Monthly Reports 2017-03 (Mar)
Page | 1
MONTHLY PROGRESS REPORT
Through
March 2017
Strong Schools Bond
Capital Improvement Projects
Prepared by
fs3|Hodges
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Capital Projects
Gunn High School – Central Building Project page 7
Palo Alto High School – Science Building Addition page 8
Palo Alto High School – Indoor PE and Athletic Facilities page 9
Palo Alto High School – Building 500 Renovation page 10
Addison Elementary School – New Library, Administration and Multipurpose Building page 11
El Carmelo Elementary School – New Multipurpose Building page 12
Escondido Elementary School – New Multipurpose Building page 13
Hays Elementary School – New Multipurpose Building page 14
Hoover Elementary School – New Library, Administration and Multipurpose Building page 15
Completed Capital Projects
Gunn High School – New Classroom Building and World Languages Building page 16
Gunn High School – New Gymnasium page 17
Gunn High School – Existing Gymnasium Modernization page 18
Gunn High School – E and K (L31 and MS) Buildings Renovation page 19
Gunn High School – Traffic Signal Replacement (Phase I‐ Improvements) page 20
Palo Alto High School – Athletic Stadium Improvements page 21
Palo Alto High School – Haymarket and Tower Building Improvements page 22
Palo Alto High School – New Classroom Building and Media Arts page 23
Palo Alto High School – Performing Arts Center page 24
Jordan Middle School page 25
J.L. Stanford Middle School page 26
J.L. Stanford Middle School – Landscape and Site Improvements page 27
Terman Middle School page 28
Duveneck Elementary School – New Classroom Buildings and Modernization page 29
Fairmeadow Elementary School – New Classroom Buildings and Modernization page 30
Ohlone Elementary School page 31
Property Acquisition – 525 San Antonio Rd page 32
Jordan Middle School – Interim Classrooms page 33
Gunn High School – Air Conditioning of Existing Buildings page 34
J.L. Stanford Middle School – Interim Classrooms page 35
Fairmeadow Elementary School – Portable Relocation page 36
Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 37
Palo Alto High School – Multi‐use Field page 38
Gunn High School – Industrial Arts Renovation page 39
Gunn High School – Aquatic Center page 40
Middle School Pre‐Design page 41
Technology page 42
Inactive Capital Projects
Garland Elementary School page 43
High School Master Plan page 44
Page | 3
EXECUTIVE SUMMARY
CURRENT CAPITAL PROJECTS
Gunn High School – Central Building Project
Project bids were received on March 21st, with Alten Construction being the successful low bidder. The Board
awarded a contract on March 28th. Alten is in the process of executing the agreement and getting bonds and
insurance in place. The pre‐construction meeting and notice to proceed is anticipated to be issued in mid‐April, with
mobilization and hazardous materials abatement work beginning in May.
Palo Alto High School – Science Building Addition
DLM continued work on construction documents, and plans to submit to DSA for review in May.
Palo Alto High School – Indoor PE and Athletic Facilities
The Main Gym wood floor is complete. Wall finishes, casework and countertops, AV equipment and MEP finish work
is also ongoing. Locker installation will begin in April. The Small Gym, Dance Studio and Wrestling room flooring is
finished, and mirrors, ceilings and specialties installation is in progress. Site work has commenced, with AC paving
along the north and east sides complete. Work continues on the pavers in the plaza area, along with added work
around the pool and south end of the building.
Palo Alto High School – Building 500 Renovation (Library)
DLM/HED received DSA approval this month, and the project is now out to bid. The bid date is May 2, and Board
approval is scheduled for May 9. This project is scheduled to be awarded in May, but will not begin construction
until August 1, 2017. Renovation of the 700 and 200 buildings is also being bid, which will occur in June and July to
allow building occupants to move into their interim spaces.
Addison Elementary School – (Donor Funded Project)
Gelfand Partners completed a Design Development package and estimate for review in March, and are on track to
submit plans to DSA for review in July 2017. The project estimates are over budget, so discussions will take place on
how to bring the project back within budget. Several meetings have taken place regarding exterior play areas, and
the potential for incorporating specialized play areas along Middlefield and Webster.
El Carmelo Elementary School – New MP Building
The Board approved beginning work on conceptual design for planning a new MP building for El Carmelo in January.
Gelfand Partners held two meetings with the El Carmelo Advisory committee in March, and will hold their 3rd
meeting in early April. Staff hopes to bring a recommendation to the Board for approval in June 2017.
Escondido Elementary School – New MP Building
The Board approved beginning work on conceptual design for planning a new MP building for Escondido in January.
Gelfand Partners held a kick off meeting with the Escondido Advisory committee, and will hold their 2nd meeting in
April 12th. Staff hopes to bring a recommendation to the Board for approval in June 2017.
Hays Elementary School – New MP Building
The Board approved beginning work on conceptual design for planning a new MP building for Hays in January.
Gelfand Partners held a kick off meeting with the Hays Advisory committee, and will hold their 3rd meeting in early
April. Staff hopes to bring a recommendation to the Board for approval in June 2017.
Hoover Elementary School
Gelfand continued meetings with the Hoover Advisory committee this month to discuss the placement of the MP,
Library, and flex rooms. A slight modification has been made to the MP room orientation and the location of the 2nd
flex room. Gelfand is working on their schematic design drawings for estimating by May 1. The schematic design
presentation to the board is now scheduled to occur during the June 6th meeting.
Page | 4
COMPLETED CAPITAL PROJECTS
Gunn High School – New Classroom Building and World Languages Building
The new Math and English Building was occupied by staff and students on August 15, 2013. World Language Building
classrooms were occupied in February, 2013.
Gunn High School – New Gymnasium
The new gymnasium was occupied on June 7, 2013 and PE classes were held in the new gym on August 15, 2013.
The tennis courts were completed August 27, 2013.
Gunn High School – Existing Gymnasium Modernization
The modernized Bow gym was occupied by the campus on November 4, 2013.
Gunn High School – E and K (L‐31 and MS) Buildings Renovation
Students occupied E and K buildings on August 13, 2014, and building E was occupied on September 15, 2014.
Gunn High School –Traffic Signal Replacement (Phase I ‐ Parking and Drop‐Off Improvements)
Columbia Electric installed the new traffic signal pole at Arastradero and Miranda Ave. and wiring has been
completed. Concrete sidewalk work was also done in late July. Final landscape improvements were completed in
August, and the first phase of this project is now complete.
Palo Alto High School – Athletics Stadium Improvements
The concessions building, track re‐surfacing, new ornamental fence, signage and entry lighting were completed for
the 2013 football season.
Palo Alto High School – Haymarket and Tower Building Improvements
All Trusty Builders completed the installation of the new windows on August 9, 2013.
Palo Alto High School – New Math/Social Sciences Building and Media Arts Building
Move in and occupancy of both buildings occurred in July 2014. Taisei has completed their work, and contract
closeout is complete, with DSA closeout in progress.
Palo Alto High School – Performing Arts Center (PAC)
Students and staff occupied the new building in July, and DSA closeout was completed in September. Additional
audio‐visual equipment, drapes and production lighting, and furniture installation was completed in September, in
preparation for the Opening Night Gala on October 1.
Jordan Middle School
Students occupied all new and modernized buildings in fall 2013.
J.L. Stanford Middle School
Students occupied all new and modernized buildings in fall 2013.
J.L. Stanford Middle School – Landscape and Sitework Improvements
Scapes completed the project on schedule in the fall 2013.
Page | 5
Terman Middle School
Students occupied the new instructional spaces and modernized buildings in fall 2013. The cafetorium
modernization was completed in October 2013.
Duveneck Elementary School – New Classroom Buildings and Modernization
All buildings were substantially complete and occupied on August 11, 2014.
Fairmeadow Elementary School – New Classroom Building and Modernization
Students occupied all new and modernized buildings in fall 2013.
525 San Antonio Road – Site Acquisition
This site has been leased to Athena Academy.
Ohlone Elementary School – New Classroom Building and Modernization
Students occupied the new building on January 3, 2012.
Jordan Middle School ‐ Interim Classrooms
The portables were installed and moved into for fall 2011. DSA closeout received November 19, 2012.
Gunn High School – Air Conditioning of Existing Buildings
Best Contracting Services Inc. completed the installation of air conditioning units and roofing in the summer 2011.
J.L. Stanford Middle School ‐ Interim Classrooms
Coulter Construction completed the work on the relocated portables in August 2011.
Fairmeadow Elementary School – Portable Relocation
Relocation of the portable was complete and occupied on August 8, 2011.
Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems
Installation of SmartBoards and Lightspeed sound assist systems were completed for all elementary school
classrooms and libraries in April 2011.
Palo Alto High School – Multi‐use Field
The fields were available for play on February 1, 2011, and the project was completed on March 9, 2011.
Gunn High School – Industrial Arts Addition & Renovation
This facility was available for instruction in January 2010. DSA closeout received on July 18, 2011.
Gunn High School – Aquatic Center
This facility was available for use in July 2009, and has been closed out with DSA.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
These projects for pre‐design work have been closed.
Technology
Equipment orders have arrived and were deployed to the various campuses for use during the 2014/15 school year.
Page | 6
INACTIVE CAPITAL PROJECTS
Garland Elementary School Renovation
The Board of Education has put new development for Garland on hold until a growth plan is established for the
elementary schools.
High School Master Plan
The Board of Education (BOE) approved the master plans for both high schools, and these projects have been closed.
Board Items in March
March 14, 2017:
Consent 3.G: Bond Citizens' Oversight Committee (COC) Replacement Member
Consent 3.I: Approval to Award Contracts for Special Testing and Inspection, Inspection of Record (IOR), and
Construction Management Services for Gunn High School Central Building Project
March 28, 2017:
Action 5.F: Authorization to Award a Contract for Construction of the Central Building Project at Gunn High
School
Discussion 5.G: Authorizations for Palo Alto High School: (1) To Bid Building 700 Renovation and (2) To
Purchase Faculty Office Furniture and Equipment
A B C C / A B - C C / B A - B
Measure A Fund
Gunn High School - High School Master Plan 172,390 166,328 147,706 86% 18,622 88.80% 6,062
Gunn High School 1 - Aquatic Center 4,862,530 4,862,530 4,862,530 100% 0 100.00% 0
Gunn High School 2 - I.A Building 5,065,128 5,065,128 5,065,128 100% 0 100.00% 0
Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100% 0 100.00% 0
Gunn High School 4 - New classroom Buildings 24,808,489 24,776,633 24,776,633 100% 0 100.00% 31,856
Gunn High School 5 - Parking & Drop Off improvements 3,939,998 2,085,755 1,855,723 47% 230,032 88.97% 1,854,243
Gunn High School 6- New/Auxiliary Gymnasium 12,450,948 12,440,998 12,440,998 100% 0 100.00% 9,950
Gunn High School 7- A/C 2,092,366 2,092,366 2,092,366 100% 0 100.00% 0
Gunn High School 8 - MS & L-31 Buildings 1,629,176 1,623,174 1,623,174 100% 0 100.00% 6,002
Gunn High School 9 - Central building 24,887,216 4,294,591 2,222,194 9% 2,072,397 51.74% 20,592,625
Gunn High School - Reserved 3,390,796 0 0 0% 0 0.00% 3,390,796
Palo Alto High Schools - High School Master Plan 172,999 167,759 161,616 93% 6,143 96.34% 5,240
Palo Alto High School 1 - Stadium Field 4,758,037 4,758,037 4,758,037 100% 0 100.00% 0
Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,609,680 100% 0 100.00% 0
Palo Alto high School 3 - New classroom & Media Art Building 36,938,516 36,824,295 36,824,295 100% 0 100.00% 114,221
Palo Alto High School 4 - New Theater 29,370,049 28,805,603 26,941,485 92% 1,864,118 93.53% 564,446
Palo Alto High School 5 - Haymarket and Tower Admin. Building 1,260,933 1,260,933 1,260,933 100% 0 100.00% 0
Palo Alto High School 6- Science Addition 5,532,205 929,614 633,002 11% 296,612 68.09% 4,602,591
Paly 7- Paly Athletic Center (Two Funds) 17,671,556 17,276,842 15,592,419 88% 1,684,423 90.25% 394,714
Paly 8-Library 10,394,140 1,087,740 710,079 7% 377,661 65.28% 9,306,400
Palo Alto High School - Reserved 3,000,000 0 0 0% 0 0.00% 3,000,000
Jordan Middle School -Program Management- MS Pre-Design 17,826 17,826 17,826 100% 0 100.00% 0
Jordan Middle Schools 1- Interim Classrooms 488,033 488,033 488,033 100% 0 100.00% 0
Jordan Middle School 2- Improvements 19,109,345 18,947,062 18,947,062 99% 0 100.00% 162,283
Jordan Middle School - Reserved 0 0 0 0% 0 0.00% 0
J.L.S Middle School - Program Management- MS Pre-Design 18,408 18,408 18,408 100% 0 100.00% 0
J.L.S Middle School 1 - Interim Classrooms 422,500 422,500 422,500 100% 0 100.00% 0
J.L.S Middle School 2- Improvements 15,670,128 15,535,784 15,535,784 99% 0 100.00% 134,344
J.L.S Middle School - Reserved 0 0 0 0% 0 0.00% 0
Terman Middle School - Program Management- MS Pre-Design 18,423 18,423 18,423 100% 0 100.00% 0
Terman Middle School 1- Improvements 13,051,488 13,003,128 13,003,128 100% 0 100.00% 48,360
Terman Middle School - Reserved 0 0 0 0% 0 0.00% 0
PAUSD Elementary Schools - Program Management- Elem. Growth Plan 308,000 93,480 87,290 28% 6,190 93.38% 214,520
Addison Elementary School 1-Phase I 21,267 21,267 21,267 100% 0 100.00% 0
El Carmelo Multi-Use Building 77,000 26,300 643 1% 25,657 2.44% 50,700
Escondido Multi-Use Building 73,000 22,100 1,650 2% 20,450 7.47% 50,900
Walter Hays Multi-Use Building 150,000 48,700 685 0% 48,015 1.41% 101,300
Hoover Elementary School 1-Phase I 23,207,165 1,694,176 239,461 1% 1,454,715 14.13% 21,512,989
Duveneck Elementary School 1-Phase I 9,230,464 9,229,952 9,229,952 100% 0 100.00% 512
Fairmeadow Elementary School 1- Phase I 7,590,515 7,590,496 7,584,495 100% 6,001 99.92% 19
Ohlone Elementary School 1- Phase I 10,528,254 10,528,254 10,528,254 100% 0 100.00% 0
Garland Elementary School 1- Phase I 280,113 280,113 280,113 100% 0 100.00% 0
Elementary Schools 1 - Elementary Classroom Improvements 1,879,695 1,879,695 1,879,695 100% 0 100.00% 0
Multi-Use Builindg - Reserved 36,832,808 0 0 0% 0 0.00% 36,832,808
PAUSD - Program Management 16,163,405 13,438,481 12,726,376 79% 712,105 94.70% 2,724,924
PAUSD - Technology 11,685,056 10,456,794 9,825,916 84% 630,878 93.97% 1,228,262
PAUSD - Technology -Reserved 2,222,312 0 0 0% 0 0.00% 2,222,312
PAUSD - Reserved 0 0 0 0% 0 0.00% 0
525 San Antonio -Property Acquisition 8,500,000 8,500,000 8,500,000 100% 0 100.00% 0
Transfer out to Planned Maintenance Fund* 17,758,557 6,330,628 6,330,628 36% 0 100.00% 11,427,929
Bond Issuance Cost 3,043,618 2,972,933 2,972,933 98% 0 100.00% 70,685
Measure A Fund Total 393,360,309 272,698,315 263,244,296 9,454,019 120,661,994
* Planned Maintenance Fund Total 6,330,629 6,075,620 5,344,874 84% 730,746 255,009
*$17,758,557 from Measure A fund to Planned Maintenance fund was approved. The budget for Planned maintenance fund will be increased about $2 M every year in 9 years.
Prepared by: Business Services Department based on QSS accounting System
BudgetSchool Name - Project Name
Percent of
Budget
Expended
Palo Alto Unified School District
Strong Schools Bond
3/31/2017
Percent of
Expended
Contract
BalanceExpenditures Budget BalanceCommitted
Page | 7
Gunn High School
Central Building Project
A. PROJECT STATUS
Project bids were received on March 21st, with
Alten Construction being the successful low bidder.
The Board awarded a contract on March 28th. Alten
is in the process of executing the agreement and
getting bonds and insurance in place. The pre‐
construction meeting and notice to proceed is
anticipated to be issued in mid‐April, with
mobilization and hazardous materials abatement
work beginning in May.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
Notice to Proceed will be issued in April.
Funding
State Funds $0
Strong Schools Bond Funds $21,087,277
Other Funding $0
Total $21,087,277
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,237,823
Construction & Equipment $17,649,454
Soft Costs Contingency $200,000
Total $19,374,242
Percent of Budget Expended 10.25%
Current Phase: Bid & Award
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) February 25, 2014
BOE Approval March 11, 2014
Schematic Design (2) June 3, 2014
BOE Approval June 17, 2014
BOE Approval of Program Change December 9, 2014
Submit to DSA February 15, 2016
Authorize to Bid (2) September 27, 2016
BOE Approval October 18, 2016
Approval by DSA February 7, 2017*
Bid Opening March 21, 2017*
Award of Contract (1) March 28, 2017*
Notice to Proceed April 15, 2017*
Substantial Completion December 15, 2018*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Palo Alto High School
Science Building Addition
A. PROJECT STATUS
DLM continued work on construction documents, and
plans to submit to DSA for review in May.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
DLM continued construction documents design efforts to submit into DSA.
Funding
State Funds $0
Strong Schools Bond Funds $5,532,204
Other Funding $0
Total $5,532,204
Budget
Salaries and Benefits $0
Supplies $60,309
Contracts & Services $842,825
Construction & Equipment $4,628,294
Soft Costs Contingency $776
Total $5,532,204
Percent of Budget Expended 11.4%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 12, 2013
BOE Approval March 19, 2013
Conceptual Design (2) March 12, 2013
BOE Approval March 19, 2013
Schematic Design (2) September 10, 2013
BOE Approval October 8, 2013
Submit to DSA February 14, 2017*
BOE Approval February 28, 2017*
Authorize to Bid (2) October 15, 2017*
BOE Approval November 8, 2017*
Approval by DSA October 15, 2017*
Bid Opening December 1, 2017*
Award of Contract (1) December 10, 2017*
Notice to Proceed January 15, 2018*
Substantial Completion March 1, 2019*
Planned Occupancy April 5, 2019*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Palo Alto High School
Indoor PE and Athletic Facilities
A. PROJECT STATUS
The Main Gym wood floor is complete. Wall finishes,
casework and countertops, AV equipment and MEP finish
work is also ongoing. Locker installation will begin in April.
The Small Gym, Dance Studio and Wrestling room flooring
is finished, and mirrors, ceilings and specialties installation
is in progress. Site work has commenced, with AC paving
along the north and east sides complete. Work continues
on the pavers in the plaza area, along with added work
around the pool and south end of the building
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
Site work has resumed with more favorable weather in March.
Funding
State Funds $0
Strong Schools Bond Funds $17,671,555
Other Funding (Deseret Trust Co.) $23,443,720
Total $41,671,555
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,991,039
Construction & Equipment $38,500,516
Soft Costs Contingency $180,000
Total $41,671,555
Percent of Budget Expended * 87.98%
(Above % of budget expended is against bond funds of
$17,671,555)
Change Order Contingency
Starting Contingency Balance $1,822,167
Remaining Contingency Balance $1,199,453
Percent of Changes 1.71%
(Change Orders + Construction Change Directives.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) March 12, 2013
BOE Approval March 19, 2013
Schematic Design (2) September 10, 2013
BOE Approval October 8, 2013
Submit to DSA December 4, 2013
Re‐Submit to DSA January 27, 2014
Approval by DSA September 22, 2014
Lease Leaseback Agreement (1) May 26, 2015
Award of LLB Contract (1) June 23, 2015
Notice to Proceed August 1, 2015
Substantial Completion May 7, 2017*
Planned Occupancy June 15, 2017*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Palo Alto High School
Building 500 Renovation (Library)
A. PROJECT STATUS
DLM/HED received DSA approval this month, and
the project is now out to bid. The bid date is May
2, and Board approval is scheduled for May 9. This
project is scheduled to be awarded in May, but
will not begin construction until August 1, 2017.
Renovation of the 700 and 200 buildings is also
being bid, which will occur in June and July to
allow building occupants to move into their
interim spaces.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.8
D. PROJECT OVERVIEW:
The project is out to bid, with bids due on May 2, 2017.
Funding
State Funds $0
Strong Schools Bond Funds $9,350,000
Other Funding $0
Total $9,350,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,886,000
Construction & Equipment $7,344,000
Soft Costs Contingency $120,000
Total $9,350,000
Percent of Budget Expended 6.7%
Current Phase: Bid & Award
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) September 23, 2014
BOE Approval October 14, 2014
Schematic Design (2) March 24, 2015
BOE Approval April 21, 2015
Submit to DSA December 15, 2015
Approval by DSA March 14, 2017*
Authorize to Bid (1) February 28, 2017*
Award of Contract (1) June 1, 2017*
Notice to Proceed August 1, 2017*
Substantial Completion November 15, 2018*
Planned Occupancy January 2019*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Addison Elementary School (Donor‐Funded Project)
New Library, Administration and Multipurpose Building
A. PROJECT STATUS
Gelfand Partners completed a Design Development
package and estimate for review in March, and are
on track to submit plans to DSA for review in July
2017. The project estimates are over budget, so
discussions will take place on how to bring the
project back within budget. Several meetings have
taken place regarding exterior play areas, and the
potential for incorporating specialized play areas
along Middlefield and Webster.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
Project is currently in Construction Documents phase, with DSA submittal planned for June 2017.
Funding
State Funds $0
Strong Schools Bond Funds $0
Other Funding – Donation $1,330,000
Total $1,330,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,330,000
Construction & Equipment $0
Soft Costs Contingency $0
Total $1,330,000
Percent of Budget Expended 22.4%
Current Phase: Construction Documents
Schedule:
Conceptual Design (2) February 23, 2016
March 8, 2016
Schematic Design (2) September 13, 2016
BOE Approval September 27, 2016
Submit to DSA June 1, 2017*
Approval by DSA February 15, 2018*
Authorize to Bid (2) February 1, 2018*
BOE Approval February 15, 2018*
Bid Opening April 15, 2018*
Award of Contract (1) May 1, 2018*
Notice to Proceed May 15, 2018*
Substantial Completion September 15, 2019*
Planned Occupancy December 20, 2019*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 12
El Carmelo Elementary School
New Multipurpose Building
A. PROJECT STATUS
The Board approved beginning work on conceptual design for planning a new MP building for El Carmelo in
January. Gelfand Partners held two meetings with the El Carmelo Advisory committee in March, and will hold
their 3rd meeting in early April. Staff hopes to bring a recommendation to the Board for approval in June 2017.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
Conceptual Design planned for board approval in June 2017.
Funding
State Funds $0
Strong Schools Bond Funds $0
Other Funding $0
Total $0
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $0
Construction & Equipment $0
Soft Costs Contingency $0
Total $0
Percent of Budget Expended 0.00%
Current Phase: Conceptual Design
Schedule:
Conceptual Design (2) June 6, 2017
BOE Approval June 20, 2017
Schematic Design (2) TBD
BOE Approval TBD
Submit to DSA TBD
Approval by DSA TBD
Authorize to Bid (2) TBD
Bid Opening TBD
Award of Contract (1) TBD
Notice to Proceed TBD
Substantial Completion TBD
Planned Occupancy TBD
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Escondido Elementary School
New Multipurpose Building
A. PROJECT STATUS
The Board approved beginning work on conceptual design for planning a new MP building for Escondido in
January. Gelfand Partners held a kick off meeting with the Escondido Advisory committee, and will hold their
2nd meeting in April 12th. Staff hopes to bring a recommendation to the Board for approval in June 2017.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
Conceptual Design planned for board approval in June 2017.
Funding
State Funds $0
Strong Schools Bond Funds $0
Other Funding $0
Total $0
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $0
Construction & Equipment $0
Soft Costs Contingency $0
Total $0
Percent of Budget Expended 0.00%
Current Phase: Conceptual Design
Schedule:
Conceptual Design (2) June 6, 2017
BOE Approval June 20, 2017
Schematic Design (2) TBD
BOE Approval TBD
Submit to DSA TBD
Approval by DSA TBD
Authorize to Bid (2) TBD
Bid Opening TBD
Award of Contract (1) TBD
Notice to Proceed TBD
Substantial Completion TBD
Planned Occupancy TBD
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Hays Elementary School
New Multipurpose Building
A. PROJECT STATUS
The Board approved beginning work on conceptual design for planning a new MP building for Hays in January.
Gelfand Partners held a kick off meeting with the Hays Advisory committee, and will hold their 3rd meeting in
early April. Staff hopes to bring a recommendation to the Board for approval in June 2017.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
Conceptual Design planned for board approval in June 2017.
Funding
State Funds $0
Strong Schools Bond Funds $0
Other Funding $0
Total $0
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $0
Construction & Equipment $0
Soft Costs Contingency $0
Total $0
Percent of Budget Expended 0.00%
Current Phase: Conceptual Design
Schedule:
Conceptual Design (2) June 6, 2017
BOE Approval June 20, 2017
Schematic Design (2) TBD
BOE Approval TBD
Submit to DSA TBD
Approval by DSA TBD
Authorize to Bid (2) TBD
Bid Opening TBD
Award of Contract (1) TBD
Notice to Proceed TBD
Substantial Completion TBD
Planned Occupancy TBD
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
Hoover Elementary School
New Library, Administration and Multipurpose Building
E. PROJECT STATUS
Gelfand continued meetings with the Hoover
Advisory committee this month to discuss the
placement of the MP, Library, and flex rooms. A slight
modification has been made to the MP room
orientation and the location of the 2
nd flex room.
Gelfand is working on their schematic design
drawings for estimating by May 1. The schematic
design presentation to the board is now scheduled to
occur during the June 6th meeting.
F. BUDGET & SCHEDULE SUMMARY
G. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
H. PROJECT OVERVIEW:
Conceptual Design was approved by the Board on January 10, 2017.
Funding
State Funds $0
Strong Schools Bond Funds $23,207,165
Other Funding $0
Total $23,207,165
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $4,848,277
Construction & Equipment $18,358,888
Soft Costs Contingency $
Total $23,207,165
Percent of Budget Expended 0.84%
Current Phase: Schematic Design
Schedule:
Conceptual Design (2) December 13, 2016
BOE Approval January 10, 2017
Schematic Design (2) June 6, 2017*
BOE Approval June 20, 2017*
Submit to DSA January 2018*
Approval by DSA September 2018*
Authorize to Bid (2) September 2018*
Bid Opening November 2018*
Award of Contract (1) December 2018*
Notice to Proceed January 2019*
Substantial Completion March 2020*
Planned Occupancy April 2020*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
The new Math and English Building was occupied by staff and
students on August 15, 2013. World Language Building classrooms
have been in use since February, 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
The World Languages building move‐in occurred on February 8, 2013, and was occupied with staff and
students on February 11, 2013. The Math & English building move‐in occurred on July 15, 2013, and was
occupied with staff and students on August 15, 2013. The project was completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $24,808,488
Other Funding $0
Total $24,808,488
Budget
Salaries and Benefits $24,948
Supplies $308,194
Contracts & Services $3,789,909
Construction & Equipment $20,685,160
Soft Costs Contingency $277
Total $24,808,488
Percent of Budget Expended 99.9%
Change Order Contingency
Starting Contingency Balance $ 1,763,200
Remaining Contingency Balance $ 99,232
Percent of Changes 9.3%
(Change Orders + Construction Change Directives vs.
Original Contract)
Project Savings Realized = $226,713
Current Phase: Occupancy – August 15, 2013
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 22, 2011
Notice to Proceed August 24, 2011
Substantial Completion July 15, 2013
Planned Occupancy August 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Gunn High School
New Gymnasium
A. PROJECT STATUS
The new gymnasium was occupied on June 7, 2013 and PE classes were held in the new gym on August 15, 2013.
The tennis courts surfacing and striping was installed and completed August 27, 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
The new gym was occupied on June 7, 2013.
Funding
State Funds $0
Strong Schools Bond Funds $ 12,450,946
Other Funding $0
Total $12,450,946
Budget
Salaries and Benefits $0
Supplies $19,706
Contracts & Services $2,461,402
Construction & Equipment $9,936,883
Soft Costs Contingency $32,955
Total $12,450,946
Percent of Budget Expended 99.9%
Change Order Contingency
Starting Contingency Balance $834,700
Remaining Contingency Balance $7,909
Percent of Changes 9.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Project Savings Realized = $463,854
Current Phase: Occupancy – June 7, 2013
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed August 1, 2011
Substantial Completion May 1, 2013
Planned Occupancy June 7, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Gunn High School
Existing Gymnasium Modernization
A. PROJECT STATUS
The modernized Bow gym was occupied by the campus on
November 4, 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
The project was completed on‐schedule and within budget. Occupancy by the school occurred on
November 12, 2013.
Funding and Budget
This project is funded by the New Gymnasium project
budget. See that project budget for status.
Change Order Contingency
Starting Contingency Balance $99,800
Remaining Contingency Balance $51,455
Percent of Changes 4.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy – November 12, 2013
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) February 12, 2013
BOE Approval February 26, 2013
Approval by DSA January 23, 2013
Bid Opening April 2, 2013
Award of Contract (1) April 9, 2013
Notice to Proceed May 31, 2013
Substantial Completion October 28, 2013
Planned Occupancy November 12, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Gunn High School
E and K (MS and L‐31) Buildings Renovation
A. PROJECT STATUS
Students occupied E and K buildings on August 13,
2014, and the flex room in building E was occupied on
September 15, 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
Construction was completed on schedule and within budget. Occupancy took place on August 13, 2014.
Funding
State Funds $0
Strong Schools Bond Funds $1,629,173
Other Funding $0
Total $1,629,173
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $428,000
Construction & Equipment $1,198,886
Soft Costs Contingency $2,287
Total $1,629,173
Percent of Budget Expended 98.2%
Change Order Contingency
Starting Contingency Balance $122,800
Remaining Contingency Balance $114,946
Percent of Changes 1.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Project Savings Realized = $491,666
Current Phase: Occupancy – August 15, 2014
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) June 11, 2013
BOE Approval June 18, 2013
Submit to DSA November 25, 2013
Authorize to Bid (2) March 25, 2014
BOE Approval April 22, 2014
Approval by DSA March 27, 2014
Bid Opening April 29, 2014
Award of Contract (1) May 20, 2014
Notice to Proceed May 27, 2014
Substantial Completion August 11, 2014
Planned Occupancy August 15, 2014
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Gunn High School
Traffic Signal Replacement
Phase I – Parking and Drop‐off Improvements
A. PROJECT STATUS
Columbia Electric installed the new traffic signal
pole at Arastradero and Miranda Ave. and wiring
has been completed. Concrete sidewalk work was
also done in late July. Final landscape
improvements were completed in August, and
the first phase of this project is now complete.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
The Miranda Ave. parking and drop‐off was phase one of a multi‐phase project for various parking and
drop off improvements. Future phases will be coordinated with the Central Building project, which will
develop a new drop off area and entry plaza in the main parking lot.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $919,858
Construction & Equipment $2,919,840
Soft Costs Contingency $100,302
Total $3,940,000
Percent of Budget Expended 47%
Change Order Contingency
Starting Contingency Balance $121,380
Remaining Contingency Balance $77,492
Percent of Changes 3.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Closeout
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 19, 2012
BOE Approval June 26, 2012
Schematic Design (2) December 18, 2012
BOE Approval January 15, 2013
Authorize to Bid (2) June 11, 2013
BOE Approval June18, 2013
Submit to DSA July 17, 2013
Approval by DSA October 2, 2013
Bid Opening November 12, 2013
Award of Contract (1) November 19, 2013
Notice to Proceed December 4, 2013
Substantial Completion August 15, 2014
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Palo Alto High School
Athletic Stadium Improvements
A. PROJECT STATUS
The concessions building, track re‐surfacing, new ornamental
fence, signage and entry lighting were completed for the Fall 2013
football season.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
The ornamental fence was completed on schedule in August 2013. The concessions building was
occupied September 10, 2012. The bleacher replacement work was completed on schedule in June 2013.
Funding
State Funds $0
Strong Schools Bond Funds $4,758,036
Other Funding $0
Total $4,758,036
Budget
Salaries and Benefits $882
Supplies $2,746
Contracts & Services $818,716
Construction & Equipment $3,935,692
Soft Costs Contingency $0
Total $4,758,036
Percent of Budget Expended 100%
Change Order Contingency
Starting Contingency Balance $310,200
Remaining Contingency Balance $364,338
Percent of Changes ‐1.7%
(Change Orders + Construction Change Directives vs.
Original Contract)
Project Savings Realized = $331,964
Current Phase: Occupancy – August 1, 2013
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) February 22, 2011
BOE Approval March 8, 2011
Submit to DSA April 4, 2011
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA July 26, 2011
Bid Opening December 1, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed January 4, 2012
Substantial Completion ‐ Concession August 31, 2012
Planned Occupancy ‐ Concessions September 10, 2012
Bleachers March 31, 2013
Fence Completion August 1, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Palo Alto High School
Haymarket and Tower Building Improvements
A. PROJECT STATUS
All Trusty Builders completed the installation of the new
windows on August 9, 2013, on schedule and within
budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
The project completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $1,260,933
Other Funding $0
Total $1,260,933
Budget
Salaries and Benefits $0
Supplies $62,844
Contracts & Services $179,000
Construction & Equipment $1,019,092
Soft Costs Contingency $0
Total $1,260,933
Percent of Budget Expended 100%
Change Order Contingency
Starting Contingency Balance $39,200
Remaining Contingency Balance $33,930
Percent of Changes 1.3%
(Change Orders + Construction Change Directives vs.
Original Contract)
Project Savings Realized = $239,067
Current Phase: Occupancy – August 9, 2013
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA May 25, 2012
Authorize to Bid (2) April 24, 2012
BOE Approval May 6, 2012
Approval by DSA August 24, 2012
Bid Opening January 17, 2013
Award of Contract (1) January 29, 2013
Notice to Proceed February 21, 2013
Substantial Completion August 9, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
Move in and occupancy of both buildings occurred in July
2014. Taisei has completed their work, and contract
closeout is complete.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
Furniture installation and occupancy of the Media Arts and Math/Social Sciences buildings completed.
Funding
State Funds $0
Strong Schools Bond Funds $36,938,515
Other Funding $0
Total $36,938,515
Budget
Salaries and Benefits $18,448
Supplies $1,325,333
Contracts & Services $6,261,915
Construction & Equipment $29,236,995
Soft Costs Contingency $95,826
Total $38,415,001
Percent of Budget Expended 99.6%
Change Order Contingency
Starting Contingency Balance $2,515,000
Remaining Contingency Balance $34,288
Percent of Changes * 9.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
* Does not include $570,000 settlement agreement with
Taisei for release of any and all claims
Project Savings Realized = $1,476,486
Current Phase: Occupancy – August 1, 2014
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA April 28, 2011
Bid Opening June 30, 2011
Award of Contract (1) July 12, 2011
Notice to Proceed August 4, 2011
Substantial Completion April 15, 2014
Planned Occupancy August 1, 2014
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Palo Alto High School
Performing Arts Center (PAC)
A. PROJECT STATUS
Students and staff occupied the new building in July, and
DSA closeout was completed in September. Additional
audio‐visual equipment, drapes and production lighting,
and furniture installation was completed in September,
in preparation for the Opening Night Gala on October 1.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
Occupancy occurred over the summer break.
Funding
State Funds $0
Strong Schools Bond Funds $29,370,049
Other Funding $0
Total $29,370,049
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $4,377,871
Construction & Equipment $24,845,000
Soft Costs Contingency $147,178
Total $29,370,049
Percent of Budget Expended 90.19%
Change Order Contingency
Starting Contingency Balance $2,184,400
Remaining Contingency Balance $1,065,582
Percent of Changes 5.12%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy – July 1, 2016
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (3) June 14, 2011
BOE Approval December 13, 2011
BOE Approval January 17, 2012
Submit to DSA March 28, 2013
Approval by DSA January 16, 2014
Authorize to Bid (2) January 14, 2014
BOE Approval January 28, 2014
Bid Opening May 13, 2014
Award of Contract (1) June 3, 2014
Notice to Proceed June 23, 2014
Substantial Completion May 5, 2016
Planned Occupancy July 1, 2016
( ) Denotes number of Board of Education Readings
Page | 25
Jordan Middle School
Classroom Wing, Cafetorium and
Campus Improvements
A. PROJECT STATUS
Students occupied all new and modernized buildings for
the start of school in fall 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
The project was completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $19,109,345
Other Funding $0
Total $19,109,345
Budget
Salaries and Benefits $6,111
Supplies $86,265
Contracts & Services $3,723,370
Construction & Equipment $15,224,812
Soft Costs Contingency $68,787
Total $19,109,345
Percent of Budget Expended 99.2%
Change Order Contingency
Starting Contingency Balance $1,398,700
Remaining Contingency Balance $202,769
Percent of Changes 8.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Project Savings Realized = $782,219
Current Phase: Close‐out / Occupancy – August 15, 2013
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA October 5, 2011
Bid Opening December 8, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed December 27, 2011
Substantial Completion August 1, 2013
Planned Occupancy August 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
J.L. Stanford Middle School
Classroom Wing and Campus Improvements
A. PROJECT STATUS
Students occupied all new and modernized buildings for
the start of school in fall 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
The project completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $15,670,127
Other Funding $0
Total $15,670,127
Budget
Salaries and Benefits $8,879
Supplies $144,790
Contracts & Services $3,545,843
Construction & Equipment $11,970,665
Soft Costs Contingency $0
Total $15,670,127
Percent of Budget Expended 99.1%
Change Order Contingency
Starting Contingency Balance $1,057,800
Remaining Contingency Balance $911,677
Percent of Changes 1.4%
(Change Orders + Construction Change Directives vs.
Original Contract)
Project Savings Realized = $1,514,522
Current Phase: Close‐out / Occupancy – August 15, 2013
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28, 2010
Submit to DSA May 6, 2011
Authorize to Bid (2) November 29, 2011
BOE Approval December 13, 2011
Approval by DSA January 24, 2012
Bid Opening May 3, 2012
Award of Contract (1) May 8, 2012
Notice to Proceed May 30, 2012
Substantial Completion August 7, 2013
Planned Occupancy August 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
J.L. Stanford Middle School
Landscape and Site Improvements
A. PROJECT STATUS
Scapes completed the project on schedule in the fall 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
The project completed on schedule and within budget.
Funding and Budget
This project is funded by the J.L. Stanford Middle School
project budget. See that project budget for status.
Percent of Budget Expended 100%
Change Order Contingency
Starting Contingency Balance $1,057,800
Remaining Contingency Balance $902,445
Percent of Changes 2.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Close‐out / Occupancy – August 16, 2013
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28, 2010
Submit to DSA May 6, 2011
Authorize to Bid (2) November 29, 2011
BOE Approval December 13, 2011
Approval by DSA January 24, 2012
Bid Opening May 3, 2013
Award of Contract (1) May 8, 2013
Notice to Proceed May 23, 2013
Substantial Completion August 16, 2013
Completion August 16, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Terman Middle School
Library Addition and Campus Improvements
A. PROJECT STATUS
Students occupied the new instructional spaces and
modernized buildings for the start of school in fall 2013. The
cafetorium modernization was completed in October 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
The project completed on schedule in August 2013, except for the Cafetorium, which was completed in
November 2013. The project has been completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,051,487
Other Funding $0
Total $13,051,487
Budget
Salaries and Benefits $4,153
Supplies $75,747
Contracts & Services $2,720,590
Construction & Equipment $10,246,249
Soft Costs Contingency $4,748
Total $13,051,487
Percent of Budget Expended 99.6%
Change Order Contingency
Starting Contingency Balance $929,900
Remaining Contingency Balance $12,909
Percent of Changes 9.4%
(Change Orders + Construction Change Directives vs.
Original Contract)
Project Savings Realized = $261,484
Current Phase: Close‐out / Occupancy – November 15, 2013
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA September 1, 2011
Bid Opening December 6, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed December 27, 2011
Substantial Completion October 31, 2013
Planned Occupancy November 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 29
Duveneck Elementary School
New Classroom Buildings and Modernization
A. PROJECT STATUS
The fence around the sod for the field area to establish
growth was removed on September 19, 2014. All buildings
were substantially complete and occupied on August 11,
2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
The project has been completed within budget, and was occupied on August 5, 2014.
Funding
State Funds $0
Strong Schools Bond Funds $9,277,534
Other Funding $0
Total $9,277,534
Budget
Salaries and Benefits $20,313
Supplies $0
Contracts & Services $2,098,650
Construction & Equipment $7,154,178
Soft Costs Contingency $4,393
Total $9,277,534
Percent of Budget Expended 99.5%
Change Order Contingency
Starting Contingency Balance $703 ,772
Remaining Contingency Balance $304,029
Percent of Changes 5.7%
(Change Orders + Construction Change Directives vs.
Original Contract)
Realized Project Savings = $500,824
Current Phase: Close‐out/Occupancy – August 5, 2014
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) December 14, 2010
BOE Approval January 11, 2011
Schematic Design (2) June 14, 2011
BOE Approval June 28, 2011
Submit to DSA February 27, 2012
Approval by DSA December 10, 2012
Authorize to Bid (2) December 18 2012
BOE Approval January 15, 2013
Bid Opening February 28, 2013
Award of Contract (1) March 12, 2013
Notice to Proceed March 25, 2013
Substantial Completion July 31, 2014
Planned Occupancy August 5, 2014
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 30
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Students occupied all new and modernized buildings for
the start of school in fall 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
The project completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $7,656,720
Other Funding $0
Total $7,656,720
Budget
Salaries and Benefits $32,377
Supplies $98,962
Contracts & Services $1,992,932
Construction & Equipment $5,531,329
Soft Costs Contingency $1,120
Total $7,656,720
Percent of Budget Expended 99.1%
Change Order Contingency
Starting Contingency Balance $642 ,300
Remaining Contingency Balance $186,122
Percent of Changes 7.1%
(Change Orders + Construction Change Directives vs.
Original Contract)
Realized Project Savings = $139,830
Current Phase: Close‐out / Occupancy – August 15, 2013
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010
BOE Approval September 28, 2010
Submit to DSA April 18, 2011
Authorize to Bid (2) October 11, 2011
BOE Approval October 25, 2011
Approval by DSA November 14, 2011
Bid Opening December 5, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed January 3, 2012
Substantial Completion August 5, 2013
Planned Occupancy August 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 31
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Move‐in to the new building and other existing classrooms
occurred in December 2011. Students occupied the new
building on January 3, 2012.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
Occupancy occurred on January 3, 2012. Project completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $10,556,389
Other Funding $0
Total $10,556,389
Budget
Salaries and Benefits $7,461
Supplies $49,049
Contracts & Services $2,180,418
Construction & Equipment $8,319,461
Soft Costs Contingency $62,598
Total $10,556,389
Percent of Budget Expended 99.7%
Change Order Contingency
Starting Contingency Balance $748,400
Remaining Contingency Balance $459,113
Percent of Changes 3.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Realized Project Savings = $41,481
Current Phase: Occupancy – January 3, 2012
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010
Award of Contract (1) August 3, 2010
Notice to Proceed August 19, 2010
Substantial Completion November 18, 2011
Planned Occupancy January 3, 2012
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 32
Site Acquisition
525 San Antonio Rd
A. PROJECT STATUS
This site has been leased to Athena Academy.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
The site has been leased to Athena Academy.
Funding
State Funds $0
Strong Schools Bond Funds $8,500,000
Other Funding $0
Total $8,500,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $8,500,000
Construction & Equipment $0
Soft Costs Contingency $0
Total $8,500,000
Percent of Budget Expended 100%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 33
Jordan Middle Schools ‐ Interim Classrooms
A. PROJECT STATUS
The portables were installed and moved into for fall 2011. DSA closeout received November 19, 2012.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
This project completed ahead of schedule and under budget.
Move in occurred on September 30, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $379,811
Other Funding $208,222
Total $488,033
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $180,286
Construction & Equipment $306,983
Soft Costs Contingency $764
Total $488,033
Percent of Budget Expended 100%
Current Phase: Move‐in
Schedule:
Approval by DSA June 16, 2011
Authorize to Bid (2) June 14, 2011
BOE Approval June 28, 2011
Bid Opening July 14, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed July 27, 2011
Substantial Completion September 20, 2011
Occupancy September 30, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 34
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
Best Contracting Services Inc. completed the installation of air
conditioning units and cool roof coating in the summer 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
Project has been closed‐out.
Funding
State Funds $0
Strong Schools Bond Funds $2,092,366
Other Funding $0
Total $2,092,366
Budget
Salaries and Benefits $1,919
Supplies $0
Contracts & Services $454,610
Construction & Equipment $1,612,946
Soft Costs Contingency $22,891
Total $2,092,366
Percent of Budget Expended 100%
Current Phase: Completed
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA October 20, 2010
Approval by DSA February 10, 2011
Authorize to Bid (2) February 22, 2011
BOE Approval March 8, 2011
Bid Opening March 28, 2011
Award of Contract (1) April 8, 2011
Notice to Proceed April 11, 2011
Substantial Completion August 8, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 35
J.L. Stanford Middle School
Interim Classrooms
A. PROJECT STATUS
Coulter Construction completed the work on the
relocated portables in August 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
Project completed on schedule and is currently in close‐out.
This portable relocation project funded by main
JLS project. Refer to pg. 14
Current Phase: Occupancy ‐ August 11, 2011
Schedule:
Approval by DSA April 19, 2011
Jordan Project June 16, 2011
Authorize to Bid (2) May 10, 2011
BOE Approval May 24, 2011
Bid Opening June 1, 2011
Award of Contract (1) June 13, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 8, 2011
Planned Occupancy August 15, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 36
Fairmeadow Elementary School
Portable Relocation Project
A. PROJECT STATUS
Relocation of the portable was complete and occupied on August 8, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 6.4
D. PROJECT OVERVIEW:
Project completed ahead of schedule on August 8, 2011.
This portable relocation project funded by main
JLS project. Refer to pg. 14
Current Phase: Occupancy ‐ August 8, 2011
Schedule:
Architect Contract (2) February 15, 2011
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA March 3, 2011
Approval by DSA March 3, 2011
Authorize to Bid (2) May 11, 2011
BOE Approval May 24, 2011
Bid Opening June 14, 2011
Award of Contract (1) June 14, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 1, 2011
Planned Occupancy August 8, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 37
Elementary Classroom Improvements
Interactive Whiteboards and Sound Assist System Installation
A. PROJECT STATUS
Installation of SmartBoards and Lightspeed sound assist
systems were completed for all elementary school
classrooms and libraries in April 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
All SmartBoards and Lightspeed sound systems installed.
Funding
State Funds $0
Strong Schools Bond Funds $1,879,695
Other Funding $0
Total $1,879,695
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $275,488
Construction & Equipment $1,604,207
Soft Costs Contingency $0
Total $1,879,695
Percent of Budget Expended 100%
Current Phase: Complete ‐ May 15, 2011
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) November 9, 2010
BOE Approval November 23, 2010
Bid Opening February 25, 2011
Award of Contract (1) March 8, 2011
Notice to Proceed March 9, 2011
Completion May 15, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 38
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
The fields were available for play on February 1, 2011, and
final change order negotiations completed on March 9,
2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
Field was open for use on February 1, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $2,609,680
Other Funding $1,007,255
Total $3,616,935
Budget
Salaries and Benefits $0
Supplies $1,506
Contracts & Services $698,293
Construction & Equipment $2,916,682
Soft Costs Contingency $454
Total $3,616,935
Percent of Budget Expended 100.0%
Change Order Contingency
Starting Contingency Balance $269,300
Remaining Contingency Balance $230,579
Percent of Changes 1.5%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy – February 1, 2011
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 18, 2008
BOE Approval December 09, 2008
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) February 24, 2009
BOE Approval March 17, 2009
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion January 31, 2011
Planned Occupancy February 1, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 39
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
This facility was available for instruction in January 2010. DSA
closeout received on July 18, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,065,128
Other Funding $0
Total $5,065,128
Budget
Salaries and Benefits $1,061
Supplies $88,985
Contracts & Services $984,783
Construction & Equipment $3,990,300
Soft Costs Contingency $0
Total $5,065,128
Percent of Budget Expended 100%
Change Order Contingency
Starting Contingency Balance $349,000
Remaining Contingency Balance $141,967
Percent of Changes 41.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy – January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 40
Gunn High School
Aquatic Center
A. PROJECT STATUS
This facility was available for use in July
2009.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $4,862,530
Other Funding $0
Total $4,862,530
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $647,169
Construction & Equipment $4,215,360
Soft Costs Contingency $0
Total $4,862,530
Percent of Budget Expended 100%
Change Order Contingency
Starting Contingency Balance $389,887
Remaining Contingency Balance $195,148
Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy – June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 41
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus
to the Board of Education for approval on September 8, which
became the program documents for the new projects at each
campus. These projects for pre‐design work have been closed,
and funds will be transferred to the program contingency on
June 14, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
This project has been completed. Board approval received on September 8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $54,658
Other Funding $0
Total $54,658
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $54,658
Construction & Equipment $0
Soft Costs Contingency $0
Total $54,658
Percent of Budget Expended 100%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 42
Technology Improvements
A. PROJECT STATUS
Equipment orders have arrived and were deployed to the various campuses for
use during the 2014/15 school year.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
Equipment has been installed for the 2014/15 school year.
Funding
State Funds $0
Strong Schools Bond Funds $10,485,054
Other Funding $0
Total $10,485,054
Budget
Salaries and Benefits $0
Supplies & Computers $6,850,644
Contracts & Services $539,269
Construction & Equipment $3,095,142
Soft Costs Contingency $0
Total $10,485,054
Percent of Budget Expended 92.2%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 43
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education has put new development for
Garland on hold until a growth plan is established for the
elementary schools. The board voted to terminate the
lease with Stratford School in June 2011. Discussions with
the Board on future plans for growth at the elementary
schools are ongoing.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,915,789
Construction & Equipment $17,400,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: On Hold
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 44
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
The Board of Education (BOE) approved the master
plans for both high schools, and these projects have
been closed, with funds transferred to the
respective campus reserve funds.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
Master planning effort complete.
Funding
State Funds $0
Strong Schools Bond Funds $285,387
Other Funding $0
Total $285,387
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $285,387
Construction & Equipment $0
Soft Costs Contingency $0
Total $285,387
Percent of Budget Expended 86.2%
Current Phase: Complete
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010
Paly MP Revision Approval (2) October 9, 2010
Gunn MP Revision Approval (2) October 12, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings