Monthly Reports 2014-02 (Feb)
Page | 1
MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
February 2014
Strong Schools Bond
Capital Improvement Projects
Prepared by
fs3|Hodges
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Capital Projects
Gunn High School – Phase I ‐ Parking and Drop‐off Sitework Improvement page 6
Gunn High School – E and K (L31 and MS) Buildings Renovation page 7
Gunn High School – Central Building Project page 8
Palo Alto High School – New Classroom Building and Media Arts page 9
Palo Alto High School – Performing Arts Center page 10
Palo Alto High School – Science Building Addition Page 11
Palo Alto High School – New Gymnasium Page 12
J.L. Stanford Middle School page 13
Duveneck Elementary School – New Classroom Buildings and Modernization page 14
Technology page 15
Completed Capital Projects
Gunn High School – New Classroom Building and World Languages Building page 16
Gunn High School – New Gymnasium page 17
Gunn High School – Existing Gymnasium Modernization page 18
Palo Alto High School – Athletic Stadium Improvements page 19
Palo Alto High School – Haymarket and Tower Building Improvements page 20
Jordan Middle School page 21
J.L. Stanford Middle School – Landscape and Site Improvements page 22
Terman Middle School page 23
Fairmeadow Elementary School – New Classroom Buildings and Modernization page 24
Ohlone Elementary School page 25
Property Acquisition – 525 San Antonio Rd page 26
Jordan Middle School – Interim Classrooms page 27
Gunn High School – Air Conditioning of Existing Buildings page 28
J.L. Stanford Middle School – Interim Classrooms page 29
Fairmeadow Elementary School – Portable Relocation page 30
Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 31
Palo Alto High School – Multi‐use Field page 32
Gunn High School – Industrial Arts Renovation page 33
Gunn High School – Aquatic Center page 34
Middle School Pre‐Design page 35
Inactive Capital Projects
Garland Elementary School page 36
High School Master Plan page 37
Hoover Elementary School page 38
Elementary Classroom Improvements page 39
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
Gunn High School – Miranda Ave. Drop‐Off (Phase I ‐ Parking and Drop‐Off Improvements)
Grade Tech, Inc. completed formwork and commenced pouring concrete for curbs, gutters and walkways. Grade
Tech also completed installation of light pole bases, electrical rough‐in and footings for seat walls and stairs.
Gunn High School – E and K (L‐31 and MS) Buildings Renovation
DLM submitted construction documents to DSA on November 25, 2013, and they have received comments back
from access compliance and fire/life safety divisions. DLM anticipates receiving structural comments from DSA in
early March 2014, and backcheck will be scheduled near the end of March 2014. The project is scheduled for
construction during late spring and summer of 2014.
Gunn High School – Central Building Project
DLM presented conceptual design of the Central Building Project to the board of education on February 25, 2014.
The project includes the replacement of the current RC building and music building, and expands the Spangenberg
Theater lobby. Conceptual design approval is anticipated on March 11, 2014.
Palo Alto High School – New Math/Social Sciences Building and Media Arts Building
Taisei Construction completed HVAC testing and balancing for the new Math/Social Sciences building. At the
Media Arts building, the contractor completed installation of casework and flooring, and continued the installation
of the audio visual equipment. Landscape planting installation work has also continued at both building locations.
Palo Alto High School – Performing Arts Center (PAC)
DSA approved the construction documents on January 16, 2014. A contractor prequalification conference was
conducted on February 13, 2014 and prequalification packages were received on February 28, 2014. This project
will be bid after the new Classroom and Media Arts buildings are complete and the contractor has vacated the site.
Palo Alto High School – Science Building Addition
DLM anticipates resuming meetings with faculty and staff in March 2014 for design development. The
construction schedule was adjusted to occur after construction of the new gymnasium, due to space constraints
and access to the site.
Palo Alto High School – Indoor PE and Athletic Facilities
The project architect, Jeremiah Tolbert Design Architects (JTDA) resubmitted construction documents to DSA on
January 27, 2014, with construction anticipated to begin during the summer of 2014.
J.L. Stanford Middle School
SAUSAL Corp. continued to correct punch list items. Close‐out efforts continued through February 2014.
Duveneck Elementary School – New Classroom Buildings and Modernization
Alpha Bay Builders (ABB) completed buildings 2 and 3, and the buildings were occupied on January 27, 2014. Roof
installation was completed on building 1, with metal wall framing and mechanical, electrical, plumbing rough‐in
nearly complete. Installation of door and window frames commenced. Demolition was completed in building F,
which will be renovated into the new library. The new foundation rebar is in place and framing will commence in
March 2014.
Technology
Installation of exterior wireless antennas and repeaters at each campus continued.
Page | 4
COMPLETED CAPITAL PROJECTS
Gunn High School – New Classroom Building and World Languages Building
The new Math and English Building was occupied by staff and students on August 15, 2013. World Language
Building classrooms have been in use since February, 2013.
Gunn High School – New Gymnasium
The new gymnasium was occupied on June 7, 2013 and PE classes were held in the new gym on August 15, 2013.
The tennis courts surfacing and striping was installed and completed August 27, 2013.
Gunn High School – Existing Gymnasium Modernization
The modernized Bow gym was occupied by the campus on November 4, 2013.
