Monthly Reports 2010-04 (Apr)
MMOONNTTHHLLYY PPRROOGGRREESSSS RREEPPOORRTT
Through
April 2010
Current Strong Schools Bond
Capital Improvement Projects
Prepared by
O’Connor Construction Management, Inc.
&
Gilbane Building Company
Page | 2
TABLE OF CONTENTS
Executive Summary page 3
Attachment 1 – Consolidated Expenditure Report
Attachment 2 – Master Project Schedule
Capital Projects
High School Master Plan page 6
Gunn High School – New Classroom Buildings A & B page 7
Gunn High School – Parking and Drop‐off Sitework Improvement page 8
Gunn High School – New Gymnasium page 9
Palo Alto High School – Stadium Field Renovation page 10
Palo Alto High School – Multi‐use Field page 11
Palo Alto High School – Classroom Building and Media Arts page 12
Palo Alto High School – Theater and Associated Site Improvements page 13
Jordan Middle School page 14
J.L. Stanford Middle School page 15
Terman Middle School page 16
Fairmeadow Elementary School page 17
Ohlone Elementary School page 18
Elementary Classroom Improvements page 19
Inactive Capital Projects
Gunn High School – Industrial Arts Renovation page 20
Gunn High School – Aquatic Center page 21
Middle School Pre‐Design page 22
Middle School Interim Classrooms page 23
Garland Elementary School page 24
Elementary School Teaching Walls – Phase 1 Schools page 25
Appendix
Exhibit A – Bond Project List
Page | 3
EXECUTIVE SUMMARY
CAPITAL PROJECTS
High School Master Plan
Gates + Associates held meetings with the landscape subcommittees to present the final draft landscape master
plans for each campus. After review by the campuses and community in May, they will be presented to the board
for approval in June.
The Mitigated Negative Declaration (MND) for Gunn high school was presented to the Board of Education (BOE) on
April 27, 2010 and is anticipated to be approved at the May 11, 2010 BOE meeting.
Gunn High School – New Classroom Buildings A & B
DLM is anticipated to submit 50% construction development drawings on May 4, 2010. To make way for
construction of the new classroom building, approximately 26 portables need to be relocated. Rodan Builders, Inc.
will begin the portable relocation project on June 14, 2010 and complete the project for fall semester occupancy.
DLM continues to prepare contract documents for the new buildings and is expecting to submit to DSA at the end
of June 2010.
Gunn High School – Parking and Drop‐off Sitework Improvement
A revised master plan project list, which included the parking and drop‐off project to include a drop‐off area from
Miranda Ave, was approved by the BOE on April 6, 2010. The future parking and drop‐off improvements design will
continue after the BOE adopts the MND in May.
Gunn High School – New Gymnasium
DLM continues to develop construction documents and will submit 50% construction development drawings in
early May 2010.
Palo Alto High School – Stadium Field Renovation
DLM and the stadium design committee met to review and refine plans for the stadium improvements. The
improvements include a new concession stand, bathrooms, and an expansion to 2,464 seats for home and visitor’s
side bleachers. The project will also coordinate with the surrounding corporation yard for maintenance functions
and the Churchill entrance.
Palo Alto High School – Multi‐use Field
Valley Crest Landscape Development was awarded the contract at the BOE meeting on April 6, 2010. Construction
commences on June 1, 2010, after the baseball and softball seasons conclude. As part of this project, the Churchill
parking lot will receive some improvements, with construction to occur after graduation and before fall semester.
The fields and dugout work has a completion date of January 31, 2010, which includes a turf establishment and
growing period.
Palo Alto High School – Classroom Building and Media Arts Building
On April 6, 2010 the BOE approved the award of a construction contract to Rodan Builders, Inc. for the portable
relocation project. Portable relocation begins on June 14, 2010 and will be complete for occupancy by the fall
semester. DLM continues to prepare construction documents (CD) for the new buildings and anticipates
submission of the 50% CDs to the district on May 4, 2010.
Palo Alto High School – Theater and Associated Site Improvements
DLM and the theater subcommittee requested approval from the FSC to develop conceptual designs on two
preferred schemes, including the incorporation of a fly tower and orchestra pit. On April 7, 2010 the FSC approved
having DLM develop concepts and massing studies for a theater configuration on two recommended schemes.
DLM followed up with the theater subcommittee to review the developed massing studies on April 29, 2010.
Page | 4
Jordan Middle School
AEDIS presented refined classroom wing and cafetorium building design to the bond advisory committee and to
the community before returning to the BOE on April 27, 2010 for approval. The BOE approved schematic design
on April 27, 2010 and authorized staff to proceed with design development. AEDIS will meet with the bond
advisory committee in May to review with the group the upcoming phases before summer break.
J.L. Stanford Middle School
AEDIS met with the bond advisory committee on April 26, 2010 to review schematic design for the new building,
classroom improvements, and landscape design. AEDIS also conducted a community meeting on April 26, 2010 to
receive feedback and input on the planned projects. Schematic design approval is anticipated to be discussed at
the May 25, 2010 board meeting.
Terman Middle School
AEDIS presented the plans for the administration/library expansion, new drama classroom, cafetorium/kitchen
improvements and other school‐wide improvements at a community meeting on April 21, 2010 in order to receive
input and comments from parents, PTA members and neighborhood association groups. AEDIS is scheduled to
present the schematic design package to the BOE on May 11, 2010 for discussion, with approval anticipated on
May 25, 2010.
Fairmeadow Elementary School – New Classroom Building and Modernization
The Board of Education approved conceptual design for Fairmeadow elementary school on April 6, 2010. Gelfand
Partners kicked off schematic design on April 28, 2010 by meeting with various user groups. Gelfand partners will
continue to meet with user groups and the site committee through to the end of school.
