Monthly Reports 2010-05 (May) MMOONNTTHHLLYY  PPRROOGGRREESSSS  RREEPPOORRTT     Through  May 2010      Current Strong Schools Bond  Capital Improvement Projects  Prepared by     O’Connor Construction Management, Inc.  &  Gilbane Building Company  Page | 2   TABLE OF CONTENTS    Executive Summary         page 3     Attachment 1 – Consolidated Expenditure Report    Attachment 2 – Master Project Schedule     Capital Projects     High School Master Plan        page 6    Gunn High School – New Classroom Buildings A & B     page 7    Gunn High School – Parking and Drop‐off Sitework Improvement    page 8    Gunn High School – New Gymnasium       page 9    Gunn High School – Air Conditioning of Existing Buildings    page 10    Palo Alto High School – Stadium Field Renovation     page 11    Palo Alto High School – Multi‐use Field      page 12    Palo Alto High School – Classroom Building and Media Arts    page 13    Palo Alto High School – Theater and Associated Site Improvements    page 14    Jordan Middle School        page 15    J.L. Stanford Middle School       page 16    Terman Middle School        page 17    Fairmeadow Elementary School       page 18    Ohlone Elementary School        page 19    Hoover Elementary School        page 20    Duveneck Elementary School       page 21    Elementary Classroom Improvements      page 22    Inactive Capital Projects    Gunn High School – Industrial Arts Renovation     page 23    Gunn High School – Aquatic Center       page 24    Middle School Pre‐Design        page 25    Middle School Interim Classrooms       page 26    Garland Elementary School       page 27    Elementary School Teaching Walls – Phase 1 Schools     page 28    Appendix  Exhibit A – Bond Project List  Page | 3   EXECUTIVE SUMMARY  CAPITAL PROJECTS   High School Master Plan  DLM held facilities steering committee (FSC) and neighborhood community meetings to present the landscape  master plans for each campus. The FSC recommended the landscape master plan be presented to the board for  approval on June 8, 2010. The Mitigated Negative Declaration (MND) was approved by the BOE on May 11, 2010  and was recorded per CEQA requirements to the County of Santa Clara.    Gunn High School – New Classroom Buildings A & B  DLM submitted 50% construction documents (CD’s) on May 14, 2010 and expects to have 95% CD’s complete in  June with final estimates, constructability and document coordination prior to DSA submittal in July. On May 17,  2010, Rodan Builders, Inc. started preparing to relocation the 26 existing portables in order to accommodate the  new buildings. The portable relocations will be finished for the beginning of the fall semester.  Gunn High School – Parking and Drop‐off Sitework Improvement  Parking and Drop‐off planning will commence this summer.  Conceptual design work on the Gunn HS landscape  master plan includes plans for the drop‐off area in front of the campus and on the Miranda Street entrance.  Gunn High School – New Gymnasium  DLM submitted 50% construction documents (CD’s) on May 14, 2010 and expects to have 95% CD’s complete in  June with final estimates, constructability and document coordination  prior to DSA submittal in July.    Gunn High School – Air Conditioning of Existing Buildings  The FSC and staff requested the installation of air conditioning for buildings L, M, S, A and portions of IA building  due to poor ventilation and the limited ability to improve the cooling of these buildings by passive means. DLM  commenced design on the air conditioning project in May, and DLM’s engineer and maintenance staff met on site  to inspect building conditions and to verify the electrical capacity.  DLM plans to submit plans to DSA by  September, 2010.  Palo Alto High School – Stadium Field Renovation  DLM presented the stadium renovation project to the FSC on May 26, 2010 and requested conceptual plan  approval. The FSC recommended the conceptual plan be presented to the BOE on June 1, 2010 for discussion.  Palo Alto High School – Multi‐use Field  Valley Crest Landscape begins work on the field portion of the project on June 1, 2010, after the baseball and  softball seasons conclude. The Churchill parking lot will remain open until after graduation and will be complete for  the fall semester.  The fields and dugout work, including a turf establishment and growing period, is scheduled for  completion by January 31, 2011.  Palo Alto High School – Classroom Building and Media Arts Building  DLM submitted 50% construction documents (CD’s) on May 14, 2010 and expects to have 95% CD’s complete in  June with final estimates, constructability and document coordination prior to DSA submittal in July.  Rodan  Builders, Inc. will begin relocating 16 portables to accommodate the new buildings upon the conclusion of the  school year on June 14, 2010.  The portable relocation will be finished for the beginning of the fall semester.   Palo Alto High School – Theater and Associated Site Improvements  DLM presented 3D modeling concepts on two recommended theater schemes to the FSC on May 26, 2010.  The  FSC recommended that the conceptual plan scheme B be presented to the BOE on June 1, 2010 for discussion.    Jordan Middle School  The BOE approved the schematic design on April 27, 2010 and authorized staff to proceed with design  development.    Page | 4   J.L. Stanford Middle School  AEDIS met with the bond advisory committee on May 17, 2010 to review the schematic design for the new  building, classroom improvements and landscape design.  AEDIS hosted an informational booth during JLS’ Open  House on May 19, 2010 to receive additional feedback and input on planned projects.  Schematic design approval  is scheduled for the June 1, 2010 board meeting.  Terman Middle School  AEDIS presented schematic design for the administration/library expansion, new drama classroom,  cafetorium/kitchen improvements and other school‐wide improvements to the BOE on May 11, 2010 and received  approval on May 25, 2010.    Fairmeadow Elementary School – New Classroom Building and Modernization  Gelfand Partners continued to meet with the various user groups before presenting initial schematic design  drawings for review with the site committee.  The Fairmeadow site committee will review the latest schematic  design drawings in June before summer break.    Ohlone Elementary School – New Classroom Building and Modernization  DSA approved the Ohlone Classroom Building and Modernization project on May 18, 2010.  The project will be bid  with 11 pre‐qualified contractors and bids will be received in early July.  