Monthly Reports 2010-06 (Jun)
MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
June 2010
Current Strong Schools Bond
Capital Improvement Projects
Prepared by
O’Connor Construction Management, Inc.
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Attachment 2 – Master Project Schedule
Capital Projects
High School Master Plan page 6
Gunn High School – New Classroom Buildings A & B page 7
Gunn High School – Parking and Drop‐off Sitework Improvement page 8
Gunn High School – New Gymnasium page 9
Gunn High School – Air Conditioning of Existing Buildings page 10
Palo Alto High School – Stadium Field Renovation page 11
Palo Alto High School – Multi‐use Field page 12
Palo Alto High School – Classroom Building and Media Arts page 13
Palo Alto High School – Theater and Associated Site Improvements page 14
Jordan Middle School page 15
J.L. Stanford Middle School page 16
Terman Middle School page 17
Fairmeadow Elementary School page 18
Ohlone Elementary School page 19
Hoover Elementary School page 20
Duveneck Elementary School page 21
Elementary Classroom Improvements page 22
Inactive Capital Projects
Gunn High School – Industrial Arts Renovation page 23
Gunn High School – Aquatic Center page 24
Middle School Pre‐Design page 25
Middle School Interim Classrooms page 26
Garland Elementary School page 27
Elementary School Teaching Walls – Phase 1 Schools page 28
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
CAPITAL PROJECTS
High School Master Plan
DLM and Gates + Associates presented the Palo Alto and Gunn High School’s landscape master plans to the Board
of Education (BOE) on June 8, 2010 as an information item. The landscape master plan and facilities steering
committees will reconvene in late August and proceed with further coordination for final approval of the updated
master plans for each campus that incorporate the work of Gates + Associates and other revisions since the
original March 31, 2009 approval.
Gunn High School – New Classroom Buildings A & B
DLM is scheduled to submit 95% CD’s by June 30, 2010. Final estimates, constructability reviews and document
coordination will be completed prior to a target DSA submittal date of August 1, 2010. Currently, Rodan Builders,
Inc. has moved all 26 existing portables in order to accommodate the new buildings. The portable classrooms are
being reassembled and will be finished by the beginning of the fall semester.
Gunn High School – Parking and Drop‐off Sitework Improvement
The City School Traffic Safety Committee (CSTSC) reviewed the construction and fencing plan that will impact
traffic flow on the first day of classes. To assist with safety coordination, the plan will be included in the “Back to
School” packets being sent to students to notify them of the changes, and to indentify the interim bicycle paths
available during construction. Parking and Drop‐off planning will commence this summer.
Gunn High School – New Gymnasium
DLM is scheduled to submit 95% CD’s by June 30, 2010. Final estimates, constructability reviews and document
coordination will be completed prior to a target DSA submittal date of August 1, 2010.
Gunn High School – Air Conditioning of Existing Buildings
DLM continues design on the air conditioning project. DLM plans to submit plans to DSA by September 2010.
Palo Alto High School – Stadium Field Renovation
DLM presented the stadium renovation conceptual plan to the BOE on June 1, 2010, and the BOE approved it on
June 22, 2010. Planning will resume in August after the Facilities Steering Committee (FSC) reviews the revised
master plan project list and budget.
Palo Alto High School – Multi‐use Field
Valley Crest Landscape began grading the existing field area on June 1, 2010 and is scheduled for completion by
January 31, 2011, which includes new dugouts and time for turf establishment. Work commenced in the south
parking lot on June 14, 2010, and improvements are expected to be complete by August 13, 2010.
Palo Alto High School – Classroom Building and Media Arts Building
DLM is scheduled to submit 95% CD’s by June 30, 2010. Final estimates, constructability reviews and document
coordination will be completed prior to a target DSA submittal date of August 1, 2010. On June 14, 2010, Rodan
Builders, Inc. commenced work on the relocation of the 16 existing portables to accommodate the new
buildings. Portable relocations will be finished by the beginning of the fall semester.
Palo Alto High School – Theater and Associated Site Improvements
On June 22, 2010 the BOE approved conceptual design and authorized DLM to proceed with schematic design.
DLM will meet with specialty consultants this summer and resume subcommittee meetings in late August.
Jordan Middle School
AEDIS has proceeded into design development and drawings are anticipated to be submitted for review in August.
Page | 4
J.L. Stanford Middle School
AEDIS presented schematic design to the BOE on June 1 and June 22 for approval. The BOE approved and
authorized staff to proceed with design development for the buildings, however the exterior site design will return
to the BOE in September for discussion. Therefore, AEDIS will meet with the advisory committee and interested
community members to refine the exterior design and landscaping in September, before returning to the BOE.
Terman Middle School
AEDIS has proceeded into design development and drawings are anticipated to be submitted for review in August.
Fairmeadow Elementary School – New Classroom Building and Modernization
Gelfand Partners will develop schematic design plans during summer break. In September, Gelfand will meet with
the site committee and the P.T.A., as well as host a community meeting before presenting the schematic design
plans, as anticipated, to the BOE on September 14, 2010.
Ohlone Elementary School – New Classroom Building and Modernization
Bids from prequalified contractors are due July 13, 2010. The project is expected to be awarded at a BOE special
meeting scheduled for July 19, 2010. Construction will commence in August 2010 with anticipated completion in
late 2011. On June 14, 2010, Coulter Construction began relocating existing portables on the site to accommodate
the new building.
Hoover Elementary School – Pre‐Design
Gelfand met with the site steering committee on June 3, 2010 to kick‐off the pre‐design project at Hoover.
Gelfand will return to Hoover’s site steering committee with planning options for the campus in September, after
summer break.
Duveneck Elementary School – Pre‐Design
Gelfand conducted a second pre‐design meeting with the site steering committee on June 8, 2010. The steering
committee will continue campus planning discussion in September, after summer break.
Elementary Classroom Improvements
The BOE approved Gelfand Partners’ addendum on June 22, 2010 for design services on the classroom
improvements. Gelfand will commence design during summer break so site staff can review proposed
improvements in September. The classroom improvements project consists of new lighting, windows and shades,
ventilation improvements and ceiling tiles. Also part of the classroom improvements project is the
implementation of a technology wall. District staff completed site walks at each elementary school and plan to bid
the technology wall project in July, allowing for construction to begin in September, 2010.
INACTIVE CAPITAL PROJECTS
Gunn High School – Industrial Arts Addition & Renovation
Of the $5,576,500 project budget, 84.6% or $4,720,037 was expended. Approved change orders were $208,756,
which is approximately 59.8% of the $349,000 construction contingency.
Gunn High School – Aquatic Center
Of the $5,013,750 project budget, 96.6%, or $4,844,070 was expended. Approved change orders were $194,739,
which is approximately 49.9% of the $389,887 construction contingency.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for
discussion and received approval on September 8 by the Board of Education to move into schematic design.
Page | 5
Middle Schools Interim Housing – Jordan and J.L. Stanford
Contracts were awarded to Coulter Construction for Jordan Middle School and Mark Electric for Stanford Middle
School following Board of Education approval on May 26, 2009. Both contractors started work on June 15, 2009
and were completed on August 3, 2009 at Jordan and August 12, 2009 at Stanford. Of the $1,047,186 project
budget, 25%, or $236,696 has been expended. Pending Change Orders are currently estimated to be a deduct of
($10,331), which is approximately 0% of the $30,698 construction contingency.
Garland Elementary School Renovation
The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.
Therefore, the district has placed the project on hold.
Elementary School Teaching Walls – Phase 1 Schools
The district placed this project on hold after review of the implementation of other classroom improvements, as
recommended by the elementary school principals. This project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
Board Actions in June
June 1, 2010
Consent 6 – Qualified School Construction Bonds (QSCB): Resolution 2009‐10.16, Amending Resolution 2009‐10.07
Regarding Terms of Sale of QSCBs; and Resolution 2009‐10.17 Authorizing the Advance of General Fund Moneys to
the Bond Interest and Redemption Fund QSCBs
Consent 7 – Authorization to Bid Procurements and Interactive Whiteboards and Sound Assist Devices
Action 8 – Reappointment of Four Members of the Citizens’ Oversight Committee for the Strong Schools Bond
June 22, 2010
Consent 9 – Five‐Year Deferred Maintenance Plan
Consent 10 – Contract with O’Connor Construction Management, Inc. for 2010‐11
Consent 11 – Authorization to Enter into Addendum No. 9 with Gelfand Partners for Additional Services for Ohlone
Elementary School and the Classroom Improvements Project
Action 26 – Approval of Schematic Design of J.L. Stanford Middle School
Action 27 – Approval of Conceptual Design and Project Budget for the New Theater Project at Palo Alto High
School
Action 28 – Approval of Conceptual Design and Project Budget for the Stadium Project at Palo Alto High School
Action 35 – Negotiation to Amend the Contract with Gilbane Building Company to Provide Project and
Construction Management Services
A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 129,431 110,244 76.0% 19,187 85.18% 15,569Gunn High School 1 - Aquatic Center 5,013,750 4,864,425 4,856,830 96.9% 7,595 99.84% 149,325Gunn High School 2 - I.A 5,511,500 5,163,451 4,921,437 89.3% 242,014 95.31% 348,049Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom A & B 24,120,000 3,129,148 1,116,080 4.6% 2,013,068 35.67% 20,990,852Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 3,530 0.1% 214,240 1.62% 3,722,230Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 1,093,201 401,533 2.9% 691,668 36.73% 12,736,799Gunn High School 7- A/C 2,600,000 0 0 0.0% 0 0.00% 2,600,000Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.00% 20,945,045Palo Alto High Schools - High School Master Plan 145,000 132,773 111,920 77.2% 20,853 84.29% 12,227Palo Alto High School 1 - Bleacher 1,358,437 162,011 141,653 10.4% 20,358 87.43% 1,196,426Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,989,809 283,749 9.5% 2,706,060 9.49% 12,254Palo Alto high School 3 - New classroom & Media Art Building 34,220,000 3,342,845 622,112 1.8% 2,720,733 18.61% 30,877,155Palo Alto High School 4 - New Theater 17,720,000 1,026,210 41,537 0.2% 984,673 4.05% 16,693,790Palo Alto High School - Reserved 42,348,045 0 0 0.0% 0 0.00% 42,348,045Jordan Middle School - Middle School Pre-Design 33,665 19,718 17,413 51.7% 2,305 88.31% 13,947Jordan Middle Schools 1- Interim Classrooms 600,342 171,102 160,878 26.8% 10,224 94.02% 429,240Jordan Middle School 2 17,943,194 1,583,569 263,471 1.5% 1,320,098 16.64% 16,359,625Jordan Middle School - Reserved 0 0 0 0.0% 0 0.00% 0J.L.S Middle School - Middle School Pre-Design 33,669 19,627 17,995 53.4% 1,632 91.68% 14,042J.L.S Middle School 1 - Interim Classrooms 446,844 337,590 317,171 71.0% 20,419 93.95% 109,254 J.L.S Middle School 2 17,184,699 1,432,112 206,088 1.2% 1,226,024 14.39% 15,752,587 J.L.S Middle School - Reserved 0 0 0 0.0% 0 0.00% 0Terman Middle School - Middle School Pre- Design 33,666 19,627 18,010 53.5% 1,617 91.76% 14,039Terman Middle School 1 12,850,071 1,187,625 157,505 1.2% 1,030,120 13.26% 11,662,446Terman Middle School - Reserved 0 0 0 0.0% 0 0.00% 0PAUSD Elementary Schools - Elementary Growth Plan 145,000 55,560 55,560 38.3% 0 100.00% 89,440Addison Elementary School 1-Phase I 5,199,727 0 0 0.0% 0 0.00% 5,199,727Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.00% 701,925Duveneck Elementary School 1-Phase I 7,019,083 27,500 0 0.0% 27,500 0.00% 6,991,583Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.00% 6,202,343Fairmeadow Elementary School 1- Phase I 9,327,500 770,909 25,000 0.3% 745,909 3.24% 8,556,591Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.00% 4,793,814Hoover Elementary School 1-Phase I 8,575,389 47,500 0 0.0% 47,500 0.00% 8,527,889Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.00% 802,200Ohlone Elementary School 1- Phase I 11,667,965 1,643,787 928,968 8.0% 714,819 56.51% 10,024,178Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.00% 3,482,885Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.00% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 133,018 106,548 1.2% 26,470 80.10% 8,754,504Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.00% 8,410,862PAUSD - Program Admin. ** 3,353,108 2,661,835 2,098,590 62.6% 563,245 78.84% 691,273PAUSD - Technology 5,995,689 2,547,823 2,297,606 38.3% 250,217 90.18% 3,447,866PAUSD - Technology -Reserved 7,911,676 0 0 0.0% 0 0.00% 7,911,676PAUSD - Reserved 6,335,945 0 0 0.0% 0 0.00% 6,335,945Total346,305,464 35,197,032 19,567,318 15,629,714 311,108,432* Old Teaching Wall ProjectPrepared by: Business Services Department based on QSS accounting SystemBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond6/29/2010Percent of ExpendedContract BalanceExpenditures Budget BalanceCommitted
Activity IDPhaseActivity NameOriginalDurationStartFinishDuration %CompleteGunn- IndusGunn- Industrial AGunn- Industrial Arts Renovation45101-Oct-08 A23-Jun-10 A100%Gunn - New Gunn - New ClassrGunn - New Classroom Building109520-Apr-09 A01-Jul-1328.49%Gunn - ParkiGunn - Parking andGunn - Parking and Drop Off89301-Sep-09 A31-Jan-1324.19%Gunn New GGunn New GymnasGunn New Gymnasium94021-Apr-09 A27-Nov-1233.09%Gunn Air CoGunn Air ConditionGunn Air Conditioning Project48001-Jan-10 A19-Jul-1142.92%Paly - StadiuPaly - Stadium FielPaly - Stadium Field Renovation Project62817-Aug-09 A24-Jan-1234.71%Paly - Multi UPaly - Multi Use FiePaly - Multi Use Field Improvements58703-Nov-08 A01-Feb-1173.59%Paly - New CPaly - New ClassroPaly - New Classroom Building & Media A...113820-Apr-09 A29-Aug-1327.42%Paly - New TPaly - New TheaterPaly - New Theater and Sitework157609-Sep-09 A14-Sep-1513.77%Jordan New Jordan New ClassrJordan New Classroom Wing & Moderniz...124103-Nov-08 A05-Aug-1334.81%Stanford NewStanford New ClasStanford New Classroom Wing123603-Nov-08 A05-Aug-1334.55%Terman AdmTerman Admin WinTerman Admin Wing Addition & Moderniz...121303-Nov-08 A03-Jul-1335.28%Garland SchGarland School MoGarland School Modernization56603-Nov-08 A30-Jun-10100%FairmeadowFairmeadow ElemeFairmeadow Elementary School119414-Dec-09 A01-Aug-1332.41%Duveneck ElDuveneck ElementDuveneck Elementary School85213-May-10 A16-Aug-133.99%Hoover ElemHoover ElementaryHoover Elementary School85412-May-10 A19-Aug-134.1%Ohlone New Ohlone New ClassOhlone New Classroom Wing97703-Nov-08 A01-Aug-1246.37%Teaching WaTeaching Walls CaTeaching Walls Casework17206-Apr-09 A28-Sep-09 A100%NDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASOND2009201020112012201320142015PALO ALTO UNIFIED SCHOOL DISTRICTSTRONG SCHOOLS BOND PROGRAMMASTER SCHEDULE SUMMARY DesignPlanningBid and AwardConstructionDSACloseoutMPage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc.
Page | 6
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
DLM and Gates + Associates presented the Palo Alto and Gunn
High School’s landscape master plans to the Board of Education
(BOE) on June 8, 2010 as an information item. The landscape
master plan and facilities steering committees will reconvene in
late August and proceed with further coordination for final
approval of the updated master plans for each campus that
incorporate the work of Gates + Associates and other revisions
since the original March 31, 2009 approval.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
• Landscape master plans for each campus to the BOE in June as information.
Funding
State Funds $0
Strong Schools Bond Funds $290,000
Other Funding $0
Total $290,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $279,521
Construction & Equipment $0
Soft Costs Contingency $9,479
Total $290,000
Percent of Budget Expended 76.5%
Current Phase: Master Planning
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 7
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
DLM is scheduled to submit 95% CD’s by June 30, 2010. Final
estimates, constructability reviews and document coordination will
be completed prior to a target DSA submittal date of August 1,
2010. Currently, Rodan Builders, Inc. has moved all 26 existing
portables in order to accommodate the new buildings. The portable
classrooms are being reassembled and will be finished by the
beginning of the fall semester.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $24,120,000
Other Funding $0
Total $24,120,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $4,315,728
Construction & Equipment $19,590,000
Soft Costs Contingency $164,272
Total $24,120,000
Percent of Budget Expended 4.6%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 1, 2010*
Approval by DSA April 15, 2011 *
Authorize to Bid (2) February 22, 2011 *
BOE Approval March 8, 2011*
Bid Opening April 19, 2011 *
Award of Contract (1) April 26, 2011 *
Notice to Proceed May 9, 2011*
Substantial Completion December 3, 2012*
Planned Occupancy June 10, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
The City School Traffic Safety Committee (CSTSC) reviewed
the construction and fencing plan that will impact traffic flow
on the first day of classes. To assist with safety coordination,
the plan will be included in the “Back to School” packets
being sent to students to notify them of the changes, and to
indentify the interim bicycle paths available during
construction. Parking and Drop‐off planning will commence
this summer.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
• This project will commence this summer.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $883,978
Construction & Equipment $2,934,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 28, 2010*
BOE Approval October 12, 2010*
Schematic Design (2) December 16, 2010*
BOE Approval December 23, 2010*
Submit to DSA October 11, 2011*
Approval by DSA April 30, 2012*
Authorize to Bid (2) February 7, 2012*
BOE Approval February 20, 2012*
Bid Opening April 17, 2012*
Award of Contract (1) May 2, 2012*
Notice to Proceed May 24, 2012*
Substantial Completion December 13, 2012*
Planned Occupancy January 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 9
Gunn High School
New Gymnasium
A. PROJECT STATUS
DLM is scheduled to submit 95% CD’s by June 30, 2010. Final
estimates, constructability reviews and document coordination
will be completed prior to a target DSA submittal date of
August 1, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,830,000
Other Funding $0
Total $13,830,000
Budget
Salaries and Benefits $0
Supplies $40,000
Contracts & Services $2,596,521
Construction & Equipment $11,109,450
Soft Costs Contingency $84,029
Total $13,830,000
Percent of Budget Expended 2.9%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 2, 2010*
Approval by DSA April 15, 2011*
Authorize to Bid (2) February 22, 2011*
BOE Approval March 8, 2011*
Bid Opening April 19, 2011*
Award of Contract (1) April 26, 2011*
Notice to Proceed May 9, 2011*
Substantial Completion October 9, 2012*
Planned Occupancy November 13, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
DLM continues design on the air conditioning project. DLM
plans to submit plans to DSA by September 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $447,110
Construction & Equipment $2,128,080
Soft Costs Contingency $24,810
Total $2,600,000
Percent of Budget Expended 0.0%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA September 28, 2010*
Approval by DSA March 8, 2011*
Authorize to Bid (2) February 22, 2011*
BOE Approval March 8, 2011*
Bid Opening March 28, 2011*
Award of Contract (1) April 4, 2011*
Notice to Proceed April 13, 2011*
Substantial Completion June 14, 2011*
Planned Occupancy July 21, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Football Stadium Renovation
A. PROJECT STATUS
DLM presented the stadium renovation conceptual
plan to the BOE on June 1, 2010, and the BOE approved
it on June 22, 2010. Planning will resume in August
after the Facilities Steering Committee (FSC) reviews
the revised master plan project list and budget.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
• Conceptual design was approved BOE on June 22, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $1,358,473
Other Funding $0
Total $1,358,437
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $127,622
Construction & Equipment $1,230,815
Soft Costs Contingency $0
Total $1,358,437
Percent of Budget Expended 10.4%
Current Phase: Programming
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) October 11, 2010*
BOE Approval October 25, 2010*
Submit to DSA January 11, 2011*
Approval by DSA May 23, 2011*
Authorize to Bid (2) March 29, 2011*
BOE Approval April 19, 2011*
Bid Opening May 13, 2011*
Award of Contract (1) May 24, 2011*
Notice to Proceed May 31, 2011*
Substantial Completion January 5, 2012*
Planned Occupancy January 31, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 12
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
Valley Crest Landscape began grading the existing field area on June 1,
2010 and is scheduled for completion by January 31, 2011, which
includes new dugouts and time for turf establishment. Work
commenced in the south parking lot on June 14, 2010, and
improvements are expected to be complete by August 13, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
• Construction commenced on June 1, 2010. Project currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $3,002,063
Other Funding $1,075,991
Total $4,078,054
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $673,020
Construction & Equipment $3,312,683
Soft Costs Contingency $92,351
Total $4,078,054
Percent of Budget Expended 9.5%
Current Phase: Construction
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) December 9, 2009
BOE Approval January 13, 2009
Schematic Design (2) February 24, 2009
BOE Approval March 17, 2009
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) January 26, 2010
BOE Approval February 9, 2010
Bid Opening March 16, 2010
Award of Contract (1) April 7, 2010
Notice to Proceed June 1, 2010
Substantial Completion January 21, 2011*
Planned Occupancy February 1, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
DLM is scheduled to submit 95% CD’s by June 30, 2010. Final
estimates, constructability reviews and document coordination will
be completed prior to a target DSA submittal date of August 1, 2010.
On June 14, 2010, Rodan Builders, Inc. commenced work on the
relocation of the 16 existing portables to accommodate the new
buildings. Portable relocations will be finished by the beginning of
the fall semester.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $34,220,000
Other Funding $0
Total $34,220,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $6,067,996
Construction & Equipment $27,876,384
Soft Costs Contingency $225,620
Total $34,220,000
Percent of Budget Expended 1.8%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 1, 2010*
Approval by DSA April 15, 2011*
Authorize to Bid (2) February 22, 2011*
BOE Approval March 8, 2011*
Bid Opening April 19, 2011*
Award of Contract (1) April 26, 2011*
Notice to Proceed May 9, 2011*
Substantial Completion March 25, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Palo Alto High School
Theater and Associated Site Improvements
A. PROJECT STATUS
On June 22, 2010 the BOE approved conceptual design and
authorized DLM to proceed with schematic design. DLM will
meet with specialty consultants this summer and resume
subcommittee meetings in late August.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
• Conceptual design was approved by BOE on June 22, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $17,720,000
Other Funding $0
Total $17,720,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $3,276,077
Construction & Equipment $14,284,700
Soft Costs Contingency $109,223
Total $109,223
Percent of Budget Expended 0.2%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010
BOE Approval June 22, 2010
Schematic Design (2) October 20, 2010*
BOE Approval November 2, 2010*
Submit to DSA August 5, 2011*
Approval by DSA February 16, 2012*
Authorize to Bid (2) February 24, 2012*
BOE Approval March 8, 2010*
Bid Opening March 25, 2012*
Award of Contract (1) June 13, 2012*
Notice to Proceed February 11, 2013*
Substantial Completion July 13, 2015*
Planned Occupancy August, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
Jordan Middle School
A. PROJECT STATUS
AEDIS has proceeded into design development and drawings
are anticipated to be submitted for review in August.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $17,943,191
Other Funding $0
Total $17,943,191
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,432,480
Construction & Equipment $14,014,500
Soft Costs Contingency $496,214
Total $17,943,194
Percent of Budget Expended 1.5%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA November 24, 2010*
Approval by DSA July 29, 2011*
Authorize to Bid (2) July 25, 2011*
BOE Approval August 5, 2011*
Bid Opening September 7, 2011*
Award of Contract (1) September 22, 2011*
Notice to Proceed October 19, 2011*
Substantial Completion April 18, 2013*
Planned Occupancy August 5, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
J.L. Stanford Middle School
A. PROJECT STATUS
AEDIS presented schematic design to the BOE on June
1 and June 22 for approval. The BOE approved and
authorized staff to proceed with design development
for the buildings, however the exterior site design will
return to the BOE in September for discussion.
Therefore, AEDIS will meet with the advisory
committee and interested community members to
refine the exterior design and landscaping in
September, before returning to the BOE.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
• Schematic design for the buildings was approved on June 22, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,697
Other Funding $0
Total $17,184,697
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,281,600
Construction & Equipment $13,406,000
Soft Costs Contingency $497,099
Total $17,184,699
Percent of Budget Expended 1.2%
Current Phase: Schematic Design/Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) June 1, 2010*
BOE Approval June 22, 2010*
Submit to DSA December 10, 2010*
Approval by DSA August 8, 2011*
Authorize to Bid (2) August 2, 2011*
BOE Approval August 15, 2011*
Bid Opening October 4, 2011*
Award of Contract (1) October 21, 2011*
Notice to Proceed November 15, 2011*
Substantial Completion March 6, 2013*
Planned Occupancy August 5, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Terman Middle School
A. PROJECT STATUS
AEDIS has proceeded into design development and drawings are
anticipated to be submitted for review in August.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $12,850,071
Other Funding $0
Total $12,850,071
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,411,150
Construction & Equipment $10,096,569
Soft Costs Contingency $342,352
Total $12,850,071
Percent of Budget Expended 1.2%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA November 29, 2010*
Approval by DSA July 26, 2011*
Authorize to Bid (2) July 27, 2011*
BOE Approval August 10, 2011*
Bid Opening September 19, 2011*
Award of Contract (1) October 4, 2011*
Notice to Proceed October 5, 2011*
Substantial Completion March 26, 2013*
Planned Occupancy July 3, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Gelfand Partners will develop schematic design plans during
summer break. In September, Gelfand will meet with the
site committee and the P.T.A., as well as host a community
meeting before presenting the schematic design plans, as
anticipated, to the BOE on September 14, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Programming in progress.
Funding
State Funds $0
Strong Schools Bond Funds $9,327,500
Other Funding $0
Total $9,327,500
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,389,619
Construction & Equipment $7,835,500
Soft Costs Contingency $102,381
Total $9,327,500
Percent of Budget Expended 0.3%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010*
BOE Approval September 28, 2010*
Submit to DSA March 18, 2011*
Approval by DSA November 11, 2011*
Authorize to Bid (2) December 23, 2011*
BOE Approval January 7, 2012*
Bid Opening February 14, 2012*
Award of Contract (1) February 27, 2012*
Notice to Proceed February 28, 2012*
Substantial Completion April 29, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Bids from prequalified contractors are due July 13, 2010. The
project is expected to be awarded at a BOE special meeting
scheduled for July 19, 2010. Construction will commence in
August 2010 with anticipated completion in late 2011. On June
14, 2010, Coulter Construction began relocating existing portables
on the site to accommodate the new building.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Bids scheduled to be opened on July 13, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,221,174
Construction & Equipment $9,181,991
Soft Costs Contingency $264,800
Total $11,667,965
Percent of Budget Expended 8.0%
Current Phase: Bid & Award
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010*
Award of Contract (1) July 19, 2010*
Notice to Proceed August 6, 2010*
Substantial Completion February 1, 2012*
Planned Occupancy February 14, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
Gelfand met with the site steering committee on June 3,
2010 to kick‐off the pre‐design project at Hoover. Gelfand
will return to Hoover’s site steering committee with
planning options for the campus in September, after
summer break.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand commenced pre‐design with the steering committee on June 3, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $8,575,389
Other Funding $0
Total $8,575,389
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,278,477
Construction & Equipment $7,196,912
Soft Costs Contingency $100,000
Total $8,575,389
Percent of Budget Expended 0.0%
Current Phase: Planning
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) September 28, 2010*
BOE Approval October 12, 2010*
Schematic Design (2) December 9, 2010*
BOE Approval December 14, 2010*
Submit to DSA June 2, 2011*
Approval by DSA January 26, 2012*
Authorize to Bid (2) March 8, 2012*
BOE Approval March 24, 2012*
Bid Opening April 30, 2012*
Award of Contract (1) May 15, 2012*
Notice to Proceed May 21, 2012*
Substantial Completion July 23, 2013*
Planned Occupancy August 16, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Duveneck Elementary School
Pre‐Design
A. PROJECT STATUS
Gelfand conducted a second pre‐design meeting with the site
steering committee on June 8, 2010. The steering committee
will continue campus planning discussion in September, after
summer break.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand will meet with the site steering committee in August.
Funding
State Funds $0
Strong Schools Bond Funds $7,019,083
Other Funding $0
Total $7,019,083
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,068,019
Construction & Equipment $5,858,683
Soft Costs Contingency $92,381
Total $7,019,083
Percent of Budget Expended 0.0%
Current Phase: Planning
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) September 28, 2010*
BOE Approval October 12, 2010*
Schematic Design (2) December 9, 2010*
BOE Approval December 14, 2010*
Submit to DSA June 2, 2011*
Approval by DSA January 26, 2012*
Authorize to Bid (2) March 8, 2012*
BOE Approval March 24, 2012*
Bid Opening April 30, 2012*
Award of Contract (1) May 15, 2012*
Notice to Proceed May 20, 2012*
Substantial Completion July 1, 2013*
Planned Occupancy August 16, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Elementary Classroom Improvements
A. PROJECT STATUS
The BOE approved Gelfand Partners’ addendum on June 22, 2010 for design services on the classroom
improvements. Gelfand will commence design during summer break so site staff can review proposed
improvements in September. The classroom improvements project consists of new lighting, windows and
shades, ventilation improvements and ceiling tiles. Also part of the classroom improvements project is the
implementation of a technology wall. District staff completed site walks at each elementary school and plan
to bid the technology wall project in July, allowing for construction to begin in September, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• Gelfand to commence design.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,193,721
Construction & Equipment $7,488,706
Soft Costs Contingency $205,095
Total $8,887,522
Percent of Budget Expended 1.3%
Current Phase: Planning
Schedule:
Architect Contract (2) June 8, 2010*
BOE Approval June 22, 2010*
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) TBD
BOE Approval N/A
Submit to DSA TBD
Approval by DSA TBD
Authorize to Bid (2) TBD
BOE Approval TBD
Bid Opening TBD
Award of Contract (1) TBD
Notice to Proceed TBD
Substantial Completion TBD
Planned Occupancy TBD
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
Of the $5,576,500 project budget, 84.6% or $4,720,037 was
expended. Approved change orders were $208,756, which is
approximately 59.8% of the $349,000 construction contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
• The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,576,500
Other Funding $0
Total $5,576,500
Budget
Salaries and Benefits $0
Supplies $10,358
Contracts & Services $1,216,066
Construction & Equipment $4,300,350
Soft Costs Contingency $49,726
Total $5,576,500
Percent of Budget Expended 89.0%
Change Order Contingency
• Starting Contingency Balance $349,000
• Remaining Contingency Balance $140,244
• Percent of Changes 59.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Gunn High School
Aquatic Center
A. PROJECT STATUS
Of the $5,013,750 project budget, 96.6%, or $4,844,070 was
expended. Approved change orders were $194,739, which is
approximately 49.9% of the $389,887 construction contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
• This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,013,750
Other Funding $0
Total $5,013,750
Budget
Salaries and Benefits $0
Supplies $7,684
Contracts & Services $679,284
Construction & Equipment $4,323,742
Soft Costs Contingency $3,040
Total $5,013,750
Percent of Budget Expended 96.8%
Change Order Contingency
• Starting Contingency Balance $389,887
• Remaining Contingency Balance $195,148
• Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education on June 23 for discussion and received approval
on September 8 by the Board of Education to move into schematic
design.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
• This project has been completed on schedule and under budget. Board approval received on September
8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $101,000
Other Funding $0
Total $101,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $85,000
Construction & Equipment $0
Soft Costs Contingency $15,000
Total $101,000
Percent of Budget Expended 52.9%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Middle Schools Interim Classrooms
Jordan and J.L. Stanford
A. PROJECT STATUS
Contracts were awarded to Coulter Construction for Jordan Middle
School and Mark Electric for Stanford Middle School following
Board of Education approval on May 26, 2009. Both contractors
started work on June 15, 2009 and were completed on August 3,
2009 at Jordan and August 12, 2009 at Stanford. Of the $1,047,186
project budget, 25%, or $236,696 has been expended. Pending
Change Orders are currently estimated to be a deduct of ($10,331),
which is approximately 0% of the $30,698 construction
contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project was completed under budget and on schedule.
Funding
State Funds $0
Strong Schools Bond Funds $1,047,186
Other Funding $0
Total $1,047,186
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $308,648
Construction & Equipment $707,840
Soft Costs Contingency $30,698
Total $1,047,186
Percent of Budget Expended 48.9%
Change Order Contingency
• Starting Contingency Balance $30,698
• Remaining Contingency Balance $30,698
• Percent of Changes 0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –August 25, 2009
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA April 14, 2009
Approval by DSA April 22, 2009
Authorize to Bid (2) March 31, 2009
BOE Approval April 14, 2009
Bid Opening May 14, 2009
Award of Contract (1) May 26, 2009
Notice to Proceed June 1, 2009
Substantial Completion August 12, 2009
Planned Occupancy August 25, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education voted on August 25, 2009 to approve the
amendment to Garland lease to Stratford School. Therefore, the
district has placed the project on hold.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,830,789
Construction & Equipment $17,485,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Elementary School Teaching Walls
Phase 1 Schools
A. PROJECT STATUS
The district placed this project on hold after review of the
implementation of other classroom improvements, as
recommended by the elementary school principals. This
project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.9
D. PROJECT OVERVIEW:
• This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary
above).
Funding
State Funds $0
Strong Schools Bond Funds $7,044,987
Other Funding $0
Total $7,044,987
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,341,394
Construction & Equipment $5,498,498
Soft Costs Contingency $205,095
Total $7,044,987
Percent of Budget Expended 1.6%
Current Phase: On Hold
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.