MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
May 2010
Current Strong Schools Bond
Capital Improvement Projects
Prepared by
O’Connor Construction Management, Inc.
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Attachment 2 – Master Project Schedule
Capital Projects
High School Master Plan page 6
Gunn High School – New Classroom Buildings A & B page 7
Gunn High School – Parking and Drop‐off Sitework Improvement page 8
Gunn High School – New Gymnasium page 9
Gunn High School – Air Conditioning of Existing Buildings page 10
Palo Alto High School – Stadium Field Renovation page 11
Palo Alto High School – Multi‐use Field page 12
Palo Alto High School – Classroom Building and Media Arts page 13
Palo Alto High School – Theater and Associated Site Improvements page 14
Jordan Middle School page 15
J.L. Stanford Middle School page 16
Terman Middle School page 17
Fairmeadow Elementary School page 18
Ohlone Elementary School page 19
Hoover Elementary School page 20
Duveneck Elementary School page 21
Elementary Classroom Improvements page 22
Inactive Capital Projects
Gunn High School – Industrial Arts Renovation page 23
Gunn High School – Aquatic Center page 24
Middle School Pre‐Design page 25
Middle School Interim Classrooms page 26
Garland Elementary School page 27
Elementary School Teaching Walls – Phase 1 Schools page 28
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
CAPITAL PROJECTS
High School Master Plan
DLM held facilities steering committee (FSC) and neighborhood community meetings to present the landscape
master plans for each campus. The FSC recommended the landscape master plan be presented to the board for
approval on June 8, 2010. The Mitigated Negative Declaration (MND) was approved by the BOE on May 11, 2010
and was recorded per CEQA requirements to the County of Santa Clara.
Gunn High School – New Classroom Buildings A & B
DLM submitted 50% construction documents (CD’s) on May 14, 2010 and expects to have 95% CD’s complete in
June with final estimates, constructability and document coordination prior to DSA submittal in July. On May 17,
2010, Rodan Builders, Inc. started preparing to relocation the 26 existing portables in order to accommodate the
new buildings. The portable relocations will be finished for the beginning of the fall semester.
Gunn High School – Parking and Drop‐off Sitework Improvement
Parking and Drop‐off planning will commence this summer. Conceptual design work on the Gunn HS landscape
master plan includes plans for the drop‐off area in front of the campus and on the Miranda Street entrance.
Gunn High School – New Gymnasium
DLM submitted 50% construction documents (CD’s) on May 14, 2010 and expects to have 95% CD’s complete in
June with final estimates, constructability and document coordination prior to DSA submittal in July.
Gunn High School – Air Conditioning of Existing Buildings
The FSC and staff requested the installation of air conditioning for buildings L, M, S, A and portions of IA building
due to poor ventilation and the limited ability to improve the cooling of these buildings by passive means. DLM
commenced design on the air conditioning project in May, and DLM’s engineer and maintenance staff met on site
to inspect building conditions and to verify the electrical capacity. DLM plans to submit plans to DSA by
September, 2010.
Palo Alto High School – Stadium Field Renovation
DLM presented the stadium renovation project to the FSC on May 26, 2010 and requested conceptual plan
approval. The FSC recommended the conceptual plan be presented to the BOE on June 1, 2010 for discussion.
Palo Alto High School – Multi‐use Field
Valley Crest Landscape begins work on the field portion of the project on June 1, 2010, after the baseball and
softball seasons conclude. The Churchill parking lot will remain open until after graduation and will be complete for
the fall semester. The fields and dugout work, including a turf establishment and growing period, is scheduled for
completion by January 31, 2011.
Palo Alto High School – Classroom Building and Media Arts Building
DLM submitted 50% construction documents (CD’s) on May 14, 2010 and expects to have 95% CD’s complete in
June with final estimates, constructability and document coordination prior to DSA submittal in July. Rodan
Builders, Inc. will begin relocating 16 portables to accommodate the new buildings upon the conclusion of the
school year on June 14, 2010. The portable relocation will be finished for the beginning of the fall semester.
Palo Alto High School – Theater and Associated Site Improvements
DLM presented 3D modeling concepts on two recommended theater schemes to the FSC on May 26, 2010. The
FSC recommended that the conceptual plan scheme B be presented to the BOE on June 1, 2010 for discussion.
Jordan Middle School
The BOE approved the schematic design on April 27, 2010 and authorized staff to proceed with design
development.
Page | 4
J.L. Stanford Middle School
AEDIS met with the bond advisory committee on May 17, 2010 to review the schematic design for the new
building, classroom improvements and landscape design. AEDIS hosted an informational booth during JLS’ Open
House on May 19, 2010 to receive additional feedback and input on planned projects. Schematic design approval
is scheduled for the June 1, 2010 board meeting.
Terman Middle School
AEDIS presented schematic design for the administration/library expansion, new drama classroom,
cafetorium/kitchen improvements and other school‐wide improvements to the BOE on May 11, 2010 and received
approval on May 25, 2010.
Fairmeadow Elementary School – New Classroom Building and Modernization
Gelfand Partners continued to meet with the various user groups before presenting initial schematic design
drawings for review with the site committee. The Fairmeadow site committee will review the latest schematic
design drawings in June before summer break.
Ohlone Elementary School – New Classroom Building and Modernization
DSA approved the Ohlone Classroom Building and Modernization project on May 18, 2010. The project will be bid
with 11 pre‐qualified contractors and bids will be received in early July. The project is expected to be awarded at a
BOE special meeting scheduled for July 19, 2010. Construction will commence in August 2010 with anticipated
completion in late 2011. Coulter Construction will begin to relocate existing portables on the site to accommodate
the new building on June 14, 2010.
Hoover Elementary School – Pre‐Design
The BOE authorized staff to issue Gelfand an addendum for pre‐design services on May 11, 2010. Gelfand will kick‐
off pre‐design in June with the site steering committee.
Duveneck Elementary School – Pre‐Design
Following the BOE approval for Gelfand to begin pre‐design on May 11, 2010, Gelfand commenced pre‐design with
the site steering committee on May 24, 2010. The steering committee will meet again in June before summer
break.
Elementary Classroom Improvements
Gelfand Partners will commence design work after the BOE approves their contract in June. The classroom
improvements project established budgets for each elementary school campus to receive new lighting, new
windows and shades, ventilation improvements and ceiling tiles. Also part of the classroom improvements project
is the implementation of a technology wall. District staff has begun conducting site walks with each school
Principal to determine placement of the interactive white board in the classroom and expect to wrap‐up in June.
INACTIVE CAPITAL PROJECTS
Gunn High School – Industrial Arts Addition & Renovation
Of the $5,576,500 project budget, 84.6% or $4,720,037 was expended. Approved change orders were $208,756,
which is approximately 59.8% of the $349,000 construction contingency.
Gunn High School – Aquatic Center
Of the $5,013,750 project budget, 96.6%, or $4,844,070 was expended. Approved change orders were $194,739,
which is approximately 49.9% of the $389,887 construction contingency.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for
discussion and received approval on September 8 by the Board of Education to move into schematic design.
Page | 5
Middle Schools Interim Housing – Jordan and J.L. Stanford
Contracts were awarded to Coulter Construction for Jordan Middle School and Mark Electric for Stanford Middle
School following Board of Education approval on May 26, 2009. Both contractors started work on June 15, 2009
and were completed on August 3, 2009 at Jordan and August 12, 2009 at Stanford. Of the $1,047,186 project
budget, 25%, or $236,696 has been expended. Pending Change Orders are currently estimated to be a deduct of
($10,331), which is approximately 0% of the $30,698 construction contingency.
Garland Elementary School Renovation
The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.
Therefore, the district has placed the project on hold.
Elementary School Teaching Walls – Phase 1 Schools
The district placed this project on hold after review of the implementation of other classroom improvements, as
recommended by the elementary school principals. This project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
Board Actions in May
May 11, 2010
Consent 6 – Adoption of the Mitigated Negative Declaration for 780 Arastradero Road, Palo Alto, CA (Gunn High
School)
Consent 8 – Authorization to Bid the Ohlone Elementary School Modernization and New Construction Project
Consent 9 – Authorization to Enter into Addendum No. 8 with Gelfand Partners for Pre‐Design Services at
Duveneck and Hoover Elementary Schools
Consent 10 – Authorization to Enter into Master Agreements for Inspector of Record Services with Bruce Mansell
Consulting and Inspection, DSA School Inspectors LLC, and King Construction Inspections
May 25, 2010
Consent 6 – Approval of Schematic Design for Terman Middle School
A B C C / A B - C C / B A - B
Gunn High School - High School Master Plan 145,000 129,431 93,084 64.2% 36,347 71.9% 15,569
Gunn High School 1 - Aquatic Center 5,013,750 4,935,692 4,854,830 96.8% 80,862 98.4% 78,058
Gunn High School 2 - I.A 5,511,500 5,156,220 4,907,275 89.0% 248,945 95.2% 355,280
Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.0% 0
Gunn High School 4 - New classroom A & B 24,120,000 3,114,323 637,958 2.6% 2,476,365 20.5% 21,005,677
Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 3,019 0.1% 214,751 1.4% 3,722,230
Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 932,150 230,733 1.7% 701,417 24.8% 12,897,850
Gunn High School 7- A/C 2,600,000 0 0 0.0% 0 0.0% 2,600,000
Gunn High School - Reserved 20,945,045 0 0 0.0% 0 0.0% 20,945,045
Palo Alto High Schools - High School Master Plan 145,000 130,597 90,699 62.6% 39,898 69.4% 14,403
Palo Alto High School 1 - Bleacher 1,358,437 140,810 115,810 8.5% 25,000 82.2% 1,217,627
Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 2,989,259 261,068 8.7% 2,728,191 8.7% 12,804
Palo Alto high School 3 - New classroom & Media Art Building 34,220,000 3,342,844 621,199 1.8% 2,721,645 18.6% 30,877,156
Palo Alto High School 4 - New Theater 17,720,000 1,026,210 7,330 0.0% 1,018,880 0.7% 16,693,790
Palo Alto High School - Reserved 42,348,045 0 0 0.0% 0 0.0% 42,348,045
Jordan Middle School - Middle School Pre-Design 33,665 19,718 17,413 51.7% 2,305 88.3% 13,947
Jordan Middle Schools 1- Interim Classrooms 600,342 186,600 160,421 26.7% 26,179 86.0% 413,742
Jordan Middle School 2 17,943,194 1,583,569 263,471 1.5% 1,320,098 16.6% 16,359,625
Jordan Middle School - Reserved 0 0 0 0.0% 0 0.0% 0
J.L.S Middle School - Middle School Pre-Design 33,669 19,627 17,995 53.4% 1,632 91.7% 14,042
J.L.S Middle School 1 - Interim Classrooms 446,844 352,233 317,171 71.0% 35,062 90.0% 94,611
J.L.S Middle School 2 17,184,699 1,432,112 206,088 1.2% 1,226,024 14.4% 15,752,587
J.L.S Middle School - Reserved 0 0 0 0.0% 0 0.0% 0
Terman Middle School - Middle School Pre- Design 33,666 19,627 18,010 53.5% 1,617 91.8% 14,039
Terman Middle School 1 12,850,071 1,187,625 157,505 1.2% 1,030,120 13.3% 11,662,446
Terman Middle School - Reserved 0 0 0 0.0% 0 0.0% 0
PAUSD Elementary Schools - Elementary Growth Plan 145,000 62,700 55,560 38.3% 7,140 88.6% 82,300
Addison Elementary School 1-Phase I 5,199,727 0 0 0.0% 0 0.0% 5,199,727
Briones Elementary School 1-Phase I 701,925 0 0 0.0% 0 0.0% 701,925
Duveneck Elementary School 1-Phase I 7,019,083 0 0 0.0% 0 0.0% 7,019,083
Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.6% 21,897,265
El Carmelo Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.0% 641,760
Escondido Elementary School 1-Phase I 6,202,343 0 0 0.0% 0 0.0% 6,202,343
Fairmeadow Elementary School 1- Phase I 9,327,500 27,500 25,000 0.3% 2,500 90.9% 9,300,000
Hays Elementary School 1-Phase I 4,793,814 0 0 0.0% 0 0.0% 4,793,814
Hoover Elementary School 1-Phase I 8,575,389 0 0 0.0% 0 0.0% 8,575,389
Nixon Elementary School 1-Phase I 802,200 0 0 0.0% 0 0.0% 802,200
Ohlone Elementary School 1- Phase I 11,667,965 1,451,692 903,729 7.7% 547,963 62.3% 10,216,273
Palo Verde Elementary School 1-Phase I 3,482,885 0 0 0.0% 0 0.0% 3,482,885
Barron Park Elementary School 1-Phase I 641,760 0 0 0.0% 0 0.0% 641,760
Elementary Schools 1 - Elementary Classroom Improvements * 8,887,522 139,822 113,352 1.3% 26,470 81.1% 8,747,700
Elementary Schools - Reserved 8,410,862 0 0 0.0% 0 0.0% 8,410,862
PAUSD - Program Admin. ** 3,353,108 2,651,404 2,057,494 61.4% 593,910 77.6% 701,704
PAUSD - Technology 5,995,689 2,426,702 2,295,231 38.3% 131,471 94.6% 3,568,987
PAUSD - Technology -Reserved 7,911,676 0 0 0.0% 0 0.0% 7,911,676
PAUSD - Reserved 6,335,945 0 0 0.0% 0 0.0% 6,335,945
Total 346,305,464 33,963,293 18,717,335 15,245,958 312,342,171
* Old Teaching Wall Project
Prepared by: Business Services Department based on QSS accounting System
BudgetSchool Name - Project Name
Percent of
Budget
Expended
Palo Alto Unified School District
Strong Schools Bond
5/31/2010
Percent of
Expended