The project is expected to be awarded at a  BOE special meeting scheduled for July 19, 2010.  Construction will commence in August 2010 with anticipated  completion in late 2011.  Coulter Construction will begin to relocate existing portables on the site to accommodate  the new building on June 14, 2010.    Hoover Elementary School – Pre‐Design  The BOE authorized staff to issue Gelfand an addendum for pre‐design services on May 11, 2010.  Gelfand will kick‐ off pre‐design in June with the site steering committee.    Duveneck Elementary School – Pre‐Design  Following the BOE approval for Gelfand to begin pre‐design on May 11, 2010, Gelfand commenced pre‐design with  the site steering committee on May 24, 2010.  The steering committee will meet again in June before summer  break.  Elementary Classroom Improvements  Gelfand Partners will commence design work after the BOE approves their contract in June.  The classroom  improvements project established budgets for each elementary school campus to receive new lighting, new  windows and shades, ventilation improvements and ceiling tiles.  Also part of the classroom improvements project  is the implementation of a technology wall.  District staff has begun conducting site walks with each school  Principal to determine placement of the interactive white board in the classroom and expect to wrap‐up in June.  INACTIVE CAPITAL PROJECTS   Gunn High School – Industrial Arts Addition & Renovation  Of the $5,576,500 project budget, 84.6% or $4,720,037 was expended.  Approved change orders were $208,756,  which is approximately 59.8% of the $349,000 construction contingency.  Gunn High School – Aquatic Center   Of the $5,013,750 project budget, 96.6%, or $4,844,070 was expended.  Approved change orders were $194,739,  which is approximately 49.9% of the $389,887 construction contingency.    Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman  AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for  discussion and received approval on September 8 by the Board of Education to move into schematic design.       Page | 5   Middle Schools Interim Housing – Jordan and J.L. Stanford  Contracts were awarded to Coulter Construction for Jordan Middle School and Mark Electric for Stanford Middle  School following Board of Education approval on May 26, 2009.  Both contractors started work on June 15, 2009  and were completed on August 3, 2009 at Jordan and August 12, 2009 at Stanford.  Of the $1,047,186 project  budget, 25%, or $236,696 has been expended. Pending Change Orders are currently estimated to be a deduct of  ($10,331), which is approximately 0% of the $30,698 construction contingency.  Garland Elementary School Renovation  The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.   Therefore, the district has placed the project on hold.    Elementary School Teaching Walls – Phase 1 Schools  The district placed this project on hold after review of the implementation of other classroom improvements, as  recommended by the elementary school principals.  This project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).     Board Actions in May  May 11, 2010  Consent 6 – Adoption of the Mitigated Negative Declaration for 780 Arastradero Road, Palo Alto, CA (Gunn High  School)    Consent 8 – Authorization to Bid the Ohlone Elementary School Modernization and New Construction Project    Consent 9 – Authorization to Enter into Addendum No. 8 with Gelfand Partners for Pre‐Design Services at  Duveneck and Hoover Elementary Schools    Consent 10 – Authorization to Enter into Master Agreements for Inspector of Record Services with Bruce Mansell  Consulting and Inspection, DSA School Inspectors LLC, and King Construction Inspections    May 25, 2010  Consent 6 – Approval of Schematic Design for Terman Middle School  A B C C / A B - C C / B A - B Gunn High School - High School Master Plan 145,000 129,431 93,084 64.2% 36,347 71.9% 15,569 Gunn High School 1 - Aquatic Center 5,013,750 4,935,692 4,854,830 96.8% 80,862 98.4% 78,058 Gunn High School 2 - I.A 5,511,500 5,156,220 4,907,275 89.0% 248,945 95.2% 355,280 Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.0% 0 Gunn High School 4 - New classroom A & B 24,120,000 3,114,323 637,958 2.6% 2,476,365 20.5% 21,005,677 Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 3,019 0.1% 214,751 1.4% 3,722,230 Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 932,150 230,733 1.7% 701,417 24.8% 12,897,850 Gunn High School 7- A/C 2,600,000 0 0 0.0% 0 0.0% 2,600,000 Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.0% 20,945,045 Palo Alto High Schools - High School Master Plan 145,000 130,597 90,699 62.6% 39,898 69.4% 14,403 Palo Alto High School 1 - Bleacher 1,358,437 140,810 115,810 8.5% 25,000 82.2% 1,217,627 Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,989,259 261,068 8.7% 2,728,191 8.7% 12,804 Palo Alto high School 3 - New classroom & Media Art Building 34,220,000 3,342,844 621,199 1.8% 2,721,645 18.6% 30,877,156 Palo Alto High School 4 - New Theater 17,720,000 1,026,210 7,330 0.0% 1,018,880 0.7% 16,693,790 Palo Alto High School - Reserved 42,348,045 0 0 0.0% 0 0.0% 42,348,045 Jordan Middle School - Middle School Pre-Design 33,665 19,718 17,413 51.7% 2,305 88.3% 13,947 Jordan Middle Schools 1- Interim Classrooms 600,342 186,600 160,421 26.7% 26,179 86.0% 413,742 Jordan Middle School 2 17,943,194 1,583,569 263,471 1.5% 1,320,098 16.6% 16,359,625 Jordan Middle School - Reserved 0 0 0 0.0% 0 0.0% 0 J.L.S Middle School - Middle School Pre-Design 33,669 19,627 17,995 53.4% 1,632 91.7% 14,042 J.L.S Middle School 1 - Interim Classrooms 446,844 352,233 317,171 71.0% 35,062 90.0% 94,611 J.L.S Middle School 2 17,184,699 1,432,112 206,088 1.2% 1,226,024 14.4% 15,752,587 J.L.S Middle School - Reserved 0 0 0 0.0% 0 0.0% 0 Terman Middle School - Middle School Pre- Design 33,666 19,627 18,010 53.5% 1,617 91.8% 14,039 Terman Middle School 1 12,850,071 1,187,625 157,505 1.2% 1,030,120 13.3% 11,662,446 Terman Middle School - Reserved 0 0 0 0.0% 0 0.0% 0 PAUSD Elementary Schools - Elementary Growth Plan 145,000 62,700 55,560 38.3% 7,140 88.6% 82,300 Addison Elementary School 1-Phase I 5,199,727 0 0 0.0% 0 0.0% 5,199,727 Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.0% 701,925 Duveneck Elementary School 1-Phase I 7,019,083 0 0 0.0% 0 0.0% 7,019,083 Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.6% 21,897,265 El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.0% 641,760 Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.0% 6,202,343 Fairmeadow Elementary School 1- Phase I 9,327,500 27,500 25,000 0.3% 2,500 90.9% 9,300,000 Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.0% 