MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
May 2013
Strong Schools Bond
Capital Improvement Projects
Prepared by
fs3Hodges
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Capital Projects
Gunn High School – New Classroom Building and World Languages Building page 6
Gunn High School – Phase I ‐ Parking and Drop‐off Sitework Improvement page 7
Gunn High School – New Gymnasium page 8
Gunn High School – Existing Gymnasium Modernization page 9
Gunn High School – L31 and MS Buildings Renovation page 10
Palo Alto High School – Athletic Stadium Improvements page 11
Palo Alto High School – New Classroom Building and Media Arts page 12
Palo Alto High School – Performing Arts Center page 13
Palo Alto High School – Haymarket and Tower Building Improvements page 14
Palo Alto High School – Science Building Addition Page 15
Jordan Middle School page 16
J.L. Stanford Middle School page 17
J.L. Stanford Middle School – Landscape and Site Improvements page 18
Terman Middle School page 19
Fairmeadow Elementary School – New Classroom Buildings and Modernization page 20
Duveneck Elementary School – New Classroom Buildings and Modernization page 21
Technology page 22
Completed Capital Projects
Ohlone Elementary School page 23
Property Acquisition – 525 San Antonio Rd page 24
Jordan Middle School – Interim Classrooms page 25
Gunn High School – Air Conditioning of Existing Buildings page 26
J.L. Stanford Middle School – Interim Classrooms page 27
Fairmeadow Elementary School – Portable Relocation page 28
Elementary Classroom Improvements – Interactive Whiteboard & Sound Assist System page 29
Palo Alto High School – Multi‐use Field page 30
Gunn High School – Industrial Arts Renovation page 31
Gunn High School – Aquatic Center page 32
Middle School Pre‐Design page 33
Inactive Capital Projects
Garland Elementary School page 34
High School Master Plan page 35
Hoover Elementary School page 36
Elementary Classroom Improvements page 37
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
Gunn High School – New Classroom Building and World Languages Building
BRCO Constructors are working on interior finishes of the new Math and English building. Move‐in is scheduled for
July 15, 2013. At the World Language Building, classrooms have been in use since February, 2013.
Gunn High School – Phase I ‐ Parking and Drop‐off Sitework Improvement
DLM continued updating the design with refinements provided from the City of Palo Alto and the County of Santa
Clara for off‐site work at Miranda Ave intersection. Construction may commence after the completion of the
classroom building project and the portables on this side of campus are vacated.
Gunn High School – New Gymnasium
S.J. Amoroso (SJA) continued to work to wrap up construction and is anticipated to turn over the building for
school use in June 2013. Occupancy anticipated in early June, 2013.
Gunn High School – Existing Gymnasium Modernization
Romkon Inc. was awarded a contract to perform the modernization work on the existing gym. Romkon is
scheduled to commence demolition in June, 2013, when school dismissed for summer break.
Gunn High School – L‐31 and MS Buildings Renovation
DLM is scheduled to present schematic plans to the BOE on June 11, 2013 for approval. Minor improvements are
planned to occur this summer for the programs located in the MS building including interior access to a restroom
and interior offices.
Palo Alto High School – Athletics Stadium Improvements
Taisei (TCC) continued to work on punchlist corrections, including the installation of emergency lighting. Also, as
part of the overall project, the track resurfacing to start in early June, 2013 and the ornamental fence panels were
installed.
Palo Alto High School – New Classroom Building and Media Arts Building
TCC continued interior and exterior work of at the new Math/Social Sciences building. At the Media Arts building,
the contractor continued exterior work and installation of interior drywall.
Palo Alto High School – Performing Arts Center (PAC)
DSA review on the March 29, 2013 plans continues. This project will be bid after completion of the new Classroom
and Media Arts buildings.
Palo Alto High School – Haymarket and Tower Building Improvements
All Trusty Builders are scheduled to commence demolition of the existing windows in June, 2013, after school
dismisses for summer break. This project is moving on schedule.
Palo Alto High School – Science Building Addtion
DLM presented an exterior option to the FSC on May 15, 2013. After discussion with the FSC it was determined
that DLM would continue to refine the exterior design and return for discussion in early June 2013.
Jordan Middle School
SJA are scheduled to commence work on the modernization of F, H, J and K wings once school dismisses for
summer break. Modernization work continued in G‐wing, the science building and M wing, the new art
classrooms. Occupancy of these buildings is anticipated in early August 2013.
Page | 4
J.L. Stanford Middle School
Sausal Corporation continued work on the new two‐story classroom building with interior finishes. Modernization
work in the science building, gymnasium and administration building commenced on June 3, 2013. Work will
continue through the summer with occupancy anticipated in August 2013.
J.L. Stanford Middle School – Landscape and Sitework Improvements
Scapes, Inc. was awarded a contract on May 8, 2013 and is anticipated to start demolition June 3, 2013, once
school dismisses for summer break. The project is anticipated to be complete in August 2013.
Terman Middle School
Hagensen Pacific continued work at the new Library for move‐in anticipated on June 25, 2013. Summer
modernization work scheduled to commence in B, G, H and J wings once school dismisses for summer break.
Project completion anticipated in August 2013.
Fairmeadow Elementary School – New Classroom Building and Modernization
Best Contracting Services (BCS) continued installation of casework, lighting and finishes in the new classroom
building. Modernization work in buildings A and D, and sitework are scheduled to commence on June 3, 2013. The
new building occupancy and project completion is anticipated in August 2013.
Duveneck Elementary School – New Classroom Buildings and Modernization
Alpha Bay Builders continued to prepare the building pads for buildings 1, 2 and 3. The concrete pour for building
2 was completed and modernization work to commence on June 3, 2013 with casework and plumbing upgrades in
buildings A and D.
Technology
Installation of exterior wireless antennas and repeaters for Palo Alto High School has commenced. Each campus
will be scheduled to receive exterior wireless antennas and repeaters after the high schools are complete.
COMPLETED CAPITAL PROJECTS
525 San Antonio Road – Site Acquisition
This site has been leased to Athena Academy.
Ohlone Elementary School – New Classroom Building and Modernization
Move‐in to the new building and other existing classrooms occurred in December 2011. Students occupied the
new building on January 3, 2012.
Jordan Middle School ‐ Interim Classrooms
The portables were installed and moved into for fall 2011. DSA closeout received November 19, 2012.
Gunn High School – Air Conditioning of Existing Buildings
Best Contracting Services Inc. completed the installation of air conditioning units and cool roof coating in the
summer 2011.
J.L. Stanford Middle School ‐ Interim Classrooms
Coulter Construction completed the work on the relocated portables in August 2011.
Fairmeadow Elementary School – Portable Relocation
Relocation of the portable was complete and occupied on August 8, 2011.
Page | 5
Elementary Classroom Improvements – Installation of Interactive Whiteboards and Sound Assist Systems
Installation of SmartBoards and Lightspeed sound assist systems were completed for all elementary school
classrooms and libraries in April 2011.
Palo Alto High School – Multi‐use Field
The fields were available for play on February 1, 2011, and final change order negotiations completed on March 9,
2011.
Gunn High School – Industrial Arts Addition & Renovation
This facility was available for instruction in January 2010. DSA closeout received on July 18, 2011.
Gunn High School – Aquatic Center
This facility was available for use in July 2009, and has been closed out with DSA.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education for approval on
September 8, which became the program documents for the new projects at each campus. These projects for pre‐
design work have been closed, and funds were transferred to the program contingency on June 14, 2011.
INACTIVE CAPITAL PROJECTS
Garland Elementary School Renovation
The Board of Education has put new development for Garland on hold until a growth plan is established for the
elementary schools. The board voted to terminate the lease with Stratford School in June 2011. Discussions with
the Board on future plans for growth at the elementary schools are ongoing.
High School Master Plan
The Board of Education (BOE) approved the master plans for both high schools, and these projects have been
closed, with funds transferred to the respective campus reserve funds.
Hoover Elementary School – Pre‐Design
This project has been put on hold until a growth plan is established for the elementary schools.
Elementary Classroom Improvements – Phase 1 Schools Barron Park and El Carmelo
The project has been placed on hold pending further discussions with the BOE about elementary growth planning.
Board Actions in May
May 7, 2013
Consent 4 – Appropriation of Strong School Bond Funds
Action 19 – Award of the Contract for Construction of the J.L. Stanford Middle School Landscape and Site
Improvements Project
May 28, 2013
Consent 6 – Approval of Strong Schools Bond Change Orders
Action 26 – Authorization to Award a Contract for Resurfacing of the Palo Alto High School Stadium Track
