Loading...
Monthly Reports 2010-04 (Apr) MMOONNTTHHLLYY  PPRROOGGRREESSSS  RREEPPOORRTT     Through  April 2010      Current Strong Schools Bond  Capital Improvement Projects  Prepared by     O’Connor Construction Management, Inc.  &  Gilbane Building Company  Page | 2   TABLE OF CONTENTS    Executive Summary         page 3      Attachment 1 – Consolidated Expenditure Report    Attachment 2 – Master Project Schedule     Capital Projects     High School Master Plan        page 6    Gunn High School – New Classroom Buildings A & B     page 7    Gunn High School – Parking and Drop‐off Sitework Improvement    page 8    Gunn High School – New Gymnasium       page 9    Palo Alto High School – Stadium Field Renovation     page 10    Palo Alto High School – Multi‐use Field      page 11    Palo Alto High School – Classroom Building and Media Arts    page 12    Palo Alto High School – Theater and Associated Site Improvements    page 13    Jordan Middle School        page 14    J.L. Stanford Middle School       page 15    Terman Middle School        page 16    Fairmeadow Elementary School       page 17    Ohlone Elementary School        page 18    Elementary Classroom Improvements      page 19    Inactive Capital Projects    Gunn High School – Industrial Arts Renovation     page 20    Gunn High School – Aquatic Center       page 21    Middle School Pre‐Design        page 22    Middle School Interim Classrooms       page 23    Garland Elementary School       page 24    Elementary School Teaching Walls – Phase 1 Schools     page 25    Appendix    Exhibit A – Bond Project List        Page | 3   EXECUTIVE SUMMARY  CAPITAL PROJECTS   High School Master Plan  Gates + Associates held meetings with the landscape subcommittees to present the final draft landscape master  plans for each campus. After review by the campuses and community in May, they will be presented to the board  for approval in June.     The Mitigated Negative Declaration (MND) for Gunn high school was presented to the Board of Education (BOE) on  April 27, 2010 and is anticipated to be approved at the May 11, 2010 BOE meeting.    Gunn High School – New Classroom Buildings A & B  DLM is anticipated to submit 50% construction development drawings on May 4, 2010. To make way for  construction of the new classroom building, approximately 26 portables need to be relocated.  Rodan Builders, Inc.  will begin the portable relocation project on June 14, 2010 and complete the project for fall semester occupancy.   DLM continues to prepare contract documents for the new buildings and is expecting to submit to DSA at the end  of June 2010.  Gunn High School – Parking and Drop‐off Sitework Improvement  A revised master plan project list, which included the parking and drop‐off project to include a drop‐off area from  Miranda Ave, was approved by the BOE on April 6, 2010. The future parking and drop‐off improvements design will  continue after the BOE adopts the MND in May.  Gunn High School – New Gymnasium  DLM continues to develop construction documents and will submit 50% construction development drawings in  early May 2010.  Palo Alto High School – Stadium Field Renovation  DLM and the stadium design committee met to review and refine plans for the stadium improvements. The  improvements include a new concession stand, bathrooms, and an expansion to 2,464 seats for home and visitor’s  side bleachers. The project will also coordinate with the surrounding corporation yard for maintenance functions  and the Churchill entrance.  Palo Alto High School – Multi‐use Field  Valley Crest Landscape Development was awarded the contract at the BOE meeting on April 6, 2010.  Construction  commences on June 1, 2010, after the baseball and softball seasons conclude. As part of this project, the Churchill  parking lot will receive some improvements, with construction to occur after graduation and before fall semester.   The fields and dugout work has a completion date of January 31, 2010, which includes a turf establishment and  growing period.  Palo Alto High School – Classroom Building and Media Arts Building  On April 6, 2010 the BOE approved the award of a construction contract to Rodan Builders, Inc. for the portable  relocation project. Portable relocation begins on June 14, 2010 and will be complete for occupancy by the fall  semester. DLM continues to prepare construction documents (CD) for the new buildings and anticipates  submission of the 50% CDs to the district on May 4, 2010.   Palo Alto High School – Theater and Associated Site Improvements  DLM and the theater subcommittee requested approval from the FSC to develop conceptual designs on two  preferred schemes, including the incorporation of a fly tower and orchestra pit.  On April 7, 2010 the FSC approved  having DLM develop concepts and massing studies for a theater configuration on two recommended schemes.   DLM followed up with the theater subcommittee to review the developed massing studies on April 29, 2010.  Page | 4   Jordan Middle School  AEDIS presented refined classroom wing and cafetorium building design to the bond advisory committee and to  the community before returning to the BOE on April 27, 2010 for approval.  The BOE approved schematic design  on April 27, 2010 and authorized staff to proceed with design development.  