4,793,814 Hoover Elementary School 1-Phase I 8,575,389 0 0 0.0% 0 0.0% 8,575,389 Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.0% 802,200 Ohlone Elementary School 1- Phase I 11,667,965 1,451,692 903,729 7.7% 547,963 62.3% 10,216,273 Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.0% 3,482,885 Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.0% 641,760 Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 139,822 113,352 1.3% 26,470 81.1% 8,747,700 Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.0% 8,410,862 PAUSD - Program Admin. ** 3,353,108 2,651,404 2,057,494 61.4% 593,910 77.6% 701,704 PAUSD - Technology 5,995,689 2,426,702 2,295,231 38.3% 131,471 94.6% 3,568,987 PAUSD - Technology -Reserved 7,911,676 0 0 0.0% 0 0.0% 7,911,676 PAUSD - Reserved 6,335,945 0 0 0.0% 0 0.0% 6,335,945 Total 346,305,464 33,963,293 18,717,335 15,245,958 312,342,171 * Old Teaching Wall Project Prepared by: Business Services Department based on QSS accounting System BudgetSchool Name - Project Name Percent of Budget Expended Palo Alto Unified School District Strong Schools Bond 5/31/2010 Percent of Expended Contract BalanceExpenditures Budget BalanceCommitted Activity IDPhaseActivity NameOriginalDurationStartFinishDuration %CompleteGunn- IndusGunn- Industrial AGunn- Industrial Arts Renovation45301-Oct-08 A25-Jun-1095.81%Gunn - New Gunn - New ClassrGunn - New Classroom Building109520-Apr-09 A01-Jul-1326.48%Gunn - ParkiGunn - Parking andGunn - Parking and Drop Off103801-Sep-09 A22-Aug-1318.79%Gunn New GGunn New GymnasGunn New Gymnasium94021-Apr-09 A27-Nov-1230.74%Gunn Air CoGunn Air ConditionGunn Air Conditioning Project48201-Jan-10 A21-Jul-1138.17%Paly - StadiuPaly - Stadium FielPaly - Stadium Field Renovation Project67717-Aug-09 A02-Apr-1229.1%Paly - Multi UPaly - Multi Use FiePaly - Multi Use Field Improvements58703-Nov-08 A01-Feb-1169.85%Paly - New CPaly - New ClassroPaly - New Classroom Building & Media Arts113820-Apr-09 A29-Aug-1325.48%Paly - New TPaly - New TheaterPaly - New Theater and Sitework157609-Sep-09 A14-Sep-1512.37%Jordan New Jordan New ClassrJordan New Classroom Wing & Modernizat...117803-Nov-08 A08-May-1334.8%Stanford NewStanford New ClasStanford New Classroom Wing115903-Nov-08 A18-Apr-1334.94%Terman AdmTerman Admin WinTerman Admin Wing Addition & Modernizat...121303-Nov-08 A03-Jul-1333.47%Garland SchGarland School MoGarland School Modernization54403-Nov-08 A31-May-10100%FairmeadowFairmeadow ElemeFairmeadow Elementary School119414-Dec-09 A01-Aug-1330.57%Duveneck ElDuveneck ElementDuveneck Elementary School85213-May-10 A16-Aug-131.41%Hoover ElemHoover ElementaryHoover Elementary School85312-May-10 A16-Aug-131.88%Ohlone New Ohlone New ClassOhlone New Classroom Wing97703-Nov-08 A01-Aug-1241.97%Teaching WaTeaching Walls CaTeaching Walls Casework17206-Apr-09 A28-Sep-09A100%SONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASO2009201020112012201320142015PALO ALTO UNIFIED SCHOOL DISTRICTSTRONG SCHOOLS BOND PROGRAMMASTER SCHEDULE SUMMARY DesignPlanningBid and AwardConstructionDSACloseoutMilestonePage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc. Page | 6   High School Master Plan  Palo Alto HS and Gunn HS  A. PROJECT STATUS    DLM held facilities steering committee (FSC) and neighborhood  community meetings to present the landscape master plans for  each campus. The FSC recommended the landscape master plan  be presented to the board for approval on June 8, 2010. The  Mitigated Negative Declaration (MND) was approved by the BOE  on May 11, 2010 and was recorded per CEQA requirements to the  County of Santa Clara.                  B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14    D. PROJECT OVERVIEW:  • Final MND documents for Gunn high school adopted by the BOE on May 11, 2010.  Landscape master  plans for each campus to the BOE in June for information     Funding  State Funds $0  Strong Schools Bond Funds $290,000  Other Funding $0  Total $290,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $279,521  Construction & Equipment $0  Soft Costs Contingency $9,479  Total $290,000    Percent of Budget Expended 63.4%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Initial Master Plan Approval (2) September 8, 2009  BOE Approval September 22, 2009    Paly CEQA Approval (2) February 9, 2010  BOE Approval February 23, 2010    Gunn Master Plan Update (2) March 23, 2010  BOE Approval April 6, 2010    Gunn CEQA Approval (2) April 27, 2010   BOE Approval May 11, 2010     Master Plan Revision Approval (2) September 14, 2010*      * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 7   Gunn High School  New Classroom Buildings A & B  A. PROJECT STATUS     DLM submitted 50% construction documents (CD’s) on May 14,  2010 and expects to have 95% CD’s complete in June with final  estimates, constructability and document coordination prior to DSA  submittal in July. On May 17, 2010, Rodan Builders, Inc. started  preparing to relocation the 26 existing portables in order to  accommodate the new buildings. The portable relocations will be  finished for the beginning of the fall semester.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.     Funding  State Funds $0  Strong Schools Bond Funds $24,120,000  Other Funding $0  Total $24,120,000    Budget  Salaries and Benefits $0  Supplies $50,000  Contracts & Services $4,315,728  Construction & Equipment $19,590,000  Soft Costs Contingency $164,272  Total $24,120,000    Percent of Budget Expended 2.6%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 1, 2010*     Approval by DSA March 17, 2011 *    Authorize to Bid (2) January 11, 2011 *  BOE Approval January 25, 2011*    Bid Opening April 7, 2011 *    Award of Contract (1) April 26, 2011 *    Notice to Proceed May 5, 2011*    Substantial Completion November 23, 2012*    Planned Occupancy June 3, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 8   Gunn High School  Parking and Drop‐off Sitework Improvement  A. PROJECT STATUS    Parking and Drop‐off planning will commence this summer.   Conceptual design work on the Gunn HS landscape master  plan includes plans for the drop‐off area in front of the  campus and on the Miranda Street entrance.                   B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:  • This project will commence this summer.     