ABCC / AB - CC / BA - BGunn High School - High School Master Plan 172,390 166,328 124,545 72.2%41,783 74.88%6,062Gunn High School 1 - Aquatic Center 4,865,425 4,862,530 4,862,530 99.9%0 100.00%2,895Gunn High School 2 - I.A Building5,082,402 5,060,578 5,059,213 99.5%1,365 99.97%21,824Gunn High School 3 - AD2- close out5,7775,7775,777 100.0%0 100.00%0Gunn High School 4 - New classroom Buildings25,035,201 24,357,554 20,149,027 80.5%4,208,527 82.72% 677,647Gunn High School 5 - Parking & Drop Off improvements3,940,000 460,991 165,018 4.2%295,973 35.80% 3,479,009Gunn High School 6- New/Auxiliary Gymnasium12,914,800 11,294,013 9,933,747 76.9%1,360,266 87.96% 1,620,787Gunn High School 7- A/C2,600,000 2,103,866 2,102,366 80.9%1,500 99.93% 496,134Gunn High School 8 - MS & L-31 Buildings2,120,83900 0.0%0 0.00% 2,120,839Gunn High School - Reserved19,374,24200 0.0%0 0.00% 19,374,242Palo Alto High Schools - High School Master Plan172,999 167,759 150,276 86.9%17,483 89.58%5,240Palo Alto High School 1 - Stadium Field5,090,000 4,867,823 4,331,443 85.1%536,380 88.98% 222,177Palo Alto High School 2 - Multi-Use Field (Multi-Fund)2,609,680 2,609,680 2,609,680 100.0%0 100.00%0Palo Alto high School 3 - New classroom & Media Art Building37,140,001 33,796,002 25,664,968 69.1%8,131,034 75.94% 3,343,999Palo Alto High School 4 - New Theater24,395,049 1,696,062 1,157,832 4.7%538,230 68.27% 22,698,987Palo Alto High School 5 - Haymarket and Tower Admin. Building1,499,999 1,160,015 457,574 30.5%702,441 39.45% 339,984Palo Alto High School 6- Science Addition5,532,204 191,0480 0.0%191,048 0.00% 5,341,156Palo Alto High School - Reserved25,074,44300 0.0%0 0.00% 25,074,443Jordan Middle School -Program Management- MS Pre-Design18,890 18,89017,826 94.4%1,064 94.37%0Jordan Middle Schools 1- Interim Classrooms600,342 464,456 461,330 76.8%3,126 99.33% 135,886Jordan Middle School 2- Improvements19,891,564 18,951,052 14,640,231 73.6%4,310,821 77.25% 940,512J.L.S Middle School - Program Management- MS Pre-Design18,799 18,79918,408 97.9%391 97.92%0J.L.S Middle School 1 - Interim Classrooms 446,844 400,612 398,788 89.2%1,824 99.54%46,232 J.L.S Middle School 2- Improvements17,184,699 15,421,770 9,829,659 57.2%5,592,111 63.74% 1,762,929Terman Middle School - Program Management- MS Pre-Design18,799 18,79918,423 98.0%376 98.00%0Terman Middle School 1- Improvements13,312,971 12,864,353 10,564,393 79.4%2,299,960 82.12% 448,618PAUSD Elementary Schools - Program Management- Elem. Growth Plan145,000 98,48089,820 61.9%8,660 91.21%46,520Addison Elementary School 1-Phase I21,267 21,26721,267 100.0%0 100.00%0Duveneck Elementary School 1-Phase I11,088,759 10,513,038 1,959,514 17.7%8,553,524 18.64% 575,721Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3%1,166 99.59% 21,897,265Fairmeadow Elementary School 1- Phase I 9,543,750 9,125,281 5,605,255 58.7%3,520,026 61.43% 418,469Hoover Elementary School 1-Phase I70,550 70,55057,165 81.0%13,385 81.03%0Ohlone Elementary School 1- Phase I 10,597,870 10,577,255 10,459,277 98.7%117,978 98.88%20,615Elementary Schools 1 - Elementary Classroom Improvements2,004,889 1,881,619 1,881,619 93.9%0 100.00% 123,270Elementary Schools - Reserved34,527,65200 0.0%0 0.00% 34,527,652PAUSD - Program Management8,481,934 6,700,641 6,140,629 72.4%560,012 91.64% 1,781,293PAUSD - Technology 9,361,656 8,107,428 8,055,863 86.1%51,565 99.36% 1,254,228PAUSD - Technology -Reserved4,545,71000 0.0%0 0.00% 4,545,710PAUSD - Reserved6,055,69700 0.0%0 0.00% 6,055,697525 San Antonio -Property Acquisition8,500,000 8,500,000 8,500,000 100.0%0 100.00%0Bond Issuance Cost2,168,731 2,168,731 2,168,731 100.0%0 100.00%0Total358,410,368 199,004,325 157,942,30641,062,019159,406,043Prepared by: Business Services Department based on QSS accounting SystemExpenditures Budget BalanceCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond5/31/2013Percent of ExpendedContract Balance
Page | 6
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
BRCO Constructors are working on interior finishes of the new Math and
English building. Move‐in is scheduled for July 15, 2013. At the World
Language Building, classrooms have been in use since February, 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
The World Languages building move‐in occurred on February 8, 2013, and was occupied with staff and
students on February 11, 2013. The Math & English building occupancy is on schedule. The project is
currently within budget.
Funding
State Funds $0
Strong Schools Bond Funds $25,035,201
Other Funding $0
Total $25,035,201
Budget
Salaries and Benefits $13,253
Supplies $0
Contracts & Services $4,466,982
Construction & Equipment $20,482,302
Soft Costs Contingency $72,664
Total $25,035,201
Percent of Budget Expended 80.5%
Change Order Contingency
Starting Contingency Balance $ 1,763,200
Remaining Contingency Balance $ 1,579,878
Percent of Changes 10.3%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 22, 2011
Notice to Proceed August 24, 2011
Substantial Completion July 15, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 7
Gunn High School
Phase I – Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
DLM continued updating the design with refinements provided
from the City of Palo Alto and the County of Santa Clara for off‐
site work at Miranda Ave intersection. Construction may
commence after the completion of the classroom building project
and the portables on this side of campus are vacated.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
Phase I, Miranda Ave. parking and drop‐off BOE authorization to bid anticipated June 18, 2013. Plans will
be submitted to DSA in July 2013.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $898,978
Construction & Equipment $2,919,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 4.2%
Current Phase:Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 19, 2012
BOE Approval June 26, 2012
Schematic Design (2) December 18, 2012
BOE Approval January 15, 2013
Authorize to Bid (2) June 11, 2013
BOE Approval June18, 2013
Submit to DSA July 3, 2013*
Approval by DSA August 1, 2013*
Bid Opening September 30, 2013*
Award of Contract (1) October 9, 2013*
Notice to Proceed October 19, 2013*
Substantial Completion February 28, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
New Gymnasium
A. PROJECT STATUS
S.J. Amoroso (SJA) continued to work to wrap up construction and is
anticipated to turn over the building for school use in June 2013.
Occupancy anticipated in early June, 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
The project move‐in has been pushed back, with occupancy of the gym received on June 7, 2013.
Funding
State Funds $0
Strong Schools Bond Funds $12,914,800
Other Funding $0
Total $12,914,800
Budget
Salaries and Benefits $0
Supplies $1,001
Contracts & Services $2,677,293
Construction & Equipment $10,158,210
Soft Costs Contingency $78,296
Total $12,914,800
Percent of Budget Expended 76.9%
Change Order Contingency
Starting Contingency Balance $834,700
Remaining Contingency Balance $554,484
Percent of Changes 3.4%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA May 27, 2011
Bid Opening July 13, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed August 1, 2011
Substantial Completion May 1, 2013
Planned Occupancy June 7, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Gunn High School
Existing Gymnasium Modernization
A. PROJECT STATUS
Romkon Inc. was awarded a contract to perform the modernization work on the existing gym. Romkon is
scheduled to commence demolition in June, 2013, when school dismissed for summer break.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
The project is proceeding on schedule, with occupancy anticipated in September 2013.
Funding
State Funds $0
Strong Schools Bond Funds $998,000
Other Funding $0
Total $998,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $0
Construction & Equipment $998,000
Soft Costs Contingency $0
Total $998,000
Percent of Budget Expended 0.0%
Change Order Contingency
Starting Contingency Balance $99,800
Remaining Contingency Balance $99,800
Percent of Changes 0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Bid & Award
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) February 12, 2013
BOE Approval February 26, 2013
Approval by DSA January 23, 2013
Bid Opening April 2, 2013
Award of Contract (1) April 9, 2013
Notice to Proceed May 31, 2013
Substantial Completion September 6, 2013
Planned Occupancy September 28, 2013
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Gunn High School
MS and L‐31 Buildings Renovation
A. PROJECT STATUS
DLM is scheduled to present schematic plans to the BOE on June 11, 2013 for approval. Minor improvements
are planned to occur this summer for the programs located in the MS building including interior access to a
restroom and interior offices.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
BOE schematic design approval scheduled for in June 2013. Design development will continue for site
review in Fall 2013.
Funding
State Funds $0
Strong Schools Bond Funds $2,120,839
Other Funding $0
Total $2,120,839
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $426,700
Construction & Equipment $1,670,000
Soft Costs Contingency $24,139
Total $2,120,839
Percent of Budget Expended 0.0%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) June 11, 2013
BOE Approval June 18, 2013
Submit to DSA November 20, 2013*
Authorize to Bid (2) April 8, 2013*
BOE Approval April 22, 2013*
Approval by DSA May 2, 2013*
Bid Opening June 1, 2013*
Award of Contract (1) June 16, 2013*
Notice to Proceed June 30, 2013*
Substantial Completion December 22, 2013*
Planned Occupancy January 2, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Athletic Stadium Improvements
A. PROJECT STATUS
Taisei (TCC) continued to work on punchlist corrections, including the
installation of emergency lighting. Also, as part of the overall project,
the track resurfacing to start in early June, 2013 and the ornamental
fence panels were installed.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
This concessions building was occupied September 10, 2012. The bleacher replacement work is on
schedule.
Funding
State Funds $0
Strong Schools Bond Funds $5,090,000
Other Funding $0
Total $5,090,000
Budget
Salaries and Benefits $882
Supplies $0
Contracts & Services $842,156
Construction & Equipment $4,221,162
Soft Costs Contingency $25,800
Total $5,090,000
Percent of Budget Expended 85.1%
Change Order Contingency
Starting Contingency Balance $310,200
Remaining Contingency Balance $265,290
Percent of Changes 14.5%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) February 22, 2011
BOE Approval March 8, 2011
Submit to DSA April 4, 2011
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA July 26, 2011
Bid Opening December 1, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed January 4, 2012
Substantial Completion ‐ Concession August 31, 2012
Planned Occupancy ‐ Concessions September 10, 2012
Bleachers March 31, 2013*
* Anticipated Dates – Subject to Change
( )Denotes number ofBoardofEducation Readings
Page | 12
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
TCC continued interior and exterior work of at the new Math/Social
Sciences building. At the Media Arts building, the contractor continued
exterior work and installation of interior drywall.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
The project move‐in has been pushed back, with occupancy of the Media Arts and Math/Social Sciences
buildings anticipated in January, 2014. The project is currently within budget.
Funding
State Funds $0
Strong Schools Bond Funds $37,140,000
Other Funding $0
Total $37,140,000
Budget
Salaries and Benefits $14,721
Supplies $26,519
Contracts & Services $7,066,446
Construction & Equipment $29,713,481
Soft Costs Contingency $318,834
Total $37,140,000
Percent of Budget Expended 69.1%
Change Order Contingency
Starting Contingency Balance $2,515,000
Remaining Contingency Balance $1,234,957
Percent of Changes 49.1%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) March 8, 2011
BOE Approval March 22, 2011
Approval by DSA April 28, 2011
Bid Opening June 30, 2011
Award of Contract (1) July 12, 2011
Notice to Proceed August 4, 2011
Substantial Completion September 20, 2013*
Planned Occupancy January, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Palo Alto High School
Performing Arts Center (PAC)
A. PROJECT STATUS
DSA review on the March 29, 2013 plans continues. This project will be bid
after completion of the new Classroom and Media Arts buildings.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
Project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $24,395,049
Other Funding $0
Total $24,395,049
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $4,481,640
Construction & Equipment $19,745,000
Soft Costs Contingency $168,409
Total $24,395,049
Percent of Budget Expended 4.7%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (3) June 14, 2011
BOE Approval December 13, 2011
BOE Approval January 17, 2012
Submit to DSA March 28, 2013*
Approval by DSA October 22, 2013*
Authorize to Bid (2) October 24, 2013*
BOE Approval November 14, 2013*
Bid Opening December 22, 2013*
Award of Contract (1) January 8, 2013*
Notice to Proceed January 18, 2013*
Substantial Completion July 13, 2015*
Planned Occupancy August 17, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Palo Alto High School
Haymarket and Tower Building Improvements
A. PROJECT STATUS
All Trusty Builders are scheduled to commence demolition of the existing windows in June, 2013, after school
dismisses for summer break. This project is moving on schedule.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
All Trusty Builders anticipated to commence work once school dismisses for summer break.
Funding
State Funds $0
Strong Schools Bond Funds $1,500,000
Other Funding $0
Total $1,500,000
Budget
Salaries and Benefits $0
Supplies $400
Contracts & Services $179,000
Construction & Equipment $1,289,600
Soft Costs Contingency $31,000
Total $1,500,000
Percent of Budget Expended 30.5%
Change Order Contingency
Starting Contingency Balance $39,200
Remaining Contingency Balance $33,930
Percent of Changes 1.2%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA May 25, 2012
Authorize to Bid (2) April 24, 2012
BOE Approval May 6, 2012
Approval by DSA August 24, 2012
Bid Opening January 17, 2013
Award of Contract (1) January 29, 2013
Notice to Proceed February 21, 2013
Substantial Completion August 9, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
Palo Alto High School
Science Building Addition
A. PROJECT STATUS
DLM presented an exterior option to the FSC on May 15, 2013. After discussion with the FSC it was
determined that DLM would continue to refine the exterior design and return for discussion in early June
2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
DLM to present exterior designs to FSC in June, 2013.
Funding
State Funds $0
Strong Schools Bond Funds $5,532,204
Other Funding $0
Total $5,532,204
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $993,052
Construction & Equipment $4,489,500
Soft Costs Contingency $49,652
Total $5,532,204
Percent of Budget Expended 0.0%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 12, 2013
BOE Approval March 19, 2013
Conceptual Design (2) March 12, 2013
BOE Approval March 19, 2013
Schematic Design (2) September 10, 2013*
BOE Approval September 24, 2013*
Submit to DSA January 7, 2013*
Authorize to Bid (2)
BOE Approval TBD
Approval by DSA TBD
Bid Opening TBD
Award of Contract (1) TBD
Notice to Proceed TBD
Substantial Completion TBD
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
Jordan Middle School
A. PROJECT STATUS
SJA are scheduled to commence work on the modernization of F, H, J and K
wings once school dismisses for summer break. Modernization work
continued in G‐wing, the science building and M wing, the new art
classrooms. Occupancy of these buildings is anticipated in early August 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
The project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $19,891,546
Other Funding $0
Total $19,891,546
Budget
Salaries and Benefits $0
Supplies $56,407
Contracts & Services $3,635,718
Construction & Equipment $16,007,031
Soft Costs Contingency $192,408
Total $19,891,564
Percent of Budget Expended 76.8%
Change Order Contingency
Starting Contingency Balance $1,398,700
Remaining Contingency Balance $1,154,017
Percent of Changes 1.7%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA October 5, 2011
Bid Opening December 8, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed December 27, 2011
Substantial Completion August 1, 2013*
Planned Occupancy August 26, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
J.L. Stanford Middle School
A. PROJECT STATUS
Sausal Corporation continued work on the new two‐story classroom
building with interior finishes. Modernization work in the science
building, gymnasium and administration building commenced on
June 3, 2013. Work will continue through the summer with
occupancy anticipated in August 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
The project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,699
Other Funding $0
Total $17,184,699
Budget
Salaries and Benefits $0
Supplies $6,958
Contracts & Services $3,513,856
Construction & Equipment $13,421,500
Soft Costs Contingency $242,385
Total $17,184,699
Percent of Budget Expended 57.2%
Change Order Contingency
Starting Contingency Balance $1,057,800
Remaining Contingency Balance $1,001,360
Percent of Changes 0.5%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28, 2010
Submit to DSA May 6, 2011
Authorize to Bid (2) November 29, 2011
BOE Approval December 13, 2011
Approval by DSA January 24, 2012
Bid Opening May 3, 2012
Award of Contract (1) May 8, 2012
Notice to Proceed May 30, 2012
Substantial Completion August 24, 2013*
Planned Occupancy January 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
J.L. Stanford Middle School
Landscape and Site Improvements
A. PROJECT STATUS
Scapes, Inc. was awarded a contract on May 8, 2013 and is anticipated
to start demolition June 3, 2013, once school dismisses for summer
break. The project is anticipated to be complete in August 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
The project is proceeding on schedule and within budget.
Funding and Budget
This project is funded by the J.L. Stanford Middle School
project budget. See that project budget for status.
Percent of Budget Expended 62.6%
Change Order Contingency
Starting Contingency Balance $1,057,800
Remaining Contingency Balance $1,001,360
Percent of Changes 0.5%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Bid & Award
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28, 2010
Submit to DSA May 6, 2011
Authorize to Bid (2) November 29, 2011
BOE Approval December 13, 2011
Approval by DSA January 24, 2012
Bid Opening May 3, 2013
Award of Contract (1) May 8, 2013
Notice to Proceed May 23, 2013
Substantial Completion August 16, 2013*
Planned Occupancy August 16, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Terman Middle School
A. PROJECT STATUS
Hagensen Pacific continued work at the new Library for move‐in anticipated
on June 25, 2013. Summer modernization work scheduled to commence in
B, G, H and J wings once school dismisses for summer break. Project
completion anticipated in August 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
The project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,312,972
Other Funding $0
Total $13,312,972
Budget
Salaries and Benefits $1,267
Supplies $0
Contracts & Services $2,663,387
Construction & Equipment $10,517,515
Soft Costs Contingency $130,803
Total $13,312,972
Percent of Budget Expended 79.4%
Change Order Contingency
Starting Contingency Balance $929,900
Remaining Contingency Balance $304,553
Percent of Changes 6.7%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA December 21, 2010
Authorize to Bid (2) June 28, 2011
BOE Approval July 19, 2011
Approval by DSA September 1, 2011
Bid Opening December 6, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed December 27, 2011
Substantial Completion August 7, 2013*
Planned Occupancy September 4, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Best Contracting Services (BCS) continued installation of casework,
lighting and finishes in the new classroom building. Modernization
work in buildings A and D, and sitework are scheduled to commence
on June 3, 2013. The new building occupancy and project
completion is anticipated in August 2013.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
The project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $9,543,751
Other Funding $0
Total $9,543,751
Budget
Salaries and Benefits $2,380
Supplies $3,132
Contracts & Services $1,936,022
Construction & Equipment $7,500,180
Soft Costs Contingency $102,037
Total $9,543,751
Percent of Budget Expended 58.7%
Change Order Contingency
Starting Contingency Balance $642 ,300
Remaining Contingency Balance $642,300
Percent of Changes 0.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010
BOE Approval September 28, 2010
Submit to DSA April 18, 2011
Authorize to Bid (2) October 11, 2011
BOE Approval October 25, 2011
Approval by DSA November 14, 2011
Bid Opening December 5, 2011
Award of Contract (1) December 13, 2011
Notice to Proceed January 3, 2012
Substantial Completion August 5, 2013*
Planned Occupancy August 20, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Duveneck Elementary School
New Classroom Buildings and Modernization
A. PROJECT STATUS
Alpha Bay Builders continued to prepare the building pads for buildings
1, 2 and 3. The concrete pour for building 2 was completed and
modernization work to commence on June 3, 2013 with casework and
plumbing upgrades in buildings A and D.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
The project is proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $11,088,759
Other Funding $0
Total $11,088,759
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,159,389
Construction & Equipment $8,803,087
Soft Costs Contingency $126,283
Total $11,088,759
Percent of Budget Expended 17.7%
Current Phase: Construction
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) December 14, 2010
BOE Approval January 11, 2011
Schematic Design (2) June 14, 2011
BOE Approval June 28, 2011
Submit to DSA February 27, 2012
Approval by DSA December 10, 2012
Authorize to Bid (2) December 18 2012
BOE Approval January 15, 2013
Bid Opening February 28, 2013
Award of Contract (1) March 12, 2013
Notice to Proceed March 25, 2013
Substantial Completion July 16, 2014*
Planned Occupancy August 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Technology Improvements
A. PROJECT STATUS
Installation of exterior wireless antennas and repeaters for Palo Alto High School has
commenced. Each campus will be scheduled to receive exterior wireless antennas and
repeaters after the high schools are complete.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
Wireless antennas and repeaters installation at each campus is on‐going.
Funding
State Funds $0
Strong Schools Bond Funds $9,361,656
Other Funding $0
Total $9,361,656
Budget
Salaries and Benefits $0
Supplies & Computers $5,727,246
Contracts & Services $539,269
Construction & Equipment $3,095,142
Soft Costs Contingency $0
Total $9,361,656
Percent of Budget Expended 86.1%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Move‐in to the new building and other existing classrooms
occurred in December 2011. Students occupied the new building
on January 3, 2012.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
Occupancy occurred on January 3, 2012. Project completed on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $8,042
Supplies $56,052
Contracts & Services $2,368,861
Construction & Equipment $9,172,412
Soft Costs Contingency $62,598
Total $11,667,965
Percent of Budget Expended 98.7%
Change Order Contingency
Starting Contingency Balance $748,400
Remaining Contingency Balance $602,714
Percent of Changes 1.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 3, 2012
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010
Award of Contract (1) August 3, 2010
Notice to Proceed August 19, 2010
Substantial Completion November 18, 2011
Planned Occupancy January 3, 2012
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Site Acquisition
525 San Antonio Rd
A. PROJECT STATUS
This site has been leased to Athena Academy.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
The site has been leased to Athena Academy.
Funding
State Funds $0
Strong Schools Bond Funds $8,500,000
Other Funding $0
Total $8,500,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $8,500,000
Construction & Equipment $0
Soft Costs Contingency $0
Total $8,500,000
Percent of Budget Expended 100.0%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Jordan Middle Schools ‐ Interim Classrooms
A. PROJECT STATUS
The portables were installed and moved into for fall 2011. DSA closeout received November 19, 2012.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
This project completed ahead of schedule and under budget.
Move in occurred on September 30, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $392,120
Other Funding $208,222
Total $600,342
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $180,286
Construction & Equipment $419,292
Soft Costs Contingency $764
Total $600,342
Percent of Budget Expended 76.8%*
*Budget previously expended
Current Phase: Move‐in
Schedule:
Approval by DSA June 16, 2011
Authorize to Bid (2) June 14, 2011
BOE Approval June 28, 2011
Bid Opening July 14, 2011
Award of Contract (1) July 20, 2011
Notice to Proceed July 27, 2011
Substantial Completion September 20, 2011
Occupancy September 30, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
Best Contracting Services Inc. completed the installation of air
conditioning units and cool roof coating in the summer 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
Project has been closed‐out.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $1,919
Supplies $0
Contracts & Services $454,160
Construction & Equipment $2,120,580
Soft Costs Contingency $22,891
Total $2,600,000
Percent of Budget Expended 80.9%
Current Phase: Completed
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA October 20, 2010
Approval by DSA February 10, 2011
Authorize to Bid (2) February 22, 2011
BOE Approval March 8, 2011
Bid Opening March 28, 2011
Award of Contract (1) April 8, 2011
Notice to Proceed April 11, 2011
Substantial Completion August 8, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
J.L. Stanford Middle School ‐ Interim Classrooms
A. PROJECT STATUS
Coulter Construction completed the work on the relocated
portables in August 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
Project completed on schedule and is currently in close‐out.
This portable relocation project funded by main
JLS project. Refer to pg. 14
Current Phase: Occupancy ‐August 11, 2011
Schedule:
Approval by DSA April 19, 2011
Jordan Project June 16, 2011
Authorize to Bid (2) May 10, 2011
BOE Approval May 24, 2011
Bid Opening June 1, 2011
Award of Contract (1) June 13, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 8, 2011
Planned Occupancy August 15, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Fairmeadow Elementary School
Portable Relocation Project
A. PROJECT STATUS
Relocation of the portable was complete and occupied on August 8, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 6.4
D. PROJECT OVERVIEW:
Project completed ahead of schedule on August 8, 2011.
This portable relocation project funded by main
JLS project. Refer to pg. 14
Current Phase: Occupancy ‐August 8, 2011
Schedule:
Architect Contract (2) February 15, 2011
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA March 3, 2011
Approval by DSA March 3, 2011
Authorize to Bid (2) May 11, 2011
BOE Approval May 24, 2011
Bid Opening June 14, 2011
Award of Contract (1) June 14, 2011
Notice to Proceed June 20, 2011
Substantial Completion August 1, 2011
Planned Occupancy August 8, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 29
Elementary Classroom Improvements
Interactive Whiteboards and Sound Assist System Installation
A. PROJECT STATUS
Installation of SmartBoards and Lightspeed sound assist systems were
completed for all elementary school classrooms and libraries in April
2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
All SmartBoards and Lightspeed sound systems installed.
Funding
State Funds $0
Strong Schools Bond Funds $2,004,889
Other Funding $0
Total $2,004,889
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $325,488
Construction & Equipment $1,679,401
Soft Costs Contingency $0
Total $2,004,889
Percent of Budget Expended 93.9%
Current Phase: Complete ‐May 15, 2011
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) November 9, 2010
BOE Approval November 23, 2010
Bid Opening February 25, 2011
Award of Contract (1) March 8, 2011
Notice to Proceed March 9, 2011
Completion May 15, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 30
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
The fields were available for play on February 1, 2011, and final
change order negotiations completed on March 9, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
Field was open for use on February 1, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $2,609,680
Other Funding $1,007,255
Total $3,616,935
Budget
Salaries and Benefits $0
Supplies $1,506
Contracts & Services $698,293
Construction & Equipment $2,916,682
Soft Costs Contingency $454
Total $3,616,935
Percent of Budget Expended 100.0%
Change Order Contingency
Starting Contingency Balance $269,300
Remaining Contingency Balance $230,579
Percent of Changes 1.7%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –February 1, 2011
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 18, 2008
BOE Approval December 09, 2008
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) February 24, 2009
BOE Approval March 17, 2009
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion January 31, 2011
Planned Occupancy February 1, 2011
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 31
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
This facility was available for instruction in January 2010. DSA closeout
received on July 18, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,082,402
Other Funding $0
Total $5,082,402
Budget
Salaries and Benefits $1,061
Supplies $88,985
Contracts & Services $1,000,861
Construction & Equipment $3,991,495
Soft Costs Contingency $0
Total $5,082,402
Percent of Budget Expended 99.3%
Change Order Contingency
Starting Contingency Balance $349,000
Remaining Contingency Balance $141,967
Percent of Changes 41.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 32
Gunn High School
Aquatic Center
A. PROJECT STATUS
This facility was available for use in July 2009, and has been closed
out with DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $4,865,423
Other Funding $0
Total $4,865,423
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $647,169
Construction & Equipment $4,218,253
Soft Costs Contingency $0
Total $4,865,423
Percent of Budget Expended 99.9%
Change Order Contingency
Starting Contingency Balance $389,887
Remaining Contingency Balance $195,148
Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 33
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education for approval on September 8, which became the
program documents for the new projects at each campus. These
projects for pre‐design work have been closed, and funds will be
transferred to the program contingency on June 14, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
This project has been completed. Board approval received on September 8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $56,488
Other Funding $0
Total $56,488
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $56,488
Construction & Equipment $0
Soft Costs Contingency $0
Total $56,488
Percent of Budget Expended 96.8%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 34
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education has put new development for Garland on
hold until a growth plan is established for the elementary schools.
The board voted to terminate the lease with Stratford School in
June 2011. Discussions with the Board on future plans for growth
at the elementary schools are ongoing.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,915,789
Construction & Equipment $17,400,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: On Hold
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 35
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
The Board of Education (BOE) approved the master plans for both
high schools, and these projects have been closed, with funds
transferred to the respective campus reserve funds.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
Master planning effort complete.
Funding
State Funds $0
Strong Schools Bond Funds $285,387
Other Funding $0
Total $285,387
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $285,387
Construction & Equipment $0
Soft Costs Contingency $0
Total $285,387
Percent of Budget Expended 86.2%
Current Phase: Complete
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010
Paly MP Revision Approval (2) October 9, 2010
Gunn MP Revision Approval (2) October 12, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 36
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
This project has been put on hold until a growth plan is established for the
elementary schools.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
Project is currently on hold.
Funding
State Funds $0
Strong Schools Bond Funds $70,550
Other Funding $0
Total $70,550
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $70,550
Construction & Equipment $60
Soft Costs Contingency $0
Total $70,550
Percent of Budget Expended 100.0%
Current Phase: On Hold
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) November 9, 2010
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 37
Elementary Classroom Improvements
A. PROJECT STATUS
DSA comments were returned to Gelfand for Phase 1 plans that include
new lighting, adding operable windows and coverings, ventilation, and
replacement of ceiling tiles for classrooms at Barron Park and El
Carmelo elementary schools. The authorization to bid has been placed
on hold pending further discussions with the BOE about elementary
growth planning.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $2,004,889
Other Funding $0
Total $2,004,889
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $325,488
Construction & Equipment $1,679,401
Soft Costs Contingency $0
Total $2,004,889
Percent of Budget Expended 93.0%
Phase 1 Schools: Barron Park and El Carmelo
Current Phase: On Hold
Schedule:
Architect Contract (2) June 8, 2010
BOE Approval June 22, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 9, 2010
BOE Approval December 7, 2010
Submit to DSA December 23, 2010
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.