Monthly Reports 2010-11 (Nov)
MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
November 2010
Current Strong Schools Bond
Capital Improvement Projects
Prepared by
O’Connor Construction Management, Inc.
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Capital Projects
High School Master Plan page 7
Gunn High School – New Classroom Buildings A & B page 8
Gunn High School – Parking and Drop‐off Sitework Improvement page 9
Gunn High School – New Gymnasium page 10
Gunn High School – Air Conditioning of Existing Buildings page 11
Palo Alto High School – Athletic Stadium Improvements page 12
Palo Alto High School – Multi‐use Field page 13
Palo Alto High School – Classroom Building and Media Arts page 14
Palo Alto High School – Theater and Associated Site Improvements page 15
Jordan Middle School page 16
J.L. Stanford Middle School page 17
Terman Middle School page 18
Fairmeadow Elementary School page 19
Ohlone Elementary School page 20
Hoover Elementary School page 21
Duveneck Elementary School page 22
Elementary Classroom Improvements page 23
Technology page 24
Completed Capital Projects
Gunn High School – Industrial Arts Renovation page 25
Gunn High School – Aquatic Center page 26
Middle School Pre‐Design page 27
Middle School Interim Classrooms page 28
Inactive Capital Projects
Garland Elementary School page 29
Elementary School Teaching Walls – Phase 1 Schools page 30
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
CAPITAL PROJECTS
High School Master Plan
The Board of Education (BOE) approved the Palo Alto high school updated master plan project list on October 9,
2010 and no further action on the high school master plans has occurred.
Gunn High School – New Classroom Buildings A & B
DLM continues to incorporate constructability review comments into the construction documents. DSA is
continuing their plan review, which is expected to be completed soon. DLM expects to receive approval in the
spring of 2011. Current estimates place the cost of the project to be over budget, so alternate packages are being
developed to mitigate this potential shortfall.
Gunn High School – Parking and Drop‐off Sitework Improvement
The updated construction site plan was presented at the facilities steering committee on November 3, 2010 and
the city school traffic safety committee (CSTSC) on November 18, 2010. The site plan will be further developed
based on their input and will be presented for approval to the facilities steering committee in January 2011.
Gunn High School – New Gymnasium
DLM continues to make corrections to the construction documents to incorporate constructability review
comments from Gilbane. DSA review is ongoing, and is expected to be complete in spring 2011.
Gunn High School – Air Conditioning of Existing Buildings
Construction documents for buildings L, S, MS, A and IA were submitted to DSA on October 20, 2010. Gilbane will
perform an estimate and constructability review in December 2010. Construction is anticipated to begin in June
2011 and be complete by the beginning of the fall 2011 semester.
Palo Alto High School – Athletics Field Renovation
DLM met several times with the athletics stadium committee this month in developing a schematic design
package. The project will be designed in two phases, with the bleachers being installed as a separate project. The
next design meeting will be held on December 9, 2010. DLM is scheduled to complete a schematic design package
in January and present to the BOE in February 2011.
Palo Alto High School – Multi‐use Field
The natural turf was installed during November and Valley Crest has commenced with the 90‐day maintenance
period on the field. The installation of the fencing and synthetic turf infield is in progress, and the parking lot
landscape work will continue through December. This project is scheduled to be complete by February 1, 2011.
Palo Alto High School – Classroom Building and Media Arts Building
DLM continues to make corrections to the construction documents to incorporate constructability review
comments from Gilbane. DSA review is ongoing, and is expected to be complete in spring 2011.
Palo Alto High School – Performing Arts Center (PAC)
DLM has developed a design alternative that meets all the program needs at a reduced cost, and presented it
during the November 18, 2010 PAC subcommittee meeting. The design included reductions and alternatives that
brought down the project cost from $30M to $23.8M. The design committee and DLM will present the revised
options to the FSC meeting on December 8, 2010.
Page | 4
Jordan Middle School
50% CD estimates were performed and are being reconciled. Soil conditions have required the implementation of
an extensive foundation system that increases project cost, therefore cost saving efforts and the development of
alternate bid pricing strategies continue. Submittal to DSA is anticipated on December 21, 2010.