Funding  State Funds $0  Strong Schools Bond Funds $3,940,000  Other Funding $0  Total $3,940,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $883,978  Construction & Equipment $2,934,840  Soft Costs Contingency $121,182  Total $3,940,000    Percent of Budget Expended 0.1%  Current Phase: Conceptual Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 28, 2010*  BOE Approval October 12, 2010*    Schematic Design (2) December 17, 2010*  BOE Approval December 27, 2010*    Submit to DSA November 2, 2011*     Approval by DSA June 5, 2012 *    Authorize to Bid (2) June 12, 2012*  BOE Approval June 26, 2012*    Bid Opening September 24, 2012 *    Award of Contract (1) October 29, 2012*    Notice to Proceed December 3, 2012*    Substantial Completion June 11, 2013*    Planned Occupancy August, 2013*    * Anticipated Dates – Subject to Change  ()Denotesnumber ofBoard of Education Readings Page | 9   Gunn High School  New Gymnasium  A. PROJECT STATUS    DLM submitted 50% construction documents (CD’s) on May 14,  2010 and expects to have 95% CD’s complete in June with final  estimates, constructability and document coordination  prior to  DSA submittal in July.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.      Funding  State Funds $0  Strong Schools Bond Funds $13,830,000  Other Funding $0  Total $13,830,000    Budget  Salaries and Benefits $0  Supplies $40,000  Contracts & Services $2,596,521  Construction & Equipment $11,109,450  Soft Costs Contingency $84,029  Total $13,830,000    Percent of Budget Expended 1.7%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 1, 2010*     Approval by DSA March 17, 2011*    Authorize to Bid (2) January 11, 2011*  BOE Approval January 25, 2011*    Bid Opening March 24, 2011*    Award of Contract (1) April 12, 2011*    Notice to Proceed April 21, 2011*    Substantial Completion September 21, 2012*    Planned Occupancy October 12, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 10   Gunn High School  Air Conditioning of Existing Buildings  A. PROJECT STATUS    The FSC and staff requested the installation of air  conditioning for buildings L, M, S, A and portions of IA  building due to poor ventilation and the limited ability to  improve the cooling of these buildings by passive means.  DLM commenced design on the air conditioning project in  May, and DLM’s engineer and maintenance staff met on  site to inspect building conditions and to verify the  electrical capacity.  DLM plans to submit plans to DSA by  September, 2010.            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.7    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.       Funding  State Funds $0  Strong Schools Bond Funds $2,600,000  Other Funding $0  Total $2,600,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $447,110  Construction & Equipment $2,128,080  Soft Costs Contingency $24,810  Total $2,600,000    Percent of Budget Expended 0.0%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 27, 2010  BOE Approval April 6, 2010    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA September 28, 2010*    Approval by DSA March 8, 2011*    Authorize to Bid (2) February 22, 2011*  BOE Approval March 8, 2011*    Bid Opening March 28, 2011*    Award of Contract (1) April 4, 2011*    Notice to Proceed April 13, 2011*    Substantial Completion June 14, 2011*    Planned Occupancy July 21, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 11   Palo Alto High School  Football Stadium Renovation  A. PROJECT STATUS    DLM presented the stadium renovation project to the  FSC on May 26, 2010 and requested conceptual plan  approval. The FSC recommended the conceptual plan  be presented to the BOE on June 1, 2010 for discussion.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.13    D. PROJECT OVERVIEW:  • Conceptual design will be discussed at the June 1, 2010 BOE meeting.     Funding  State Funds $0  Strong Schools Bond Funds $1,358,473  Other Funding $0  Total $1,358,437    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $127,622  Construction & Equipment $1,230,815  Soft Costs Contingency $0  Total $1,358,437    Percent of Budget Expended 8.5%  Current Phase: Programming   Schedule:  Architect Contract (2) January 26, 2010  BOE Approval February 9, 2010    Conceptual Design (2) June 1, 2010*  BOE Approval June 22, 2010*    Schematic Design (2) August 24, 2010*  BOE Approval September 14, 2010*    Submit to DSA December 15, 2010*     Approval by DSA April 1, 2011*    Authorize to Bid (2) March 28, 2011*  BOE Approval April 18, 2011*    Bid Opening May 16, 2011*    Award of Contract (1) May 26, 2011*    Notice to Proceed June 2, 2011*    Substantial Completion January 9, 2012*    Planned Occupancy January 31, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 12   Palo Alto High School  Multi‐Use Field  A. PROJECT STATUS     Valley Crest Landscape begins work on the field portion of the  project on June 1, 2010, after the baseball and softball seasons  conclude. The Churchill parking lot will remain open until after  graduation and will be complete for the fall semester.  The fields  and dugout work, including a turf establishment and growing  period, is scheduled for completion by January 31, 2011.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.14    D. PROJECT OVERVIEW:  • Construction will begin on June 1, 2010.     Funding  State Funds $0  Strong Schools Bond Funds $3,002,063  Other Funding $1,075,991  Total $4,078,054    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $673,020  Construction & Equipment $3,312,683  Soft Costs Contingency $92,351  Total $4,078,054    Percent of Budget Expended 8.7%  Current Phase: Bid & Award   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) December 9, 2009  BOE Approval January 13, 2009    Schematic Design (2) February 24, 2009  BOE Approval March 17, 2009    Submit to DSA March 19, 2009     Approval by DSA September 30, 2009    Authorize to Bid (2) January 26, 2010  BOE Approval February 9, 2010    Bid Opening March 16, 2010    Award of Contract (1) April 6, 2010    Notice to Proceed May 3, 2010    Substantial Completion November 30, 2010*    Planned Occupancy February 1, 2010*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 13   Palo Alto High School  Classroom Building and Media Arts  A. PROJECT STATUS     DLM submitted 50% construction documents (CD’s) on May 14, 2010  and expects to have 95% CD’s complete in June with final estimates,  constructability and document coordination prior to DSA submittal in  July.  Rodan Builders, Inc. will begin relocating 16 portables to  accommodate the new buildings upon the conclusion of the school  year on June 14, 2010.  The portable relocation will be finished for  the beginning of the fall semester.                 