AEDIS will meet with the bond  advisory committee in May to review with the group the upcoming phases before summer break.  J.L. Stanford Middle School  AEDIS met with the bond advisory committee on April 26, 2010 to review schematic design for the new building,  classroom improvements, and landscape design.  AEDIS also conducted a community meeting on April 26, 2010 to  receive feedback and input on the planned projects.  Schematic design approval is anticipated to be discussed at  the May 25, 2010 board meeting.  Terman Middle School  AEDIS presented the plans for the administration/library expansion, new drama classroom, cafetorium/kitchen  improvements and other school‐wide improvements at a community meeting on April 21, 2010 in order to receive  input and comments from parents, PTA members and neighborhood association groups.  AEDIS is scheduled to  present the schematic design package to the BOE on May 11, 2010 for discussion, with approval anticipated on  May 25, 2010.    Fairmeadow Elementary School – New Classroom Building and Modernization  The Board of Education approved conceptual design for Fairmeadow elementary school on April 6, 2010.  Gelfand  Partners kicked off schematic design on April 28, 2010 by meeting with various user groups.  Gelfand partners will  continue to meet with user groups and the site committee through to the end of school.    Ohlone Elementary School – New Classroom Building and Modernization  DSA continues its review of the Ohlone classroom building and modernization project, which is expected to be  completed no later than August 2010. Coulter Construction is scheduled to begin work immediately following  school dismissal for summer on relocating the portables to make way for the construction of the two story building  scheduled to begin late fall.  Pre‐qualification proposals are under review received from 13 contractors seeking to  bid on the new building and modernization project.  Elementary Classroom Improvements  The Elementary Classroom Improvements project was approved by BOE on April 27, 2010.  The classroom  improvements project established budgets for each elementary school campus to receive a technology wall, new  lighting, new windows and shades, ventilation improvements and ceiling tiles. Gelfand Partners will be the  architect for this project, and design work will commence after the board approves their contract.  INACTIVE CAPITAL PROJECTS   Gunn High School – Industrial Arts Addition & Renovation  Of the $5,576,500 project budget, 84.6% or $4,720,037 was expended.  Approved change orders were $208,756,  which is approximately 59.8% of the $349,000 construction contingency.  Gunn High School – Aquatic Center   Of the $5,013,750 project budget, 96.6%, or $4,844,070 was expended.  Approved change orders were $194,739,  which is approximately 49.9% of the $389,887 construction contingency.    Middle Schools Pre‐Design – Jordan, J.L. Stanford and Terman  AEDIS presented recommended concept plans for each campus to the Board of Education on June 23 for  discussion and received approval on September 8 by the Board of Education to move into schematic design.       Page | 5   Middle Schools Interim Housing – Jordan and J.L. Stanford  Contracts were awarded to Coulter Construction for Jordan Middle School and Mark Electric for Stanford Middle  School following Board of Education approval on May 26, 2009.  Both contractors started work on June 15, 2009  and were completed on August 3, 2009 at Jordan and August 12, 2009 at Stanford.  Of the $1,047,186 project  budget, 25%, or $236,696 has been expended. Pending Change Orders are currently estimated to be a deduct of  ($10,331), which is approximately 0% of the $30,698 construction contingency.  Garland Elementary School Renovation  The Board of Education voted on August 25, 2009 to approve the amendment to Garland lease to Stratford School.   Therefore, the district has placed the project on hold.  Elementary School Teaching Walls – Phase 1 Schools  The district placed this project on hold after review of the implementation of other classroom improvements, as  recommended by the elementary school principals.  This project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).     Board Actions in April  April 6, 2010  Consent 6 – Approval of Updated Project List for Gunn High School Master Plan    Consent 7 – Approval of Air Conditioning of Existing Buildings Project at Gunn High School and Authorization to  Issue Addendum No. 7 for Design Services to DLM Architecture    Action 17 – Approval of Conceptual Design and Project for Fairmeadow Elementary School    Action 19 – Authorization to Award Contract for Construction of the Palo Alto High School Multi‐use Fields    Action 20 – Authorization to Award Contract for Site Work and Relocation of Modular Classroom Buildings to  Accommodate Construction at Palo Alto High School    Action 21 – Authorization to Award Contract for Site Work and Relocation of Modular Classroom Buildings to  Accommodate Construction at Gunn High School    April 27, 2010  Consent 6 – Authorization to Enter into Addendum No. 7 with Gelfand Partners for Design Services at Fairmeadow  Elementary School    Action 10 – Approval of Schematic Design for Jordan Middle School    Action 14 – Strong Schools Bond Plan and Budget for Elementary