Palo Alto High School – Athletics Stadium Improvements
The main project including a concessions building, track re‐surfacing, new ornamental fence, signage and entry
lighting has been completed.
Palo Alto High School – Haymarket and Tower Building Improvements
All Trusty Builders completed the installation of the new windows on August 9, 2013.
Jordan Middle School
Close‐out efforts continued through February 2014.
J.L. Stanford Middle School – Landscape and Sitework Improvements
Close‐out efforts continued through February 2014.
Terman Middle School
Close‐out efforts continued through February 2014.
Fairmeadow Elementary School – New Classroom Building and Modernization
Close‐out efforts continued through February 2014.
525 San Antonio Road – Site Acquisition
This site has been leased to Athena Academy.
Ohlone Elementary School – New Classroom Building and Modernization
Move‐in to the new building and other existing classrooms occurred in December 2011. Students occupied the
new building on January 3, 2012.
Jordan Middle School ‐ Interim Classrooms
The portables were installed and moved into for fall 2011. DSA closeout received November 19, 2012.
Gunn High School – Air Conditioning of Existing Buildings
Best Contracting Services Inc. completed the installation of air conditioning units and cool roof coating in the
summer 2011.
J.L. Stanford Middle School ‐ Interim Classrooms
Coulter Construction completed the work on the relocated portables in August 2011.
Fairmeadow Elementary School – Portable Relocation
Relocation of the portable was complete and occupied on August 8, 2011.
Page | 5
Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems
Installation of SmartBoards and Lightspeed sound assist systems were completed for all elementary school
classrooms and libraries in April 2011.
Palo Alto High School – Multi‐use Field
The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9,
2011.
Gunn High School – Industrial Arts Addition & Renovation
This facility was available for instruction in January 2010. DSA closeout received on July 18, 2011.
Gunn High School – Aquatic Center
This facility was available for use in July 2009, and has been closed out with DSA.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education for approval on
September 8, which became the program documents for the new projects at each campus. These projects for pre‐
design work have been closed, and funds were transferred to the program contingency on June 14, 2011.
INACTIVE CAPITAL PROJECTS
Garland Elementary School Renovation
The Board of Education has put new development for Garland on hold until a growth plan is established for the
elementary schools. Discussions with the Board on future plans for growth at the elementary schools are ongoing.
High School Master Plan
The Board of Education (BOE) approved the master plans for both high schools, and these projects have been
closed, with funds transferred to the respective campus reserve funds.
Hoover Elementary School – Pre‐Design
This project has been put on hold until a growth plan is established for the elementary schools.
Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo
The project has been placed on hold pending further discussions with the BOE about elementary growth planning.
Board Actions in February
February 25, 2014
Consent 4 – Approval of Change Orders
Consent 6 – Approval of Budget Transfer and Authorization to Purchase Furniture and Equipment for the Media
Arts Center and Classroom Building at Palo Alto High School
A B C C / A B - C C / B A - BGunn High School - High School Master Plan 172,390 166,328 136,129 79.0% 30,199 81.84% 6,062Gunn High School 1 - Aquatic Center 4,865,425 4,862,530 4,862,530 99.9% 0 100.00% 2,895Gunn High School 2 - I.A Building 5,082,402 5,066,038 5,063,308 99.6% 2,730 99.95% 16,364Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 25,035,201 25,031,116 24,688,990 98.6% 342,126 98.63% 4,085Gunn High School 5 - Parking & Drop Off improvements 3,940,000 1,979,315 833,667 21.2% 1,145,648 42.12% 1,960,685Gunn High School 6- New/Auxiliary Gymnasium 12,914,800 12,520,517 11,796,527 91.3% 723,990 94.22% 394,283Gunn High School 7- A/C 2,600,000 2,103,866 2,102,366 80.9% 1,500 99.93% 496,134Gunn High School 8 - MS & L-31 Buildings 2,120,839 292,373 109,013 5.1% 183,360 37.29% 1,828,466Gunn High School - Reserved 19,374,242 0 0 0.0% 0 0.00% 19,374,242Palo Alto High Schools - High School Master Plan 172,999 167,759 161,616 93.4% 6,143 96.34% 5,240Palo Alto High School 1 - Stadium Field 5,090,000 5,080,732 4,733,770 93.0% 346,962 93.17% 9,268Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 2,609,680 2,609,680 2,609,680 100.0% 0 100.00% 0Palo Alto high School 3 - New classroom & Media Art Building 38,415,001 34,499,814 31,160,186 81.1% 3,339,628 90.32% 3,915,187Palo Alto High School 4 - New Theater 24,395,049 1,696,624 1,188,083 4.9% 508,541 70.03% 22,698,425Palo Alto High School 5 - Haymarket and Tower Admin. Building 1,499,999 1,292,909 1,228,687 81.9% 64,222 95.03% 207,090Palo Alto High School 6- Science Addition 5,532,204 636,101 315,683 5.7% 320,418 49.63% 4,896,103Paly 7- indoor phusical ed and athletic facilities 250,000 155,122 154,722 61.9% 400 99.74% 94,878Palo Alto High School - Reserved 23,549,443 0 0 0.0% 0 0.00% 23,549,443Jordan Middle School -Program Management- MS Pre-Design 18,890 17,826 17,826 94.4% 0 100.00% 1,064Jordan Middle Schools 1- Interim Classrooms 600,342 488,684 479,501 79.9% 9,183 98.12% 111,658Jordan Middle School 2- Improvements 19,891,564 19,174,401 17,989,003 90.4% 1,185,398 93.82% 717,163J.L.S Middle School - Program Management- MS Pre-Design 18,799 18,408 18,408 97.9% 0 100.00% 391J.L.S Middle School 1 - Interim Classrooms 446,844 422,500 417,028 93.3% 5,472 98.70% 24,344 J.L.S Middle School 2- Improvements 17,184,699 16,606,260 15,211,126 88.5% 1,395,134 91.60% 578,439Terman Middle School - Program Management- MS Pre-Design 18,799 18,423 18,423 98.0% 0 100.00% 376Terman Middle School 1- Improvements 13,312,971 13,073,284 12,817,657 96.3% 255,627 98.04% 239,687PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 98,480 92,290 63.6% 6,190 93.71% 46,520Addison Elementary School 1-Phase I 21,267 21,267 21,267 100.0% 0 100.00% 0Duveneck Elementary School 1-Phase I 9,778,358 9,413,308 5,772,493 59.0% 3,640,815 61.32% 365,050Garland Elementary School 1- Phase I 22,178,544 280,113 280,113 1.3% 0 100.00% 21,898,431Fairmeadow Elementary School 1- Phase I 7,796,550 7,723,695 7,302,272 93.7% 421,423 94.54% 72,855Hoover Elementary School 1-Phase I 70,550 70,550 57,165 81.0% 13,385 81.03% 0Ohlone Elementary School 1- Phase I 10,597,870 10,578,054 10,481,389 98.9% 96,665 99.09% 19,816Elementary Schools 1 - Elementary Classroom Improvements 2,004,889 1,879,695 1,879,695 93.8% 0 100.00% 125,194Elementary Schools - Reserved 37,585,253 0 0 0.0% 0 0.00% 37,585,253PAUSD - Program Management 10,380,131 8,768,328 7,685,095 74.0% 1,083,233 87.65% 1,611,803PAUSD - Technology 10,485,054 9,289,773 9,246,677 88.2% 43,096 99.54% 1,195,281PAUSD - Technology -Reserved 3,422,312 0 0 0.0% 0 0.00% 3,422,312PAUSD - Reserved 6,055,697 0 0 0.0% 0 0.00% 6,055,697525 San Antonio -Property Acquisition 8,500,000 8,500,000 8,500,000 100.0% 0 100.00% 0Bond Issuance Cost & Other Transfer Out 19,927,288 19,927,288 19,927,288 100.0% 0 100.00% 0Total378,067,122 224,536,937 209,365,449 15,171,488 153,530,185Prepared by: Business Services Department based on QSS accounting SystemExpenditures Budget BalanceCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond2/28/2014Percent of ExpendedContract Balance
Page | 6
Gunn High School
Miranda Ave. Drop Off
Phase I – Parking and Drop‐off Improvements
A. PROJECT STATUS
Grade Tech, Inc. completed formwork and commenced pouring concrete for
curbs, gutters and walkways. Grade Tech also completed installation of light
pole bases, electrical rough‐in and footings for seat walls and stairs.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
Phase I, Miranda Ave. parking and drop‐off project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $919,858
Construction & Equipment $2,919,840
Soft Costs Contingency $100,302
Total $3,940,000
Percent of Budget Expended 21.2%
Change Order Contingency
Starting Contingency Balance $121,380
Remaining Contingency Balance $107,476
Percent of Changes 1.2%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase:Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 19, 2012
BOE Approval June 26, 2012
Schematic Design (2) December 18, 2012
BOE Approval January 15, 2013
Authorize to Bid (2) June 11, 2013
BOE Approval June18, 2013
Submit to DSA July 17, 2013
Approval by DSA October 2, 2013
Bid Opening November 12, 2013
Award of Contract (1) November 19, 2013
Notice to Proceed December 4, 2013
Substantial Completion June 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 7
Gunn High School
E and K (MS and L‐31) Buildings Renovation
A. PROJECT STATUS
DLM submitted construction documents to DSA on November 25, 2013,
and they have received comments back from access compliance and
fire/life safety divisions. DLM anticipates receiving structural comments
from DSA in early March 2014, and backcheck will be scheduled near the
end of March 2014. The project is scheduled for construction during late
spring and summer of 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
Plans were submitted to DSA on November 25, 2013. Plans anticipated to be approved in March 2014
and authorization to bid planned for March 25 and April 22 board meetings.
Funding
State Funds $0
Strong Schools Bond Funds $2,120,839
Other Funding $0
Total $2,120,839
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $428,000
Construction & Equipment $1,689,952
Soft Costs Contingency $2,887
Total $2,120,839
Percent of Budget Expended 5.1%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) June 11, 2013
BOE Approval June 18, 2013
Submit to DSA November 25, 2013
Authorize to Bid (2) March 25, 2014*
BOE Approval April 22, 2014*
Approval by DSA March 27, 2014*
Bid Opening April 30, 2014*
Award of Contract (1) May 13, 2014*
Notice to Proceed May 23, 2014*
Substantial Completion October 1, 2014*
Planned Occupancy October 16, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
Central Building Project
A. PROJECT STATUS
DLM presented conceptual design of the Central Building Project to the board
of education on February 25, 2014. The project includes the replacement of the
current RC building and music building, and expands the Spangenberg
Theater lobby. Conceptual design approval is anticipated on March
11, 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
Conceptual design approval anticipated on March 11, 2014. Schematic design to commence after BOE
approval.
Funding
State Funds $0
Strong Schools Bond Funds $19,374,242
Other Funding $0
Total $19,374,242
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,237,823
Construction & Equipment $15,936,419
Soft Costs Contingency $200,000
Total $19,374,242
Percent of Budget Expended 0.0%
Current Phase:Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) February 25, 2014
BOE Approval March 11, 2014*
Schematic Design (2) May 27, 2014*
BOE Approval June 10, 2014*
Submit to DSA October 20, 2014*
Authorize to Bid (2) May 20, 2015*
BOE Approval June 11, 2015*
Approval by DSA May 25, 2015*
Bid Opening July 12, 2015*
Award of Contract (1) August 1, 2015*
Notice to Proceed August 10, 2015*
Substantial Completion January, 2017*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
Taisei Construction completed HVAC testing and balancing for the new
Math/Social Sciences building. At the Media Arts building, the contractor
completed installation of casework and flooring, and continued the
installation of the audio visual equipment. Landscape planting installation
work has also continued at both building locations.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
The project continues to be delayed by the contractor, with occupancy of the Media Arts and Math/Social
Sciences buildings now anticipated in Summer 2014.
Funding
State Funds $0
Strong Schools Bond Funds $37,140,001
Other Funding $0
Total $37,140,001
Budget
Salaries and Benefits $18,448
Supplies $26,519
Contracts & Services $7,066,446
Construction & Equipment $29,713,481
Soft Costs Contingency $315,107
Total $37,140,001
Percent of Budget Expended 81.1%
Change Order Contingency
Starting Contingency Balance $2,515,000
Remaining Contingency Balance $384,543
Percent of Changes 8.5%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA April 28, 2011
Bid Opening June 30, 2011
Award of Contract (1) July 12, 2011
Notice to Proceed August 4, 2011
Substantial Completion April 15, 2014*
Planned Occupancy August 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Palo Alto High School
Performing Arts Center (PAC)
A. PROJECT STATUS
DSA approved the construction documents on January 16, 2014. A
contractor prequalification conference was conducted on February 13, 2014
and prequalification packages were received on February 28, 2014. This
project will be bid after the new Classroom and Media Arts buildings are
complete and the contractor has vacated the site.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $24,395,049
Other Funding $0
Total $24,395,049
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $4,481,640
Construction & Equipment $19,745,000
Soft Costs Contingency $168,409
Total $24,395,049
Percent of Budget Expended 4.9%
Current Phase: Bid & Award
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (3) June 14, 2011
BOE Approval December 13, 2011
BOE Approval January 17, 2012
Submit to DSA March 28, 2013
Approval by DSA January 16, 2014
Authorize to Bid (2) January 14, 2014
BOE Approval January 28, 2014
Bid Opening May 20, 2014*
Award of Contract (1) May 27, 2014*
Notice to Proceed June 20, 2014*
Substantial Completion July 31, 2016*
Planned Occupancy August 15, 2016*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Science Building Addition
A. PROJECT STATUS
DLM anticipates resuming meetings with faculty and staff in March 2014 for
design development. The construction schedule was adjusted to occur after
construction of the new gymnasium, due to space constraints and access to
the site.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
Schematic Design approval received October 8, 2013, and design development proceeding.
Funding
State Funds $0
Strong Schools Bond Funds $5,532,204
Other Funding $0
Total $5,532,204
Budget
Salaries and Benefits $0
Supplies $48,121
Contracts & Services $832,654
Construction & Equipment $4,628,294
Soft Costs Contingency $23,135
Total $5,532,204
Percent of Budget Expended 5.7%
Current Phase: Design Development
Schedule:
Architect Contract (2) March 12, 2013
BOE Approval March 19, 2013
Conceptual Design (2) March 12, 2013
BOE Approval March 19, 2013
Schematic Design (2) September 10, 2013
BOE Approval October 8, 2013
Submit to DSA July 7, 2014*
Authorize to Bid (2) December 9, 2014*
BOE Approval January 11, 2015*
Approval by DSA December 2, 2014*
Bid Opening March 30, 2015*
Award of Contract (1) May 4, 2015*
Notice to Proceed August 1, 2015*
Substantial Completion May 20, 2016*
Planned Occupancy August 15, 2016*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 12
Palo Alto High School
Indoor PE and Athletic Facilities
A. PROJECT STATUS
The project architect, Jeremiah Tolbert Design Architects
(JTDA) resubmitted construction documents to DSA on
January 27, 2014, with construction anticipated to begin
during the summer of 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
Plans re‐submitted into DSA for review on January 27, 2014.
Funding
State Funds $0
Strong Schools Bond Funds $250,000
Other Funding $0
Total $250,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $225,000
Construction & Equipment $25,000
Soft Costs Contingency $0
Total $250,000
Percent of Budget Expended 61.9%
Current Phase: DSA Review
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) March 12, 2013
BOE Approval March 19, 2013
Schematic Design (2) September 10, 2013
BOE Approval October 8, 2013
Submit to DSA December 4, 2013
Re‐Submit to DSA January 27, 2014
Review Lease Leaseback Agreement May 27, 2014*
Approval by DSA June 22, 2014*
Award of Contract (1) June 24, 2014*
Notice to Proceed July 1, 2014
Substantial Completion October 1, 2015*
Planned Occupancy August 15, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
J.L. Stanford Middle School
A. PROJECT STATUS
SAUSAL Corp. continued to correct punch list items. Close‐out efforts
continued through February 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
The project completed on schedule and within budget. Close‐out in progress.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,699
Other Funding $0
Total $17,184,699
Budget
Salaries and Benefits $7,597
Supplies $144,790
Contracts & Services $3,544,351
Construction & Equipment $13,487,961
Soft Costs Contingency $0
Total $17,184,699
Percent of Budget Expended 88.5%
Change Order Contingency
Starting Contingency Balance $1,057,800
Remaining Contingency Balance $953,375
Percent of Changes 2.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Close‐out / Occupancy – August 15, 2013
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28, 2010
Submit to DSA May 6, 2011
Authorize to Bid (2) November 29, 2011
BOE Approval December 13, 2011
Approval by DSA January 24, 2012
Bid Opening May 3, 2012
Award of Contract (1) May 8, 2012
Notice to Proceed May 30, 2012
Substantial Completion August 7, 2013
Planned Occupancy August 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Duveneck Elementary School
New Classroom Buildings and Modernization
A. PROJECT STATUS
Alpha Bay Builders (ABB) completed buildings 2 and 3, and the buildings
were occupied on January 27, 2014. Roof installation was completed on
building 1, with metal wall framing and mechanical, electrical, plumbing
rough‐in nearly complete. Installation of door and window frames
commenced. Demolition was completed in building F, which will be
renovated into the new library. The new foundation rebar is in place and
framing will commence in March 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
The project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $9,778,358
Other Funding $0
Total $9,778,358
Budget
Salaries and Benefits $10,492
Supplies $0
Contracts & Services $2,108,378
Construction & Equipment $7,648,045
Soft Costs Contingency $11,443
Total $9,778,358
Percent of Budget Expended 59.0%
Change Order Contingency
Starting Contingency Balance $703 ,700
Remaining Contingency Balance $557,490
Percent of Changes 2.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) December 14, 2010
BOE Approval January 11, 2011
Schematic Design (2) June 14, 2011
BOE Approval June 28, 2011
Submit to DSA February 27, 2012
Approval by DSA December 10, 2012
Authorize to Bid (2) December 18 2012
BOE Approval January 15, 2013
Bid Opening February 28, 2013
Award of Contract (1) March 12, 2013
Notice to Proceed March 25, 2013
Substantial Completion July 16, 2014*
Planned Occupancy August 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
Technology Improvements
A. PROJECT STATUS
Installation of exterior wireless antennas and repeaters at each campus continued.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
Wireless antennas and repeaters installation at each campus is on‐going.
Funding
State Funds $0
Strong Schools Bond Funds $10,485,054
Other Funding $0
Total $10,485,054
Budget
Salaries and Benefits $0
Supplies & Computers $6,850,644
Contracts & Services $539,269
Construction & Equipment $3,095,142
Soft Costs Contingency $0
Total $10,485,054
Percent of Budget Expended 88.2%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
The new Math and English Building was occupied by staff and students on
August 15, 2013. World Language Building classrooms have been in use
since February, 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
The World Languages building move‐in occurred on February 8, 2013, and was occupied with staff and
students on February 11, 2013. The Math & English building move‐in occurred on July 15, 2013, and was
occupied with staff and students on August 15, 2013. The project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $25,035,201
Other Funding $0
Total $25,035,201
Budget
Salaries and Benefits $24,401
Supplies $308,194
Contracts & Services $3,798,481
Construction & Equipment $20,903,848
Soft Costs Contingency $277
Total $25,035,201
Percent of Budget Expended 98.6%
Change Order Contingency
Starting Contingency Balance $ 1,763,200
Remaining Contingency Balance $ 126,231
Percent of Changes 9.3%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Close‐out / Occupancy – August 15, 2013
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 22, 2011
Notice to Proceed August 24, 2011
Substantial Completion July 15, 2013
Planned Occupancy August 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Gunn High School
New Gymnasium
A. PROJECT STATUS
The new gymnasium was occupied on June 7, 2013 and PE classes were
held in the new gym on August 15, 2013. The tennis courts surfacing and
striping was installed and completed August 27, 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
The new gym was occupied on June 7, 2013.
Funding
State Funds $0
Strong Schools Bond Funds $12,914,800
Other Funding $0
Total $12,914,800
Budget
Salaries and Benefits $0
Supplies $19,706
Contracts & Services $2,461,402
Construction & Equipment $10,391,248
Soft Costs Contingency $42,444
Total $12,914,800
Percent of Budget Expended 91.3%
Change Order Contingency
Starting Contingency Balance $834,700
Remaining Contingency Balance $480,396
Percent of Changes 4.3%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 7, 2013
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed August 1, 2011
Substantial Completion May 1, 2013
Planned Occupancy June 7, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Gunn High School
Existing Gymnasium Modernization
A. PROJECT STATUS
Romkon Inc. continued punch list corrections through November 2013.