Contract
BalanceExpenditures Budget
BalanceCommitted
Activity IDPhaseActivity NameOriginalDurationStartFinishDuration %CompleteGunn- IndusGunn- Industrial AGunn- Industrial Arts Renovation45301-Oct-08 A25-Jun-1095.81%Gunn - New Gunn - New ClassrGunn - New Classroom Building109520-Apr-09 A01-Jul-1326.48%Gunn - ParkiGunn - Parking andGunn - Parking and Drop Off103801-Sep-09 A22-Aug-1318.79%Gunn New GGunn New GymnasGunn New Gymnasium94021-Apr-09 A27-Nov-1230.74%Gunn Air CoGunn Air ConditionGunn Air Conditioning Project48201-Jan-10 A21-Jul-1138.17%Paly - StadiuPaly - Stadium FielPaly - Stadium Field Renovation Project67717-Aug-09 A02-Apr-1229.1%Paly - Multi UPaly - Multi Use FiePaly - Multi Use Field Improvements58703-Nov-08 A01-Feb-1169.85%Paly - New CPaly - New ClassroPaly - New Classroom Building & Media Arts113820-Apr-09 A29-Aug-1325.48%Paly - New TPaly - New TheaterPaly - New Theater and Sitework157609-Sep-09 A14-Sep-1512.37%Jordan New Jordan New ClassrJordan New Classroom Wing & Modernizat...117803-Nov-08 A08-May-1334.8%Stanford NewStanford New ClasStanford New Classroom Wing115903-Nov-08 A18-Apr-1334.94%Terman AdmTerman Admin WinTerman Admin Wing Addition & Modernizat...121303-Nov-08 A03-Jul-1333.47%Garland SchGarland School MoGarland School Modernization54403-Nov-08 A31-May-10100%FairmeadowFairmeadow ElemeFairmeadow Elementary School119414-Dec-09 A01-Aug-1330.57%Duveneck ElDuveneck ElementDuveneck Elementary School85213-May-10 A16-Aug-131.41%Hoover ElemHoover ElementaryHoover Elementary School85312-May-10 A16-Aug-131.88%Ohlone New Ohlone New ClassOhlone New Classroom Wing97703-Nov-08 A01-Aug-1241.97%Teaching WaTeaching Walls CaTeaching Walls Casework17206-Apr-09 A28-Sep-09A100%SONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASO2009201020112012201320142015PALO ALTO UNIFIED SCHOOL DISTRICTSTRONG SCHOOLS BOND PROGRAMMASTER SCHEDULE SUMMARY DesignPlanningBid and AwardConstructionDSACloseoutMilestonePage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc.
Page | 6
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
DLM held facilities steering committee (FSC) and neighborhood
community meetings to present the landscape master plans for
each campus. The FSC recommended the landscape master plan
be presented to the board for approval on June 8, 2010. The
Mitigated Negative Declaration (MND) was approved by the BOE
on May 11, 2010 and was recorded per CEQA requirements to the
County of Santa Clara.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
• Final MND documents for Gunn high school adopted by the BOE on May 11, 2010. Landscape master
plans for each campus to the BOE in June for information
Funding
State Funds $0
Strong Schools Bond Funds $290,000
Other Funding $0
Total $290,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $279,521
Construction & Equipment $0
Soft Costs Contingency $9,479
Total $290,000
Percent of Budget Expended 63.4%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010
Master Plan Revision Approval (2) September 14, 2010*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 7
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
DLM submitted 50% construction documents (CD’s) on May 14,
2010 and expects to have 95% CD’s complete in June with final
estimates, constructability and document coordination prior to DSA
submittal in July. On May 17, 2010, Rodan Builders, Inc. started
preparing to relocation the 26 existing portables in order to
accommodate the new buildings. The portable relocations will be
finished for the beginning of the fall semester.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $24,120,000
Other Funding $0
Total $24,120,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $4,315,728
Construction & Equipment $19,590,000
Soft Costs Contingency $164,272
Total $24,120,000
Percent of Budget Expended 2.6%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 1, 2010*
Approval by DSA March 17, 2011 *
Authorize to Bid (2) January 11, 2011 *
BOE Approval January 25, 2011*
Bid Opening April 7, 2011 *
Award of Contract (1) April 26, 2011 *
Notice to Proceed May 5, 2011*
Substantial Completion November 23, 2012*
Planned Occupancy June 3, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
Parking and Drop‐off planning will commence this summer.
Conceptual design work on the Gunn HS landscape master
plan includes plans for the drop‐off area in front of the
campus and on the Miranda Street entrance.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
• This project will commence this summer.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $883,978
Construction & Equipment $2,934,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 28, 2010*
BOE Approval October 12, 2010*
Schematic Design (2) December 17, 2010*
BOE Approval December 27, 2010*
Submit to DSA November 2, 2011*
Approval by DSA June 5, 2012 *
Authorize to Bid (2) June 12, 2012*
BOE Approval June 26, 2012*
Bid Opening September 24, 2012 *
Award of Contract (1) October 29, 2012*
Notice to Proceed December 3, 2012*
Substantial Completion June 11, 2013*
Planned Occupancy August, 2013*
* Anticipated Dates – Subject to Change
()Denotesnumber ofBoard of Education Readings
Page | 9
Gunn High School
New Gymnasium
A. PROJECT STATUS
DLM submitted 50% construction documents (CD’s) on May 14,
2010 and expects to have 95% CD’s complete in June with final
estimates, constructability and document coordination prior to
DSA submittal in July.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,830,000
Other Funding $0
Total $13,830,000
Budget
Salaries and Benefits $0
Supplies $40,000
Contracts & Services $2,596,521
Construction & Equipment $11,109,450
Soft Costs Contingency $84,029
Total $13,830,000
Percent of Budget Expended 1.7%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 1, 2010*
Approval by DSA March 17, 2011*
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Bid Opening March 24, 2011*
Award of Contract (1) April 12, 2011*
Notice to Proceed April 21, 2011*
Substantial Completion September 21, 2012*
Planned Occupancy October 12, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Gunn High School
Air Conditioning of Existing Buildings
A. PROJECT STATUS
The FSC and staff requested the installation of air
conditioning for buildings L, M, S, A and portions of IA
building due to poor ventilation and the limited ability to
improve the cooling of these buildings by passive means.
DLM commenced design on the air conditioning project in
May, and DLM’s engineer and maintenance staff met on
site to inspect building conditions and to verify the
electrical capacity. DLM plans to submit plans to DSA by
September, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.7
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $2,600,000
Other Funding $0
Total $2,600,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $447,110
Construction & Equipment $2,128,080
Soft Costs Contingency $24,810
Total $2,600,000
Percent of Budget Expended 0.0%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 27, 2010
BOE Approval April 6, 2010
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA September 28, 2010*
Approval by DSA March 8, 2011*
Authorize to Bid (2) February 22, 2011*
BOE Approval March 8, 2011*
Bid Opening March 28, 2011*
Award of Contract (1) April 4, 2011*
Notice to Proceed April 13, 2011*
Substantial Completion June 14, 2011*
Planned Occupancy July 21, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Football Stadium Renovation
A. PROJECT STATUS
DLM presented the stadium renovation project to the
FSC on May 26, 2010 and requested conceptual plan
approval. The FSC recommended the conceptual plan
be presented to the BOE on June 1, 2010 for discussion.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
• Conceptual design will be discussed at the June 1, 2010 BOE meeting.
Funding
State Funds $0
Strong Schools Bond Funds $1,358,473
Other Funding $0
Total $1,358,437
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $127,622
Construction & Equipment $1,230,815
Soft Costs Contingency $0
Total $1,358,437
Percent of Budget Expended 8.5%
Current Phase: Programming
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010*
BOE Approval June 22, 2010*
Schematic Design (2) August 24, 2010*
BOE Approval September 14, 2010*
Submit to DSA December 15, 2010*
Approval by DSA April 1, 2011*
Authorize to Bid (2) March 28, 2011*
BOE Approval April 18, 2011*
Bid Opening May 16, 2011*
Award of Contract (1) May 26, 2011*
Notice to Proceed June 2, 2011*
Substantial Completion January 9, 2012*
Planned Occupancy January 31, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 12
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
Valley Crest Landscape begins work on the field portion of the
project on June 1, 2010, after the baseball and softball seasons
conclude. The Churchill parking lot will remain open until after
graduation and will be complete for the fall semester. The fields
and dugout work, including a turf establishment and growing
period, is scheduled for completion by January 31, 2011.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
• Construction will begin on June 1, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $3,002,063
Other Funding $1,075,991
Total $4,078,054
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $673,020
Construction & Equipment $3,312,683
Soft Costs Contingency $92,351
Total $4,078,054
Percent of Budget Expended 8.7%
Current Phase: Bid & Award
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) December 9, 2009
BOE Approval January 13, 2009
Schematic Design (2) February 24, 2009
BOE Approval March 17, 2009
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) January 26, 2010
BOE Approval February 9, 2010
Bid Opening March 16, 2010
Award of Contract (1) April 6, 2010
Notice to Proceed May 3, 2010
Substantial Completion November 30, 2010*
Planned Occupancy February 1, 2010*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
DLM submitted 50% construction documents (CD’s) on May 14, 2010
and expects to have 95% CD’s complete in June with final estimates,
constructability and document coordination prior to DSA submittal in
July. Rodan Builders, Inc. will begin relocating 16 portables to
accommodate the new buildings upon the conclusion of the school
year on June 14, 2010. The portable relocation will be finished for
the beginning of the fall semester.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $34,220,000
Other Funding $0
Total $34,220,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $6,067,996
Construction & Equipment $27,876,384
Soft Costs Contingency $225,620
Total $34,220,000
Percent of Budget Expended 1.8%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA August 1, 2010*
Approval by DSA March 17, 2011*
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Bid Opening April 7, 2011*
Award of Contract (1) April 26, 2011*
Notice to Proceed May 5, 2011*
Substantial Completion March 25, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Palo Alto High School
Theater and Associated Site Improvements
A. PROJECT STATUS
DLM presented 3D modeling concepts on two recommended
theater schemes to the FSC on May 26, 2010. The FSC
recommended that the conceptual plan scheme B be presented
to the BOE on June 1, 2010 for discussion.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
• Conceptual design will be discussed at the June 1, 2010 BOE meeting.
Funding
State Funds $0
Strong Schools Bond Funds $17,720,000
Other Funding $0
Total $17,720,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $3,276,077
Construction & Equipment $14,284,700
Soft Costs Contingency $109,223
Total $109,223
Percent of Budget Expended 0.0%
Current Phase: Planning
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010*
BOE Approval June 22, 2010*
Schematic Design (2) December 7, 2010*
BOE Approval December 14, 2010*
Submit to DSA August, 2011*
Approval by DSA June, 2012*
Authorize to Bid (2) August, 2012*
BOE Approval August, 2010*
Bid Opening October, 2012*
Award of Contract (1) November, 2012*
Notice to Proceed February, 2013*
Substantial Completion March, 2015*
Planned Occupancy August, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
Jordan Middle School
A. PROJECT STATUS
The BOE approved the schematic design on April 27, 2010 and
authorized staff to proceed with design development.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
• Board approval for schematic design received on April 27, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $17,943,191
Other Funding $0
Total $17,943,191
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,432,480
Construction & Equipment $14,014,500
Soft Costs Contingency $496,214
Total $17,943,194
Percent of Budget Expended 1.5%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA October 15, 2010*
Approval by DSA June 22, 2011*
Authorize to Bid (2) June 27, 2011*
BOE Approval July 8, 2011*
Bid Opening August 10, 2011*
Award of Contract (1) August 25, 2011*
Notice to Proceed September 21, 2011*
Substantial Completion March 21, 2013*
Planned Occupancy August, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
J.L. Stanford Middle School
A. PROJECT STATUS
AEDIS met with the bond advisory committee on May
17, 2010 to review the schematic design for the new
building, classroom improvements and landscape
design. AEDIS hosted an informational booth during
JLS’ Open House on May 19, 2010 to receive
additional feedback and input on planned projects.
Schematic design approval is scheduled for the June 1,
2010 board meeting.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
• Schematic design approval is scheduled to be discussed at May 25, 2010 board meeting.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,697
Other Funding $0
Total $17,184,697
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,281,600
Construction & Equipment $13,406,000
Soft Costs Contingency $497,099
Total $17,184,699
Percent of Budget Expended 1.2%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) June 1, 2010*
BOE Approval June 22, 2010*
Submit to DSA November 25, 2010*
Approval by DSA July 12, 2011*
Authorize to Bid (2) July 6, 2011*
BOE Approval July 19, 2011*
Bid Opening September 7, 2011*
Award of Contract (1) September 26, 2011*
Notice to Proceed October 19, 2011*
Substantial Completion February 7, 2013*
Planned Occupancy March 28, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Terman Middle School
A. PROJECT STATUS
AEDIS presented schematic design for the
administration/library expansion, new drama classroom,
cafetorium/kitchen improvements and other school‐wide
improvements to the BOE on May 11, 2010 and received
approval on May 25, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
• Board approval for schematic design received on May 25, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $12,850,071
Other Funding $0
Total $12,850,071
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,411,150
Construction & Equipment $10,096,569
Soft Costs Contingency $342,352
Total $12,850,071
Percent of Budget Expended 1.2%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010
BOE Approval May 25, 2010
Submit to DSA November 29, 2010*
Approval by DSA July 26, 2011*
Authorize to Bid (2) July 27, 2011*
BOE Approval August 10, 2011*
Bid Opening September 19, 2011*
Award of Contract (1) October 4, 2011*
Notice to Proceed October 5, 2011*
Substantial Completion March 26, 2013*
Planned Occupancy July 3, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
Gelfand Partners continued to meet with the various user
groups before presenting initial schematic design
drawings for review with the site committee. The
Fairmeadow site committee will review the latest
schematic design drawings in June before summer break.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Programming in progress.
Funding
State Funds $0
Strong Schools Bond Funds $9,327,500
Other Funding $0
Total $9,327,500
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,389,619
Construction & Equipment $7,835,500
Soft Costs Contingency $102,381
Total $9,327,500
Percent of Budget Expended 0.3%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) September 14, 2010*
BOE Approval September 28, 2010*
Submit to DSA March 4, 2011*
Approval by DSA October 28, 2011*
Authorize to Bid (2) December 9, 2011*
BOE Approval December 16, 2011*
Bid Opening January 31, 2012*
Award of Contract (1) October 9, 2012*
Notice to Proceed October 19, 2012*
Substantial Completion April 2, 2013*
Planned Occupancy August 13, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
DSA approved the Ohlone Classroom Building and Modernization
project on May 18, 2010. The project will be bid with 11 pre‐
qualified contractors and bids will be received in early July. The
project is expected to be awarded at a BOE special meeting
scheduled for July 19, 2010. Construction will commence in
August 2010 with anticipated completion in late 2011. Coulter
Construction will begin to relocate existing portables on the site to
accommodate the new building on June 14, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• DSA approval was received on May 18, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,221,174
Construction & Equipment $9,181,991
Soft Costs Contingency $264,800
Total $11,667,965
Percent of Budget Expended 7.7%
Current Phase: DSA Review
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Authorize to Bid (2) April 27, 2010
BOE Approval May 11, 2010
Approval by DSA May 18, 2010
Bid Opening July 13, 2010*
Award of Contract (1) July 19, 2010*
Notice to Proceed August 2, 2010*
Substantial Completion October 2, 2011*
Planned Occupancy January, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Hoover Elementary School
Pre‐Design
A. PROJECT STATUS
The BOE authorized staff to issue Gelfand an addendum
for pre‐design services on May 11, 2010. Gelfand will
kick‐off pre‐design in June with the site steering
committee.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand will commence pre‐design with the steering committee in June.
Funding
State Funds $0
Strong Schools Bond Funds $8,575,389
Other Funding $0
Total $8,575,389
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,278,477
Construction & Equipment $7,196,912
Soft Costs Contingency $100,000
Total $8,575,389
Percent of Budget Expended 0.0%
Current Phase: Planning
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) September 28, 2010*
BOE Approval October 13, 2010*
Schematic Design (2) December 9, 2010*
BOE Approval December 14, 2010*
Submit to DSA June 2, 2011*
Approval by DSA January 26, 2012*
Authorize to Bid (2) March 8, 2012*
BOE Approval March 24, 2012*
Bid Opening April 30, 2012*
Award of Contract (1) May 15, 2012*
Notice to Proceed May 20, 2012*
Substantial Completion July 1, 2013*
Planned Occupancy August 16, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Duveneck Elementary School
Pre‐Design
A. PROJECT STATUS
Following the BOE approval for Gelfand to begin pre‐design
on May 11, 2010, Gelfand commenced pre‐design with the
site steering committee on May 24, 2010. The steering
committee will meet again in June before summer break.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand commenced pre‐design with steering committee on May 24, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $7,019,083
Other Funding $0
Total $7,019,083
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,068,019
Construction & Equipment $5,858,683
Soft Costs Contingency $92,381
Total $7,019,083
Percent of Budget Expended 0.0%
Current Phase: Planning
Schedule:
Architect Contract (2) April 27, 2010
BOE Approval May 11, 2010
Conceptual Design (2) September 28, 2010*
BOE Approval October 12, 2010*
Schematic Design (2) December 9, 2010*
BOE Approval December 14, 2010*
Submit to DSA June 2, 2011*
Approval by DSA January 26, 2012*
Authorize to Bid (2) March 8, 2012*
BOE Approval March 24, 2012*
Bid Opening April 30, 2012*
Award of Contract (1) May 15, 2012*
Notice to Proceed May 20, 2012*
Substantial Completion July 1, 2013*
Planned Occupancy August 16, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Elementary Classroom Improvements
A. PROJECT STATUS
Gelfand Partners will commence design work after the BOE approves their contract in June. The classroom
improvements project established budgets for each elementary school campus to receive new lighting, new
windows and shades, ventilation improvements and ceiling tiles. Also part of the classroom improvements
project is the implementation of a technology wall. District staff has begun conducting site walks with each
school Principal to determine placement of the interactive white board in the classroom and expect to wrap‐
up in June.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• Planning will commence once Gelfand’s contract is approved in June.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,193,721
Construction & Equipment $7,488,706
Soft Costs Contingency $205,095
Total $8,887,522
Percent of Budget Expended 1.3%
Current Phase: Planning
Schedule:
Architect Contract (2) June 8, 2010*
BOE Approval June 22, 2010*
Conceptual Design (2) TBD
BOE Approval TBD
Schematic Design (2) TBD
BOE Approval TBD
Submit to DSA TBD
Approval by DSA TBD
Authorize to Bid (2) TBD
BOE Approval TBD
Bid Opening TBD
Award of Contract (1) TBD
Notice to Proceed TBD
Substantial Completion TBD
Planned Occupancy TBD
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
Of the $5,576,500 project budget, 84.6% or $4,720,037 was
expended. Approved change orders were $208,756, which is
approximately 59.8% of the $349,000 construction contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
• The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,576,500
Other Funding $0
Total $5,576,500
Budget
Salaries and Benefits $0
Supplies $10,358
Contracts & Services $1,216,066
Construction & Equipment $4,300,350
Soft Costs Contingency $49,726
Total $5,576,500
Percent of Budget Expended 89.0%
Change Order Contingency
• Starting Contingency Balance $349,000
• Remaining Contingency Balance $140,244
• Percent of Changes 59.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Gunn High School
Aquatic Center
A. PROJECT STATUS
Of the $5,013,750 project budget, 96.6%, or $4,844,070 was
expended. Approved change orders were $194,739, which is
approximately 49.9% of the $389,887 construction contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
• This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,013,750
Other Funding $0
Total $5,013,750
Budget
Salaries and Benefits $0
Supplies $7,684
Contracts & Services $679,284
Construction & Equipment $4,323,742
Soft Costs Contingency $3,040
Total $5,013,750
Percent of Budget Expended 96.8%
Change Order Contingency
• Starting Contingency Balance $389,887
• Remaining Contingency Balance $195,148
• Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education on June 23 for discussion and received approval
on September 8 by the Board of Education to move into schematic
design.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
• This project has been completed on schedule and under budget. Board approval received on September
8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $101,000
Other Funding $0
Total $101,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $85,000
Construction & Equipment $0
Soft Costs Contingency $15,000
Total $101,000
Percent of Budget Expended 52.9%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 26
Middle Schools Interim Classrooms
Jordan and J.L. Stanford
A. PROJECT STATUS
Contracts were awarded to Coulter Construction for Jordan Middle
School and Mark Electric for Stanford Middle School following
Board of Education approval on May 26, 2009. Both contractors
started work on June 15, 2009 and were completed on August 3,
2009 at Jordan and August 12, 2009 at Stanford. Of the $1,047,186
project budget, 25%, or $236,696 has been expended. Pending
Change Orders are currently estimated to be a deduct of ($10,331),
which is approximately 0% of the $30,698 construction
contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project was completed under budget and on schedule.
Funding
State Funds $0
Strong Schools Bond Funds $1,047,186
Other Funding $0
Total $1,047,186
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $308,648
Construction & Equipment $707,840
Soft Costs Contingency $30,698
Total $1,047,186
Percent of Budget Expended 48.9%
Change Order Contingency
• Starting Contingency Balance $30,698
• Remaining Contingency Balance $30,698
• Percent of Changes 0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –August 25, 2009
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA April 14, 2009
Approval by DSA April 22, 2009
Authorize to Bid (2) March 31, 2009
BOE Approval April 14, 2009
Bid Opening May 14, 2009
Award of Contract (1) May 26, 2009
Notice to Proceed June 1, 2009
Substantial Completion August 12, 2009
Planned Occupancy August 25, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 27
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education voted on August 25, 2009 to approve the
amendment to Garland lease to Stratford School. Therefore, the
district has placed the project on hold.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,830,789
Construction & Equipment $17,485,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 28
Elementary School Teaching Walls
Phase 1 Schools
A. PROJECT STATUS
The district placed this project on hold after review of the
implementation of other classroom improvements, as
recommended by the elementary school principals. This
project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.9
D. PROJECT OVERVIEW:
• This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary
above).
Funding
State Funds $0
Strong Schools Bond Funds $7,044,987
Other Funding $0
Total $7,044,987
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,341,394
Construction & Equipment $5,498,498
Soft Costs Contingency $205,095
Total $7,044,987
Percent of Budget Expended 1.6%
Current Phase: On Hold
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.