Schools  A B C C / A B - C C / B A - BGunn High School - High School Master Plan 145,000 127,371 85,996 59.3% 41,375 67.52% 17,629Gunn High School 1 - Aquatic Center 5,013,750 4,935,692 4,854,830 96.8% 80,862 98.36% 78,058Gunn High School 2 - I.A 5,511,500 5,153,175 4,841,935 87.9% 311,240 93.96% 358,325Gunn High School 3 - AD2- close out 5,777 5,777 5,777 100.0% 0 100.00% 0Gunn High School 4 - New classroom A & B 24,120,000 2,195,034 562,577 2.3% 1,632,457 25.63% 21,924,966Gunn High School 5 - Parking & Drop Off improvements 3,940,000 217,770 3,019 0.1% 214,751 1.39% 3,722,230Gunn High School 6- New/Auxiliary Gymnasium 13,830,000 932,150 182,835 1.3% 749,315 19.61% 12,897,850Gunn High School 7- A/C 0 0 0 0.0% 0 0.00% 0Gunn High School - Reserved 23,545,045 0 0 0.0% 0 0.00% 23,545,045Palo Alto High Schools - High School Master Plan 145,000 130,597 90,699 62.6% 39,898 69.45% 14,403Palo Alto High School 1 - Bleacher 1,358,437 140,810 115,810 8.5% 25,000 82.25% 1,217,627Palo Alto High School 2 - Multi-Use Field (Multi-Fund) 3,002,063 482,999 256,858 8.6% 226,141 53.18% 2,519,064Palo Alto high School 3 - New classroom & Media Art Building 34,220,000 2,559,228 569,720 1.7% 1,989,508 22.26% 31,660,772Palo Alto High School 4 - New Theater 17,720,000 1,026,210 7,330 0.0% 1,018,880 0.71% 16,693,790Palo Alto High School - Reserved 42,348,045 0 0 0.0% 0 0.00% 42,348,045Jordan Middle School - Middle School Pre-Design 33,665 19,718 17,413 51.7% 2,305 88.31% 13,947Jordan Middle Schools 1- Interim Classrooms 600,342 186,569 157,893 26.3% 28,676 84.63% 413,773Jordan Middle School 2 17,943,194 1,583,569 249,279 1.4% 1,334,290 15.74% 16,359,625Jordan Middle School - Reserved 0 0 0 0.0% 0 0.00% 0J.L.S Middle School - Middle School Pre-Design 33,669 19,627 17,995 53.4% 1,632 91.68% 14,042J.L.S Middle School 1 - Interim Classrooms 446,844 351,408 312,937 70.0% 38,471 89.05% 95,436 J.L.S Middle School 2 17,184,699 1,432,112 186,682 1.1% 1,245,430 13.04% 15,752,587 J.L.S Middle School - Reserved 0 0 0 0.0% 0 0.00% 0Terman Middle School - Middle School Pre- Design 33,666 19,627 18,010 53.5% 1,617 91.76% 14,039Terman Middle School 1 12,850,071 1,187,625 157,461 1.2% 1,030,164 13.26% 11,662,446Terman Middle School - Reserved 0 0 0 0.0% 0 0.00% 0PAUSD Elementary Schools - Elementary Growth Plan 145,000 62,700 55,560 38.3% 7,140 88.61% 82,300Garland Elementary School 1- Phase I 22,178,544 281,279 280,113 1.3% 1,166 99.59% 21,897,265Fairmeadow Elementary School 1- Phase I 9,327,500 27,500 25,000 0.3% 2,500 90.91% 9,300,000Ohlone Elementary School 1- Phase I 11,667,965 1,448,811 891,700 7.6% 557,111 61.55% 10,219,154 Elementary Schools 1 - Elem Teaching Wall Project 7,044,987 139,822 113,352 1.6% 26,470 81.07% 6,905,165Elementary Schools - Reserved 48,314,283 0 0 0.0% 0 0.00% 48,314,283PAUSD - Program Admin. ** 3,353,108 2,700,233 1,895,640 56.5% 804,593 70.20% 652,875PAUSD - Technology 5,995,689 2,286,331 2,079,428 34.7% 206,903 90.95% 3,709,358PAUSD - Technology -Reserved 7,911,676 0 0 0.0% 0 0.00% 7,911,676PAUSD - Reserved 6,335,945 0 0 0.0% 0 0.00% 6,335,945Total346,305,464 29,653,744 18,035,849 11,617,895 316,651,720Prepared by: Business Services Department based on QSS accounting SystemCommittedBudgetSchool Name - Project NamePercent of Budget ExpendedPalo Alto Unified School DistrictStrong Schools Bond4/30/2010Percent of ExpendedContract BalanceExpenditures Budget Balance Activity IDPhaseActivity NameOriginalDurationStartFinishDuration %CompleteGunn- IndusGunn- Industrial AGunn- Industrial Arts Renovation43101-Oct-08 A26-May-1095.59%Gunn - New Gunn - New ClassrGunn - New Classroom Building107520-Apr-09 A03-Jun-1325.02%Gunn - ParkiGunn - Parking andGunn - Parking and Drop Off102101-Sep-09 A30-Jul-1316.94%Gunn New GGunn New GymnasGunn New Gymnasium92021-Apr-09 A30-Oct-1229.13%Paly - Home Paly - Home Side BPaly - Home Side Bleachers64417-Aug-09 A15-Feb-1227.17%Paly - Multi UPaly - Multi Use FiePaly - Multi Use Field Improvements58703-Nov-08 A01-Feb-1166.27%Paly - New CPaly - New ClassroPaly - New Classroom Building & Media Arts111820-Apr-09 A01-Aug-1324.06%Paly - New TPaly - New TheaterPaly - New Theater and Sitework149709-Sep-09 A26-May-1511.62%Jordan New Jordan New ClassrJordan New Classroom Wing & Modernizat...117103-Nov-08 A29-Apr-1333.22%Stanford NewStanford New ClasStanford New Classroom Wing114403-Nov-08 A28-Mar-1333.57%Terman AdmTerman Admin WinTerman Admin Wing Addition & Modernizat...121303-Nov-08 A03-Jul-1331.74%Garland SchGarland School MoGarland School Modernization52303-Nov-08 A30-Apr-10100%FairmeadowFairmeadow ElemeFairmeadow Elementary School119414-Dec-09 A01-Aug-1328.81%Ohlone New Ohlone New ClassOhlone New Classroom Wing97703-Nov-08 A31-Jul-1239.82%Teaching WaTeaching Walls CaTeaching Walls Casework17206-Apr-09 A28-Sep-09 A100%NDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJA2009201020112012201320142015PALO ALTO UNIFIED SCHOOL DISTRICTSTRONG SCHOOLS BOND PROGRAMMASTER SCHEDULE SUMMARY DesignPlanningBid and AwardConstructionDSACloseoutMilestonePage 1 of 1TASK filter: All Activities(c) Primavera Systems, Inc. Page | 6   High School Master Plan  Palo Alto HS and Gunn HS  A. PROJECT STATUS    Gates + Associates held meetings with the landscape  subcommittees to present the final draft landscape master plans  for each campus.  