The modernized Bow gym was occupied by the campus on November 4,
2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
The project is proceeding on‐schedule and within budget. Occupancy by the school occurred on
November 12, 2013.
Funding and Budget
This project is funded by the New Gymnasium project
budget. See that project budget for status.
Change Order Contingency
Starting Contingency Balance $99,800
Remaining Contingency Balance $99,800
Percent of Changes 0.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase:Close‐out / Occupancy – November 12, 2013
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) February 12, 2013
BOE Approval February 26, 2013
Approval by DSA January 23, 2013
Bid Opening April 2, 2013
Award of Contract (1) April 9, 2013
Notice to Proceed May 31, 2013
Substantial Completion October 28, 2013
Planned Occupancy November 12, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Palo Alto High School
Athletic Stadium Improvements
A. PROJECT STATUS
The main project including a concessions building, track re‐surfacing,
new ornamental fence, signage and entry lighting has been completed.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
The ornamental fence was completed on schedule in August 2013. The concessions building was
occupied September 10, 2012. The bleacher replacement work was completed on schedule in June 2013.
Funding
State Funds $0
Strong Schools Bond Funds $5,090,000
Other Funding $0
Total $5,090,000
Budget
Salaries and Benefits $882
Supplies $2,746
Contracts & Services $835,339
Construction & Equipment $4,251,003
Soft Costs Contingency $0
Total $5,090,000
Percent of Budget Expended 93.0%
Change Order Contingency
Starting Contingency Balance $310,200
Remaining Contingency Balance $310,200
Percent of Changes 0.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Close‐out / Occupancy – August 1, 2013
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) February 22, 2011
BOE Approval March 8, 2011
Submit to DSA April 4, 2011
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA July 26, 2011
Bid Opening December 1, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed January 4, 2012
Substantial Completion ‐ Concession August 31, 2012
Planned Occupancy ‐ Concessions September 10, 2012
Bleachers March 31, 2013
Fence Completion August 1, 2013
* Anticipated Dates – Subject to Change
()Denotes number ofBoardofEducation Readings
Page | 20
Palo Alto High School
Haymarket and Tower Building Improvements
A. PROJECT STATUS
All Trusty Builders completed the installation of the new windows on
August 9, 2013, on schedule and within budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
The project completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $1,500,000
Other Funding $0
Total $1,500,000
Budget
Salaries and Benefits $0
Supplies $37,045
Contracts & Services $179,000
Construction & Equipment $1,283,955
Soft Costs Contingency $0
Total $1,500,000
Percent of Budget Expended 81.9%
Change Order Contingency
Starting Contingency Balance $39,200
Remaining Contingency Balance $33,930
Percent of Changes 1.3%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Close‐out / Occupancy – August 9, 2013
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA May 25, 2012
Authorize to Bid (2) April 24, 2012
BOE Approval May 6, 2012
Approval by DSA August 24, 2012
Bid Opening January 17, 2013
Award of Contract (1) January 29, 2013
Notice to Proceed February 21, 2013
Substantial Completion August 9, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Jordan Middle School
A. PROJECT STATUS
Close‐out efforts continued through February 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
The project is completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $19,891,564
Other Funding $0
Total $19,891,564
Budget
Salaries and Benefits $6,111
Supplies $86,265
Contracts & Services $3,723,370
Construction & Equipment $16,007,031
Soft Costs Contingency $68,787
Total $19,891,564
Percent of Budget Expended 90.4%
Change Order Contingency
Starting Contingency Balance $1,398,700
Remaining Contingency Balance $873,071
Percent of Changes 3.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Close‐out / Occupancy – August 15, 2013
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA October 5, 2011
Bid Opening December 8, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed December 27, 2011
Substantial Completion August 1, 2013
Planned Occupancy August 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
J.L. Stanford Middle School
Landscape and Site Improvements
A. PROJECT STATUS
Close‐out efforts continued through February 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
The project completed on schedule and within budget.
Funding and Budget
This project is funded by the J.L. Stanford Middle School
project budget. See that project budget for status.
Percent of Budget Expended 88.5%
Change Order Contingency
Starting Contingency Balance $1,057,800
Remaining Contingency Balance $953,375
Percent of Changes 1.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Close‐out / Occupancy – August 16, 2013
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28, 2010
Submit to DSA May 6, 2011
Authorize to Bid (2) November 29, 2011
BOE Approval December 13, 2011
Approval by DSA January 24, 2012
Bid Opening May 3, 2013
Award of Contract (1) May 8, 2013
Notice to Proceed May 23, 2013
Substantial Completion August 16, 2013
Completion August 16, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Terman Middle School
A. PROJECT STATUS
Close‐out efforts continued through February 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
The project completed on schedule, with exception of the Cafetorium, which was occupied on November
15, 2013. The project is currently within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,312,971
Other Funding $0
Total $13,312,971
Budget
Salaries and Benefits $3,593
Supplies $69,043
Contracts & Services $2,746,045
Construction & Equipment $10,489,542
Soft Costs Contingency $4,748
Total $13,312,971
Percent of Budget Expended 96.3%
Change Order Contingency
Starting Contingency Balance $929,900
Remaining Contingency Balance $56,283
Percent of Changes 9.4%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Close‐out / Occupancy – November 15, 2013
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA September 1, 2011
Bid Opening December 6, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed December 27, 2011
Substantial Completion October 31, 2013
Planned Occupancy November 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Close‐out efforts continued through February 2014.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
The project completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $7,796,550
Other Funding $0
Total $7,796,550
Budget
Salaries and Benefits $32,381
Supplies $98,962
Contracts & Services $2,040,510
Construction & Equipment $5,623,577
Soft Costs Contingency $1,120
Total $7,796,550
Percent of Budget Expended 93.7%
Change Order Contingency
Starting Contingency Balance $642 ,300
Remaining Contingency Balance $186,122
Percent of Changes 7.1%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase:Close‐out / Occupancy – August 15, 2013
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010
BOE Approval September 28, 2010
Submit to DSA April 18, 2011
Authorize to Bid (2) October 11, 2011
BOE Approval October 25, 2011
Approval by DSA November 14, 2011
Bid Opening December 5, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed January 3, 2012
Substantial Completion August 5, 2013
Planned Occupancy August 15, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Move‐in to the new building and other existing classrooms
occurred in December 2011. Students occupied the new building
on January 3, 2012.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
Occupancy occurred on January 3, 2012. Project completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $10,597,870
Other Funding $0
Total $10,597,870
Budget
Salaries and Benefits $7,461
Supplies $49,049
Contracts & Services $2,180,418
Construction & Equipment $8,360,942
Soft Costs Contingency $62,598
Total $10,597,870
Percent of Budget Expended 98.7%
Change Order Contingency
Starting Contingency Balance $748,400
Remaining Contingency Balance $459,113
Percent of Changes 3.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 3, 2012
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010
Award of Contract (1) August 3, 2010
Notice to Proceed August 19, 2010
Substantial Completion November 18, 2011
Planned Occupancy January 3, 2012
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Site Acquisition
525 San Antonio Rd
A. PROJECT STATUS
This site has been leased to Athena Academy.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
The site has been leased to Athena Academy.
Funding
State Funds $0
Strong Schools Bond Funds $8,500,000
Other Funding $0
Total $8,500,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $8,500,000
Construction & Equipment $0
Soft Costs Contingency $0
Total $8,500,000
Percent of Budget Expended 100.0%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
Jordan Middle Schools ‐ Interim Classrooms
A. PROJECT STATUS
The portables were installed and moved into for fall 2011. DSA closeout received November 19, 2012.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
This project completed ahead of schedule and under budget.
Move in occurred on September 30, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $392,120
Other Funding $208,222
Total $600,342
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $180,286
Construction & Equipment $419,292
Soft Costs Contingency $764
Total $600,342
Percent of Budget Expended 76.8%*
*Budget previously expended
Current Phase: Move‐in
Schedule:
Approval by DSA June 16, 2011
Authorize to Bid (2) June 14, 2011
BOE Approval June 28, 2011
Bid Opening July 14, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed July 27, 2011
Substantial Completion September 20, 2011
Occupancy September 30, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
Best Contracting Services Inc. completed the installation of air
conditioning units and cool roof coating in the summer 2011. Some
warranty work on the cool roof coating needs to be completed by
Best.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
Project has been closed‐out.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $1,919
Supplies $0
Contracts & Services $454,610
Construction & Equipment $2,120,580
Soft Costs Contingency $22,891
Total $2,600,000
Percent of Budget Expended 80.9%
Current Phase: Completed
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA October 20, 2010
Approval by DSA February 10, 2011
Authorize to Bid (2) February 22, 2011
BOE Approval March 8, 2011
Bid Opening March 28, 2011
Award of Contract (1) April 8, 2011
Notice to Proceed April 11, 2011
Substantial Completion August 8, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 29
J.L. Stanford Middle School ‐ Interim Classrooms
A. PROJECT STATUS
Coulter Construction completed the work on the relocated
portables in August 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
Project completed on schedule and is currently in close‐out.
This portable relocation project funded by main
JLS project. Refer to pg. 14
Current Phase: Occupancy ‐August 11, 2011
Schedule:
Approval by DSA April 19, 2011
Jordan Project June 16, 2011
Authorize to Bid (2) May 10, 2011
BOE Approval May 24, 2011
Bid Opening June 1, 2011
Award of Contract (1) June 13, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 8, 2011
Planned Occupancy August 15, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 30
Fairmeadow Elementary School
Portable Relocation Project
A. PROJECT STATUS
Relocation of the portable was complete and occupied on August 8, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 6.4
D. PROJECT OVERVIEW:
Project completed ahead of schedule on August 8, 2011.
This portable relocation project funded by main
JLS project. Refer to pg. 14
Current Phase: Occupancy ‐August 8, 2011
Schedule:
Architect Contract (2) February 15, 2011
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA March 3, 2011
Approval by DSA March 3, 2011
Authorize to Bid (2) May 11, 2011
BOE Approval May 24, 2011
Bid Opening June 14, 2011
Award of Contract (1) June 14, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 1, 2011
Planned Occupancy August 8, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 31
Elementary Classroom Improvements
Interactive Whiteboards and Sound Assist System Installation
A. PROJECT STATUS
Installation of SmartBoards and Lightspeed sound assist systems were
completed for all elementary school classrooms and libraries in April
2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
All SmartBoards and Lightspeed sound systems installed.
Funding
State Funds $0
Strong Schools Bond Funds $2,004,889
Other Funding $0
Total $2,004,889
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $275,488
Construction & Equipment $1,729,401
Soft Costs Contingency $0
Total $2,004,889
Percent of Budget Expended 93.9%
Current Phase: Complete ‐May 15, 2011
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) November 9, 2010
BOE Approval November 23, 2010
Bid Opening February 25, 2011
Award of Contract (1) March 8, 2011
Notice to Proceed March 9, 2011
Completion May 15, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 32
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
The fields were available for play on February 1, 2011, and final
change order negotiations completed on March 9, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
Field was open for use on February 1, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $2,609,680
Other Funding $1,007,255
Total $3,616,935
Budget
Salaries and Benefits $0
Supplies $1,506
Contracts & Services $698,293
Construction & Equipment $2,916,682
Soft Costs Contingency $454
Total $3,616,935
Percent of Budget Expended 100.0%
Change Order Contingency
Starting Contingency Balance $269,300
Remaining Contingency Balance $231,185
Percent of Changes 1.4%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –February 1, 2011
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 18, 2008
BOE Approval December 09, 2008
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) February 24, 2009
BOE Approval March 17, 2009
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion January 31, 2011
Planned Occupancy February 1, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 33
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
This facility was available for instruction in January 2010. DSA closeout
received on July 18, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,082,402
Other Funding $0
Total $5,082,402
Budget
Salaries and Benefits $1,061
Supplies $88,985
Contracts & Services $1,002,057
Construction & Equipment $3,990,300
Soft Costs Contingency $0
Total $5,082,402
Percent of Budget Expended 99.3%
Change Order Contingency
Starting Contingency Balance $349,000
Remaining Contingency Balance $141,967
Percent of Changes 41.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 34
Gunn High School
Aquatic Center
A. PROJECT STATUS
This facility was available for use in July 2009, and has been closed
out with DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $4,865,423
Other Funding $0
Total $4,865,423
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $647,169
Construction & Equipment $4,218,253
Soft Costs Contingency $0
Total $4,865,423
Percent of Budget Expended 99.9%
Change Order Contingency
Starting Contingency Balance $389,887
Remaining Contingency Balance $195,148
Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 35
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education for approval on September 8, which became the
program documents for the new projects at each campus. These
projects for pre‐design work have been closed, and funds will be
transferred to the program contingency on June 14, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
This project has been completed. Board approval received on September 8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $56,488
Other Funding $0
Total $56,488
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $56,488
Construction & Equipment $0
Soft Costs Contingency $0
Total $56,488
Percent of Budget Expended 96.8%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 36
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education has put new development for Garland on
hold until a growth plan is established for the elementary schools.
The board voted to terminate the lease with Stratford School in
June 2011. Discussions with the Board on future plans for growth
at the elementary schools are ongoing.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,915,789
Construction & Equipment $17,400,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: On Hold
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 37
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
The Board of Education (BOE) approved the master plans for both
high schools, and these projects have been closed, with funds
transferred to the respective campus reserve funds.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
Master planning effort complete.
Funding
State Funds $0
Strong Schools Bond Funds $285,387
Other Funding $0
Total $285,387
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $285,387
Construction & Equipment $0
Soft Costs Contingency $0
Total $285,387
Percent of Budget Expended 86.2%
Current Phase: Complete
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010
Paly MP Revision Approval (2) October 9, 2010
Gunn MP Revision Approval (2) October 12, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 38
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
This project has been put on hold until a growth plan is established for the
elementary schools.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
Project is currently on hold.
Funding
State Funds $0
Strong Schools Bond Funds $70,550
Other Funding $0
Total $70,550
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $70,550
Construction & Equipment $60
Soft Costs Contingency $0
Total $70,550
Percent of Budget Expended 81.0%
Current Phase: On Hold
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) November 9, 2010
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 39
Elementary Classroom Improvements
A. PROJECT STATUS
DSA comments were returned to Gelfand for Phase 1 plans that include
new lighting, adding operable windows and coverings, ventilation, and
replacement of ceiling tiles for classrooms at Barron Park and El
Carmelo elementary schools. The authorization to bid has been placed
on hold pending further discussions with the BOE about elementary
growth planning.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $2,004,889
Other Funding $0
Total $2,004,889
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $275,488
Construction & Equipment $1,729,401
Soft Costs Contingency $0
Total $2,004,889
Percent of Budget Expended 93.9%
Phase 1 Schools: Barron Park and El Carmelo
Current Phase: On Hold
Schedule:
Architect Contract (2) June 8, 2010
BOE Approval June 22, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 9, 2010
BOE Approval December 7, 2010
Submit to DSA December 23, 2010
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.