532,204    Budget  Salaries and Benefits  $0  Supplies  $60,309  Contracts & Services  $842,825  Construction & Equipment  $4,628,294  Soft Costs Contingency  $776  Total  $5,532,204    Percent of Budget Expended  15.20%      Current Phase:   DSA Review    Schedule:  Architect Contract (2)  March 12, 2013  BOE Approval  March 19, 2013    Conceptual Design (2)  March 12, 2013  BOE Approval  March 19, 2013    Schematic Design (2)  September 10, 2013  BOE Approval  October 8, 2013    Submit to DSA  February 14, 2017  BOE Approval  February 28, 2017    Authorize to Bid (2)  March 13, 2018*  BOE Approval  March 27, 2018*    Approval by DSA  March 15, 2018*    Bid Opening  May 1, 2018*    Award of Contract (1)   May 8, 2018*    Notice to Proceed  June 1, 2018*    Substantial Completion  August 1, 2019*    Planned Occupancy October 1, 2019*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  10  Addison Elementary School (Donor‐Funded Project)  New Library, Administration and Multipurpose Building  A. PROJECT STATUS  Gelfand Partners has submitted construction  documents to DSA for review on September 5th, and  has begun to receive comments back already from  their review, which is ahead of schedule. Staff has  also completed updating estimates and performing  constructability reviews. Estimates are reflecting the  project is over budget, due mostly to increasing  construction costs in the Bay Area. Constructability  review comments will be picked up in December.  Staff is hopeful that DSA will provide their remaining  structural comments by the end of December as  well.      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   DSA has begun returning comments to Gelfand, which is ahead of schedule.       Funding  State Funds  $0  Strong Schools Bond Funds  $0  Other Funding – Donation  $1,330,000  Total  $1,330,000    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $1,330,000  Construction & Equipment  $0  Soft Costs Contingency  $0  Total  $1,330,000    Percent of Budget Expended  77%  Current Phase: DSA Review    Schedule:  Conceptual Design (2)  February 23, 2016    March 8, 2016    Schematic Design (2)  September 13, 2016  BOE Approval  September 27, 2016    Submit to DSA  September 5, 2017     Approval by DSA  February 15, 2018*    Authorize to Bid (2)  February 1, 2018*  BOE Approval  February 15, 2018*    Bid Opening  April 15, 2018*    Award of Contract (1)  May 1, 2018*    Notice to Proceed  May 15, 2018*    Substantial Completion  September 15, 2019*    Planned Occupancy  December 20, 2019*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  11  El Carmelo Elementary School  New Multipurpose Building  A. PROJECT STATUS  The conceptual design was presented to the Board of  Education on October 24. The Board decided to defer  any decision to move forward until staff can provide a  project list of other potential projects for their review,  prior to committing funds to this project.                    B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   This project is on hold.           Funding  State Funds  $0  Strong Schools Bond Funds  $77,000  Other Funding  $0  Total  $0    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $77,000  Construction & Equipment  $0  Soft Costs Contingency  $0  Total  $77,000    Percent of Budget Expended  34.26%  Current Phase:   Conceptual Design    Schedule:  Conceptual Design (2)  October 10, 2017  BOE Approval  October 24, 2017    Schematic Design (2)  TBD  BOE Approval  TBD     Submit to DSA  TBD     Approval by DSA  TBD    Authorize to Bid (2)  TBD    Bid Opening  TBD    Award of Contract (1)  TBD    Notice to Proceed  TBD    Substantial Completion  TBD    Planned Occupancy  TBD    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  12    Escondido Elementary School  New Multipurpose Building  A. PROJECT STATUS  The conceptual design was presented to the Board of  Education on October 24. The Board decided to defer  any decision to move forward until staff can provide  a  project  list  of  other  potential  projects  for  their  review, prior to committing funds to this project.              B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   This project is on hold.               Funding  State Funds  $0  Strong Schools Bond Funds  $73,000  Other Funding  $0  Total  $0    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $73,000  Construction & Equipment  $0  Soft Costs Contingency  $0  Total  $73,000    Percent of Budget Expended  27.6%    Current Phase:   Conceptual Design    Schedule:  Conceptual Design (2)  October 10, 2017  BOE Approval  October 24, 2017    Schematic Design (2)  TBD  BOE Approval  TBD     Submit to DSA  TBD     Approval by DSA  TBD    Authorize to Bid (2)  TBD    Bid Opening  TBD    Award of Contract (1)  TBD    Notice to Proceed  TBD    Substantial Completion  TBD    Planned Occupancy  TBD    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  13    Hays Elementary School  New Multipurpose Building  A. PROJECT STATUS  The conceptual design was presented to the Board  of Education on October 24. The Board decided to  defer any decision to move forward until staff can  provide a project list of other potential projects for  their  review,  prior  to  committing  funds  to  this  project.                  B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   This project is on hold.          Funding  State Funds  $0  Strong Schools Bond Funds  $150,000  Other Funding  $0  Total  $0    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $150,000  Construction & Equipment  $0  Soft Costs Contingency  $0  Total  $150,000      Percent of Budget Expended  16.3%      Current Phase:   Conceptual Design    Schedule:  Conceptual Design (2)  October 10, 2017  BOE Approval  October 24, 2017    Schematic Design (2)  TBD  BOE Approval  TBD     Submit to DSA  TBD     Approval by DSA  TBD    Authorize to Bid (2)  TBD    Bid Opening  TBD    Award of Contract (1)  TBD    Notice to Proceed  TBD    Substantial Completion  TBD    Planned Occupancy  TBD    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  14  Hoover Elementary School  New Library, Administration and Multipurpose Building  A. PROJECT STATUS    The Board of Education approved the schematic  design for Hoover on October 24th, and Gelfand is  working on design development drawings. Staff  continued to hold several DD design meetings with  Hoover staff in November to lay out specific needs in  individual spaces. Gelfand is scheduled to submit  plans to DSA next spring.                   B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   Schematic design was approved by the Board on October 24, 2017.       Funding  State Funds  $0  Strong Schools Bond Funds  $23,207,165  Other Funding  $0  Total  $23,207,165    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $4,848,277  Construction & Equipment  $18,358,888  Soft Costs Contingency  $  Total  $23,207,165    Percent of Budget Expended  2%  Current Phase: Design Development    Schedule:  Conceptual Design (2)  December 13, 2016  BOE Approval  January 10, 2017    Schematic Design (2)  October 10, 2017*  BOE Approval  October 24, 2017*    Submit to DSA  April 2018*     Approval by DSA  November 2018*    Authorize to Bid (2)  November 2018*    Bid Opening  January 2019*    Award of Contract (1)  February 2019*    Notice to Proceed  March 2019*    Substantial Completion  November 2020*    Planned Occupancy December 2020*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  15  Gunn High School  Aquatic Center  A. PROJECT STATUS  This facility was available for use in July  2009.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.12    D. PROJECT OVERVIEW:   This project completed within budget. Funding  State Funds  $0  Strong Schools Bond Funds  $4,862,530  Other Funding  $0  Total  $4,862,530    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $647,169  Construction & Equipment  $4,215,360  Soft Costs Contingency  $0  Total  $4,862,530    Percent of Budget Expended  100%    Change Order Contingency   Starting Contingency Balance  $389,887   Remaining Contingency Balance  $195,148   Percent of Changes  49.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase:  Occupancy – June 15, 2009    Schedule:  Architect Contract (2)  N/A  BOE Approval  N/A    Conceptual Design (2)  N/A  BOE Approval  N/A    Schematic Design (2)  N/A  BOE Approval  N/A    Submit to DSA  December 11, 2007     Approval by DSA  April 24, 2008    Authorize to Bid (2)  April 8, 2008  BOE Approval  April 22, 2008    Bid Opening  May 28, 2008    Award of Contract (1)  June 4, 2008    Notice to Proceed  December 6, 2008    Substantial Completion  June 15, 2009    Planned Occupancy  June 15, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 16   Gunn High School  Industrial Arts Addition and Renovation  A. PROJECT STATUS  This facility was available for instruction in January 2010. DSA  closeout received on July 18, 2011.          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11    D. PROJECT OVERVIEW:   The building occupied as scheduled, and the project completed within budget. Funding  State Funds  $0  Strong Schools Bond Funds  $5,065,128  Other Funding  $0  Total  $5,065,128    Budget  Salaries and Benefits  $1,061  Supplies  $88,985  Contracts & Services  $984,783  Construction & Equipment  $3,990,300  Soft Costs Contingency  $0  Total  $5,065,128    Percent of Budget Expended  100%    Change Order Contingency   Starting Contingency Balance  $349,000   Remaining Contingency Balance  $141,967   Percent of Changes  41.6%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase:  Occupancy – January 4, 2010   Schedule:  Architect Contract (2)  N/A  BOE Approval  N/A    Conceptual Design (2)  N/A  BOE Approval  N/A    Schematic Design (2)  N/A  BOE Approval  N/A    Submit to DSA  June 17, 2008     Approval by DSA  December 24, 2008    Authorize to Bid (2)  October 14, 2008  BOE Approval  October 28, 2008    Bid Opening  December 16, 2008    Award of Contract (1)  December 24, 2008    Notice to Proceed  January 6, 2009    Substantial Completion  November 25, 2009    Planned Occupancy  January 4, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 17   Gunn High School   New Classroom Buildings A & B   A. PROJECT STATUS  The  new  Math  and  English  Building  was  occupied  by  staff  and  students on August 15, 2013.  World Language Building classrooms  have been in use since February 2013.                       B. BUDGET & SCHEDULE SUMMARY                                                C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4    D. PROJECT OVERVIEW:   The World Languages building move‐in occurred on February 8, 2013, and was occupied with staff and  students on February 11, 2013.  The Math & English building move‐in occurred on July 15, 2013, and was  occupied with staff and students on August 15, 2013.  The project was completed within budget.      Funding  State Funds  $0  Strong Schools Bond Funds  $24,808,488  Other Funding  $0  Total  $24,808,488    Budget  Salaries and Benefits  $24,948  Supplies  $308,194  Contracts & Services  $3,789,909  Construction & Equipment  $20,685,160  Soft Costs Contingency  $277  Total  $24,808,488    Percent of Budget Expended  99.9%    Change Order Contingency   Starting Contingency Balance  $ 1,763,200   Remaining Contingency Balance  $ 99,232   Percent of Changes  9.3%  (Change Orders + Construction Change Directives vs.  Original Contract)    Project Savings Realized = $226,713    Current Phase:  Occupancy – August 15, 2013    Schedule:  Architect Contract (2)  March 31, 2009  BOE Approval  April 14, 2009    Conceptual Design (2)  September 8, 2009  BOE Approval  September 22, 2009    Schematic Design (2)  January 12, 2010  BOE Approval  January 26, 2010    Submit to DSA  August 4, 2010     Authorize to Bid (2)  March 8, 2011  BOE Approval  March 22, 2011    Approval by DSA  May 27, 2011    Bid Opening  July 13, 2011    Award of Contract (1)  July 22, 2011    Notice to Proceed  August 24, 2011    Substantial Completion  July 15, 2013    Planned Occupancy  August 15, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 18   Gunn High School   New Gymnasium   A. PROJECT STATUS  The new gymnasium was occupied on June 7, 2013 and PE classes were held in the new gym on August 15, 2013.   The tennis courts surfacing and striping was installed and completed August 27, 2013.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:   The new gym was occupied on June 7, 2013.     Funding  State Funds  $0  Strong Schools Bond Funds  $ 12,450,946  Other Funding  $0  Total  $12,450,946    Budget  Salaries and Benefits  $0  Supplies  $19,706  Contracts & Services  $2,461,402  Construction & Equipment  $9,936,883  Soft Costs Contingency  $32,955  Total  $12,450,946    Percent of Budget Expended  99.9%    Change Order Contingency   Starting Contingency Balance  $834,700   Remaining Contingency Balance  $7,909   Percent of Changes  9.9%  (Change Orders + Construction Change Directives vs.  Original Contract)    Project Savings Realized = $463,854  Current Phase:  Occupancy – June 7, 2013    Schedule:  Architect Contract (2)  March 31, 2009  BOE Approval  April 14, 2009    Conceptual Design (2)  September 8, 2009  BOE Approval  September 22, 2009    Schematic Design (2)  January 12, 2010  BOE Approval  January 26, 2010    Submit to DSA  August 4, 2010    Authorize to Bid (2)  March 8, 2011  BOE Approval  March 22, 2011    Approval by DSA  May 27, 2011    Bid Opening  July 13, 2011    Award of Contract (1)  July 20, 2011    Notice to Proceed  August 1, 2011    Substantial Completion  May 1, 2013    Planned Occupancy  June 7, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 19   Gunn High School  Air Conditioning of Existing Buildings  A. PROJECT STATUS  Best  Contracting  Services  Inc.  completed  the  installation  of  air  conditioning units and cool roof coating in the summer 2011.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.7    D. PROJECT OVERVIEW:   Project has been closed‐out.       Funding  State Funds  $0  Strong Schools Bond Funds  $2,092,366  Other Funding  $0  Total  $2,092,366    Budget  Salaries and Benefits  $1,919  Supplies  $0  Contracts & Services  $454,610  Construction & Equipment  $1,612,946  Soft Costs Contingency  $22,891  Total  $2,092,366    Percent of Budget Expended  100%  Current Phase:    Completed    Schedule:  Architect Contract (2)  March 27, 2010  BOE Approval  April 6, 2010    Conceptual Design (2)  N/A  BOE Approval  N/A    Schematic Design (2)  N/A  BOE Approval  N/A    Submit to DSA  October 20, 2010    Approval by DSA  February 10, 2011    Authorize to Bid (2)  February 22, 2011  BOE Approval  March 8, 2011    Bid Opening  March 28, 2011    Award of Contract (1)  April 8, 2011    Notice to Proceed  April 11, 2011    Substantial Completion  August 8, 2011      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 20   Gunn High School   Existing Gymnasium Modernization  A. PROJECT STATUS  The modernized Bow gym was occupied by the campus on  November 4, 2013.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:   The project was completed on‐schedule and within budget. Occupancy by the school occurred on  November 12, 2013.        Funding and Budget  This project is funded by the New Gymnasium project  budget.  See that project budget for status.    Change Order Contingency   Starting Contingency Balance  $99,800   Remaining Contingency Balance  $51,455   Percent of Changes  4.8%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase:  Occupancy – November 12, 2013    Schedule:  Architect Contract (2)  March 31, 2009  BOE Approval  April 14, 2009    Conceptual Design (2)  September 8, 2009  BOE Approval  September 22, 2009    Schematic Design (2)  January 12, 2010  BOE Approval  January 26, 2010    Submit to DSA  August 4, 2010    Authorize to Bid (2)  February 12, 2013  BOE Approval  February 26, 2013    Approval by DSA  January 23, 2013    Bid Opening  April 2, 2013    Award of Contract (1)  April 9, 2013    Notice to Proceed  May 31, 2013    Substantial Completion  October 28, 2013    Planned Occupancy  November 12, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 21   Gunn High School   E and K (MS and L‐31) Buildings Renovation   A. PROJECT STATUS  Students occupied E and K buildings on August 13,  2014, and the flex room in building E was occupied on  September 15, 2014.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:   Construction was completed on schedule and within budget.  Occupancy took place on August 13, 2014.             Funding  State Funds  $0  Strong Schools Bond Funds  $1,629,173  Other Funding  $0  Total  $1,629,173    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $428,000  Construction & Equipment  $1,198,886  Soft Costs Contingency  $2,287  Total  $1,629,173    Percent of Budget Expended  99.63%    Change Order Contingency   Starting Contingency Balance  $122,800   Remaining Contingency Balance  $114,946   Percent of Changes  1.0%  (Change Orders + Construction Change Directives vs.  Original Contract)    Project Savings Realized = $491,666  Current Phase:       Occupancy – August 15, 2014    Schedule:  Architect Contract (2)  March 31, 2009  BOE Approval  April 14, 2009    Conceptual Design (2)  September 8, 2009  BOE Approval  September 22, 2009    Schematic Design (2)  June 11, 2013  BOE Approval  June 18, 2013    Submit to DSA  November 25, 2013    Authorize to Bid (2)  March 25, 2014  BOE Approval  April 22, 2014    Approval by DSA  March 27, 2014    Bid Opening  April 29, 2014    Award of Contract (1)  May 20, 2014    Notice to Proceed  May 27, 2014    Substantial Completion  August 11, 2014    Planned Occupancy  August 15, 2014    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 22   Gunn High School  Traffic Signal Replacement  Phase I – Parking and Drop‐off Improvements   A. PROJECT STATUS  Columbia Electric installed the new traffic signal  pole at Arastradero and Miranda Ave. and wiring  has been completed. Concrete sidewalk work was  also done in late July.  Final  landscape  improvements  were  completed  in  August,  and  the first phase of this project is now complete.                B. BUDGET & SCHEDULE SUMMARY                                                C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:   The Miranda Ave. parking and drop‐off was phase one of a multi‐phase project for various parking and  drop off improvements. Future phases will be coordinated with the Central Building project, which will  develop a new drop off area and entry plaza in the main parking lot.     Funding  State Funds  $0  Strong Schools Bond Funds  $3,940,000  Other Funding  $0  Total  $3,940,000    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $919,858  Construction & Equipment  $2,919,840  Soft Costs Contingency  $100,302  Total  $3,940,000    Percent of Budget Expended  47.1%    Change Order Contingency   Starting Contingency Balance  $121,380   Remaining Contingency Balance  $77,492   Percent of Changes  3.6%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase:  Closeout    Schedule:  Architect Contract (2)  March 31, 2009  BOE Approval  April 14, 2009    Conceptual Design (2)  June 19, 2012  BOE Approval  June 26, 2012    Schematic Design (2)  December 18, 2012  BOE Approval  January 15, 2013    Authorize to Bid (2)  June 11, 2013  BOE Approval  June18, 2013    Submit to DSA  July 17, 2013     Approval by DSA  October 2, 2013    Bid Opening  November 12, 2013    Award of Contract (1)  November 19, 2013    Notice to Proceed  December 4, 2013    Substantial Completion  August 15, 2014      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 23   Palo Alto High School   Athletic Stadium Improvements   A. PROJECT STATUS  The  concessions  building,  track  re‐surfacing,  new  ornamental  fence,  signage  and  entry  lighting  were  completed for the Fall 2013 football season.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.13    D. PROJECT OVERVIEW:   The ornamental fence was completed on schedule in August 2013.  The concessions building was  occupied September 10, 2012.  The bleacher replacement work was completed on schedule in June 2013.         Funding  State Funds  $0  Strong Schools Bond Funds  $4,758,036  Other Funding  $0  Total  $4,758,036    Budget  Salaries and Benefits  $882  Supplies  $2,746  Contracts & Services  $818,716  Construction & Equipment  $3,935,692  Soft Costs Contingency  $0  Total  $4,758,036    Percent of Budget Expended  100%    Change Order Contingency   Starting Contingency Balance  $310,200   Remaining Contingency Balance  $364,338   Percent of Changes  ‐1.7%  (Change Orders + Construction Change Directives vs.  Original Contract)    Project Savings Realized = $331,964    Current Phase:  Occupancy – August 1, 2013    Schedule:  Architect Contract (2)  January 26, 2010  BOE Approval  February 9, 2010    Conceptual Design (2)  June 1, 2010  BOE Approval  June 22, 2010    Schematic Design (2)  February 22, 2011  BOE Approval  March 8, 2011    Submit to DSA  April 4, 2011    Authorize to Bid (2)  June 28, 2011  BOE Approval  July 19, 2011    Approval by DSA  July 26, 2011     Bid Opening  December 1, 2011    Award of Contract (1)  December 13, 2011    Notice to Proceed  January 4, 2012    Substantial Completion ‐ Concession  August 31, 2012  Planned Occupancy ‐ Concessions  September 10, 2012  Bleachers  March 31, 2013  Fence Completion  August 1, 2013  * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings Page | 24   Palo Alto High School  Multi‐Use Field  A. PROJECT STATUS  The fields were available for play on February 1, 2011, and  final change order negotiations completed on March 9,  2011.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.14    D. PROJECT OVERVIEW:   Field was open for use on February 1, 2011.       Funding  State Funds  $0  Strong Schools Bond Funds  $2,609,680  Other Funding  $1,007,255  Total  $3,616,935    Budget  Salaries and Benefits  $0  Supplies  $1,506  Contracts & Services  $698,293  Construction & Equipment  $2,916,682  Soft Costs Contingency  $454  Total  $3,616,935     Percent of Budget Expended  100.0%    Change Order Contingency   Starting Contingency Balance  $269,300   Remaining Contingency Balance  $230,579   Percent of Changes  1.5%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase:    Occupancy – February 1, 2011    Schedule:  Architect Contract (2)  September 30, 2008  BOE Approval  October 14, 2008    Conceptual Design (2)  N/A  BOE Approval  N/A    Schematic Design (2)  November 18, 2008  BOE Approval  December 09, 2008    Submit to DSA  March 19, 2009     Approval by DSA  September 30, 2009    Authorize to Bid (2)  February 24, 2009  BOE Approval  March 17, 2009    Bid Opening  March 16, 2010    Award of Contract (1)  April 7, 2010    Notice to Proceed  June 1, 2010    Substantial Completion  January 31, 2011    Planned Occupancy February 1, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 25   Palo Alto High School  Haymarket and Tower Building Improvements     A. PROJECT STATUS   All Trusty Builders completed the installation of the new  windows  on  August  9,  2013,  on  schedule  and  within  budget.      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   The project completed on schedule and within budget.     Funding  State Funds  $0  Strong Schools Bond Funds  $1,260,933  Other Funding  $0  Total  $1,260,933    Budget  Salaries and Benefits  $0  Supplies  $62,844  Contracts & Services  $179,000  Construction & Equipment  $1,019,092  Soft Costs Contingency  $0  Total  $1,260,933    Percent of Budget Expended  100%    Change Order Contingency   Starting Contingency Balance  $39,200   Remaining Contingency Balance  $33,930   Percent of Changes  1.3%  (Change Orders + Construction Change Directives vs.  Original Contract)    Project Savings Realized = $239,067  Current Phase:  Occupancy – August 9, 2013    Schedule:  Architect Contract (2)  N/A  BOE Approval  N/A    Conceptual Design (2)  N/A  BOE Approval  N/A    Schematic Design (2)  N/A  BOE Approval  N/A    Submit to DSA  May 25, 2012    Authorize to Bid (2)  April 24, 2012  BOE Approval  May 6, 2012    Approval by DSA  August 24, 2012    Bid Opening  January 17, 2013    Award of Contract (1)  January 29, 2013    Notice to Proceed  February 21, 2013    Substantial Completion  August 9, 2013      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 26   Palo Alto High School   Classroom Building and Media Arts   A. PROJECT STATUS   Move in and occupancy of both buildings occurred in July  2014.    Taisei  has  completed  their  work,  and  contract  closeout is complete.                              B. BUDGET & SCHEDULE SUMMARY                                                C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   Furniture installation and occupancy of the Media Arts and Math/Social Sciences buildings completed.      Funding  State Funds  $0  Strong Schools Bond Funds  $36,938,515  Other Funding  $0  Total  $36,938,515    Budget  Salaries and Benefits  $18,448  Supplies  $1,325,333  Contracts & Services  $6,261,915  Construction & Equipment  $29,236,995  Soft Costs Contingency  $95,826  Total  $38,415,001    Percent of Budget Expended  99.68%    Change Order Contingency   Starting Contingency Balance  $2,515,000   Remaining Contingency Balance  $34,288   Percent of Changes * 9.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  * Does not include $570,000 settlement agreement with  Taisei for release of any and all claims    Project Savings Realized = $1,476,486  Current Phase:  Occupancy – August 1, 2014     Schedule:  Architect Contract (2)  March 31, 2009  BOE Approval  April 14, 2009    Conceptual Design (2)  September 8, 2009  BOE Approval  September 22, 2009    Schematic Design (2)  January 12, 2010  BOE Approval  January 26, 2010    Submit to DSA  August 4, 2010    Authorize to Bid (2)  March 8, 2011  BOE Approval  March 22, 2011    Approval by DSA  April 28, 2011    Bid Opening  June 30, 2011    Award of Contract (1)  July 12, 2011    Notice to Proceed  August 4, 2011    Substantial Completion  April 15, 2014    Planned Occupancy August 1, 2014    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 27   Palo Alto High School  Performing Arts Center (PAC)  A. PROJECT STATUS  Students and staff occupied the new building in July, and  Students and staff occupied the new building in July, and  DSA closeout was completed in September 2016.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.11    D. PROJECT OVERVIEW:   Occupancy occurred during summer 2016.   Funding  State Funds  $0  Strong Schools Bond Funds  $29,370,049  Other Funding  $0  Total  $29,370,049    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $4,377,871  Construction & Equipment  $24,845,000  Soft Costs Contingency  $147,178  Total  $29,370,049    Percent of Budget Expended  98.58%    Change Order Contingency   Starting Contingency Balance  $2,184,400   Remaining Contingency Balance  $1,065,582  Percent of Changes  5.12%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy – July 1, 2016   Schedule:  Architect Contract (2)  March 31, 2009  BOE Approval  April 14, 2009    Conceptual Design (2)  June 1, 2010  BOE Approval  June 22, 2010    Schematic Design (3)  June 14, 2011  BOE Approval  December 13, 2011  BOE Approval  January 17, 2012    Submit to DSA  March 28, 2013    Approval by DSA  January 16, 2014    Authorize to Bid (2)  January 14, 2014  BOE Approval  January 28, 2014    Bid Opening  May 13, 2014    Award of Contract (1)  June 3, 2014    Notice to Proceed  June 23, 2014    Substantial Completion  May 5, 2016    Planned Occupancy  July 1, 2016     ( ) Denotes number of Board of Education Readings  Page | 28   Palo Alto High School  Indoor PE and Athletic Facilities     A. PROJECT STATUS     The new facility was occupied for the fall quarter of  2017.  Some  remaining furnishing  items  and  equipment remain to be installed, and new gates will  be installed by Vance Brown for the pool in October.  DSA closeout will be completed by November 17th.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:   Project is complete, and was occupied in August 2017.   Funding  State Funds  $0  Strong Schools Bond Funds  $17,671,555  Other Funding (Deseret Trust Co.)  $23,443,720  Total  $41,671,555    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $2,991,039  Construction & Equipment  $38,500,516  Soft Costs Contingency  $180,000  Total  $41,671,555    Percent of Budget Expended *  95.93%  (Above % of budget expended is against bond funds of  $17,671,555)    Change Order Contingency   Starting Contingency Balance  $1,822,167   Remaining Contingency Balance  $78,672   Percent of Changes  4.78%  (Change Orders + Construction Change Directives.  Original Contract)    Current Phase:   Closeout    Schedule:  Architect Contract (2)  N/A  BOE Approval  N/A    Conceptual Design (2)  March 12, 2013  BOE Approval  March 19, 2013    Schematic Design (2)  September 10, 2013  BOE Approval  October 8, 2013    Submit to DSA  December 4, 2013  Re‐Submit to DSA  January 27, 2014    Approval by DSA  September 22, 2014    Lease Leaseback Agreement (1)  May 26, 2015  Award of LLB Contract (1)  June 23, 2015    Notice to Proceed  August 1, 2015    Substantial Completion  May 7, 2017    Occupancy  July 21, 2017*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 29   Jordan Middle School   Classroom Wing, Cafetorium and   Campus Improvements  A. PROJECT STATUS  Students occupied all new and modernized buildings for  the start of school in fall 2013.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5    D. PROJECT OVERVIEW:   The project was completed on schedule and within budget.     Funding  State Funds  $0  Strong Schools Bond Funds  $19,109,345  Other Funding  $0  Total  $19,109,345      Budget  Salaries and Benefits  $6,111  Supplies  $86,265  Contracts & Services  $3,723,370  Construction & Equipment  $15,224,812  Soft Costs Contingency  $68,787  Total  $19,109,345    Percent of Budget Expended  99.2%    Change Order Contingency   Starting Contingency Balance  $1,398,700   Remaining Contingency Balance  $202,769   Percent of Changes  8.6%  (Change Orders + Construction Change Directives vs.  Original Contract)    Project Savings Realized = $782,219  Current Phase:  Close‐out / Occupancy – August 15, 2013    Schedule:  Architect Contract (2)  October 28, 2008  BOE Approval  October 30, 2008    Conceptual Design (2)  June 23, 2009  BOE Approval  September 8, 2009    Schematic Design (2)  March 23, 2010  BOE Approval  April 27, 2010    Submit to DSA  December 21, 2010     Authorize to Bid (2)  June 28, 2011  BOE Approval  July 19, 2011    Approval by DSA  October 5, 2011    Bid Opening  December 8, 2011    Award of Contract (1)  December 13, 2011    Notice to Proceed  December 27, 2011    Substantial Completion  August 1, 2013    Planned Occupancy  August 15, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 30   Jordan Middle School  Interim Classrooms  A. PROJECT STATUS  The portables were installed and moved into for fall 2011.  DSA closeout received November 19, 2012.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:   This project completed ahead of schedule and under budget.   Move in occurred on September 30, 2011.         Funding  State Funds  $0  Strong Schools Bond Funds  $379,811  Other Funding  $208,222  Total  $488,033      Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $180,286  Construction & Equipment  $306,983  Soft Costs Contingency  $764  Total  $488,033    Percent of Budget Expended  100%      Current Phase:    Move‐in    Schedule:  Approval by DSA  June 16, 2011    Authorize to Bid (2)  June 14, 2011  BOE Approval  June 28, 2011    Bid Opening  July 14, 2011    Award of Contract (1)  July 20, 2011    Notice to Proceed  July 27, 2011    Substantial Completion  September 20, 2011    Occupancy  September 30, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 31   J.L. Stanford Middle School Classroom Wing and Campus Improvements  A. PROJECT STATUS   Students occupied all new and modernized buildings for  the start of school in fall 2013.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:   The project completed on schedule and within budget.       Funding  State Funds  $0  Strong Schools Bond Funds  $15,670,127  Other Funding  $0  Total  $15,670,127    Budget  Salaries and Benefits  $8,879  Supplies  $144,790  Contracts & Services  $3,545,843  Construction & Equipment  $11,970,665  Soft Costs Contingency  $0  Total  $15,670,127    Percent of Budget Expended  99.1%    Change Order Contingency   Starting Contingency Balance  $1,057,800   Remaining Contingency Balance  $911,677   Percent of Changes  1.4%  (Change Orders + Construction Change Directives vs.  Original Contract)    Project Savings Realized = $1,514,522  Current Phase:  Close‐out / Occupancy – August 15, 2013    Schedule:  Architect Contract (2)  October 28, 2008  BOE Approval  October 30, 2008    Conceptual Design (2)  June 23, 2009  BOE Approval  September 8, 2009    Schematic Design (3)  June 1, 2010  BOE Approval  June 22, 2010  BOE Approval (Sitework)  September 28, 2010    Submit to DSA  May 6, 2011     Authorize to Bid (2)  November 29, 2011  BOE Approval  December 13, 2011    Approval by DSA  January 24, 2012    Bid Opening  May 3, 2012    Award of Contract (1)  May 8, 2012    Notice to Proceed  May 30, 2012    Substantial Completion  August 7, 2013    Planned Occupancy  August 15, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 32   J.L. Stanford Middle School   Landscape and Site Improvements    A. PROJECT STATUS   Scapes completed the project on schedule in the fall 2013.                              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:   The project completed on schedule and within budget.       Funding and Budget  This project is funded by the J.L. Stanford Middle School  project budget.  See that project budget for status.    Percent of Budget Expended  100%    Change Order Contingency   Starting Contingency Balance  $1,057,800   Remaining Contingency Balance  $902,445   Percent of Changes  2.8%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase:  Close‐out / Occupancy – August 16, 2013   Schedule:  Architect Contract (2)  October 28, 2008  BOE Approval  October 30, 2008    Conceptual Design (2)  June 23, 2009  BOE Approval  September 8, 2009    Schematic Design (3)  June 1, 2010  BOE Approval  June 22, 2010  BOE Approval (Sitework)  September 28, 2010    Submit to DSA  May 6, 2011     Authorize to Bid (2)  November 29, 2011  BOE Approval  December 13, 2011    Approval by DSA  January 24, 2012    Bid Opening  May 3, 2013    Award of Contract (1)  May 8, 2013    Notice to Proceed  May 23, 2013    Substantial Completion  August 16, 2013    Completion  August 16, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 33   J.L. Stanford Middle School    Interim Classrooms  A. PROJECT STATUS  Coulter  Construction  completed  the  work  on  the  relocated portables in August 2011.                            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:   Project completed on schedule and is currently in close‐out.             This portable relocation project funded by main  JLS project.  Refer to pg. 14    Current Phase: Occupancy ‐ August 11, 2011   Schedule:  Approval by DSA  April 19, 2011  Jordan Project  June 16, 2011     Authorize to Bid (2)  May 10, 2011  BOE Approval  May 24, 2011    Bid Opening  June 1, 2011    Award of Contract (1)  June 13, 2011    Notice to Proceed  June 20, 2011    Substantial Completion  August 8, 2011    Planned Occupancy  August 15, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 34   Terman Middle School   Library Addition and Campus Improvements  A. PROJECT STATUS  Students  occupied  the  new  instructional  spaces  and  modernized buildings for the start of school in fall 2013.  The  cafetorium modernization was completed in October 2013.        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12    D. PROJECT OVERVIEW:   The project completed on schedule in August 2013, except for the Cafetorium, which was completed in  November 2013.  The project has been completed within budget.     Funding  State Funds  $0  Strong Schools Bond Funds  $13,051,487  Other Funding  $0  Total  $13,051,487      Budget  Salaries and Benefits  $4,153  Supplies  $75,747  Contracts & Services  $2,720,590  Construction & Equipment  $10,246,249  Soft Costs Contingency  $4,748  Total  $13,051,487    Percent of Budget Expended  99.6%    Change Order Contingency   Starting Contingency Balance  $929,900   Remaining Contingency Balance  $12,909   Percent of Changes  9.4%  (Change Orders + Construction Change Directives vs.  Original Contract)    Project Savings Realized = $261,484  Current Phase:  Close‐out / Occupancy – November 15, 2013   Schedule:  Architect Contract (2)  October 28, 2008  BOE Approval  October 30, 2008    Conceptual Design (2)  June 23, 2009  BOE Approval  September 8, 2009    Schematic Design (2)  May 11, 2010  BOE Approval  May 25, 2010    Submit to DSA  December 21, 2010    Authorize to Bid (2)  June 28, 2011  BOE Approval  July 19, 2011    Approval by DSA  September 1, 2011    Bid Opening  December 6, 2011    Award of Contract (1)  December 13, 2011    Notice to Proceed  December 27, 2011    Substantial Completion  October 31, 2013    Planned Occupancy  November 15, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 35   Duveneck Elementary School   New Classroom Buildings and Modernization  A. PROJECT STATUS   The fence around the sod for the field area to establish  growth was removed on September 19, 2014.  All buildings  were substantially complete and occupied on August 11,  2014.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   The project has been completed within budget, and was occupied on August 5, 2014.        Funding  State Funds  $0  Strong Schools Bond Funds  $9,277,534  Other Funding  $0  Total  $9,277,534    Budget  Salaries and Benefits  $20,313  Supplies  $0  Contracts & Services  $2,098,650  Construction & Equipment  $7,154,178  Soft Costs Contingency  $4,393  Total  $9,277,534    Percent of Budget Expended  100%    Change Order Contingency   Starting Contingency Balance  $703 ,772   Remaining Contingency Balance  $304,029   Percent of Changes  5.7%  (Change Orders + Construction Change Directives vs.  Original Contract)    Realized Project Savings = $500,824  Current Phase:  Close‐out/Occupancy – August 5, 2014    Schedule:  Architect Contract (2)  April 27, 2010  BOE Approval  May 11, 2010    Conceptual Design (2)  December 14, 2010  BOE Approval  January 11, 2011    Schematic Design (2)  June 14, 2011  BOE Approval  June 28, 2011    Submit to DSA  February 27, 2012     Approval by DSA  December 10, 2012    Authorize to Bid (2)  December 18 2012  BOE Approval  January 15, 2013    Bid Opening  February 28, 2013    Award of Contract (1)  March 12, 2013    Notice to Proceed  March 25, 2013    Substantial Completion  July 31, 2014    Planned Occupancy August 5, 2014    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 36   Fairmeadow Elementary School   New Classroom Building and Modernization   A. PROJECT STATUS  Students occupied all new and modernized buildings for  the start of school in fall 2013.      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   The project completed on schedule and within budget.     Funding  State Funds  $0  Strong Schools Bond Funds  $7,656,720  Other Funding  $0  Total  $7,656,720    Budget  Salaries and Benefits  $32,377  Supplies  $98,962  Contracts & Services  $1,992,932  Construction & Equipment  $5,531,329  Soft Costs Contingency  $1,120  Total  $7,656,720    Percent of Budget Expended  100%    Change Order Contingency   Starting Contingency Balance  $642 ,300   Remaining Contingency Balance  $186,122   Percent of Changes  7.1%  (Change Orders + Construction Change Directives vs.  Original Contract)    Realized Project Savings = $139,830  Current Phase: Close‐out / Occupancy – August 15, 2013    Schedule:  Architect Contract (2)  October 13, 2009  BOE Approval  October 27, 2009    Conceptual Design (2)  March 23, 2010  BOE Approval  April 6, 2010    Schematic Design (2)  September 14, 2010  BOE Approval  September 28, 2010    Submit to DSA  April 18, 2011     Authorize to Bid (2)  October 11, 2011  BOE Approval  October 25, 2011    Approval by DSA  November 14, 2011    Bid Opening  December 5, 2011    Award of Contract (1)  December 13, 2011    Notice to Proceed  January 3, 2012    Substantial Completion  August 5, 2013    Planned Occupancy  August 15, 2013    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 37   Fairmeadow Elementary School  Portable Relocation Project  A. PROJECT STATUS   Relocation of the portable was complete and occupied on August 8, 2011.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 6.4    D. PROJECT OVERVIEW:   Project completed ahead of schedule on August 8, 2011.              This portable relocation project funded by main  JLS project.  Refer to pg. 14  Current Phase:    Occupancy ‐ August 8, 2011    Schedule:  Architect Contract (2)  February 15, 2011  BOE Approval  N/A    Conceptual Design (2)  N/A  BOE Approval  N/A    Schematic Design (2)  N/A  BOE Approval  N/A    Submit to DSA  March 3, 2011     Approval by DSA  March 3, 2011    Authorize to Bid (2)  May 11, 2011  BOE Approval  May 24, 2011    Bid Opening  June 14, 2011    Award of Contract (1)  June 14, 2011    Notice to Proceed  June 20, 2011    Substantial Completion  August 1, 2011    Planned Occupancy August 8, 2011    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 38   Ohlone Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS   Move‐in to the new building and other existing classrooms  occurred in December 2011.  Students occupied the new  building on January 3, 2012.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   Occupancy occurred on January 3, 2012.  Project completed on schedule and within budget.     Funding  State Funds  $0  Strong Schools Bond Funds  $10,556,389  Other Funding  $0  Total  $10,556,389      Budget  Salaries and Benefits  $7,461  Supplies  $49,049  Contracts & Services  $2,180,418  Construction & Equipment  $8,319,461  Soft Costs Contingency  $62,598  Total  $10,556,389    Percent of Budget Expended  100%    Change Order Contingency   Starting Contingency Balance  $748,400   Remaining Contingency Balance  $459,113   Percent of Changes  3.9%  (Change Orders + Construction Change Directives vs.  Original Contract)    Realized Project Savings = $41,481  Current Phase:  Occupancy – January 3, 2012   Schedule:  Architect Contract (2)  September 30, 2008  BOE Approval  October 14, 2008    Conceptual Design (2)  March 3, 2009  BOE Approval  March 17, 2009    Schematic Design (2)  June 2, 2009  BOE Approval  June 23, 2009    Submit to DSA  November 24, 2009    Authorize to Bid (2)  April 27, 2010  BOE Approval  May 11, 2010    Approval by DSA  May 18, 2010    Bid Opening  July 13, 2010    Award of Contract (1)  August 3, 2010    Notice to Proceed  August 19, 2010    Substantial Completion  November 18, 2011    Planned Occupancy  January 3, 2012    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 39   Elementary Classroom Improvements  Interactive Whiteboards and Sound Assist System Installation  A. PROJECT STATUS  Installation of SmartBoards and Lightspeed sound assist  systems  were  completed  for  all  elementary  school  classrooms and libraries in April 2011.                          B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:   All SmartBoards and Lightspeed sound systems installed.       Funding  State Funds  $0  Strong Schools Bond Funds  $1,879,695  Other Funding  $0  Total  $1,879,695    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $275,488  Construction & Equipment  $1,604,207  Soft Costs Contingency  $0  Total  $1,879,695    Percent of Budget Expended  100%    Current Phase:  Complete ‐ May 15, 2011    Schedule:  Architect Contract (2)  N/A  BOE Approval  N/A    Conceptual Design (2)  N/A  BOE Approval  N/A    Schematic Design (2)  N/A  BOE Approval  N/A    Submit to DSA  N/A     Approval by DSA  N/A    Authorize to Bid (2)  November 9, 2010  BOE Approval  November 23, 2010    Bid Opening  February 25, 2011    Award of Contract (1)  March 8, 2011    Notice to Proceed  March 9, 2011    Completion  May 15, 2011      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 40   Site Acquisition  525 San Antonio Rd   A. PROJECT STATUS  This site has been leased to Athena Academy.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:   The site has been leased to Athena Academy.         Funding  State Funds  $0  Strong Schools Bond Funds  $8,500,000  Other Funding  $0  Total  $8,500,000    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $8,500,000  Construction & Equipment  $0  Soft Costs Contingency  $0  Total  $8,500,000    Percent of Budget Expended  100%  Current Phase:    N/A    Schedule:  Architect Contract (2)  N/A  BOE Approval  N/A    Conceptual Design (2)  N/A  BOE Approval  N/A    Schematic Design (2)  N/A  BOE Approval  N/A    Submit to DSA  N/A     Approval by DSA  N/A    Authorize to Bid (2)  N/A  BOE Approval  N/A    Bid Opening  N/A    Award of Contract (1)  N/A    Notice to Proceed  N/A    Substantial Completion  N/A    Planned Occupancy  N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 41   Middle School Pre‐Design  Jordan, J.L. Stanford and Terman  A. PROJECT STATUS  AEDIS presented recommended concept plans for each campus  to the Board of Education for approval on September 8, which  became the program documents for the new projects at each  campus.  These projects for pre‐design work have been closed,  and funds will be transferred to the program contingency on  June 14, 2011.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12    D. PROJECT OVERVIEW:   This project has been completed. Board approval received on September 8, 2009. Funding  State Funds  $0  Strong Schools Bond Funds  $54,658  Other Funding  $0  Total  $54,658      Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $54,658  Construction & Equipment  $0  Soft Costs Contingency  $0  Total  $54,658    Percent of Budget Expended  100%    Current Phase:    Complete    Schedule:  Architect Contract (2)  October 28, 2008  BOE Approval  October 30, 2008    Conceptual Design (2)  June 23, 2009  BOE Approval  September 8, 2009    Schematic Design (2)  N/A  BOE Approval  N/A    Submit to DSA  N/A     Approval by DSA  N/A    Authorize to Bid (2)  N/A  BOE Approval  N/A    Bid Opening  N/A    Award of Contract (1)  N/A    Notice to Proceed  N/A    Substantial Completion  N/A    Planned Occupancy  N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 42   Technology Improvements   A. PROJECT STATUS   Equipment orders have arrived and were deployed to the various campuses for  use during the 2014/15 school year.            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:   Equipment has been installed for the 2014/15 school year.       Funding  State Funds  $0  Strong Schools Bond Funds  $10,485,054  Other Funding  $0  Total  $10,485,054    Budget  Salaries and Benefits  $0  Supplies & Computers  $6,850,644  Contracts & Services  $539,269  Construction & Equipment  $3,095,142  Soft Costs Contingency  $0  Total  $10,485,054    Percent of Budget Expended  92.2%    Current Phase:    N/A    Schedule:  Architect Contract (2)  N/A  BOE Approval  N/A    Conceptual Design (2)  N/A  BOE Approval  N/A    Schematic Design (2)  N/A  BOE Approval  N/A    Submit to DSA  N/A     Approval by DSA  N/A    Authorize to Bid (2)  N/A  BOE Approval  N/A    Bid Opening  N/A    Award of Contract (1)  N/A    Notice to Proceed  N/A    Substantial Completion  N/A    Planned Occupancy  N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 43   Garland Elementary School  Campus Modernization  A. PROJECT STATUS  The Board of Education has put new development for  Garland on hold until a growth plan is established for the  elementary schools.  The board voted to terminate the  lease with Stratford School in June 2011. Discussions with  the Board on future plans for growth at the elementary  schools are ongoing.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10    D. PROJECT OVERVIEW:   This project has been placed on hold. Funding  State Funds  $0  Strong Schools Bond Funds  $22,178,544  Other Funding  $0  Total  $22,178,544    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $3,915,789  Construction & Equipment  $17,400,000  Soft Costs Contingency  $862,755  Total  $22,178,544    Percent of Budget Expended  1.3%  Current Phase:    On Hold    Schedule:  Architect Contract (2)  October 28, 2008  BOE Approval  October 30, 2008    Conceptual Design (2)  February 10, 2009  BOE Approval  February 24, 2009    Schematic Design (2)  June 2, 2009  BOE Approval  June 23, 2009    Submit to DSA  N/A     Approval by DSA  N/A    Authorize to Bid (2)  N/A  BOE Approval  N/A    Bid Opening  N/A    Award of Contract (1)  N/A    Notice to Proceed  N/A    Substantial Completion  N/A    Planned Occupancy  N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 44   High School Master Plan  Palo Alto HS and Gunn HS  A. PROJECT STATUS  The Board of Education (BOE) approved the master  plans for both high schools, and these projects have  been  closed,  with  funds  transferred  to  the  respective campus reserve funds.                    B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14    D. PROJECT OVERVIEW:   Master planning effort complete.                Funding  State Funds  $0  Strong Schools Bond Funds  $285,387  Other Funding  $0  Total  $285,387    Budget  Salaries and Benefits  $0  Supplies  $0  Contracts & Services  $285,387  Construction & Equipment  $0  Soft Costs Contingency  $0  Total  $285,387    Percent of Budget Expended  86.2%  Current Phase:    Complete    Schedule:  Architect Contract (2)  March 31, 2009  BOE Approval  April 14, 2009    Initial Master Plan Approval (2)  September 8, 2009  BOE Approval  September 22, 2009    Paly CEQA Approval (2)  February 9, 2010  BOE Approval  February 23, 2010    Gunn Master Plan Update (2)  March 23, 2010  BOE Approval  April 6, 2010    Gunn CEQA Approval (2)  April 27, 2010   BOE Approval  May 11, 2010     Master Plan Revision Approval (2)  September 14, 2010  Paly MP Revision Approval (2)  October 9, 2010  Gunn MP Revision Approval (2)  October 12, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings