Loading...
Monthly Reports 2010-06 (Jun) MMOONNTTHHLLYY  PPRROOGGRREESSSS  RREEPPOORRTT     Through  June 2010      Current Strong Schools Bond  Capital Improvement Projects  Prepared by     O’Connor Construction Management, Inc.  &  Gilbane Building Company  Page | 2   TABLE OF CONTENTS    Executive Summary         page 3     Attachment 1 – Consolidated Expenditure Report    Attachment 2 – Master Project Schedule     Capital Projects     High School Master Plan        page 6    Gunn High School – New Classroom Buildings A & B     page 7    Gunn High School – Parking and Drop‐off Sitework Improvement    page 8    Gunn High School – New Gymnasium       page 9    Gunn High School – Air Conditioning of Existing Buildings    page 10    Palo Alto High School – Stadium Field Renovation     page 11    Palo Alto High School – Multi‐use Field      page 12    Palo Alto High School – Classroom Building and Media Arts    page 13    Palo Alto High School – Theater and Associated Site Improvements    page 14    Jordan Middle School        page 15    J.L. Stanford Middle School       page 16    Terman Middle School        page 17    Fairmeadow Elementary School       page 18    Ohlone Elementary School        page 19    Hoover Elementary School        page 20    Duveneck Elementary School       page 21    Elementary Classroom Improvements      page 22    Inactive Capital Projects    Gunn High School – Industrial Arts Renovation     page 23    Gunn High School – Aquatic Center       page 24    Middle School Pre‐Design        page 25    Middle School Interim Classrooms       page 26    Garland Elementary School       page 27    Elementary School Teaching Walls – Phase 1 Schools     page 28    Appendix  Exhibit A – Bond Project List  Page | 3   EXECUTIVE SUMMARY  CAPITAL PROJECTS   High School Master Plan  DLM and Gates + Associates presented the Palo Alto and Gunn High School’s landscape master plans to the Board  of Education (BOE) on June 8, 2010 as an information item.  The landscape master plan and facilities steering  committees will reconvene in late August and proceed with further coordination for final approval of the updated  master plans for each campus that incorporate the work of Gates + Associates and other revisions since the  original March 31, 2009 approval.    Gunn High School – New Classroom Buildings A & B  DLM is scheduled to submit 95% CD’s by June 30, 2010. Final estimates, constructability reviews and document  coordination will be completed prior to a target DSA submittal date of August 1, 2010. Currently, Rodan Builders,  Inc. has moved all 26 existing portables in order to accommodate the new buildings. The portable classrooms are  being reassembled and will be finished by the beginning of the fall semester.  Gunn High School – Parking and Drop‐off Sitework Improvement  The City School Traffic Safety Committee (CSTSC) reviewed the construction and fencing plan that will impact  traffic flow on the first day of classes.  To assist with safety coordination, the plan will be included in the “Back to  School” packets being sent to students to notify them of the changes, and to indentify the interim bicycle paths  available during construction.  Parking and Drop‐off planning will commence this summer.  Gunn High School – New Gymnasium  DLM is scheduled to submit 95% CD’s by June 30, 2010. Final estimates, constructability reviews and document  coordination will be completed prior to a target DSA submittal date of August 1, 2010.    Gunn High School – Air Conditioning of Existing Buildings  DLM continues design on the air conditioning project.  DLM plans to submit plans to DSA by September 2010.  Palo Alto High School – Stadium Field Renovation  DLM presented the stadium renovation conceptual plan to the BOE on June 1, 2010, and the BOE approved it on  June 22, 2010.  Planning will resume in August after the Facilities Steering Committee (FSC) reviews the revised  master plan project list and budget.  Palo Alto High School – Multi‐use Field  Valley Crest Landscape began grading the existing field area on June 1, 2010 and is scheduled for completion by  January 31, 2011, which includes new dugouts and time for turf establishment.  Work commenced in the south  parking lot on June 14, 2010, and improvements are expected to be complete by August 13, 2010.  Palo Alto High School – Classroom Building and Media Arts Building  DLM is scheduled to submit 95% CD’s by June 30, 2010.  Final estimates, constructability reviews and document  coordination will be completed prior to a target DSA submittal date of August 1, 2010. On June 14, 2010, Rodan  Builders, Inc. commenced work on the relocation of the 16 existing portables to accommodate the new  buildings. Portable relocations will be finished by the beginning of the fall semester.   Palo Alto High School – Theater and Associated Site Improvements  On June 22, 2010 the BOE approved conceptual design and authorized DLM to proceed with schematic design.    DLM will meet with specialty consultants this summer and resume subcommittee meetings in late August.    Jordan Middle School  AEDIS has proceeded into design development and drawings are anticipated to be submitted for review in August.         Page | 4   J.L. Stanford Middle School  AEDIS presented schematic design to the BOE on June 1 and June 22 for approval.  The BOE approved and  authorized staff to proceed with design development for the buildings, however the exterior site design will return  to the BOE in September for discussion.  Therefore, AEDIS will meet with the advisory committee and interested  community members to refine the exterior design and landscaping in September, before returning to the BOE.  Terman Middle School  AEDIS has proceeded into design development and drawings are anticipated to be submitted for review in August.      Fairmeadow Elementary School – New Classroom Building and Modernization  Gelfand Partners will develop schematic design plans during summer break.  In September, Gelfand will meet with  the site committee and the P.T.A., as well as host a community meeting before presenting the schematic design  plans, as anticipated, to the BOE on September 14, 2010.    Ohlone Elementary School – New Classroom Building and Modernization  Bids from prequalified contractors are due July 13, 2010.  The project is expected to be awarded at a BOE special  meeting scheduled for July 19, 2010.  Construction will commence in August 2010 with anticipated completion in  late 2011.  On June 14, 2010, Coulter Construction began relocating existing portables on the site to accommodate  the new building.    Hoover Elementary School – Pre‐Design  Gelfand met with the site steering committee on June 3, 2010 to kick‐off the pre‐design project at Hoover.   Gelfand will return to Hoover’s site steering committee with planning options for the campus in September, after  summer break.    Duveneck Elementary School – Pre‐Design  Gelfand conducted a second pre‐design meeting with the site steering committee on June 8, 2010.  The steering  committee will continue campus planning discussion in September, after summer break.  Elementary Classroom Improvements  The BOE approved Gelfand Partners’ addendum on June 22, 2010 for design services on the classroom  improvements.  Gelfand will commence design during summer break so site staff can review proposed  improvements in September.  The classroom improvements project consists of new lighting, windows and shades,  ventilation improvements and ceiling tiles.  Also part of the classroom improvements project is the  implementation of a technology wall.  District staff completed site walks at each elementary school and plan to bid  the technology wall project in July, allowing for construction to begin in September, 2010.    INACTIVE CAPITAL PROJECTS   Gunn High School – Industrial Arts Addition & Renovation  Of the $5,576,500 project budget, 84.6% or $4,720,037 was expended.  Approved change orders were $208,756,  which is approximately 59.8% of the $349,000 construction contingency.  Gunn High School – Aquatic Center   Of the $5,013,750 project budget, 96.6%, or $4,844,070 was expended.  Approved change orders were $194,739,  which is approximately 49.9% of the $389,887 construction contingency.    Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman  AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for  discussion and received approval on September 8 by the Board of Education to move into schematic design.       Page | 5   Middle Schools Interim Housing – Jordan and J.L. Stanford  Contracts were awarded to Coulter Construction for Jordan Middle School and Mark Electric for Stanford Middle  School following Board of Education approval on May 26, 2009.  Both contractors started work on June 15, 2009  and were completed on August 3, 2009 at Jordan and August 12, 2009 at Stanford.  Of the $1,047,186 project  budget, 25%, or $236,696 has been expended. Pending Change Orders are currently estimated to be a deduct of  ($10,331), which is approximately 0% of the $30,698 construction contingency.  Garland Elementary School Renovation  The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.   Therefore, the district has placed the project on hold.    Elementary School Teaching Walls – Phase 1 Schools  The district placed this project on hold after review of the implementation of other classroom improvements, as  recommended by the elementary school principals.  This project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).     Board Actions in June  June 1, 2010  Consent 6 – Qualified School Construction Bonds (QSCB): Resolution 2009‐10.16, Amending Resolution 2009‐10.07  Regarding Terms of Sale of QSCBs; and Resolution 2009‐10.17 Authorizing the Advance of General Fund Moneys to  the Bond Interest and Redemption Fund QSCBs    Consent 7 – Authorization to Bid Procurements and Interactive Whiteboards and Sound Assist Devices    Action 8 – Reappointment of Four Members of the Citizens’ Oversight Committee for the Strong Schools Bond    June 22, 2010  Consent 9 – Five‐Year Deferred Maintenance Plan    Consent 10 – Contract with O’Connor Construction Management, Inc. for 2010‐11    Consent 11 – Authorization to Enter into Addendum No. 9 with Gelfand Partners for Additional Services for Ohlone  Elementary School and the Classroom Improvements Project    Action 26 – Approval of Schematic Design of J.L. Stanford Middle School    Action 27 – Approval of Conceptual Design and Project Budget for the New Theater Project at Palo Alto High  School    Action 28 – Approval of Conceptual Design and Project Budget for the Stadium Project at Palo Alto High School    Action 35 – Negotiation to Amend the Contract with Gilbane Building Company to Provide Project and  Construction Management Services  A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 129,431 110,244 76.0% 19,187 85.18% 15,569Gunn High School 1 - Aquatic Center 5,013,750 4,864,425 4,856,830 96.9% 7,595 99.84% 149,325Gunn High School 2 - I.A 5,511,500 5,163,451 4,921,437 89.3% 242,014 95.31% 348,049Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom A & B 24,120,000 3,129,148 1,116,080 4.6% 2,013,068 35.67% 20,990,852Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 3,530 0.1% 214,240 1.62% 3,722,230Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 1,093,201 401,533 2.9% 691,668 36.73% 12,736,799Gunn High School 7- A/C 2,600,000 0 0 0.0% 0 0.00% 2,600,000Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.00% 20,945,045Palo Alto High Schools - High School Master Plan 145,000 132,773 111,920 77.2% 20,853 84.29% 12,227Palo Alto High School 1 - Bleacher 1,358,437 162,011 141,653 10.4% 20,358 87.43% 1,196,426Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,989,809 283,749 9.5% 2,706,060 9.49% 12,254Palo Alto high School 3 - New classroom & Media Art Building 34,220,000 3,342,845 622,112 1.8% 2,720,733 18.61% 30,877,155Palo Alto High School 4 - New Theater 17,720,000 1,026,210 41,537 0.2% 984,673 4.05% 16,693,790Palo Alto High School - Reserved 42,348,045 0 0 0.0% 0 0.00% 42,348,045Jordan Middle School - Middle School Pre-Design 33,665 19,718 17,413 51.7% 2,305 88.31% 13,947Jordan Middle Schools 1- Interim Classrooms 600,342 171,102 160,878 26.8% 10,224 94.02% 429,240Jordan Middle School 2 17,943,194 1,583,569 263,471 1.5% 1,320,098 16.64% 16,359,625Jordan Middle School - Reserved 0 0 0 0.0% 0 0.00% 0J.L.S Middle School - Middle School Pre-Design 33,669 19,627 17,995 53.4% 1,632 91.68% 14,042J.L.S Middle School 1 - Interim Classrooms 446,844 337,590 317,171 71.0% 20,419 93.95% 109,254 J.L.S Middle School 2 17,184,699 1,432,112 206,088 1.2% 1,226,024 14.39% 15,752,587 J.L.S Middle School - Reserved 0 0 0 0.0% 0 0.00% 0Terman Middle School - Middle School Pre- Design 33,666 19,627 18,010 53.5% 1,617 91.76% 14,039Terman Middle School 1 12,850,071 1,187,625 157,505 1.2% 1,030,120 13.26% 11,662,446Terman Middle School - Reserved 0 0 0 0.0% 0 0.00% 0PAUSD Elementary Schools - Elementary Growth Plan 145,000 55,560 55,560 38.3% 0 100.00% 89,440Addison Elementary School 1-Phase I 5,199,727 0 0 0.0% 0 0.00% 5,199,727Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 7,019,083 27,500 0 0.0% 27,500 0.00% 6,991,583Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 770,909 25,000 0.3% 745,909 3.24% 8,556,591Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 47,500 0 0.0% 47,500 0.00% 8,527,889Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 1,643,787 928,968 8.0% 714,819 56.51% 10,024,178Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 133,018 106,548 1.2% 26,470 80.10% 8,754,504Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.00% 8,410,862PAUSD - Program Admin. ** 3,353,108 2,661,835 2,098,590 62.6% 563,245 78.84% 691,273PAUSD - Technology 5,995,689 2,547,823 2,297,606 38.3% 250,217 90.18% 3,447,866PAUSD - Technology -Reserved 7,911,676 0 0 0.0% 0 0.00% 7,911,676PAUSD - Reserved 6,335,945 0 0 0.0% 0 0.00% 6,335,945Total346,305,464 35,197,032 19,567,318 15,629,714 311,108,432* Old Teaching Wall ProjectPrepared by: Business Services Department based on QSS accounting SystemBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond6/29/2010Percent of ExpendedContract BalanceExpenditures Budget BalanceCommitted Activity IDPhaseActivity NameOriginalDurationStartFinishDuration %CompleteGunn- IndusGunn- Industrial AGunn- Industrial Arts Renovation45101-Oct-08 A23-Jun-10 A100%Gunn - New Gunn - New ClassrGunn - New Classroom Building109520-Apr-09 A01-Jul-1328.49%Gunn - ParkiGunn - Parking andGunn - Parking and Drop Off89301-Sep-09 A31-Jan-1324.19%Gunn New GGunn New GymnasGunn New Gymnasium94021-Apr-09 A27-Nov-1233.09%Gunn Air CoGunn Air ConditionGunn Air Conditioning Project48001-Jan-10 A19-Jul-1142.92%Paly - StadiuPaly - Stadium FielPaly - Stadium Field Renovation Project62817-Aug-09 A24-Jan-1234.71%Paly - Multi UPaly - Multi Use FiePaly - Multi Use Field Improvements58703-Nov-08 A01-Feb-1173.59%Paly - New CPaly - New ClassroPaly - New Classroom Building & Media A...113820-Apr-09 A29-Aug-1327.42%Paly - New TPaly - New TheaterPaly - New Theater and Sitework157609-Sep-09 A14-Sep-1513.77%Jordan New Jordan New ClassrJordan New Classroom Wing & Moderniz...124103-Nov-08 A05-Aug-1334.81%Stanford NewStanford New ClasStanford New Classroom Wing123603-Nov-08 A05-Aug-1334.55%Terman AdmTerman Admin WinTerman Admin Wing Addition & Moderniz...121303-Nov-08 A03-Jul-1335.28%Garland SchGarland School MoGarland School Modernization56603-Nov-08 A30-Jun-10100%FairmeadowFairmeadow ElemeFairmeadow Elementary School119414-Dec-09 A01-Aug-1332.41%Duveneck ElDuveneck ElementDuveneck Elementary School85213-May-10 A16-Aug-133.99%Hoover ElemHoover ElementaryHoover Elementary School85412-May-10 A19-Aug-134.1%Ohlone New Ohlone New ClassOhlone New Classroom Wing97703-Nov-08 A01-Aug-1246.37%Teaching WaTeaching Walls CaTeaching Walls Casework17206-Apr-09 A28-Sep-09 A100%NDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASOND2009201020112012201320142015PALO ALTO UNIFIED SCHOOL DISTRICTSTRONG SCHOOLS BOND PROGRAMMASTER SCHEDULE SUMMARY DesignPlanningBid and AwardConstructionDSACloseoutMPage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc. Page | 6   High School Master Plan  Palo Alto HS and Gunn HS  A. PROJECT STATUS    DLM and Gates + Associates presented the Palo Alto and Gunn  High School’s landscape master plans to the Board of Education  (BOE) on June 8, 2010 as an information item.  The landscape  master plan and facilities steering committees will reconvene in  late August and proceed with further coordination for final  approval of the updated master plans for each campus that  incorporate the work of Gates + Associates and other revisions  since the original March 31, 2009 approval.                    B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14    D. PROJECT OVERVIEW:  • Landscape master plans for each campus to the BOE in June as information.     Funding  State Funds $0  Strong Schools Bond Funds $290,000  Other Funding $0  Total $290,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $279,521  Construction & Equipment $0  Soft Costs Contingency $9,479  Total $290,000    Percent of Budget Expended 76.5%  Current Phase: Master Planning    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Initial Master Plan Approval (2) September 8, 2009  BOE Approval September 22, 2009    Paly CEQA Approval (2) February 9, 2010  BOE Approval February 23, 2010    Gunn Master Plan Update (2) March 23, 2010  BOE Approval April 6, 2010    Gunn CEQA Approval (2) April 27, 2010   BOE Approval May 11, 2010     Master Plan Revision Approval (2) September 14, 2010*      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 7   Gunn High School  New Classroom Buildings A & B  A. PROJECT STATUS    DLM is scheduled to submit 95% CD’s by June 30, 2010. Final  estimates, constructability reviews and document coordination will  be completed prior to a target DSA submittal date of August 1,  2010. Currently, Rodan Builders, Inc. has moved all 26 existing  portables in order to accommodate the new buildings. The portable  classrooms are being reassembled and will be finished by the  beginning of the fall semester.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.     Funding  State Funds $0  Strong Schools Bond Funds $24,120,000  Other Funding $0  Total $24,120,000    Budget  Salaries and Benefits $0  Supplies $50,000  Contracts & Services $4,315,728  Construction & Equipment $19,590,000  Soft Costs Contingency $164,272  Total $24,120,000    Percent of Budget Expended 4.6%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 1, 2010*     Approval by DSA April 15, 2011 *    Authorize to Bid (2) February 22, 2011 *  BOE Approval March 8, 2011*    Bid Opening April 19, 2011 *    Award of Contract (1) April 26, 2011 *    Notice to Proceed May 9, 2011*    Substantial Completion December 3, 2012*    Planned Occupancy June 10, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 8   Gunn High School  Parking and Drop‐off Sitework Improvement  A. PROJECT STATUS    The City School Traffic Safety Committee (CSTSC) reviewed  the construction and fencing plan that will impact traffic flow  on the first day of classes.  To assist with safety coordination,  the plan will be included in the “Back to School” packets  being sent to students to notify them of the changes, and to  indentify the interim bicycle paths available during  construction.  Parking and Drop‐off planning will commence  this summer.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:  • This project will commence this summer.     Funding  State Funds $0  Strong Schools Bond Funds $3,940,000  Other Funding $0  Total $3,940,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $883,978  Construction & Equipment $2,934,840  Soft Costs Contingency $121,182  Total $3,940,000    Percent of Budget Expended 0.1%  Current Phase: Conceptual Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 28, 2010*  BOE Approval October 12, 2010*    Schematic Design (2) December 16, 2010*  BOE Approval December 23, 2010*    Submit to DSA October 11, 2011*     Approval by DSA April 30, 2012*    Authorize to Bid (2) February 7, 2012*  BOE Approval February 20, 2012*    Bid Opening April 17, 2012*    Award of Contract (1) May 2, 2012*    Notice to Proceed May 24, 2012*    Substantial Completion December 13, 2012*    Planned Occupancy January 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 9   Gunn High School  New Gymnasium  A. PROJECT STATUS    DLM is scheduled to submit 95% CD’s by June 30, 2010. Final  estimates, constructability reviews and document coordination  will be completed prior to a target DSA submittal date of  August 1, 2010.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.      Funding  State Funds $0  Strong Schools Bond Funds $13,830,000  Other Funding $0  Total $13,830,000    Budget  Salaries and Benefits $0  Supplies $40,000  Contracts & Services $2,596,521  Construction & Equipment $11,109,450  Soft Costs Contingency $84,029  Total $13,830,000    Percent of Budget Expended 2.9%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 2, 2010*     Approval by DSA April 15, 2011*    Authorize to Bid (2) February 22, 2011*  BOE Approval March 8, 2011*    Bid Opening April 19, 2011*    Award of Contract (1) April 26, 2011*    Notice to Proceed May 9, 2011*    Substantial Completion October 9, 2012*    Planned Occupancy November 13, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 10   Gunn High School  Air Conditioning of Existing Buildings  A. PROJECT STATUS    DLM continues design on the air conditioning project.  DLM  plans to submit plans to DSA by September 2010.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.7    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.       Funding  State Funds $0  Strong Schools Bond Funds $2,600,000  Other Funding $0  Total $2,600,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $447,110  Construction & Equipment $2,128,080  Soft Costs Contingency $24,810  Total $2,600,000    Percent of Budget Expended 0.0%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 27, 2010  BOE Approval April 6, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA September 28, 2010*    Approval by DSA March 8, 2011*    Authorize to Bid (2) February 22, 2011*  BOE Approval March 8, 2011*    Bid Opening March 28, 2011*    Award of Contract (1) April 4, 2011*    Notice to Proceed April 13, 2011*    Substantial Completion June 14, 2011*    Planned Occupancy July 21, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 11   Palo Alto High School  Football Stadium Renovation  A. PROJECT STATUS    DLM presented the stadium renovation conceptual  plan to the BOE on June 1, 2010, and the BOE approved  it on June 22, 2010.  Planning will resume in August  after the Facilities Steering Committee (FSC) reviews  the revised master plan project list and budget.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.13    D. PROJECT OVERVIEW:  • Conceptual design was approved BOE on June 22, 2010.     Funding  State Funds $0  Strong Schools Bond Funds $1,358,473  Other Funding $0  Total $1,358,437    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $127,622  Construction & Equipment $1,230,815  Soft Costs Contingency $0  Total $1,358,437    Percent of Budget Expended 10.4%  Current Phase: Programming   Schedule:  Architect Contract (2) January 26, 2010  BOE Approval February 9, 2010    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) October 11, 2010*  BOE Approval October 25, 2010*    Submit to DSA January 11, 2011*     Approval by DSA May 23, 2011*    Authorize to Bid (2) March 29, 2011*  BOE Approval April 19, 2011*    Bid Opening May 13, 2011*    Award of Contract (1) May 24, 2011*    Notice to Proceed May 31, 2011*    Substantial Completion January 5, 2012*    Planned Occupancy January 31, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 12   Palo Alto High School  Multi‐Use Field  A. PROJECT STATUS    Valley Crest Landscape began grading the existing field area on June 1,  2010 and is scheduled for completion by January 31, 2011, which  includes new dugouts and time for turf establishment.  Work  commenced in the south parking lot on June 14, 2010, and  improvements are expected to be complete by August 13, 2010.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.14    D. PROJECT OVERVIEW:  • Construction commenced on June 1, 2010.  Project currently proceeding on schedule and within budget.     Funding  State Funds $0  Strong Schools Bond Funds $3,002,063  Other Funding $1,075,991  Total $4,078,054    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $673,020  Construction & Equipment $3,312,683  Soft Costs Contingency $92,351  Total $4,078,054    Percent of Budget Expended 9.5%  Current Phase: Construction   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) December 9, 2009  BOE Approval January 13, 2009    Schematic Design (2) February 24, 2009  BOE Approval March 17, 2009    Submit to DSA March 19, 2009     Approval by DSA September 30, 2009    Authorize to Bid (2) January 26, 2010  BOE Approval February 9, 2010    Bid Opening March 16, 2010    Award of Contract (1) April 7, 2010    Notice to Proceed June 1, 2010    Substantial Completion January 21, 2011*    Planned Occupancy February 1, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 13   Palo Alto High School  Classroom Building and Media Arts  A. PROJECT STATUS    DLM is scheduled to submit 95% CD’s by June 30, 2010.  Final  estimates, constructability reviews and document coordination will  be completed prior to a target DSA submittal date of August 1, 2010.  On June 14, 2010, Rodan Builders, Inc. commenced work on the  relocation of the 16 existing portables to accommodate the new  buildings. Portable relocations will be finished by the beginning of  the fall semester.                 B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget. Funding  State Funds $0  Strong Schools Bond Funds $34,220,000  Other Funding $0  Total $34,220,000    Budget  Salaries and Benefits $0  Supplies $50,000  Contracts & Services $6,067,996  Construction & Equipment $27,876,384  Soft Costs Contingency $225,620  Total $34,220,000    Percent of Budget Expended 1.8%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 1, 2010*     Approval by DSA April 15, 2011*    Authorize to Bid (2) February 22, 2011*  BOE Approval March 8, 2011*    Bid Opening April 19, 2011*    Award of Contract (1) April 26, 2011*    Notice to Proceed May 9, 2011*    Substantial Completion March 25, 2013*    Planned Occupancy August 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 14   Palo Alto High School  Theater and Associated Site Improvements  A. PROJECT STATUS    On June 22, 2010 the BOE approved conceptual design and  authorized DLM to proceed with schematic design.   DLM will  meet with specialty consultants this summer and resume  subcommittee meetings in late August.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.11    D. PROJECT OVERVIEW:  • Conceptual design was approved by BOE on June 22, 2010. Funding  State Funds $0  Strong Schools Bond Funds $17,720,000  Other Funding $0  Total $17,720,000    Budget  Salaries and Benefits $0  Supplies $50,000  Contracts & Services $3,276,077  Construction & Equipment $14,284,700  Soft Costs Contingency $109,223  Total $109,223    Percent of Budget Expended 0.2%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 1, 2010  BOE Approval June 22, 2010    Schematic Design (2) October 20, 2010*  BOE Approval November 2, 2010*    Submit to DSA August 5, 2011*    Approval by DSA February 16, 2012*    Authorize to Bid (2) February 24, 2012*  BOE Approval March 8, 2010*    Bid Opening March 25, 2012*    Award of Contract (1) June 13, 2012*    Notice to Proceed February 11, 2013*    Substantial Completion July 13, 2015*    Planned Occupancy August, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 15   Jordan Middle School  A. PROJECT STATUS    AEDIS has proceeded into design development and drawings  are anticipated to be submitted for review in August.                                 B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $17,943,191  Other Funding $0  Total $17,943,191    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,432,480  Construction & Equipment $14,014,500  Soft Costs Contingency $496,214  Total $17,943,194    Percent of Budget Expended 1.5%  Current Phase: Design Development    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) March 23, 2010  BOE Approval April 27, 2010    Submit to DSA November 24, 2010*     Approval by DSA July 29, 2011*    Authorize to Bid (2) July 25, 2011*  BOE Approval August 5, 2011*    Bid Opening September 7, 2011*    Award of Contract (1) September 22, 2011*    Notice to Proceed October 19, 2011*    Substantial Completion April 18, 2013*    Planned Occupancy August 5, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 16   J.L. Stanford Middle School  A. PROJECT STATUS    AEDIS presented schematic design to the BOE on June  1 and June 22 for approval.  The BOE approved and  authorized staff to proceed with design development  for the buildings, however the exterior site design will  return to the BOE in September for discussion.   Therefore, AEDIS will meet with the advisory  committee and interested community members to  refine the exterior design and landscaping in  September, before returning to the BOE.                     B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:  • Schematic design for the buildings was approved on June 22, 2010. Funding  State Funds $0  Strong Schools Bond Funds $17,184,697  Other Funding $0  Total $17,184,697    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,281,600  Construction & Equipment $13,406,000  Soft Costs Contingency $497,099  Total $17,184,699    Percent of Budget Expended 1.2%  Current Phase: Schematic Design/Design Development   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) June 1, 2010*  BOE Approval June 22, 2010*    Submit to DSA December 10, 2010*     Approval by DSA August 8, 2011*    Authorize to Bid (2) August 2, 2011*  BOE Approval August 15, 2011*    Bid Opening October 4, 2011*    Award of Contract (1) October 21, 2011*    Notice to Proceed November 15, 2011*    Substantial Completion March 6, 2013*    Planned Occupancy August 5, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 17   Terman Middle School  A. PROJECT STATUS    AEDIS has proceeded into design development and drawings are  anticipated to be submitted for review in August.                                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.  Funding  State Funds $0  Strong Schools Bond Funds $12,850,071  Other Funding $0  Total $12,850,071    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,411,150  Construction & Equipment $10,096,569  Soft Costs Contingency $342,352  Total $12,850,071    Percent of Budget Expended 1.2%  Current Phase: Design Development    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) May 11, 2010  BOE Approval May 25, 2010    Submit to DSA November 29, 2010*    Approval by DSA July 26, 2011*    Authorize to Bid (2) July 27, 2011*  BOE Approval August 10, 2011*    Bid Opening September 19, 2011*    Award of Contract (1) October 4, 2011*    Notice to Proceed October 5, 2011*    Substantial Completion March 26, 2013*    Planned Occupancy July 3, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 18   Fairmeadow Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    Gelfand Partners will develop schematic design plans during  summer break.  In September, Gelfand will meet with the  site committee and the P.T.A., as well as host a community  meeting before presenting the schematic design plans, as  anticipated, to the BOE on September 14, 2010.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Programming in progress. Funding  State Funds $0  Strong Schools Bond Funds $9,327,500  Other Funding $0  Total $9,327,500    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,389,619  Construction & Equipment $7,835,500  Soft Costs Contingency $102,381  Total $9,327,500    Percent of Budget Expended 0.3%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) October 13, 2009  BOE Approval October 27, 2009    Conceptual Design (2) March 23, 2010  BOE Approval April 6, 2010    Schematic Design (2) September 14, 2010*  BOE Approval September 28, 2010*    Submit to DSA March 18, 2011*     Approval by DSA November 11, 2011*    Authorize to Bid (2) December 23, 2011*  BOE Approval January 7, 2012*    Bid Opening February 14, 2012*    Award of Contract (1) February 27, 2012*    Notice to Proceed February 28, 2012*    Substantial Completion April 29, 2013*    Planned Occupancy August 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 19   Ohlone Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    Bids from prequalified contractors are due July 13, 2010.  The  project is expected to be awarded at a BOE special meeting  scheduled for July 19, 2010.  Construction will commence in  August 2010 with anticipated completion in late 2011.  On June  14, 2010, Coulter Construction began relocating existing portables  on the site to accommodate the new building.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Bids scheduled to be opened on July 13, 2010.        Funding  State Funds $0  Strong Schools Bond Funds $11,667,965  Other Funding $0  Total $11,667,965    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,221,174  Construction & Equipment $9,181,991  Soft Costs Contingency $264,800  Total $11,667,965    Percent of Budget Expended 8.0%  Current Phase: Bid & Award   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) March 3, 2009  BOE Approval March 17, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA November 24, 2009    Authorize to Bid (2) April 27, 2010  BOE Approval May 11, 2010    Approval by DSA May 18, 2010    Bid Opening July 13, 2010*    Award of Contract (1) July 19, 2010*    Notice to Proceed August 6, 2010*    Substantial Completion February 1, 2012*    Planned Occupancy February 14, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 20   Hoover Elementary School  Pre‐Design  A. PROJECT STATUS    Gelfand met with the site steering committee on June 3,  2010 to kick‐off the pre‐design project at Hoover.  Gelfand  will return to Hoover’s site steering committee with  planning options for the campus in September, after  summer break.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Gelfand commenced pre‐design with the steering committee on June 3, 2010. Funding  State Funds $0  Strong Schools Bond Funds $8,575,389  Other Funding $0  Total $8,575,389    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,278,477  Construction & Equipment $7,196,912  Soft Costs Contingency $100,000  Total $8,575,389    Percent of Budget Expended 0.0%  Current Phase: Planning   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) September 28, 2010*  BOE Approval October 12, 2010*    Schematic Design (2) December 9, 2010*  BOE Approval December 14, 2010*    Submit to DSA June 2, 2011*     Approval by DSA January 26, 2012*    Authorize to Bid (2) March 8, 2012*  BOE Approval March 24, 2012*    Bid Opening April 30, 2012*    Award of Contract (1) May 15, 2012*    Notice to Proceed May 21, 2012*    Substantial Completion July 23, 2013*    Planned Occupancy August 16, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 21   Duveneck Elementary School  Pre‐Design  A. PROJECT STATUS    Gelfand conducted a second pre‐design meeting with the site  steering committee on June 8, 2010.  The steering committee  will continue campus planning discussion in September, after  summer break.                   B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Gelfand will meet with the site steering committee in August. Funding  State Funds $0  Strong Schools Bond Funds $7,019,083  Other Funding $0  Total $7,019,083    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,068,019  Construction & Equipment $5,858,683  Soft Costs Contingency $92,381  Total $7,019,083    Percent of Budget Expended 0.0%  Current Phase: Planning   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) September 28, 2010*  BOE Approval October 12, 2010*    Schematic Design (2) December 9, 2010*  BOE Approval December 14, 2010*    Submit to DSA June 2, 2011*     Approval by DSA January 26, 2012*    Authorize to Bid (2) March 8, 2012*  BOE Approval March 24, 2012*    Bid Opening April 30, 2012*    Award of Contract (1) May 15, 2012*    Notice to Proceed May 20, 2012*    Substantial Completion July 1, 2013*    Planned Occupancy August 16, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 22   Elementary Classroom Improvements  A. PROJECT STATUS    The BOE approved Gelfand Partners’ addendum on June 22, 2010 for design services on the classroom  improvements.  Gelfand will commence design during summer break so site staff can review proposed  improvements in September.  The classroom improvements project consists of new lighting, windows and  shades, ventilation improvements and ceiling tiles.  Also part of the classroom improvements project is the  implementation of a technology wall.  District staff completed site walks at each elementary school and plan  to bid the technology wall project in July, allowing for construction to begin in September, 2010.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • Gelfand to commence design.  Funding  State Funds $0  Strong Schools Bond Funds $8,887,522  Other Funding $0  Total $8,887,522    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,193,721  Construction & Equipment $7,488,706  Soft Costs Contingency $205,095  Total $8,887,522    Percent of Budget Expended 1.3%    Current Phase: Planning   Schedule:  Architect Contract (2) June 8, 2010*  BOE Approval June 22, 2010*    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) TBD  BOE Approval N/A    Submit to DSA TBD     Approval by DSA TBD    Authorize to Bid (2) TBD   BOE Approval TBD    Bid Opening TBD    Award of Contract (1) TBD    Notice to Proceed TBD    Substantial Completion TBD    Planned Occupancy TBD    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 23   Gunn High School  Industrial Arts Addition and Renovation  A. PROJECT STATUS    Of the $5,576,500 project budget, 84.6% or $4,720,037 was  expended.  Approved change orders were $208,756, which is  approximately 59.8% of the $349,000 construction contingency.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11    D. PROJECT OVERVIEW:  • The building occupied as scheduled, and the project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,576,500  Other Funding $0  Total $5,576,500    Budget  Salaries and Benefits $0  Supplies $10,358  Contracts & Services $1,216,066  Construction & Equipment $4,300,350  Soft Costs Contingency $49,726  Total $5,576,500    Percent of Budget Expended 89.0%    Change Order Contingency  • Starting Contingency Balance $349,000  • Remaining Contingency Balance $140,244  • Percent of Changes 59.8%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –January 4, 2010    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA June 17, 2008     Approval by DSA December 24, 2008    Authorize to Bid (2) October 14, 2008  BOE Approval October 28, 2008    Bid Opening December 16, 2008    Award of Contract (1) December 24, 2008    Notice to Proceed January 6, 2009    Substantial Completion November 25, 2009    Planned Occupancy January 4, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 24   Gunn High School  Aquatic Center  A. PROJECT STATUS    Of the $5,013,750 project budget, 96.6%, or $4,844,070 was  expended.  Approved change orders were $194,739, which is  approximately 49.9% of the $389,887 construction contingency.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.12    D. PROJECT OVERVIEW:  • This project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,013,750  Other Funding $0  Total $5,013,750    Budget  Salaries and Benefits $0  Supplies $7,684  Contracts & Services $679,284  Construction & Equipment $4,323,742  Soft Costs Contingency $3,040  Total $5,013,750    Percent of Budget Expended 96.8%    Change Order Contingency  • Starting Contingency Balance $389,887  • Remaining Contingency Balance $195,148  • Percent of Changes 49.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –June 15, 2009    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA December 11, 2007     Approval by DSA April 24, 2008    Authorize to Bid (2) April 8, 2008  BOE Approval April 22, 2008    Bid Opening May 28, 2008    Award of Contract (1) June 4, 2008    Notice to Proceed December 6, 2008    Substantial Completion June 15, 2009    Planned Occupancy June 15, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 25   Middle School Pre‐Design  Jordan, J.L. Stanford and Terman  A. PROJECT STATUS     AEDIS presented recommended concept plans for each campus to the  Board of Education on June 23 for discussion and received approval  on September 8 by the Board of Education to move into schematic  design.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12    D. PROJECT OVERVIEW:  • This project has been completed on schedule and under budget. Board approval received on September  8, 2009. Funding  State Funds $0  Strong Schools Bond Funds $101,000  Other Funding $0  Total $101,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $85,000  Construction & Equipment $0  Soft Costs Contingency $15,000  Total $101,000    Percent of Budget Expended 52.9%    Current Phase: Complete   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 26   Middle Schools Interim Classrooms  Jordan and J.L. Stanford  A. PROJECT STATUS     Contracts were awarded to Coulter Construction for Jordan Middle  School and Mark Electric for Stanford Middle School following  Board of Education approval on May 26, 2009.  Both contractors  started work on June 15, 2009 and were completed on August 3,  2009 at Jordan and August 12, 2009 at Stanford.  Of the $1,047,186  project budget, 25%, or $236,696 has been expended. Pending  Change Orders are currently estimated to be a deduct of ($10,331),  which is approximately 0% of the $30,698 construction  contingency.            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:  • This project was completed under budget and on schedule. Funding  State Funds $0  Strong Schools Bond Funds $1,047,186  Other Funding $0  Total $1,047,186    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $308,648  Construction & Equipment $707,840  Soft Costs Contingency $30,698  Total $1,047,186    Percent of Budget Expended 48.9%    Change Order Contingency  • Starting Contingency Balance $30,698  • Remaining Contingency Balance $30,698  • Percent of Changes 0%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –August 25, 2009    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA April 14, 2009     Approval by DSA April 22, 2009    Authorize to Bid (2) March 31, 2009  BOE Approval April 14, 2009    Bid Opening May 14, 2009    Award of Contract (1) May 26, 2009    Notice to Proceed June 1, 2009    Substantial Completion August 12, 2009    Planned Occupancy August 25, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 27   Garland Elementary School  Campus Modernization  A. PROJECT STATUS    The Board of Education voted on August 25, 2009 to approve the  amendment to Garland lease to Stratford School.  Therefore, the  district has placed the project on hold.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10    D. PROJECT OVERVIEW:  • This project has been placed on hold. Funding  State Funds $0  Strong Schools Bond Funds $22,178,544  Other Funding $0  Total $22,178,544    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,830,789  Construction & Equipment $17,485,000  Soft Costs Contingency $862,755  Total $22,178,544    Percent of Budget Expended 1.3%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) February 10, 2009  BOE Approval February 24, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 28   Elementary School Teaching Walls  Phase 1 Schools  A. PROJECT STATUS    The district placed this project on hold after review of the  implementation of other classroom improvements, as  recommended by the elementary school principals.  This  project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.9    D. PROJECT OVERVIEW:  • This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary  above).  Funding  State Funds $0  Strong Schools Bond Funds $7,044,987  Other Funding $0  Total $7,044,987    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,341,394  Construction & Equipment $5,498,498  Soft Costs Contingency $205,095  Total $7,044,987    Percent of Budget Expended 1.6%  Current Phase: On Hold   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  OHS WEST:260388860.1 A-1 EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. Numbers Added A-2 OHS WEST:260388860.1 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. A-3 OHS WEST:260388860.1 3. GUNN HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Demolish old library building. 3. Replace temporary classrooms with permanent classrooms. 4. Construct additional restrooms. 5. Construct second gymnasium. 6. Construct new soccer field. 7. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 9. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 10. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 11. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 12. Replace swimming pool with new 35-meter pool, pool equipment and support structures, pool decking, bleachers, storage, restrooms, showers, associated equipment. 13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace athletic equipment. 14. Modernize football stadium, including new bathrooms and concession stands. A-4 OHS WEST:260388860.1 4. PALO ALTO HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Construct additional restrooms. 4. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 6. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 7. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 8. Library modernization and building interior improvements, including infrastructure and major building system upgrades. 9. Renovation or replacement of the Tower Building to accommodate administration, classroom and program support space. 10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility improvements; construction of new restrooms; install new roofing; replace doors and windows; replace gymnasium floors and athletic equipment, bleachers and renovation of interior. Renovation or replacement of weight training facility. 11. Construct new theater building. 12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing and storage. 13. Modernize football stadium, including replace bleachers; new bathrooms and concession stands. 14. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. A-5 OHS WEST:260388860.1 5. OTHER DISTRICT-WIDE PROJECTS Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and equipment for all classrooms, athletic facilities and other facilities, as needed. 1. Replace existing or acquire new computers, technology and related equipment on an ongoing basis. 2. Establish a planned maintenance fund to address maintenance work expected to be needed to all District facilities on an ongoing basis (other than as may be necessary for current maintenance, operation or repairs), in order to implement the District’s comprehensive facilities maintenance plan. 3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease- purchase arrangements, or execute purchase option under a lease for any of these authorized facilities. 4. If and as opportunities become available, and to the extent the Board of Education determines that bond funds are available for the purpose, acquisition of land and other interests in real property for future school buildings and other District facilities, and construction of such facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise listed. 5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field equipment and facilities (including nets, basketball standards, goals and goalposts, backstops), field lighting, etc. 6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS 1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead, etc., where necessary. 2. Address unforeseen conditions revealed by construction/modernization (including plumbing or gas line breaks, dry rot, seismic, structural, etc.). 3. Other improvements required to comply with existing building codes, including the Field Act, and access requirements of the Americans with Disabilities Act (ADA). 4. Site preparation/restoration in connection with new construction, renovation or remodeling, or installation or removal of relocatable classrooms, including ingress and egress, demolition of existing structures, removing, replacing, or installing irrigation and drainage, utility lines (such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any necessary easements, licenses, or rights of way to the property. 5. Rental or construction of storage facilities and other space on an interim basis, as needed to accommodate construction materials, equipment, and personnel, and interim classrooms (including relocatables) for students and school functions or other storage for classroom materials displaced during construction. A-6 OHS WEST:260388860.1 7. RENOVATION/MODERNIZATION (DEFINED) For purposes of the Bond Project List, renovation and modernization projects are intended to restore the building systems and infrastructure, weather protections, finishes, and technology, or reallocate and reorganize space, to a condition that will provide a sustainable, functional educational and administrative environment for future years, comparable to new construction. Renovation projects may include, but are not limited to nor necessarily encompass, all of the following, depending upon the age, condition and needs of each particular school facility: 1. upgrade electrical, communication, fire alarm, and similar building systems as well as main power service and distribution, which may include active and passive solar power and heating system acquisition, installation and construction 2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply, meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within buildings and sites and to connect with city supply and drainage systems 3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient heating and air cooling systems (HVAC), including installing energy management systems (EMS); 4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and fixtures, as necessary; 5. Repair, modify and construct structural elements of the existing structure as necessary; 6. Replace or repair aging roofs with similar materials or District standard materials; 7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes, doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces (including white boards, marker boards, tack boards, television mounts, scoreboards, fire extinguishers, kitchen cabinets/equipment, etc.); 8. Upgrade, modify and construct restroom facilities; 9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24 requirements; 10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood siding, paint, etc.); replace doors and windows 11. Modify, expand, separate, convert and construct school support areas; staff work and lunch areas; and educational areas to provide adequate, functional environments; 12. Modify, replace and construct functional components of altered or replaced building components (including rainwater leaders, fascias, mansards, etc.); ™ For any project involving renovation, modernization, remodeling or rehabilitation of a building or the major portion of a building, the District may proceed with new replacement construction instead (including any necessary demolition), if the Board of Education determines that replacement and new construction is more practical than rehabilitation and renovation, considering the building’s age, condition, expected remaining life, comparative cost, and other relevant factors.