B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget. Funding  State Funds $0  Strong Schools Bond Funds $34,220,000  Other Funding $0  Total $34,220,000    Budget  Salaries and Benefits $0  Supplies $50,000  Contracts & Services $6,067,996  Construction & Equipment $27,876,384  Soft Costs Contingency $225,620  Total $34,220,000    Percent of Budget Expended 1.8%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA August 1, 2010*     Approval by DSA March 17, 2011*    Authorize to Bid (2) January 11, 2011*  BOE Approval January 25, 2011*    Bid Opening April 7, 2011*    Award of Contract (1) April 26, 2011*    Notice to Proceed May 5, 2011*    Substantial Completion March 25, 2013*    Planned Occupancy August 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 14   Palo Alto High School  Theater and Associated Site Improvements  A. PROJECT STATUS    DLM presented 3D modeling concepts on two recommended  theater schemes to the FSC on May 26, 2010.  The FSC  recommended that the conceptual plan scheme B be presented  to the BOE on June 1, 2010 for discussion.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.11    D. PROJECT OVERVIEW:  • Conceptual design will be discussed at the June 1, 2010 BOE meeting. Funding  State Funds $0  Strong Schools Bond Funds $17,720,000  Other Funding $0  Total $17,720,000    Budget  Salaries and Benefits $0  Supplies $50,000  Contracts & Services $3,276,077  Construction & Equipment $14,284,700  Soft Costs Contingency $109,223  Total $109,223    Percent of Budget Expended 0.0%  Current Phase: Planning   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 1, 2010*  BOE Approval June 22, 2010*    Schematic Design (2) December 7, 2010*  BOE Approval December 14, 2010*    Submit to DSA August, 2011*     Approval by DSA June, 2012*    Authorize to Bid (2) August, 2012*  BOE Approval August, 2010*    Bid Opening October, 2012*    Award of Contract (1) November, 2012*    Notice to Proceed February, 2013*    Substantial Completion March, 2015*    Planned Occupancy August, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 15   Jordan Middle School  A. PROJECT STATUS     The BOE approved the schematic design on April 27, 2010 and  authorized staff to proceed with design development.                              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5    D. PROJECT OVERVIEW:  • Board approval for schematic design received on April 27, 2010. Funding  State Funds $0  Strong Schools Bond Funds $17,943,191  Other Funding $0  Total $17,943,191    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,432,480  Construction & Equipment $14,014,500  Soft Costs Contingency $496,214  Total $17,943,194    Percent of Budget Expended 1.5%  Current Phase: Design Development    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) March 23, 2010  BOE Approval April 27, 2010    Submit to DSA October 15, 2010*     Approval by DSA June 22, 2011*    Authorize to Bid (2) June 27, 2011*  BOE Approval July 8, 2011*    Bid Opening August 10, 2011*    Award of Contract (1) August 25, 2011*    Notice to Proceed September 21, 2011*    Substantial Completion March 21, 2013*    Planned Occupancy August, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 16   J.L. Stanford Middle School  A. PROJECT STATUS    AEDIS met with the bond advisory committee on May  17, 2010 to review the schematic design for the new  building, classroom improvements and landscape  design.  AEDIS hosted an informational booth during  JLS’ Open House on May 19, 2010 to receive  additional feedback and input on planned projects.   Schematic design approval is scheduled for the June 1,  2010 board meeting.                     B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:  • Schematic design approval is scheduled to be discussed at May 25, 2010 board meeting. Funding  State Funds $0  Strong Schools Bond Funds $17,184,697  Other Funding $0  Total $17,184,697    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,281,600  Construction & Equipment $13,406,000  Soft Costs Contingency $497,099  Total $17,184,699    Percent of Budget Expended 1.2%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) June 1, 2010*  BOE Approval June 22, 2010*    Submit to DSA November 25, 2010*     Approval by DSA July 12, 2011*    Authorize to Bid (2) July 6, 2011*  BOE Approval July 19, 2011*    Bid Opening September 7, 2011*    Award of Contract (1) September 26, 2011*    Notice to Proceed October 19, 2011*    Substantial Completion February 7, 2013*    Planned Occupancy March 28, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 17   Terman Middle School  A. PROJECT STATUS     AEDIS presented schematic design for the  administration/library expansion, new drama classroom,  cafetorium/kitchen improvements and other school‐wide  improvements to the BOE on May 11, 2010 and received  approval on May 25, 2010.                        B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12    D. PROJECT OVERVIEW:  • Board approval for schematic design received on May 25, 2010. Funding  State Funds $0  Strong Schools Bond Funds $12,850,071  Other Funding $0  Total $12,850,071    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,411,150  Construction & Equipment $10,096,569  Soft Costs Contingency $342,352  Total $12,850,071    Percent of Budget Expended 1.2%  Current Phase: Design Development    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) May 11, 2010  BOE Approval May 25, 2010    Submit to DSA November 29, 2010*     Approval by DSA July 26, 2011*    Authorize to Bid (2) July 27, 2011*  BOE Approval August 10, 2011*    Bid Opening September 19, 2011*    Award of Contract (1) October 4, 2011*    Notice to Proceed October 5, 2011*    Substantial Completion March 26, 2013*    Planned Occupancy July 3, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 18   Fairmeadow Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    Gelfand Partners continued to meet with the various user  groups before presenting initial schematic design  drawings for review with the site committee.  The  Fairmeadow site committee will review the latest  schematic design drawings in June before summer break.               B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Programming in progress. Funding  State Funds $0  Strong Schools Bond Funds $9,327,500  Other Funding $0  Total $9,327,500    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,389,619  Construction & Equipment $7,835,500  Soft Costs Contingency $102,381  Total $9,327,500    Percent of Budget Expended 0.3%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) October 13, 2009  BOE Approval October 27, 2009    Conceptual Design (2) March 23, 2010  BOE Approval April 6, 2010    Schematic Design (2) September 14, 2010*  BOE Approval September 28, 2010*    Submit to DSA March 4, 2011*     Approval by DSA October 28, 2011*    Authorize to Bid (2) December 9, 2011*  BOE Approval December 16, 2011*    Bid Opening January 31, 2012*    Award of Contract (1) October 9, 2012*    Notice to Proceed October 19, 2012*    Substantial Completion April 2, 2013*    Planned Occupancy August 13, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 19   Ohlone Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    DSA approved the Ohlone Classroom Building and Modernization  project on May 18, 2010.  The project will be bid with 11 pre‐ qualified contractors and bids will be received in early July.  The  project is expected to be awarded at a BOE special meeting  scheduled for July 19, 2010.  Construction will commence in  August 2010 with anticipated completion in late 2011.  Coulter  Construction will begin to relocate existing portables on the site to  accommodate the new building on June 14, 2010.                   B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • DSA approval was received on May 18, 2010.    Funding  State Funds $0  Strong Schools Bond Funds $11,667,965  Other Funding $0  Total $11,667,965    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,221,174  Construction & Equipment $9,181,991  Soft Costs Contingency $264,800  Total $11,667,965    Percent of Budget Expended 7.7%  Current Phase: DSA Review   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) March 3, 2009  BOE Approval March 17, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA November 24, 2009    Authorize to Bid (2) April 27, 2010  BOE Approval May 11, 2010    Approval by DSA May 18, 2010    Bid Opening July 13, 2010*    Award of Contract (1) July 19, 2010*    Notice to Proceed August 2, 2010*    Substantial Completion October 2, 2011*    Planned Occupancy January, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 20   Hoover Elementary School  Pre‐Design  A. PROJECT STATUS    The BOE authorized staff to issue Gelfand an addendum  for pre‐design services on May 11, 2010.  Gelfand will  kick‐off pre‐design in June with the site steering  committee.                  B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Gelfand will commence pre‐design with the steering committee in June. Funding  State Funds $0  Strong Schools Bond Funds $8,575,389  Other Funding $0  Total $8,575,389    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,278,477  Construction & Equipment $7,196,912  Soft Costs Contingency $100,000  Total $8,575,389    Percent of Budget Expended 0.0%  Current Phase: Planning   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) September 28, 2010*  BOE Approval October 13, 2010*    Schematic Design (2) December 9, 2010*  BOE Approval December 14, 2010*    Submit to DSA June 2, 2011*     Approval by DSA January 26, 2012*    Authorize to Bid (2) March 8, 2012*  BOE Approval March 24, 2012*    Bid Opening April 30, 2012*    Award of Contract (1) May 15, 2012*    Notice to Proceed May 20, 2012*    Substantial Completion July 1, 2013*    Planned Occupancy August 16, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 21   Duveneck Elementary School  Pre‐Design  A. PROJECT STATUS    Following the BOE approval for Gelfand to begin pre‐design  on May 11, 2010, Gelfand commenced pre‐design with the  site steering committee on May 24, 2010.  The steering  committee will meet again in June before summer break.                   B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Gelfand commenced pre‐design with steering committee on May 24, 2010. Funding  State Funds $0  Strong Schools Bond Funds $7,019,083  Other Funding $0  Total $7,019,083    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,068,019  Construction & Equipment $5,858,683  Soft Costs Contingency $92,381  Total $7,019,083    Percent of Budget Expended 0.0%  Current Phase: Planning   Schedule:  Architect Contract (2) April 27, 2010  BOE Approval May 11, 2010    Conceptual Design (2) September 28, 2010*  BOE Approval October 12, 2010*    Schematic Design (2) December 9, 2010*  BOE Approval December 14, 2010*    Submit to DSA June 2, 2011*     Approval by DSA January 26, 2012*    Authorize to Bid (2) March 8, 2012*  BOE Approval March 24, 2012*    Bid Opening April 30, 2012*    Award of Contract (1) May 15, 2012*    Notice to Proceed May 20, 2012*    Substantial Completion July 1, 2013*    Planned Occupancy August 16, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 22   Elementary Classroom Improvements  A. PROJECT STATUS    Gelfand Partners will commence design work after the BOE approves their contract in June.  The classroom  improvements project established budgets for each elementary school campus to receive new lighting, new  windows and shades, ventilation improvements and ceiling tiles.  Also part of the classroom improvements  project is the implementation of a technology wall.  District staff has begun conducting site walks with each  school Principal to determine placement of the interactive white board in the classroom and expect to wrap‐ up in June.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • Planning will commence once Gelfand’s contract is approved in June.  Funding  State Funds $0  Strong Schools Bond Funds $8,887,522  Other Funding $0  Total $8,887,522    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,193,721  Construction & Equipment $7,488,706  Soft Costs Contingency $205,095  Total $8,887,522    Percent of Budget Expended 1.3%    Current Phase: Planning   Schedule:  Architect Contract (2) June 8, 2010*  BOE Approval June 22, 2010*    Conceptual Design (2) TBD  BOE Approval TBD    Schematic Design (2) TBD  BOE Approval TBD    Submit to DSA TBD     Approval by DSA TBD    Authorize to Bid (2) TBD   BOE Approval TBD    Bid Opening TBD    Award of Contract (1) TBD    Notice to Proceed TBD    Substantial Completion TBD    Planned Occupancy TBD    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 23   Gunn High School  Industrial Arts Addition and Renovation  A. PROJECT STATUS    Of the $5,576,500 project budget, 84.6% or $4,720,037 was  expended.  Approved change orders were $208,756, which is  approximately 59.8% of the $349,000 construction contingency.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11    D. PROJECT OVERVIEW:  • The building occupied as scheduled, and the project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,576,500  Other Funding $0  Total $5,576,500    Budget  Salaries and Benefits $0  Supplies $10,358  Contracts & Services $1,216,066  Construction & Equipment $4,300,350  Soft Costs Contingency $49,726  Total $5,576,500    Percent of Budget Expended 89.0%    Change Order Contingency  • Starting Contingency Balance $349,000  • Remaining Contingency Balance $140,244  • Percent of Changes 59.8%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –January 4, 2010    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA June 17, 2008     Approval by DSA December 24, 2008    Authorize to Bid (2) October 14, 2008  BOE Approval October 28, 2008    Bid Opening December 16, 2008    Award of Contract (1) December 24, 2008    Notice to Proceed January 6, 2009    Substantial Completion November 25, 2009    Planned Occupancy January 4, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 24   Gunn High School  Aquatic Center  A. PROJECT STATUS    Of the $5,013,750 project budget, 96.6%, or $4,844,070 was  expended.  Approved change orders were $194,739, which is  approximately 49.9% of the $389,887 construction contingency.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.12    D. PROJECT OVERVIEW:  • This project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,013,750  Other Funding $0  Total $5,013,750    Budget  Salaries and Benefits $0  Supplies $7,684  Contracts & Services $679,284  Construction & Equipment $4,323,742  Soft Costs Contingency $3,040  Total $5,013,750    Percent of Budget Expended 96.8%    Change Order Contingency  • Starting Contingency Balance $389,887  • Remaining Contingency Balance $195,148  • Percent of Changes 49.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –June 15, 2009    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA December 11, 2007     Approval by DSA April 24, 2008    Authorize to Bid (2) April 8, 2008  BOE Approval April 22, 2008    Bid Opening May 28, 2008    Award of Contract (1) June 4, 2008    Notice to Proceed December 6, 2008    Substantial Completion June 15, 2009    Planned Occupancy June 15, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 25   Middle School Pre‐Design  Jordan, J.L. Stanford and Terman  A. PROJECT STATUS     AEDIS presented recommended concept plans for each campus to the  Board of Education on June 23 for discussion and received approval  on September 8 by the Board of Education to move into schematic  design.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12    D. PROJECT OVERVIEW:  • This project has been completed on schedule and under budget. Board approval received on September  8, 2009. Funding  State Funds $0  Strong Schools Bond Funds $101,000  Other Funding $0  Total $101,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $85,000  Construction & Equipment $0  Soft Costs Contingency $15,000  Total $101,000    Percent of Budget Expended 52.9%    Current Phase: Complete   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 26   Middle Schools Interim Classrooms  Jordan and J.L. Stanford  A. PROJECT STATUS     Contracts were awarded to Coulter Construction for Jordan Middle  School and Mark Electric for Stanford Middle School following  Board of Education approval on May 26, 2009.  Both contractors  started work on June 15, 2009 and were completed on August 3,  2009 at Jordan and August 12, 2009 at Stanford.  Of the $1,047,186  project budget, 25%, or $236,696 has been expended. Pending  Change Orders are currently estimated to be a deduct of ($10,331),  which is approximately 0% of the $30,698 construction  contingency.            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:  • This project was completed under budget and on schedule. Funding  State Funds $0  Strong Schools Bond Funds $1,047,186  Other Funding $0  Total $1,047,186    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $308,648  Construction & Equipment $707,840  Soft Costs Contingency $30,698  Total $1,047,186    Percent of Budget Expended 48.9%    Change Order Contingency  • Starting Contingency Balance $30,698  • Remaining Contingency Balance $30,698  • Percent of Changes 0%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –August 25, 2009    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA April 14, 2009     Approval by DSA April 22, 2009    Authorize to Bid (2) March 31, 2009  BOE Approval April 14, 2009    Bid Opening May 14, 2009    Award of Contract (1) May 26, 2009    Notice to Proceed June 1, 2009    Substantial Completion August 12, 2009    Planned Occupancy August 25, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 27   Garland Elementary School  Campus Modernization  A. PROJECT STATUS    The Board of Education voted on August 25, 2009 to approve the  amendment to Garland lease to Stratford School.  Therefore, the  district has placed the project on hold.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10    D. PROJECT OVERVIEW:  • This project has been placed on hold. Funding  State Funds $0  Strong Schools Bond Funds $22,178,544  Other Funding $0  Total $22,178,544    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,830,789  Construction & Equipment $17,485,000  Soft Costs Contingency $862,755  Total $22,178,544    Percent of Budget Expended 1.3%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) February 10, 2009  BOE Approval February 24, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 28   Elementary School Teaching Walls  Phase 1 Schools  A. PROJECT STATUS    The district placed this project on hold after review of the  implementation of other classroom improvements, as  recommended by the elementary school principals.  This  project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.9    D. PROJECT OVERVIEW:  • This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary  above).  Funding  State Funds $0  Strong Schools Bond Funds $7,044,987  Other Funding $0  Total $7,044,987    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,341,394  Construction & Equipment $5,498,498  Soft Costs Contingency $205,095  Total $7,044,987    Percent of Budget Expended 1.6%  Current Phase: On Hold   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  OHS WEST:260388860.1 A-1 EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. Numbers Added A-2 OHS WEST:260388860.1 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. A-3 OHS WEST:260388860.1 3. GUNN HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Demolish old library building. 3. Replace temporary classrooms with permanent classrooms. 4. Construct additional restrooms. 5. Construct second gymnasium. 6. Construct new soccer field. 7. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 9. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 10. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 11. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 12. Replace swimming pool with new 35-meter pool, pool equipment and support structures, pool decking, bleachers, storage, restrooms, showers, associated equipment. 13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace athletic equipment. 14. Modernize football stadium, including new bathrooms and concession stands. A-4 OHS WEST:260388860.1 4. PALO ALTO HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Construct additional restrooms. 4. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 6. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 7. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 8. Library modernization and building interior improvements, including infrastructure and major building system upgrades. 9. Renovation or replacement of the Tower Building to accommodate administration, classroom and program support space. 10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility improvements; construction of new restrooms; install new roofing; replace doors and windows; replace gymnasium floors and athletic equipment, bleachers and renovation of interior. Renovation or replacement of weight training facility. 11. Construct new theater building. 12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing and storage. 13. Modernize football stadium, including replace bleachers; new bathrooms and concession stands. 14. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. A-5 OHS WEST:260388860.1 5. OTHER DISTRICT-WIDE PROJECTS Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and equipment for all classrooms, athletic facilities and other facilities, as needed. 1. Replace existing or acquire new computers, technology and related equipment on an ongoing basis. 2. Establish a planned maintenance fund to address maintenance work expected to be needed to all District facilities on an ongoing basis (other than as may be necessary for current maintenance, operation or repairs), in order to implement the District’s comprehensive facilities maintenance plan. 3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease- purchase arrangements, or execute purchase option under a lease for any of these authorized facilities. 4. If and as opportunities become available, and to the extent the Board of Education determines that bond funds are available for the purpose, acquisition of land and other interests in real property for future school buildings and other District facilities, and construction of such facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise listed. 5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field equipment and facilities (including nets, basketball standards, goals and goalposts, backstops), field lighting, etc. 6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS 1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead, etc., where necessary. 2. Address unforeseen conditions revealed by construction/modernization (including plumbing or gas line breaks, dry rot, seismic, structural, etc.). 3. Other improvements required to comply with existing building codes, including the Field Act, and access requirements of the Americans with Disabilities Act (ADA). 4. Site preparation/restoration in connection with new construction, renovation or remodeling, or installation or removal of relocatable classrooms, including ingress and egress, demolition of existing structures, removing, replacing, or installing irrigation and drainage, utility lines (such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any necessary easements, licenses, or rights of way to the property. 5. Rental or construction of storage facilities and other space on an interim basis, as needed to accommodate construction materials, equipment, and personnel, and interim classrooms (including relocatables) for students and school functions or other storage for classroom materials displaced during construction. A-6 OHS WEST:260388860.1 7. RENOVATION/MODERNIZATION (DEFINED) For purposes of the Bond Project List, renovation and modernization projects are intended to restore the building systems and infrastructure, weather protections, finishes, and technology, or reallocate and reorganize space, to a condition that will provide a sustainable, functional educational and administrative environment for future years, comparable to new construction. Renovation projects may include, but are not limited to nor necessarily encompass, all of the following, depending upon the age, condition and needs of each particular school facility: 1. upgrade electrical, communication, fire alarm, and similar building systems as well as main power service and distribution, which may include active and passive solar power and heating system acquisition, installation and construction 2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply, meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within buildings and sites and to connect with city supply and drainage systems 3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient heating and air cooling systems (HVAC), including installing energy management systems (EMS); 4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and fixtures, as necessary; 5. Repair, modify and construct structural elements of the existing structure as necessary; 6. Replace or repair aging roofs with similar materials or District standard materials; 7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes, doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces (including white boards, marker boards, tack boards, television mounts, scoreboards, fire extinguishers, kitchen cabinets/equipment, etc.); 8. Upgrade, modify and construct restroom facilities; 9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24 requirements; 10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood siding, paint, etc.); replace doors and windows 11. Modify, expand, separate, convert and construct school support areas; staff work and lunch areas; and educational areas to provide adequate, functional environments; 12. Modify, replace and construct functional components of altered or replaced building components (including rainwater leaders, fascias, mansards, etc.); ™ For any project involving renovation, modernization, remodeling or rehabilitation of a building or the major portion of a building, the District may proceed with new replacement construction instead (including any necessary demolition), if the Board of Education determines that replacement and new construction is more practical than rehabilitation and renovation, considering the building’s age, condition, expected remaining life, comparative cost, and other relevant factors.