J.L. Stanford Middle School
AEDIS is nearing completion on a 100% design development package, with estimating, plan reviews and value
engineering to follow. Staff held a follow up community meeting in November to review modifications to the site
design to wrap up comments made during the presentation to the BOE in October. DSA submittal is scheduled to
occur in February 2011.
Terman Middle School
50% CD estimates were performed and are being reconciled. Efforts to find cost saving opportunities and
alternate bid pricing strategies continue. DSA submission is scheduled for December 21, 2010.
Fairmeadow Elementary School – New Classroom Building and Modernization
Gelfand Partners met with the site steering committee on November 1, 2010 to wrap up the design development
phase of the project, and also conducted a landscape meeting to review site design. Gelfand submitted 100%
design development drawings to the district on November 22, 2010. O’Connor is performing a cost estimate and
constructability review in December, and will conduct a value engineering session in January as Gelfand continues
with construction documents.
Ohlone Elementary School – New Classroom Building and Modernization
Jeff Luchetti Construction continued with structural footings and site utilities. Grade beams and footings were
excavated, rebar installed, and concrete placed. Anchor bolts were installed to get ready for structural steel
installation in December 2010. The elevator pit was excavated and waterproofed prior to rebar and concrete
installation.
Hoover Elementary School – Pre‐Design
Gelfand presented the recommended conceptual design to the BOE on November 9, 2010. Staff has put this
project on hold, until growth projections are reviewed and a growth plan is established for the elementary schools.
Duveneck Elementary School – Pre‐Design
Gelfand provided options to reduce project costs before the conceptual design could be presented to the BOE.
The steering committees’ recommended design will be presented to the BOE on December 14, 2010.
Elementary Classroom Improvements
Gelfand presented a cost estimate and scope of work to the BOE on November 9, 1010 for discussion and BOE
approval is anticipated on December 7, 2010. Project scope of work is to include new indirect lighting, adding
operable windows and coverings, vents, and replacement of ceiling tiles for the least renovated classrooms at
Barron Park and El Carmelo Elementary. This project is also funding installation of new interactive whiteboards and
sound assist systems. Coulter Construction contracts were awarded for IWB and SAS installation for Phase 2 and 3
schools (Barron Park, Briones, Palo Verde, and Fairmeadow) during a special BOE meeting on November 22, 2010.
Technology
80% of the computer purchases planned for the 2010/11 school year have been made. The district continues to
purchase more Apple products than PC products. In addition to traditional desktops and laptops, schools have
purchased iPod touches, iPads and netbooks for pilot projects.
Page | 5
COMPLETED CAPITAL PROJECTS
Gunn High School – Industrial Arts Addition & Renovation
Of the $5,511,500 project budget, 90.5% or $4,997,072 was expended. Approved change orders were $207,033,
approximately 41.6% of the $349,000 construction contingency. This project will be closed pending final closeout
of the project by DSA.
Gunn High School – Aquatic Center
Of the $5,013,750 project budget, 96.9%, or $4,860,823 was expended. Approved change orders were $194,739,
approximately 49.9% of the $389,887 construction contingency. This project will be closed pending final closeout
of the project by DSA.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for
discussion and received approval on September 8 by the Board of Education to move into schematic design. This
project is now closed, and funds will soon be transferred to program contingency.
Middle Schools Interim Housing – Jordan and J.L. Stanford
Contractors completed the installation of these new portables on August 3, 2009 at Jordan and August 12, 2009 at
Stanford. Of the $1,047,186 project budget, 48.9%, or $488,536 was expended. Pending Change Orders were
estimated to be $26,381, which is approximately 49.6% of the $52,379 construction contingency. These projects
will be closed pending final closeout of the projects by DSA.
INACTIVE CAPITAL PROJECTS
Garland Elementary School Renovation
The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.
Therefore, the district has placed the project on hold.
Elementary School Teaching Walls – Phase 1 Schools
The district placed this project on hold after review of the implementation of other classroom improvements, as
recommended by the elementary school principals. This project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
Board Actions in November
November 9, 2010
Consent 4 – Authorization to Issue Addendum No. 2 to TestMarc Commissioning Solutions for Commissioning
Agent Services at Fairmeadow Elementary School
Consent 5 – Authorization to Issue Addendum No. 10 to Deems Lewis McKinley Architecture (DLM) to update the
Palo Alto High School and Gunn High School master plans.
November 22, 2010
Action 1 – Authorization to Award Contracts for the Installation of Interactive Whiteboards and Sound Assist
Devices, Phase 2 and 3
A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 132,391 117,359 80.9% 15,032 88.65% 12,609Gunn High School 1 - Aquatic Center 5,013,750 4,865,424 4,860,823 96.9% 4,601 99.91% 148,326Gunn High School 2 - I.A Building 5,511,500 5,045,703 4,997,526 90.7% 48,177 99.05% 465,797Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom Buildings 24,120,000 3,963,033 2,331,216 9.7% 1,631,817 58.82% 20,156,967Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 4,041 0.1% 213,729 1.86% 3,722,230Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 1,593,953 719,397 5.2% 874,556 45.13% 12,236,047Gunn High School 7- A/C 2,600,000 319,199 59,867 0.0% 259,332 18.76% 2,280,801Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.00% 20,945,045Palo Alto High Schools - High School Master Plan 145,000 132,997 119,107 82.1% 13,890 89.56% 12,003Palo Alto High School 1 - Stadium Field 1,358,437 351,184 168,449 12.4% 182,735 47.97% 1,007,253Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,988,139 2,286,312 76.2% 701,827 76.51% 13,924Palo Alto high School 3 - New classroom & Media Art Building 37,140,000 4,998,768 2,534,471 6.8% 2,464,297 50.70% 32,141,232Palo Alto High School 4 - New Theater 17,720,000 1,364,139 128,547 0.7% 1,235,592 9.42% 16,355,861Palo Alto High School - Reserved 39,428,045 0 0 0.0% 0 0.00% 39,428,045Jordan Middle School -Program Management- MS Pre-Design 33,665 18,890 17,826 53.0% 1,064 94.37% 14,775Jordan Middle Schools 1- Interim Classrooms 600,342 171,101 163,157 27.2% 7,944 95.36% 429,241Jordan Middle School 2- Improvements 17,943,194 2,538,284 551,100 3.1% 1,987,184 21.71% 15,404,910J.L.S Middle School - Program Management- MS Pre-Design 33,669 18,799 18,408 54.7% 391 97.92% 14,870J.L.S Middle School 1 - Interim Classrooms 446,844 344,590 326,291 73.0% 18,299 94.69% 102,254 J.L.S Middle School 2- Improvements 17,184,699 2,353,971 457,928 2.7% 1,896,043 19.45% 14,830,728Terman Middle School - Program Management- MS Pre-Design 33,666 18,799 18,423 54.7% 376 98.00% 14,867Terman Middle School 1- Improvements 12,850,071 1,860,197 410,093 3.2% 1,450,104 22.05% 10,989,874PAUSD Elementary Schools - Program Management- Elem. Growth Plan 145,000 55,560 55,560 38.3% 0 100.00% 89,440Addison Elementary School 1-Phase I 5,199,727 0 0 0.0% 0 0.00% 5,199,727Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 7,019,083 49,351 10,176 0.1% 39,175 20.62% 6,969,732Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 792,656 207,451 2.2% 585,205 26.17% 8,534,844Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 69,350 34,115 0.4% 35,235 49.19% 8,506,039Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 10,300,045 1,676,645 14.4% 8,623,400 16.28% 1,367,920Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 841,685 547,006 6.2% 294,679 64.99% 8,045,837Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.00% 8,410,862PAUSD - Program Management 5,042,021 3,814,691 2,764,670 54.8% 1,050,021 72.47% 1,227,330PAUSD - Technology 7,101,063 3,421,567 3,417,805 48.1% 3,762 99.89% 3,679,496PAUSD - Technology -Reserved 6,806,302 0 0 0.0% 0 0.00% 6,806,302PAUSD - Reserved 7,185,694 0 0 0.0% 0 0.00% 7,185,694Bond Issuance Cost 1,840,700 1,840,700 1,840,700 100.0% 0 100.00% 0Total350,684,826 54,769,992 31,130,359 23,639,633 295,914,834Prepared by: Business Services Department based on QSS accounting SystemSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond11/30/2010Percent of ExpendedContract BalanceExpenditures Budget BalanceCommittedBudget
Page | 6
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
The Board of Education (BOE) approved the Palo Alto high
school updated master plan project list on October 9, 2010 and
no further action on the high school master plans has occurred.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
• No further action since Paly’s updated master plan project list was approved by BOE on October 9, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $290,000
Other Funding $0
Total $290,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $286,826
Construction & Equipment $0
Soft Costs Contingency $2,174
Total $290,000
Percent of Budget Expended 81.5%
Current Phase: Master Planning
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010
Paly MP Revision Approval (2) October 9, 2010
Gunn MP Revision Approval (2) October 12, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 7
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
DLM continues to incorporate constructability review comments
into the construction documents. DSA is continuing their plan
review, which is expected to be completed soon. DLM expects to
receive approval in the spring of 2011. Current estimates place the
cost of the project to be over budget, so alternate packages are
being developed to mitigate this potential shortfall.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule. Budget estimates are currently high and will be evaluated at
bid time.
Funding
State Funds $0
Strong Schools Bond Funds $24,120,000
Other Funding $0
Total $24,120,000
Budget
Salaries and Benefits $11,661
Supplies $0
Contracts & Services $4,376,965
Construction & Equipment $19,567,102
Soft Costs Contingency $164,272
Total $24,120,000
Percent of Budget Expended 9.7%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Approval by DSA March 24, 2011*
Bid Opening May 5, 2011*
Award of Contract (1) May 24, 2011*
Notice to Proceed June 13, 2011*
Substantial Completion July 15, 2013*
Planned Occupancy July 30, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
The updated construction site plan was presented at the
facilities steering committee on November 3, 2010 and the
city school traffic safety committee (CSTSC) on November 18,
2010. The site plan will be further developed based on their
input and will be presented for approval to the facilities
steering committee in January 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
• Updated parking and drop‐off layout will be presented to FSC in January, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $898,978
Construction & Equipment $2,919,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) January 25, 2011*
BOE Approval February 8, 2011*
Schematic Design (2) June 6, 2011*
BOE Approval June 13, 2011*
Submit to DSA April 18, 2012*
Approval by DSA November 20, 2012*
Authorize to Bid (2) November 21, 2012*
BOE Approval December 4, 2012*
Bid Opening March 5, 2013*
Award of Contract (1) April 9, 2013*
Notice to Proceed May 1, 2013*
Substantial Completion November 20, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Gunn High School
New Gymnasium
A. PROJECT STATUS
DLM continues to make corrections to the construction
documents to incorporate constructability review comments
from Gilbane. DSA review is ongoing, and is expected to be
complete in spring 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,830,000
Other Funding $0
Total $13,830,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,651,521
Construction & Equipment $11,094,450
Soft Costs Contingency $84,029
Total $13,830,000
Percent of Budget Expended 5.2%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Approval by DSA March 18, 2011*
Bid Opening April 19, 2011*
Award of Contract (1) April 27, 2011*
Notice to Proceed May 10, 2011*
Substantial Completion July 12, 2012*
Planned Occupancy August 6, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
Construction documents for buildings L, S, MS, A and IA
were submitted to DSA on October 20, 2010. Gilbane will
perform an estimate and constructability review in
December 2010. Construction is anticipated to begin in
June 2011 and be complete by the beginning of the fall
2011 semester.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule. Estimating efforts to begin in December, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $454,610
Construction & Equipment $2,120,580
Soft Costs Contingency $24,810
Total $2,600,000
Percent of Budget Expended 0.0%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA October 20, 2010
Approval by DSA March 15, 2011*
Authorize to Bid (2) February 8, 2011*
BOE Approval February 22, 2011*
Bid Opening April 15, 2011*
Award of Contract (1) April 26, 2011*
Notice to Proceed April 28, 2011*
Substantial Completion August 10, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Athletic Stadium Improvements
A. PROJECT STATUS
DLM met several times with the athletics stadium committee
this month in developing a schematic design package. The
project will be designed in two phases, with the bleachers
being installed as a separate project. The next design meeting
will be held on December 9, 2010. DLM is scheduled to
complete a schematic design package in January and present
to the BOE in February 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
• Project currently under schematic design phase and anticipated to present to BOE in January, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $1,358,473
Other Funding $0
Total $1,358,437
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $259,847
Construction & Equipment $1,098,590
Soft Costs Contingency $0
Total $1,358,437
Percent of Budget Expended 12.4%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) January 11, 2011*
BOE Approval January 25, 2011*
Submit to DSA August 25, 2011*
Approval by DSA March 20, 2012*
Authorize to Bid (2) March 13, 2012*
BOE Approval March 27, 2012*
Bid Opening May 30, 2012*
Award of Contract (1) June 11, 2012*
Notice to Proceed June 14, 2012*
Substantial Completion March 22, 2013*
Planned Occupancy August 14, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 12
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
The natural turf was installed during November and Valley Crest has
commenced with the 90‐day maintenance period on the field. The
installation of the fencing and synthetic turf infield is in progress, and the
parking lot landscape work will continue through December. This project is
scheduled to be complete by February 1, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
• Project currently within budget and anticipated for use by February 15, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $3,002,063
Other Funding $1,075,991
Total $4,078,054
Budget
Salaries and Benefits $0
Supplies $6
Contracts & Services $678,289
Construction & Equipment $3,380,258
Soft Costs Contingency $19,501
Total $4,078,054
Percent of Budget Expended 76.2%
Change Order Contingency
• Starting Contingency Balance $269,300
• Remaining Contingency Balance $230,579
• Percent of Changes 1.7%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 18, 2008
BOE Approval December 09, 2008
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) February 24, 2009
BOE Approval March 17, 2009
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion February 10, 2011*
Planned Occupancy February 15, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
DLM continues to make corrections to the construction documents to
incorporate constructability review comments from Gilbane. DSA
review is ongoing, and is expected to be complete in spring 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule under DSA’s anticipated review time.
Funding
State Funds $0
Strong Schools Bond Funds $37,125,279
Other Funding $0
Total $37,125,279
Budget
Salaries and Benefits $14,721
Supplies $0
Contracts & Services $6,955,269
Construction & Equipment $29,740,000
Soft Costs Contingency $430,010
Total $37,125,279
Percent of Budget Expended 6.8%
Current Phase: DSA Review
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 4, 2010
Approval by DSA March 24, 2011*
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Bid Opening March 15, 2011*
Award of Contract (1) March 23, 2011*
Notice to Proceed April 1, 2011*
Substantial Completion May 13, 2013*
Planned Occupancy July 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Palo Alto High School
Performing Arts Center (PAC)
A. PROJECT STATUS
DLM has developed a design alternative that meets all the program needs
at a reduced cost, and presented it during the November 18, 2010 PAC
subcommittee meeting. The design included reductions and alternatives
that brought down the project cost from $30M to $23.8M. The design
committee and DLM will present the revised options to the FSC meeting on
December 8, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
• Project is progressing through the schematic design phase.
Funding
State Funds $0
Strong Schools Bond Funds $17,720,000
Other Funding $0
Total $17,720,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,451,077
Construction & Equipment $14,159,700
Soft Costs Contingency $109,223
Total $17,720,000
Percent of Budget Expended 0.7%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) January 11, 2011*
BOE Approval January 25, 2011*
Submit to DSA June 11, 2012*
Approval by DSA January 16, 2013*
Authorize to Bid (2) January 17, 2013*
BOE Approval January 30, 2013*
Bid Opening March 21, 2013*
Award of Contract (1) April 11, 2013*
Notice to Proceed May 10, 2013*
Substantial Completion December 1, 2014*
Planned Occupancy January, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
Jordan Middle School
A. PROJECT STATUS
50% CD estimates were performed and are being reconciled. Soil
conditions have required the implementation of an extensive
foundation system that increases project cost, therefore cost saving
efforts and the development of alternate bid pricing strategies
continue. Submittal to DSA is anticipated on December 21, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule. Estimates will be updated based on 50% CDs.
Funding
State Funds $0
Strong Schools Bond Funds $17,943,191
Other Funding $0
Total $17,943,191
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,501,930
Construction & Equipment $13,949,500
Soft Costs Contingency $491,764
Total $17,943,194
Percent of Budget Expended 3.1%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA December 21, 2010*
Approval by DSA August 17, 2011*
Authorize to Bid (2) August 11, 2011*
BOE Approval August 24, 2011*
Bid Opening September 26, 2011*
Award of Contract (1) October 11, 2011*
Notice to Proceed November 7, 2011*
Substantial Completion May 7, 2013*
Planned Occupancy August 5, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
J.L. Stanford Middle School
A. PROJECT STATUS
AEDIS is nearing completion on a 100% design
development package, with estimating, plan reviews
and value engineering to follow. Staff held a follow up
community meeting in November to review
modifications to the site design to wrap up comments
made during the presentation to the BOE in October. DSA
submittal is scheduled to occur in February 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
• Project currently proceeding within budget and anticipate to submit to DSA in February, 2011.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,697
Other Funding $0
Total $17,184,697
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,354,000
Construction & Equipment $13,341,000
Soft Costs Contingency $489,699
Total $17,184,699
Percent of Budget Expended 2.7%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (3) June 1, 2010
BOE Approval June 22, 2010
BOE Approval (Sitework) September 28. 2010
Submit to DSA February 16, 2011*
Approval by DSA October 18, 2011*
Authorize to Bid (2) October 25, 2011*
BOE Approval November 8, 2011*
Bid Opening December 13, 2011*
Award of Contract (1) December 27, 2011*
Notice to Proceed December 30, 2011*
Substantial Completion February 12, 2013*
Planned Occupancy August 5, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Terman Middle School
A. PROJECT STATUS
50% CD estimates were performed and are being reconciled. Efforts
to find cost saving opportunities and alternate bid pricing strategies
continue. DSA submission is scheduled for December 21, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule. Estimates will be updated based on 50% CDs.
Funding
State Funds $0
Strong Schools Bond Funds $12,850,071
Other Funding $0
Total $12,850,071
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,477,950
Construction & Equipment $10,031,569
Soft Costs Contingency $340,552
Total $12,850,071
Percent of Budget Expended 3.2%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA December 21, 2010*
Approval by DSA August 2, 2011*
Authorize to Bid (2) August 3, 2011*
BOE Approval August 10, 2011*
Bid Opening September 19, 2011*
Award of Contract (1) October 4, 2011*
Notice to Proceed October 5, 2011*
Substantial Completion March 26, 2013*
Planned Occupancy July 3, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Gelfand Partners met with the site steering committee on November 1,
2010 to wrap up the design development phase of the project, and also
conducted a landscape meeting to review site design. Gelfand
submitted 100% design development drawings to the district on
November 22, 2010. O’Connor is performing a cost estimate and
constructability review in December, and will conduct a value
engineering session in January as Gelfand continues with construction
documents.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand continued design efforts and met with site committee in November to review design
development documents.
Funding
State Funds $0
Strong Schools Bond Funds $9,327,500
Other Funding $0
Total $9,327,500
Budget
Salaries and Benefits $0
Supplies $7,697
Contracts & Services $1,805,519
Construction & Equipment $7,443,000
Soft Costs Contingency $71,284
Total $9,327,500
Percent of Budget Expended 2.2%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010
BOE Approval September 28, 2010
Submit to DSA March 1, 2011*
Approval by DSA October 20, 2011*
Authorize to Bid (2) November 9, 2011*
BOE Approval November 23, 2012*
Bid Opening January 9, 2012*
Award of Contract (1) February 27, 2012*
Notice to Proceed March 12, 2012*
Substantial Completion May 13, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Jeff Luchetti Construction continued with structural footings and site
utilities. Grade beams and footings were excavated, rebar installed, and
concrete placed. Anchor bolts were installed to get ready for structural steel
installation in December 2010. The elevator pit was excavated and
waterproofed prior to rebar and concrete installation.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,322,677
Construction & Equipment $9,169,121
Soft Costs Contingency $176,167
Total $11,667,965
Percent of Budget Expended 14.4%
Change Order Contingency
• Starting Contingency Balance $748,400
• Remaining Contingency Balance $748,400
• Percent of Changes 0.0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010
Award of Contract (1) August 3, 2010
Notice to Proceed August 11, 2010
Substantial Completion December 1, 2011*
Planned Occupancy January 4, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
Gelfand presented the recommended conceptual design to the BOE on
November 9, 2010. Staff has put this project on hold, until growth
projections are reviewed and a growth plan is established for the
elementary schools.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Conceptual design presented to the BOE on November 9, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $8,575,389
Other Funding $0
Total $8,575,389
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,643,477
Construction & Equipment $6,831,912
Soft Costs Contingency $100,000
Total $8,575,389
Percent of Budget Expended 0.4%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) November 9, 2010*
BOE Approval December 7, 2010*
Schematic Design (2) February 9, 2011*
BOE Approval February 22, 2011*
Submit to DSA July 19, 2011*
Approval by DSA March 13, 2012*
Authorize to Bid (2) April 24, 2012*
BOE Approval May 6, 2012*
Bid Opening June 14, 2012*
Award of Contract (1) June 30, 2012*
Notice to Proceed July 6, 2012*
Substantial Completion November 4, 2013*
Planned Occupancy January 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Duveneck Elementary School
Pre‐Design
A. PROJECT STATUS
Gelfand provided options to reduce project costs before the conceptual design
could be presented to the BOE. The steering committees’ recommended
design will be presented to the BOE on December 14, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Conceptual design to be presented to the BOE in December, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $7,019,083
Other Funding $0
Total $7,019,083
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,368,869
Construction & Equipment $5,559,683
Soft Costs Contingency $90,531
Total $7,019,083
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) December 14, 2010*
BOE Approval January 11, 2011*
Schematic Design (2) February 22, 2011*
BOE Approval March 8, 2011*
Submit to DSA August 19, 2011*
Approval by DSA April 13, 2012*
Authorize to Bid (2) May 25, 2012*
BOE Approval June 6, 2012*
Bid Opening July 7, 2012*
Award of Contract (1) July 17, 2012*
Notice to Proceed July 24, 2012*
Substantial Completion November 19, 2013*
Planned Occupancy January 1, 2014*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Elementary Classroom Improvements
Phase 1 – Barron Park and El Carmelo
A. PROJECT STATUS
Gelfand presented a cost estimate and scope of work to the BOE on
November 9, 1010 for discussion and BOE approval is anticipated on
December 7, 2010. Project scope of work is to include new indirect
lighting, adding operable windows and coverings, vents, and
replacement of ceiling tiles for the least renovated classrooms at
Barron Park and El Carmelo Elementary. This project is also funding
installation of new interactive whiteboards and sound assist systems.
Coulter Construction contracts were awarded for IWB and SAS
installation for Phase 2 and 3 schools (Barron Park, Briones, Palo
Verde, and Fairmeadow) during a special BOE meeting on November
22, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• Gelfand presented planned work for phase 1 schools to BOE on November 9, 2010. Installation of
technology wall underway.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,194,920
Construction & Equipment $7,488,707
Soft Costs Contingency $203,895
Total $8,887,522
Percent of Budget Expended 6.2%
Phase 1 Schools: Barron Park and El Carmelo
Current Phase: Schematic Design
Schedule:
Architect Contract (2) June 8, 2010
BOE Approval June 22, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) November 9, 2010*
BOE Approval December 7, 2010*
Submit to DSA November 22, 2010*
Approval by DSA May 9, 2011*
Authorize to Bid (2) April 15, 2011*
BOE Approval April 30, 2011*
Bid Opening May 12, 2011*
Award of Contract (1) May 24, 2011*
Notice to Proceed June 1, 2011*
Substantial Completion August 15, 2011*
Planned Occupancy August 17, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Technology Improvements
A. PROJECT STATUS
80% of the computer purchases planned for the 2010/11 school year have
been made. The district continues to purchase more Apple products than
PC products. In addition to traditional desktops and laptops, schools have
purchased iPod touches, iPads and netbooks for pilot projects.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• New computers delivered to schools.
Funding
State Funds $0
Strong Schools Bond Funds $7,080,712
Other Funding $0
Total $7,080,712
Budget
Salaries and Benefits $0
Supplies & Computers $6,698,117
Contracts & Services $180,173
Construction & Equipment $202,422
Soft Costs Contingency $0
Total $7,080,712
Percent of Budget Expended 48.1%
Current Phase: N/A
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
Of the $5,511,500 project budget, 90.5% or $4,997,072 was
expended. Approved change orders were $207,033, approximately
41.6% of the $349,000 construction contingency. This project will be
closed pending final closeout of the project by DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
• The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,511,500
Other Funding $0
Total $5,511,500
Budget
Salaries and Benefits $1,063
Supplies $76,657
Contracts & Services $1,232,253
Construction & Equipment $4,200,322
Soft Costs Contingency $1,205
Total $5,511,500
Percent of Budget Expended 90.7%
Change Order Contingency
• Starting Contingency Balance $349,000
• Remaining Contingency Balance $141,967
• Percent of Changes 41.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Gunn High School
Aquatic Center
A. PROJECT STATUS
Of the $5,013,750 project budget, 96.9%, or $4,860,823 was
expended. Approved change orders were $194,739, approximately
49.9% of the $389,887 construction contingency. This project will be
closed pending final closeout of the project by DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
• This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,013,750
Other Funding $0
Total $5,013,750
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $692,797
Construction & Equipment $4,318,858
Soft Costs Contingency $1,095
Total $5,013,750
Percent of Budget Expended 96.9%
Change Order Contingency
• Starting Contingency Balance $389,887
• Remaining Contingency Balance $195,148
• Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education on June 23 for discussion and received approval
on September 8 by the Board of Education to move into schematic
design.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
• This project has been completed on schedule and under budget. Board approval received on September
8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $101,000
Other Funding $0
Total $101,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $85,000
Construction & Equipment $0
Soft Costs Contingency $15,000
Total $101,000
Percent of Budget Expended 52.9%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
Middle Schools Interim Classrooms
Jordan and J.L. Stanford
A. PROJECT STATUS
Contractors completed the installation of these new portables on
August 3, 2009 at Jordan and August 12, 2009 at Stanford. Of the
$1,047,186 project budget, 48.9%, or $488,536 was expended.
Pending Change Orders were estimated to be $26,381, which is
approximately 49.6% of the $52,379 construction contingency.
These projects will be closed pending final closeout of the projects
by DSA.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project was completed under budget and on schedule.
Funding
State Funds $0
Strong Schools Bond Funds $1,047,186
Other Funding $0
Total $1,047,186
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $346,148
Construction & Equipment $698,490
Soft Costs Contingency $2,548
Total $1,047,186
Percent of Budget Expended 48.9%
Change Order Contingency
• Starting Contingency Balance $52,379
• Remaining Contingency Balance $25,998
• Percent of Changes 49.6%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –August 25, 2009
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA April 14, 2009
Approval by DSA April 22, 2009
Authorize to Bid (2) March 31, 2009
BOE Approval April 14, 2009
Bid Opening May 14, 2009
Award of Contract (1) May 26, 2009
Notice to Proceed June 1, 2009
Substantial Completion August 12, 2009
Planned Occupancy August 25, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education voted on August 25, 2009 to approve the
amendment to Garland lease to Stratford School. Therefore, the
district has placed the project on hold.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,915,789
Construction & Equipment $17,400,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: On Hold
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 29
Elementary School Teaching Walls
Phase 1 Schools
A. PROJECT STATUS
The district placed this project on hold after review of the
implementation of other classroom improvements, as
recommended by the elementary school principals. This
project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.9
D. PROJECT OVERVIEW:
• This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary
above).
Funding
State Funds $0
Strong Schools Bond Funds $7,044,987
Other Funding $0
Total $7,044,987
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,341,394
Construction & Equipment $5,498,498
Soft Costs Contingency $205,095
Total $7,044,987
Percent of Budget Expended 1.6%
Current Phase: Project Renamed. See Classroom
Improvements Project
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates –Subject to Change
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.