Ohlone Elementary School – New Classroom Building and Modernization
DSA continues its review of the Ohlone classroom building and modernization project, which is expected to be
completed no later than August 2010. Coulter Construction is scheduled to begin work immediately following
school dismissal for summer on relocating the portables to make way for the construction of the two story building
scheduled to begin late fall. Pre‐qualification proposals are under review received from 13 contractors seeking to
bid on the new building and modernization project.
Elementary Classroom Improvements
The Elementary Classroom Improvements project was approved by BOE on April 27, 2010. The classroom
improvements project established budgets for each elementary school campus to receive a technology wall, new
lighting, new windows and shades, ventilation improvements and ceiling tiles. Gelfand Partners will be the
architect for this project, and design work will commence after the board approves their contract.
INACTIVE CAPITAL PROJECTS
Gunn High School – Industrial Arts Addition & Renovation
Of the $5,576,500 project budget, 84.6% or $4,720,037 was expended. Approved change orders were $208,756,
which is approximately 59.8% of the $349,000 construction contingency.
Gunn High School – Aquatic Center
Of the $5,013,750 project budget, 96.6%, or $4,844,070 was expended. Approved change orders were $194,739,
which is approximately 49.9% of the $389,887 construction contingency.
Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman
AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for
discussion and received approval on September 8 by the Board of Education to move into schematic design.
Page | 5
Middle Schools Interim Housing – Jordan and J.L. Stanford
Contracts were awarded to Coulter Construction for Jordan Middle School and Mark Electric for Stanford Middle
School following Board of Education approval on May 26, 2009. Both contractors started work on June 15, 2009
and were completed on August 3, 2009 at Jordan and August 12, 2009 at Stanford. Of the $1,047,186 project
budget, 25%, or $236,696 has been expended. Pending Change Orders are currently estimated to be a deduct of
($10,331), which is approximately 0% of the $30,698 construction contingency.
Garland Elementary School Renovation
The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.
Therefore, the district has placed the project on hold.
Elementary School Teaching Walls – Phase 1 Schools
The district placed this project on hold after review of the implementation of other classroom improvements, as
recommended by the elementary school principals. This project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
Board Actions in April
April 6, 2010
Consent 6 – Approval of Updated Project List for Gunn High School Master Plan
Consent 7 – Approval of Air Conditioning of Existing Buildings Project at Gunn High School and Authorization to
Issue Addendum No. 7 for Design Services to DLM Architecture
Action 17 – Approval of Conceptual Design and Project for Fairmeadow Elementary School
Action 19 – Authorization to Award Contract for Construction of the Palo Alto High School Multi‐use Fields
Action 20 – Authorization to Award Contract for Site Work and Relocation of Modular Classroom Buildings to
Accommodate Construction at Palo Alto High School
Action 21 – Authorization to Award Contract for Site Work and Relocation of Modular Classroom Buildings to
Accommodate Construction at Gunn High School
April 27, 2010
Consent 6 – Authorization to Enter into Addendum No. 7 with Gelfand Partners for Design Services at Fairmeadow
Elementary School
Action 10 – Approval of Schematic Design for Jordan Middle School
Action 14 – Strong Schools Bond Plan and Budget for Elementary Schools
A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 127,371 85,996 59.3% 41,375 67.52% 17,629Gunn High School 1 - Aquatic Center 5,013,750 4,935,692 4,854,830 96.8% 80,862 98.36% 78,058Gunn High School 2 - I.A 5,511,500 5,153,175 4,841,935 87.9% 311,240 93.96% 358,325Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom A & B 24,120,000 2,195,034 562,577 2.3% 1,632,457 25.63% 21,924,966Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 3,019 0.1% 214,751 1.39% 3,722,230Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 932,150 182,835 1.3% 749,315 19.61% 12,897,850Gunn High School 7- A/C 0 0 0 0.0% 0 0.00% 0Gunn High School - Reserved 23,545,045 0 0 0.0% 0 0.00% 23,545,045Palo Alto High Schools - High School Master Plan 145,000 130,597 90,699 62.6% 39,898 69.45% 14,403Palo Alto High School 1 - Bleacher 1,358,437 140,810 115,810 8.5% 25,000 82.25% 1,217,627Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 482,999 256,858 8.6% 226,141 53.18% 2,519,064Palo Alto high School 3 - New classroom & Media Art Building 34,220,000 2,559,228 569,720 1.7% 1,989,508 22.26% 31,660,772Palo Alto High School 4 - New Theater 17,720,000 1,026,210 7,330 0.0% 1,018,880 0.71% 16,693,790Palo Alto High School - Reserved 42,348,045 0 0 0.0% 0 0.00% 42,348,045Jordan Middle School - Middle School Pre-Design 33,665 19,718 17,413 51.7% 2,305 88.31% 13,947Jordan Middle Schools 1- Interim Classrooms 600,342 186,569 157,893 26.3% 28,676 84.63% 413,773Jordan Middle School 2 17,943,194 1,583,569 249,279 1.4% 1,334,290 15.74% 16,359,625Jordan Middle School - Reserved 0 0 0 0.0% 0 0.00% 0J.L.S Middle School - Middle School Pre-Design 33,669 19,627 17,995 53.4% 1,632 91.68% 14,042J.L.S Middle School 1 - Interim Classrooms 446,844 351,408 312,937 70.0% 38,471 89.05% 95,436 J.L.S Middle School 2 17,184,699 1,432,112 186,682 1.1% 1,245,430 13.04% 15,752,587 J.L.S Middle School - Reserved 0 0 0 0.0% 0 0.00% 0Terman Middle School - Middle School Pre- Design 33,666 19,627 18,010 53.5% 1,617 91.76% 14,039Terman Middle School 1 12,850,071 1,187,625 157,461 1.2% 1,030,164 13.26% 11,662,446Terman Middle School - Reserved 0 0 0 0.0% 0 0.00% 0PAUSD Elementary Schools - Elementary Growth Plan 145,000 62,700 55,560 38.3% 7,140 88.61% 82,300Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265Fairmeadow Elementary School 1- Phase I 9,327,500 27,500 25,000 0.3% 2,500 90.91% 9,300,000Ohlone Elementary School 1- Phase I 11,667,965 1,448,811 891,700 7.6% 557,111 61.55% 10,219,154 Elementary Schools 1 - Elem Teaching Wall Project 7,044,987 139,822 113,352 1.6% 26,470 81.07% 6,905,165Elementary Schools - Reserved 48,314,283 0 0 0.0% 0 0.00% 48,314,283PAUSD - Program Admin. ** 3,353,108 2,700,233 1,895,640 56.5% 804,593 70.20% 652,875PAUSD - Technology 5,995,689 2,286,331 2,079,428 34.7% 206,903 90.95% 3,709,358PAUSD - Technology -Reserved 7,911,676 0 0 0.0% 0 0.00% 7,911,676PAUSD - Reserved 6,335,945 0 0 0.0% 0 0.00% 6,335,945Total346,305,464 29,653,744 18,035,849 11,617,895 316,651,720Prepared by: Business Services Department based on QSS accounting SystemCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond4/30/2010Percent of ExpendedContract BalanceExpenditures Budget Balance
Activity IDPhaseActivity NameOriginalDurationStartFinishDuration %CompleteGunn- IndusGunn- Industrial AGunn- Industrial Arts Renovation43101-Oct-08 A26-May-1095.59%Gunn - New Gunn - New ClassrGunn - New Classroom Building107520-Apr-09 A03-Jun-1325.02%Gunn - ParkiGunn - Parking andGunn - Parking and Drop Off102101-Sep-09 A30-Jul-1316.94%Gunn New GGunn New GymnasGunn New Gymnasium92021-Apr-09 A30-Oct-1229.13%Paly - Home Paly - Home Side BPaly - Home Side Bleachers64417-Aug-09 A15-Feb-1227.17%Paly - Multi UPaly - Multi Use FiePaly - Multi Use Field Improvements58703-Nov-08 A01-Feb-1166.27%Paly - New CPaly - New ClassroPaly - New Classroom Building & Media Arts111820-Apr-09 A01-Aug-1324.06%Paly - New TPaly - New TheaterPaly - New Theater and Sitework149709-Sep-09 A26-May-1511.62%Jordan New Jordan New ClassrJordan New Classroom Wing & Modernizat...117103-Nov-08 A29-Apr-1333.22%Stanford NewStanford New ClasStanford New Classroom Wing114403-Nov-08 A28-Mar-1333.57%Terman AdmTerman Admin WinTerman Admin Wing Addition & Modernizat...121303-Nov-08 A03-Jul-1331.74%Garland SchGarland School MoGarland School Modernization52303-Nov-08 A30-Apr-10100%FairmeadowFairmeadow ElemeFairmeadow Elementary School119414-Dec-09 A01-Aug-1328.81%Ohlone New Ohlone New ClassOhlone New Classroom Wing97703-Nov-08 A31-Jul-1239.82%Teaching WaTeaching Walls CaTeaching Walls Casework17206-Apr-09 A28-Sep-09 A100%NDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJA2009201020112012201320142015PALO ALTO UNIFIED SCHOOL DISTRICTSTRONG SCHOOLS BOND PROGRAMMASTER SCHEDULE SUMMARY DesignPlanningBid and AwardConstructionDSACloseoutMilestonePage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc.
Page | 6
High School Master Plan
Palo Alto HS and Gunn HS
A. PROJECT STATUS
Gates + Associates held meetings with the landscape
subcommittees to present the final draft landscape master plans
for each campus. After review by the campuses and community in
May, they will be presented to the board for approval in June.
The Mitigated Negative Declaration (MND) for Gunn high school
was presented to the Board of Education (BOE) on April 27, 2010
and is anticipated to be approved on consent at the May 11, 2010
BOE meeting.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14
D. PROJECT OVERVIEW:
• Final MND documents for Gunn high school scheduled to be adopted by the BOE in May.
Funding
State Funds $0
Strong Schools Bond Funds $290,000
Other Funding $0
Total $290,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $279,521
Construction & Equipment $0
Soft Costs Contingency $9,479
Total $290,000
Percent of Budget Expended 60.9%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Initial Master Plan Approval (2) September 8, 2009
BOE Approval September 22, 2009
Paly CEQA Approval (2) February 9, 2010
BOE Approval February 23, 2010
Gunn Master Plan Update (2) March 23, 2010
BOE Approval April 6, 2010
Gunn CEQA Approval (2) April 27, 2010
BOE Approval May 11, 2010 *
Paly Master Plan Update (2) June 1, 2010 *
Landscape Master Plan Approval June 22, 2010 *
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 7
Gunn High School
New Classroom Buildings A & B
A. PROJECT STATUS
DLM is anticipated to submit 50% construction development
drawings on May 4, 2010. To make way for construction of the new
classroom building, approximately 26 portables need to be
relocated. Rodan Builders, Inc. will begin the portable relocation
project on June 14, 2010 and complete the project for fall semester
occupancy. DLM continues to prepare contract documents for the
new buildings and is expecting to submit to DSA at the end of June
2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $24,120,000
Other Funding $0
Total $24,120,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $4,315,728
Construction & Equipment $19,590,000
Soft Costs Contingency $164,272
Total $24,120,000
Percent of Budget Expended 2.3%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA July 1, 2010*
Approval by DSA March 17, 2011 *
Authorize to Bid (2) January 11, 2011 *
BOE Approval January 25, 2011*
Bid Opening April 7, 2011 *
Award of Contract (1) April 26, 2011 *
Notice to Proceed May 5, 2011*
Substantial Completion November 23, 2012*
Planned Occupancy June 3, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 8
Gunn High School
Parking and Drop‐off Sitework Improvement
A. PROJECT STATUS
A revised master plan project list, which included the parking
and drop‐off project to include a drop‐off area from Miranda
Ave, was approved by the BOE on April 6, 2010. The future
parking and drop‐off improvements design will continue after
the BOE adopts the MND in May.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 5.5
D. PROJECT OVERVIEW:
• This project will re‐commence after completion of CEQA process.
Funding
State Funds $0
Strong Schools Bond Funds $3,940,000
Other Funding $0
Total $3,940,000
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $883,978
Construction & Equipment $2,934,840
Soft Costs Contingency $121,182
Total $3,940,000
Percent of Budget Expended 0.1%
Current Phase: Conceptual Design
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 28, 2010*
BOE Approval September 22, 2010*
Schematic Design (2) December 17, 2010*
BOE Approval December 27, 2010*
Submit to DSA November 2, 2011*
Approval by DSA June 5, 2012 *
Authorize to Bid (2) June 12, 2012*
BOE Approval June 26, 2012*
Bid Opening September 24, 2012 *
Award of Contract (1) October 29, 2012*
Notice to Proceed December 3, 2012*
Substantial Completion June 11, 2013*
Planned Occupancy August, 2013*
* Anticipated Dates – Subject to Change
()Denotesnumber ofBoard of Education Readings
Page | 9
Gunn High School
New Gymnasium
A. PROJECT STATUS
DLM continues to develop construction documents and will
submit 50% construction development drawings in early May
2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $13,830,000
Other Funding $0
Total $13,830,000
Budget
Salaries and Benefits $0
Supplies $40,000
Contracts & Services $2,596,521
Construction & Equipment $11,109,450
Soft Costs Contingency $84,029
Total $13,830,000
Percent of Budget Expended 1.3%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA July 1, 2010*
Approval by DSA March 17, 2011*
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Bid Opening March 24, 2011*
Award of Contract (1) April 12, 2011*
Notice to Proceed April 21, 2011*
Substantial Completion September 21, 2012*
Planned Occupancy October 12, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 10
Palo Alto High School
Football Stadium Renovation
A. PROJECT STATUS
DLM and the stadium design committee met to review
and refine plans for the stadium improvements. The
improvements include a new concession stand,
bathrooms, and an expansion to 2,464 seats for home
and visitor’s side bleachers. The project will also
coordinate with the surrounding corporation yard for
maintenance functions and the Churchill entrance.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.13
D. PROJECT OVERVIEW:
• Programming in progress
Funding
State Funds $0
Strong Schools Bond Funds $1,358,473
Other Funding $0
Total $1,358,437
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $127,622
Construction & Equipment $1,230,815
Soft Costs Contingency $0
Total $1,358,437
Percent of Budget Expended 8.5%
Current Phase: Programming
Schedule:
Architect Contract (2) January 26, 2010
BOE Approval February 9, 2010
Conceptual Design (2) June 1, 2010*
BOE Approval June 22, 2010*
Schematic Design (2) August 24, 2010*
BOE Approval September 14, 2010*
Submit to DSA December 15, 2010*
Approval by DSA April 1, 2011*
Authorize to Bid (2) March 28, 2011*
BOE Approval April 18, 2011*
Bid Opening May 16, 2011*
Award of Contract (1) May 26, 2011*
Notice to Proceed June 2, 2011*
Substantial Completion January 9, 2012*
Planned Occupancy January 31, 2012*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 11
Palo Alto High School
Multi‐Use Field
A. PROJECT STATUS
Valley Crest Landscape Development was awarded the contract at
the BOE meeting on April 6, 2010. Construction commences on
June 1, 2010, after the baseball and softball seasons conclude. As
part of this project, the Churchill parking lot will receive some
improvements, with construction to occur after graduation and
before fall semester. The fields and dugout work has a
completion date of January 31, 2010, which includes a turf
establishment and growing period.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.14
D. PROJECT OVERVIEW:
• Project awarded on April 6, 2010 and will begin construction on June 1, 2010
Funding
State Funds $0
Strong Schools Bond Funds $3,002,063
Other Funding $1,075,991
Total $4,078,054
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $673,020
Construction & Equipment $3,312,683
Soft Costs Contingency $92,351
Total $4,078,054
Percent of Budget Expended 8.6%
Current Phase: Bid & Award
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) December 9, 2009
BOE Approval January 13, 2009
Schematic Design (2) February 24, 2009
BOE Approval March 17, 2009
Submit to DSA March 19, 2009
Approval by DSA September 30, 2009
Authorize to Bid (2) January 26, 2010
BOE Approval February 9, 2010
Bid Opening March 16, 2010
Award of Contract (1) April 6, 2010
Notice to Proceed May 3, 2010*
Substantial Completion November 30, 2010*
Planned Occupancy February 1, 2010*
* Anticipated Dates – Subject to Change
( ) Denotesnumber of Board of Education Readings
Page | 12
Palo Alto High School
Classroom Building and Media Arts
A. PROJECT STATUS
On April 6, 2010 the BOE approved the award of a construction
contract to Rodan Builders, Inc. for the portable relocation project.
Portable relocation begins on June 14, 2010 and will be complete for
occupancy by the fall semester. DLM continues to prepare
construction documents (CD) for the new buildings and anticipates
submission of the 50% CDs to the district on May 4, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3
D. PROJECT OVERVIEW:
• Project is currently proceeding on schedule and within budget.
Funding
State Funds $0
Strong Schools Bond Funds $34,220,000
Other Funding $0
Total $34,220,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $6,067,996
Construction & Equipment $27,876,384
Soft Costs Contingency $225,620
Total $34,220,000
Percent of Budget Expended 1.7%
Current Phase: Construction Documents
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) September 8, 2009
BOE Approval September 22, 2009
Schematic Design (2) January 12, 2010
BOE Approval January 26, 2010
Submit to DSA July 1, 2010*
Approval by DSA March 17, 2011*
Authorize to Bid (2) January 11, 2011*
BOE Approval January 25, 2011*
Bid Opening April 7, 2011*
Award of Contract (1) April 26, 2011*
Notice to Proceed May 5, 2011*
Substantial Completion March 25, 2013*
Planned Occupancy August 1, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 13
Palo Alto High School
Theater and Associated Site Improvements
A. PROJECT STATUS
DLM and the theater subcommittee requested approval from the
FSC to develop conceptual designs on two preferred schemes,
including the incorporation of a fly tower and orchestra pit. On
April 7, 2010 the FSC approved having DLM develop concepts and
massing studies for a theater configuration on two recommended
schemes. DLM followed up with the theater subcommittee to
review the developed massing studies on April 29, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 4.11
D. PROJECT OVERVIEW:
• Programming in progress.
Funding
State Funds $0
Strong Schools Bond Funds $17,720,000
Other Funding $0
Total $17,720,000
Budget
Salaries and Benefits $0
Supplies $50,000
Contracts & Services $3,276,077
Construction & Equipment $14,284,700
Soft Costs Contingency $109,223
Total $109,223
Percent of Budget Expended 0.0%
Current Phase: Planning
Schedule:
Architect Contract (2) March 31, 2009
BOE Approval April 14, 2009
Conceptual Design (2) June 1, 2010*
BOE Approval June 22, 2010*
Schematic Design (2) December 7, 2010*
BOE Approval December 14, 2010*
Submit to DSA August, 2011*
Approval by DSA June, 2012*
Authorize to Bid (2) August, 2012*
BOE Approval August, 2010*
Bid Opening October, 2012*
Award of Contract (1) November, 2012*
Notice to Proceed February, 2013*
Substantial Completion March, 2015*
Planned Occupancy August, 2015*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 14
Jordan Middle School
A. PROJECT STATUS
AEDIS presented refined classroom wing and cafetorium
building design to the bond advisory committee and to the
community before returning to the BOE on April 27, 2010 for
approval. The BOE approved schematic design on April 27,
2010 and authorized staff to proceed with design
development. AEDIS will meet with the bond advisory
committee in May to review with the group the upcoming
phases before summer break.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5
D. PROJECT OVERVIEW:
• Board approval for schematic design received on April 27, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $17,943,191
Other Funding $0
Total $17,943,191
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,432,480
Construction & Equipment $14,014,500
Soft Costs Contingency $496,214
Total $17,943,194
Percent of Budget Expended 1.4%
Current Phase: Design Development
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) March 23, 2010
BOE Approval April 27, 2010
Submit to DSA October 15, 2010*
Approval by DSA June 22, 2011*
Authorize to Bid (2) June 27, 2011*
BOE Approval July 8, 2011*
Bid Opening August 10, 2011*
Award of Contract (1) August 25, 2011*
Notice to Proceed September 21, 2011*
Substantial Completion March 21, 2013*
Planned Occupancy August, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 15
J.L. Stanford Middle School
A. PROJECT STATUS
AEDIS met with the bond advisory committee on April
26, 2010 to review schematic design for the new
building, classroom improvements, and landscape
design. AEDIS also conducted a community meeting
on April 26, 2010 to receive feedback and input on the
planned projects. Schematic design approval is
anticipated to be discussed at the May 25, 2010 board
meeting.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5
D. PROJECT OVERVIEW:
• Schematic design approval is scheduled to be discussed at May 25, 2010 board meeting.
Funding
State Funds $0
Strong Schools Bond Funds $17,184,697
Other Funding $0
Total $17,184,697
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,281,600
Construction & Equipment $13,406,000
Soft Costs Contingency $497,099
Total $17,184,699
Percent of Budget Expended 1.1%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 25, 2010*
BOE Approval June 1, 2010*
Submit to DSA November 25, 2010*
Approval by DSA July 12, 2011*
Authorize to Bid (2) July 6, 2011*
BOE Approval July 19, 2011*
Bid Opening September 7, 2011*
Award of Contract (1) September 26, 2011*
Notice to Proceed October 19, 2011*
Substantial Completion February 7, 2013*
Planned Occupancy March 28, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 16
Terman Middle School
A. PROJECT STATUS
AEDIS presented the plans for the administration/library
expansion, new drama classroom, cafetorium/kitchen
improvements and other school‐wide improvements at a
community meeting on April 21, 2010 in order to receive input
and comments from parents, PTA members and neighborhood
association groups. AEDIS is scheduled to present the
schematic design package to the BOE on May 11, 2010 for
discussion, with approval anticipated on May 25, 2010.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12
D. PROJECT OVERVIEW:
• Schematic design approval will be discussed at the May 11, 2010 board meeting.
Funding
State Funds $0
Strong Schools Bond Funds $12,850,071
Other Funding $0
Total $12,850,071
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,411,150
Construction & Equipment $10,096,569
Soft Costs Contingency $342,352
Total $12,850,071
Percent of Budget Expended 1.2%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) May 11, 2010*
BOE Approval May 25, 2010*
Submit to DSA November 29, 2010*
Approval by DSA July 26, 2011*
Authorize to Bid (2) July 27, 2011*
BOE Approval August 10, 2011*
Bid Opening September 19, 2011*
Award of Contract (1) October 4, 2011*
Notice to Proceed October 5, 2011*
Substantial Completion March 26, 2013*
Planned Occupancy July 3, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 17
Fairmeadow Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
The Board of Education approved conceptual design for Fairmeadow
elementary school on April 6, 2010. Gelfand Partners kicked off
schematic design on April 28, 2010 by meeting with various user
groups. Gelfand partners will continue to meet with user groups and
the site committee through to the end of school.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Board approved conceptual design on April 6, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $290,000
Other Funding $0
Total $290,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $279,521
Construction & Equipment $0
Soft Costs Contingency $9,479
Total $290,000
Percent of Budget Expended 0.3%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 13, 2009
BOE Approval October 27, 2009
Conceptual Design (2) March 23, 2010
BOE Approval April 6, 2010
Schematic Design (2) August 24, 2010*
BOE Approval September 14, 2010*
Submit to DSA March 4, 2011*
Approval by DSA October 28, 2011*
Authorize to Bid (2) December 9, 2011*
BOE Approval December 16, 2011*
Bid Opening January 31, 2012*
Award of Contract (1) October 9, 2012*
Notice to Proceed October 19, 2012*
Substantial Completion April 2, 2013*
Planned Occupancy August 13, 2013*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 18
Ohlone Elementary School
New Classroom Building and Modernization
A. PROJECT STATUS
DSA continues its review of the Ohlone classroom building and
modernization project, which is expected to be completed no
later than August 2010. Coulter Construction is scheduled to begin
work immediately following school dismissal for summer on
relocating the portables to make way for the construction of the
two story building scheduled to begin late fall. Pre‐qualification
proposals are under review received from 13 contractors seeking
to bid on the new building and modernization project.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10
D. PROJECT OVERVIEW:
• Gelfand submitted to DSA on November 24, 2009 and will schedule the backcheck appointment in May.
Funding
State Funds $0
Strong Schools Bond Funds $11,667,965
Other Funding $0
Total $11,667,965
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $2,221,174
Construction & Equipment $9,181,991
Soft Costs Contingency $264,800
Total $11,667,965
Percent of Budget Expended 7.6%
Current Phase: DSA Review
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) March 3, 2009
BOE Approval March 17, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA November 24, 2009
Approval by DSA July 30, 2010 *
Authorize to Bid (2) September 1, 2010*
BOE Approval September 9, 2010*
Bid Opening November 3, 2010*
Award of Contract (1) November 16, 2010*
Notice to Proceed December 6, 2010*
Substantial Completion January 31, 2011*
Planned Occupancy August 25, 2011*
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 19
Elementary Classroom Improvements
A. PROJECT STATUS
The Elementary Classroom Improvements project was approved by BOE on April 27, 2010. The classroom
improvements project established budgets for each elementary school campus to receive a technology wall,
new lighting, new windows and shades, ventilation improvements and ceiling tiles. Gelfand Partners will be
the architect for this project, and design work will commence after the board approves their contract.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7
D. PROJECT OVERVIEW:
• Board of Education approved project budgets for the elementary schools on April 27, 2010.
Funding
State Funds $0
Strong Schools Bond Funds $8,887,522
Other Funding $0
Total $8,887,522
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,193,721
Construction & Equipment $7,488,706
Soft Costs Contingency $205,095
Total $8,887,522
Percent of Budget Expended 0.78%*
*Reflects Teaching Wall Project expenditure.
Current Phase: Planning
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) TBD
BOE Approval TBD
Schematic Design (2) TBD
BOE Approval TBD
Submit to DSA TBD
Approval by DSA TBD
Authorize to Bid (2) TBD
BOE Approval TBD
Bid Opening TBD
Award of Contract (1) TBD
Notice to Proceed TBD
Substantial Completion TBD
Planned Occupancy TBD
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 20
Gunn High School
Industrial Arts Addition and Renovation
A. PROJECT STATUS
Of the $5,576,500 project budget, 84.6% or $4,720,037 was
expended. Approved change orders were $208,756, which is
approximately 59.8% of the $349,000 construction contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11
D. PROJECT OVERVIEW:
• The building occupied as scheduled, and the project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,576,500
Other Funding $0
Total $5,576,500
Budget
Salaries and Benefits $0
Supplies $10,358
Contracts & Services $1,216,066
Construction & Equipment $4,300,350
Soft Costs Contingency $49,726
Total $5,576,500
Percent of Budget Expended 87.9%
Change Order Contingency
• Starting Contingency Balance $349,000
• Remaining Contingency Balance $140,244
• Percent of Changes 59.8%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –January 4, 2010
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA June 17, 2008
Approval by DSA December 24, 2008
Authorize to Bid (2) October 14, 2008
BOE Approval October 28, 2008
Bid Opening December 16, 2008
Award of Contract (1) December 24, 2008
Notice to Proceed January 6, 2009
Substantial Completion November 25, 2009
Planned Occupancy January 4, 2010
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 21
Gunn High School
Aquatic Center
A. PROJECT STATUS
Of the $5,013,750 project budget, 96.6%, or $4,844,070 was
expended. Approved change orders were $194,739, which is
approximately 49.9% of the $389,887 construction contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 3.12
D. PROJECT OVERVIEW:
• This project completed within budget.
Funding
State Funds $0
Strong Schools Bond Funds $5,013,750
Other Funding $0
Total $5,013,750
Budget
Salaries and Benefits $0
Supplies $7,684
Contracts & Services $679,284
Construction & Equipment $4,323,742
Soft Costs Contingency $3,040
Total $5,013,750
Percent of Budget Expended 96.8%
Change Order Contingency
• Starting Contingency Balance $389,887
• Remaining Contingency Balance $195,148
• Percent of Changes 49.9%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –June 15, 2009
Schedule:
Architect Contract (2) N/A
BOE Approval N/A
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA December 11, 2007
Approval by DSA April 24, 2008
Authorize to Bid (2) April 8, 2008
BOE Approval April 22, 2008
Bid Opening May 28, 2008
Award of Contract (1) June 4, 2008
Notice to Proceed December 6, 2008
Substantial Completion June 15, 2009
Planned Occupancy June 15, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 22
Middle School Pre‐Design
Jordan, J.L. Stanford and Terman
A. PROJECT STATUS
AEDIS presented recommended concept plans for each campus to the
Board of Education on June 23 for discussion and received approval
on September 8 by the Board of Education to move into schematic
design.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12
D. PROJECT OVERVIEW:
• This project has been completed on schedule and under budget. Board approval received on September
8, 2009.
Funding
State Funds $0
Strong Schools Bond Funds $101,000
Other Funding $0
Total $101,000
Budget
Salaries and Benefits $0
Supplies $1,000
Contracts & Services $85,000
Construction & Equipment $0
Soft Costs Contingency $15,000
Total $101,000
Percent of Budget Expended 39.9%
Current Phase: Complete
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) June 23, 2009
BOE Approval September 8, 2009
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 23
Middle Schools Interim Classrooms
Jordan and J.L. Stanford
A. PROJECT STATUS
Contracts were awarded to Coulter Construction for Jordan Middle
School and Mark Electric for Stanford Middle School following
Board of Education approval on May 26, 2009. Both contractors
started work on June 15, 2009 and were completed on August 3,
2009 at Jordan and August 12, 2009 at Stanford. Of the $1,047,186
project budget, 25%, or $236,696 has been expended. Pending
Change Orders are currently estimated to be a deduct of ($10,331),
which is approximately 0% of the $30,698 construction
contingency.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5
D. PROJECT OVERVIEW:
• This project was completed under budget and on schedule.
Funding
State Funds $0
Strong Schools Bond Funds $1,047,186
Other Funding $0
Total $1,047,186
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $308,648
Construction & Equipment $707,840
Soft Costs Contingency $30,698
Total $1,047,186
Percent of Budget Expended 24.8%
Change Order Contingency
• Starting Contingency Balance $30,698
• Remaining Contingency Balance $30,698
• Percent of Changes 0%
(Change Orders + Construction Change Directives vs.
Original Contract)
Current Phase: Occupancy –August 25, 2009
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA April 14, 2009
Approval by DSA April 22, 2009
Authorize to Bid (2) March 31, 2009
BOE Approval April 14, 2009
Bid Opening May 14, 2009
Award of Contract (1) May 26, 2009
Notice to Proceed June 1, 2009
Substantial Completion August 12, 2009
Planned Occupancy August 25, 2009
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 24
Garland Elementary School
Campus Modernization
A. PROJECT STATUS
The Board of Education voted on August 25, 2009 to approve the
amendment to Garland lease to Stratford School. Therefore, the
district has placed the project on hold.
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10
D. PROJECT OVERVIEW:
• This project has been placed on hold.
Funding
State Funds $0
Strong Schools Bond Funds $22,178,544
Other Funding $0
Total $22,178,544
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $3,830,789
Construction & Equipment $17,485,000
Soft Costs Contingency $862,755
Total $22,178,544
Percent of Budget Expended 1.3%
Current Phase: Schematic Design
Schedule:
Architect Contract (2) October 28, 2008
BOE Approval October 30, 2008
Conceptual Design (2) February 10, 2009
BOE Approval February 24, 2009
Schematic Design (2) June 2, 2009
BOE Approval June 23, 2009
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
Page | 25
Elementary School Teaching Walls
Phase 1 Schools
A. PROJECT STATUS
The district placed this project on hold after review of the
implementation of other classroom improvements, as
recommended by the elementary school principals. This
project has been renamed ‘Elementary Classroom
Improvements’ (see Capital Projects summary above).
B. BUDGET & SCHEDULE SUMMARY
C. BOND PROJECT LIST REFERENCE: 1.9
D. PROJECT OVERVIEW:
• This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary
above).
Funding
State Funds $0
Strong Schools Bond Funds $7,044,987
Other Funding $0
Total $7,044,987
Budget
Salaries and Benefits $0
Supplies $0
Contracts & Services $1,341,394
Construction & Equipment $5,498,498
Soft Costs Contingency $205,095
Total $7,044,987
Percent of Budget Expended 1.6%
Current Phase: On Hold
Schedule:
Architect Contract (2) September 30, 2008
BOE Approval October 14, 2008
Conceptual Design (2) N/A
BOE Approval N/A
Schematic Design (2) N/A
BOE Approval N/A
Submit to DSA N/A
Approval by DSA N/A
Authorize to Bid (2) N/A
BOE Approval N/A
Bid Opening N/A
Award of Contract (1) N/A
Notice to Proceed N/A
Substantial Completion N/A
Planned Occupancy N/A
* Anticipated Dates – Subject to Change
( ) Denotes number of Board of Education Readings
OHS WEST:260388860.1 A-1
EXHIBIT A
PALO ALTO UNIFIED SCHOOL DISTRICT
BOND PROJECT LIST
[Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed
projects will be completed at every site.]
1. ELEMENTARY SCHOOL PROJECTS
Addison Barron Park Briones Duveneck El Carmelo
Escondido Fairmeadow Garland Greendell Hays
Hoover Nixon Ohlone Palo Verde
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Acquire and install modular classrooms, as needed.
4. Expand libraries to accommodate enrollment growth.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
9. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
10. Modernization/replacement of administration/multipurpose/library space.
Numbers Added
A-2
OHS WEST:260388860.1
2. MIDDLE SCHOOL PROJECTS
David Starr Jordan Jane Lathrop Stanford Terman
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
3. Construct extra school-wide storage space.
4. Expand classrooms and classroom wings, library and administration spaces.
5. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
6. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic
equipment; upgrade building infrastructure, including power and water distribution.
9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms;
upgrade pool equipment.
10. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and
driveways.
12. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
A-3
OHS WEST:260388860.1
3. GUNN HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Demolish old library building.
3. Replace temporary classrooms with permanent classrooms.
4. Construct additional restrooms.
5. Construct second gymnasium.
6. Construct new soccer field.
7. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
9. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
10. Improve or provide new security systems, including alarms, lighting, locks, monitoring
systems, fencing, etc.
11. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
12. Replace swimming pool with new 35-meter pool, pool equipment and support structures,
pool decking, bleachers, storage, restrooms, showers, associated equipment.
13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace
athletic equipment.
14. Modernize football stadium, including new bathrooms and concession stands.
A-4
OHS WEST:260388860.1
4. PALO ALTO HIGH SCHOOL PROJECTS
1. Construct new permanent classrooms and classroom buildings to accommodate enrollment
growth and expanded programs.
2. Replace temporary classrooms with permanent classrooms.
3. Construct additional restrooms.
4. Upgrade climate control systems, including passive technologies to conserve energy, such as
shade canopies, energy-efficient windows, window coverings and shade control;
install/replace heating, ventilation and air conditioning.
5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to
accommodate technology upgrades; install/upgrade communications systems.
6. Building exterior and building shell renovation, including seismic structural upgrades and
Americans with Disability Act (ADA) improvements to bring all buildings to current code;
roofs; repainting and/or resurfacing.
7. Classroom and other school facilities modernization and building interior improvements,
including infrastructure and major building system upgrades.
8. Library modernization and building interior improvements, including infrastructure and
major building system upgrades.
9. Renovation or replacement of the Tower Building to accommodate administration,
classroom and program support space.
10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility
improvements; construction of new restrooms; install new roofing; replace doors and
windows; replace gymnasium floors and athletic equipment, bleachers and renovation of
interior. Renovation or replacement of weight training facility.
11. Construct new theater building.
12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing
and storage.
13. Modernize football stadium, including replace bleachers; new bathrooms and concession
stands.
14. Replace and/or improve play fields, including drainage and irrigation, install water meters;
replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic
equipment.
A-5
OHS WEST:260388860.1
5. OTHER DISTRICT-WIDE PROJECTS
Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms
and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and
equipment for all classrooms, athletic facilities and other facilities, as needed.
1. Replace existing or acquire new computers, technology and related equipment on an ongoing
basis.
2. Establish a planned maintenance fund to address maintenance work expected to be needed to
all District facilities on an ongoing basis (other than as may be necessary for current
maintenance, operation or repairs), in order to implement the District’s comprehensive facilities
maintenance plan.
3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease-
purchase arrangements, or execute purchase option under a lease for any of these authorized
facilities.
4. If and as opportunities become available, and to the extent the Board of Education determines
that bond funds are available for the purpose, acquisition of land and other interests in real
property for future school buildings and other District facilities, and construction of such
facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise
listed.
5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including
off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard
courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field
equipment and facilities (including nets, basketball standards, goals and goalposts, backstops),
field lighting, etc.
6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS
1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead,
etc., where necessary.
2. Address unforeseen conditions revealed by construction/modernization (including plumbing
or gas line breaks, dry rot, seismic, structural, etc.).
3. Other improvements required to comply with existing building codes, including the Field Act,
and access requirements of the Americans with Disabilities Act (ADA).
4. Site preparation/restoration in connection with new construction, renovation or remodeling,
or installation or removal of relocatable classrooms, including ingress and egress, demolition
of existing structures, removing, replacing, or installing irrigation and drainage, utility lines
(such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and
landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any
necessary easements, licenses, or rights of way to the property.
5. Rental or construction of storage facilities and other space on an interim basis, as needed to
accommodate construction materials, equipment, and personnel, and interim classrooms
(including relocatables) for students and school functions or other storage for classroom
materials displaced during construction.
A-6
OHS WEST:260388860.1
7. RENOVATION/MODERNIZATION (DEFINED)
For purposes of the Bond Project List, renovation and modernization projects are intended to
restore the building systems and infrastructure, weather protections, finishes, and technology, or
reallocate and reorganize space, to a condition that will provide a sustainable, functional educational
and administrative environment for future years, comparable to new construction.
Renovation projects may include, but are not limited to nor necessarily encompass, all of the
following, depending upon the age, condition and needs of each particular school facility:
1. upgrade electrical, communication, fire alarm, and similar building systems as well as main
power service and distribution, which may include active and passive solar power and
heating system acquisition, installation and construction
2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply,
meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within
buildings and sites and to connect with city supply and drainage systems
3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient
heating and air cooling systems (HVAC), including installing energy management systems
(EMS);
4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and
fixtures, as necessary;
5. Repair, modify and construct structural elements of the existing structure as necessary;
6. Replace or repair aging roofs with similar materials or District standard materials;
7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes,
doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces
(including white boards, marker boards, tack boards, television mounts, scoreboards, fire
extinguishers, kitchen cabinets/equipment, etc.);
8. Upgrade, modify and construct restroom facilities;
9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24
requirements;
10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood
siding, paint, etc.); replace doors and windows
11. Modify, expand, separate, convert and construct school support areas; staff work and lunch
areas; and educational areas to provide adequate, functional environments;
12. Modify, replace and construct functional components of altered or replaced building
components (including rainwater leaders, fascias, mansards, etc.);
For any project involving renovation, modernization, remodeling or rehabilitation of a
building or the major portion of a building, the District may proceed with new replacement
construction instead (including any necessary demolition), if the Board of Education
determines that replacement and new construction is more practical than rehabilitation and
renovation, considering the building’s age, condition, expected remaining life, comparative
cost, and other relevant factors.