After review by the campuses and community in  May, they will be presented to the board for approval in June.      The Mitigated Negative Declaration (MND) for Gunn high school  was presented to the Board of Education (BOE) on April 27, 2010  and is anticipated to be approved on consent at the May 11, 2010  BOE meeting.                 B. BUDGET & SCHEDULE SUMMARY                                              C. BOND PROJECT LIST REFERENCE: 3.1 – 3.14, 4.1 – 4.14    D. PROJECT OVERVIEW:  • Final MND documents for Gunn high school scheduled to be adopted by the BOE in May.     Funding  State Funds $0  Strong Schools Bond Funds $290,000  Other Funding $0  Total $290,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $279,521  Construction & Equipment $0  Soft Costs Contingency $9,479  Total $290,000    Percent of Budget Expended 60.9%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Initial Master Plan Approval (2) September 8, 2009  BOE Approval September 22, 2009    Paly CEQA Approval (2) February 9, 2010  BOE Approval February 23, 2010    Gunn Master Plan Update (2) March 23, 2010  BOE Approval April 6, 2010    Gunn CEQA Approval (2) April 27, 2010   BOE Approval May 11, 2010 *    Paly Master Plan Update (2) June 1, 2010 *    Landscape Master Plan Approval June 22, 2010 *    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 7   Gunn High School  New Classroom Buildings A & B  A. PROJECT STATUS     DLM is anticipated to submit 50% construction development  drawings on May 4, 2010. To make way for construction of the new  classroom building, approximately 26 portables need to be  relocated.  Rodan Builders, Inc. will begin the portable relocation  project on June 14, 2010 and complete the project for fall semester  occupancy.  DLM continues to prepare contract documents for the  new buildings and is expecting to submit to DSA at the end of June  2010.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.3, 3.4    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.     Funding  State Funds $0  Strong Schools Bond Funds $24,120,000  Other Funding $0  Total $24,120,000    Budget  Salaries and Benefits $0  Supplies $50,000  Contracts & Services $4,315,728  Construction & Equipment $19,590,000  Soft Costs Contingency $164,272  Total $24,120,000    Percent of Budget Expended 2.3%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA July 1, 2010*     Approval by DSA March 17, 2011 *    Authorize to Bid (2) January 11, 2011 *  BOE Approval January 25, 2011*    Bid Opening April 7, 2011 *    Award of Contract (1) April 26, 2011 *    Notice to Proceed May 5, 2011*    Substantial Completion November 23, 2012*    Planned Occupancy June 3, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 8   Gunn High School  Parking and Drop‐off Sitework Improvement  A. PROJECT STATUS    A revised master plan project list, which included the parking  and drop‐off project to include a drop‐off area from Miranda  Ave, was approved by the BOE on April 6, 2010. The future  parking and drop‐off improvements design will continue after  the BOE adopts the MND in May.                   B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 5.5    D. PROJECT OVERVIEW:  • This project will re‐commence after completion of CEQA process.     Funding  State Funds $0  Strong Schools Bond Funds $3,940,000  Other Funding $0  Total $3,940,000    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $883,978  Construction & Equipment $2,934,840  Soft Costs Contingency $121,182  Total $3,940,000    Percent of Budget Expended 0.1%  Current Phase: Conceptual Design    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 28, 2010*  BOE Approval September 22, 2010*    Schematic Design (2) December 17, 2010*  BOE Approval December 27, 2010*    Submit to DSA November 2, 2011*     Approval by DSA June 5, 2012 *    Authorize to Bid (2) June 12, 2012*  BOE Approval June 26, 2012*    Bid Opening September 24, 2012 *    Award of Contract (1) October 29, 2012*    Notice to Proceed December 3, 2012*    Substantial Completion June 11, 2013*    Planned Occupancy August, 2013*    * Anticipated Dates – Subject to Change  ()Denotesnumber ofBoard of Education Readings Page | 9   Gunn High School  New Gymnasium  A. PROJECT STATUS    DLM continues to develop construction documents and will  submit 50% construction development drawings in early May  2010.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.4, 3.5, 3.13    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget.     Funding  State Funds $0  Strong Schools Bond Funds $13,830,000  Other Funding $0  Total $13,830,000    Budget  Salaries and Benefits $0  Supplies $40,000  Contracts & Services $2,596,521  Construction & Equipment $11,109,450  Soft Costs Contingency $84,029  Total $13,830,000    Percent of Budget Expended 1.3%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA July 1, 2010*     Approval by DSA March 17, 2011*    Authorize to Bid (2) January 11, 2011*  BOE Approval January 25, 2011*    Bid Opening March 24, 2011*    Award of Contract (1) April 12, 2011*    Notice to Proceed April 21, 2011*    Substantial Completion September 21, 2012*    Planned Occupancy October 12, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 10   Palo Alto High School  Football Stadium Renovation  A. PROJECT STATUS    DLM and the stadium design committee met to review  and refine plans for the stadium improvements. The  improvements include a new concession stand,  bathrooms, and an expansion to 2,464 seats for home  and visitor’s side bleachers. The project will also  coordinate with the surrounding corporation yard for  maintenance functions and the Churchill entrance.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.13    D. PROJECT OVERVIEW:  • Programming in progress     Funding  State Funds $0  Strong Schools Bond Funds $1,358,473  Other Funding $0  Total $1,358,437    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $127,622  Construction & Equipment $1,230,815  Soft Costs Contingency $0  Total $1,358,437    Percent of Budget Expended 8.5%  Current Phase: Programming   Schedule:  Architect Contract (2) January 26, 2010  BOE Approval February 9, 2010    Conceptual Design (2) June 1, 2010*  BOE Approval June 22, 2010*    Schematic Design (2) August 24, 2010*  BOE Approval September 14, 2010*    Submit to DSA December 15, 2010*     Approval by DSA April 1, 2011*    Authorize to Bid (2) March 28, 2011*  BOE Approval April 18, 2011*    Bid Opening May 16, 2011*    Award of Contract (1) May 26, 2011*    Notice to Proceed June 2, 2011*    Substantial Completion January 9, 2012*    Planned Occupancy January 31, 2012*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 11   Palo Alto High School  Multi‐Use Field  A. PROJECT STATUS     Valley Crest Landscape Development was awarded the contract at  the BOE meeting on April 6, 2010.  Construction commences on  June 1, 2010, after the baseball and softball seasons conclude. As  part of this project, the Churchill parking lot will receive some  improvements, with construction to occur after graduation and  before fall semester.  The fields and dugout work has a  completion date of January 31, 2010, which includes a turf  establishment and growing period.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.14    D. PROJECT OVERVIEW:  • Project awarded on April 6, 2010 and will begin construction on June 1, 2010     Funding  State Funds $0  Strong Schools Bond Funds $3,002,063  Other Funding $1,075,991  Total $4,078,054    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $673,020  Construction & Equipment $3,312,683  Soft Costs Contingency $92,351  Total $4,078,054    Percent of Budget Expended 8.6%  Current Phase: Bid & Award   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) December 9, 2009  BOE Approval January 13, 2009    Schematic Design (2) February 24, 2009  BOE Approval March 17, 2009    Submit to DSA March 19, 2009     Approval by DSA September 30, 2009    Authorize to Bid (2) January 26, 2010  BOE Approval February 9, 2010    Bid Opening March 16, 2010    Award of Contract (1) April 6, 2010    Notice to Proceed May 3, 2010*    Substantial Completion November 30, 2010*    Planned Occupancy February 1, 2010*    * Anticipated Dates – Subject to Change  ( ) Denotesnumber of Board of Education Readings  Page | 12   Palo Alto High School  Classroom Building and Media Arts  A. PROJECT STATUS     On April 6, 2010 the BOE approved the award of a construction  contract to Rodan Builders, Inc. for the portable relocation project.  Portable relocation begins on June 14, 2010 and will be complete for  occupancy by the fall semester. DLM continues to prepare  construction documents (CD) for the new buildings and anticipates  submission of the 50% CDs to the district on May 4, 2010.                 B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.1 ‐ 4.3    D. PROJECT OVERVIEW:  • Project is currently proceeding on schedule and within budget. Funding  State Funds $0  Strong Schools Bond Funds $34,220,000  Other Funding $0  Total $34,220,000    Budget  Salaries and Benefits $0  Supplies $50,000  Contracts & Services $6,067,996  Construction & Equipment $27,876,384  Soft Costs Contingency $225,620  Total $34,220,000    Percent of Budget Expended 1.7%  Current Phase: Construction Documents    Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) September 8, 2009  BOE Approval September 22, 2009    Schematic Design (2) January 12, 2010  BOE Approval January 26, 2010    Submit to DSA July 1, 2010*     Approval by DSA March 17, 2011*    Authorize to Bid (2) January 11, 2011*  BOE Approval January 25, 2011*    Bid Opening April 7, 2011*    Award of Contract (1) April 26, 2011*    Notice to Proceed May 5, 2011*    Substantial Completion March 25, 2013*    Planned Occupancy August 1, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 13   Palo Alto High School  Theater and Associated Site Improvements  A. PROJECT STATUS    DLM and the theater subcommittee requested approval from the  FSC to develop conceptual designs on two preferred schemes,  including the incorporation of a fly tower and orchestra pit.  On  April 7, 2010 the FSC approved having DLM develop concepts and  massing studies for a theater configuration on two recommended  schemes.  DLM followed up with the theater subcommittee to  review the developed massing studies on April 29, 2010.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 4.11    D. PROJECT OVERVIEW:  • Programming in progress. Funding  State Funds $0  Strong Schools Bond Funds $17,720,000  Other Funding $0  Total $17,720,000    Budget  Salaries and Benefits $0  Supplies $50,000  Contracts & Services $3,276,077  Construction & Equipment $14,284,700  Soft Costs Contingency $109,223  Total $109,223    Percent of Budget Expended 0.0%  Current Phase: Planning   Schedule:  Architect Contract (2) March 31, 2009  BOE Approval April 14, 2009    Conceptual Design (2) June 1, 2010*  BOE Approval June 22, 2010*    Schematic Design (2) December 7, 2010*  BOE Approval December 14, 2010*    Submit to DSA August, 2011*     Approval by DSA June, 2012*    Authorize to Bid (2) August, 2012*  BOE Approval August, 2010*    Bid Opening October, 2012*    Award of Contract (1) November, 2012*    Notice to Proceed February, 2013*    Substantial Completion March, 2015*    Planned Occupancy August, 2015*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 14   Jordan Middle School  A. PROJECT STATUS     AEDIS presented refined classroom wing and cafetorium  building design to the bond advisory committee and to the  community before returning to the BOE on April 27, 2010 for  approval.  The BOE approved schematic design on April 27,  2010 and authorized staff to proceed with design  development.  AEDIS will meet with the bond advisory  committee in May to review with the group the upcoming  phases before summer break.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.6 – 2.8, 2.10 – 2.12, 6.3 – 6.5    D. PROJECT OVERVIEW:  • Board approval for schematic design received on April 27, 2010. Funding  State Funds $0  Strong Schools Bond Funds $17,943,191  Other Funding $0  Total $17,943,191    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,432,480  Construction & Equipment $14,014,500  Soft Costs Contingency $496,214  Total $17,943,194    Percent of Budget Expended 1.4%  Current Phase: Design Development    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) March 23, 2010  BOE Approval April 27, 2010    Submit to DSA October 15, 2010*     Approval by DSA June 22, 2011*    Authorize to Bid (2) June 27, 2011*  BOE Approval July 8, 2011*    Bid Opening August 10, 2011*    Award of Contract (1) August 25, 2011*    Notice to Proceed September 21, 2011*    Substantial Completion March 21, 2013*    Planned Occupancy August, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 15   J.L. Stanford Middle School  A. PROJECT STATUS    AEDIS met with the bond advisory committee on April  26, 2010 to review schematic design for the new  building, classroom improvements, and landscape  design.  AEDIS also conducted a community meeting  on April 26, 2010 to receive feedback and input on the  planned projects.  Schematic design approval is  anticipated to be discussed at the May 25, 2010 board  meeting.                      B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.3, 2.5 – 2.8, 2.11 – 2.12, 6.4, 6.5    D. PROJECT OVERVIEW:  • Schematic design approval is scheduled to be discussed at May 25, 2010 board meeting. Funding  State Funds $0  Strong Schools Bond Funds $17,184,697  Other Funding $0  Total $17,184,697    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,281,600  Construction & Equipment $13,406,000  Soft Costs Contingency $497,099  Total $17,184,699    Percent of Budget Expended 1.1%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) May 25, 2010*  BOE Approval June 1, 2010*    Submit to DSA November 25, 2010*     Approval by DSA July 12, 2011*    Authorize to Bid (2) July 6, 2011*  BOE Approval July 19, 2011*    Bid Opening September 7, 2011*    Award of Contract (1) September 26, 2011*    Notice to Proceed October 19, 2011*    Substantial Completion February 7, 2013*    Planned Occupancy March 28, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 16   Terman Middle School  A. PROJECT STATUS    AEDIS presented the plans for the administration/library  expansion, new drama classroom, cafetorium/kitchen  improvements and other school‐wide improvements at a  community meeting on April 21, 2010 in order to receive input  and comments from parents, PTA members and neighborhood  association groups.  AEDIS is scheduled to present the  schematic design package to the BOE on May 11, 2010 for  discussion, with approval anticipated on May 25, 2010.                   B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.8, 2.11 – 2.12    D. PROJECT OVERVIEW:  • Schematic design approval will be discussed at the May 11, 2010 board meeting. Funding  State Funds $0  Strong Schools Bond Funds $12,850,071  Other Funding $0  Total $12,850,071    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,411,150  Construction & Equipment $10,096,569  Soft Costs Contingency $342,352  Total $12,850,071    Percent of Budget Expended 1.2%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) May 11, 2010*  BOE Approval May 25, 2010*    Submit to DSA November 29, 2010*     Approval by DSA July 26, 2011*    Authorize to Bid (2) July 27, 2011*  BOE Approval August 10, 2011*    Bid Opening September 19, 2011*    Award of Contract (1) October 4, 2011*    Notice to Proceed October 5, 2011*    Substantial Completion March 26, 2013*    Planned Occupancy July 3, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 17   Fairmeadow Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    The Board of Education approved conceptual design for Fairmeadow  elementary school on April 6, 2010.  Gelfand Partners kicked off  schematic design on April 28, 2010 by meeting with various user  groups.  Gelfand partners will continue to meet with user groups and  the site committee through to the end of school.               B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Board approved conceptual design on April 6, 2010. Funding  State Funds $0  Strong Schools Bond Funds $290,000  Other Funding $0  Total $290,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $279,521  Construction & Equipment $0  Soft Costs Contingency $9,479  Total $290,000    Percent of Budget Expended 0.3%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) October 13, 2009  BOE Approval October 27, 2009    Conceptual Design (2) March 23, 2010  BOE Approval April 6, 2010    Schematic Design (2) August 24, 2010*  BOE Approval September 14, 2010*    Submit to DSA March 4, 2011*     Approval by DSA October 28, 2011*    Authorize to Bid (2) December 9, 2011*  BOE Approval December 16, 2011*    Bid Opening January 31, 2012*    Award of Contract (1) October 9, 2012*    Notice to Proceed October 19, 2012*    Substantial Completion April 2, 2013*    Planned Occupancy August 13, 2013*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 18   Ohlone Elementary School  New Classroom Building and Modernization  A. PROJECT STATUS    DSA continues its review of the Ohlone classroom building and  modernization project, which is expected to be completed no  later than August 2010. Coulter Construction is scheduled to begin  work immediately following school dismissal for summer on  relocating the portables to make way for the construction of the  two story building scheduled to begin late fall.  Pre‐qualification  proposals are under review received from 13 contractors seeking  to bid on the new building and modernization project.                   B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1 – 1.2, 1.4 – 1.10    D. PROJECT OVERVIEW:  • Gelfand submitted to DSA on November 24, 2009 and will schedule the backcheck appointment in May. Funding  State Funds $0  Strong Schools Bond Funds $11,667,965  Other Funding $0  Total $11,667,965    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $2,221,174  Construction & Equipment $9,181,991  Soft Costs Contingency $264,800  Total $11,667,965    Percent of Budget Expended 7.6%  Current Phase: DSA Review   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) March 3, 2009  BOE Approval March 17, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA November 24, 2009     Approval by DSA July 30, 2010 *    Authorize to Bid (2) September 1, 2010*  BOE Approval September 9, 2010*    Bid Opening November 3, 2010*    Award of Contract (1) November 16, 2010*    Notice to Proceed December 6, 2010*    Substantial Completion January 31, 2011*    Planned Occupancy August 25, 2011*    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 19   Elementary Classroom Improvements  A. PROJECT STATUS    The Elementary Classroom Improvements project was approved by BOE on April 27, 2010.  The classroom  improvements project established budgets for each elementary school campus to receive a technology wall,  new lighting, new windows and shades, ventilation improvements and ceiling tiles. Gelfand Partners will be  the architect for this project, and design work will commence after the board approves their contract.                 B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.5 – 1.7    D. PROJECT OVERVIEW:  • Board of Education approved project budgets for the elementary schools on April 27, 2010.  Funding  State Funds $0  Strong Schools Bond Funds $8,887,522  Other Funding $0  Total $8,887,522    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,193,721  Construction & Equipment $7,488,706  Soft Costs Contingency $205,095  Total $8,887,522    Percent of Budget Expended 0.78%*  *Reflects Teaching Wall Project expenditure.    Current Phase: Planning   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) TBD  BOE Approval TBD    Schematic Design (2) TBD  BOE Approval TBD    Submit to DSA TBD     Approval by DSA TBD    Authorize to Bid (2) TBD   BOE Approval TBD    Bid Opening TBD    Award of Contract (1) TBD    Notice to Proceed TBD    Substantial Completion TBD    Planned Occupancy TBD    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 20   Gunn High School  Industrial Arts Addition and Renovation  A. PROJECT STATUS    Of the $5,576,500 project budget, 84.6% or $4,720,037 was  expended.  Approved change orders were $208,756, which is  approximately 59.8% of the $349,000 construction contingency.                       B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.1, 3.7, 3.11    D. PROJECT OVERVIEW:  • The building occupied as scheduled, and the project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,576,500  Other Funding $0  Total $5,576,500    Budget  Salaries and Benefits $0  Supplies $10,358  Contracts & Services $1,216,066  Construction & Equipment $4,300,350  Soft Costs Contingency $49,726  Total $5,576,500    Percent of Budget Expended 87.9%    Change Order Contingency  • Starting Contingency Balance $349,000  • Remaining Contingency Balance $140,244  • Percent of Changes 59.8%  (Change Orders + Construction Change Directives vs.  Original Contract)    Current Phase: Occupancy –January 4, 2010    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA June 17, 2008     Approval by DSA December 24, 2008    Authorize to Bid (2) October 14, 2008  BOE Approval October 28, 2008    Bid Opening December 16, 2008    Award of Contract (1) December 24, 2008    Notice to Proceed January 6, 2009    Substantial Completion November 25, 2009    Planned Occupancy January 4, 2010    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 21   Gunn High School  Aquatic Center  A. PROJECT STATUS    Of the $5,013,750 project budget, 96.6%, or $4,844,070 was  expended.  Approved change orders were $194,739, which is  approximately 49.9% of the $389,887 construction contingency.              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 3.12    D. PROJECT OVERVIEW:  • This project completed within budget. Funding  State Funds $0  Strong Schools Bond Funds $5,013,750  Other Funding $0  Total $5,013,750    Budget  Salaries and Benefits $0  Supplies $7,684  Contracts & Services $679,284  Construction & Equipment $4,323,742  Soft Costs Contingency $3,040  Total $5,013,750    Percent of Budget Expended 96.8%    Change Order Contingency  • Starting Contingency Balance $389,887  • Remaining Contingency Balance $195,148  • Percent of Changes 49.9%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –June 15, 2009    Schedule:  Architect Contract (2) N/A  BOE Approval N/A    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA December 11, 2007     Approval by DSA April 24, 2008    Authorize to Bid (2) April 8, 2008  BOE Approval April 22, 2008    Bid Opening May 28, 2008    Award of Contract (1) June 4, 2008    Notice to Proceed December 6, 2008    Substantial Completion June 15, 2009    Planned Occupancy June 15, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 22   Middle School Pre‐Design  Jordan, J.L. Stanford and Terman  A. PROJECT STATUS     AEDIS presented recommended concept plans for each campus to the  Board of Education on June 23 for discussion and received approval  on September 8 by the Board of Education to move into schematic  design.                    B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1 – 2.12    D. PROJECT OVERVIEW:  • This project has been completed on schedule and under budget. Board approval received on September  8, 2009. Funding  State Funds $0  Strong Schools Bond Funds $101,000  Other Funding $0  Total $101,000    Budget  Salaries and Benefits $0  Supplies $1,000  Contracts & Services $85,000  Construction & Equipment $0  Soft Costs Contingency $15,000  Total $101,000    Percent of Budget Expended 39.9%    Current Phase: Complete   Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) June 23, 2009  BOE Approval September 8, 2009    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 23   Middle Schools Interim Classrooms  Jordan and J.L. Stanford  A. PROJECT STATUS     Contracts were awarded to Coulter Construction for Jordan Middle  School and Mark Electric for Stanford Middle School following  Board of Education approval on May 26, 2009.  Both contractors  started work on June 15, 2009 and were completed on August 3,  2009 at Jordan and August 12, 2009 at Stanford.  Of the $1,047,186  project budget, 25%, or $236,696 has been expended. Pending  Change Orders are currently estimated to be a deduct of ($10,331),  which is approximately 0% of the $30,698 construction  contingency.            B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 2.1, 6.4, 6.5    D. PROJECT OVERVIEW:  • This project was completed under budget and on schedule. Funding  State Funds $0  Strong Schools Bond Funds $1,047,186  Other Funding $0  Total $1,047,186    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $308,648  Construction & Equipment $707,840  Soft Costs Contingency $30,698  Total $1,047,186    Percent of Budget Expended 24.8%    Change Order Contingency  • Starting Contingency Balance $30,698  • Remaining Contingency Balance $30,698  • Percent of Changes 0%  (Change Orders + Construction Change Directives vs.  Original Contract)  Current Phase: Occupancy –August 25, 2009    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA April 14, 2009     Approval by DSA April 22, 2009    Authorize to Bid (2) March 31, 2009  BOE Approval April 14, 2009    Bid Opening May 14, 2009    Award of Contract (1) May 26, 2009    Notice to Proceed June 1, 2009    Substantial Completion August 12, 2009    Planned Occupancy August 25, 2009    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 24   Garland Elementary School  Campus Modernization  A. PROJECT STATUS    The Board of Education voted on August 25, 2009 to approve the  amendment to Garland lease to Stratford School.  Therefore, the  district has placed the project on hold.                B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.1, 1.4 – 1.10    D. PROJECT OVERVIEW:  • This project has been placed on hold. Funding  State Funds $0  Strong Schools Bond Funds $22,178,544  Other Funding $0  Total $22,178,544    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $3,830,789  Construction & Equipment $17,485,000  Soft Costs Contingency $862,755  Total $22,178,544    Percent of Budget Expended 1.3%  Current Phase: Schematic Design    Schedule:  Architect Contract (2) October 28, 2008  BOE Approval October 30, 2008    Conceptual Design (2) February 10, 2009  BOE Approval February 24, 2009    Schematic Design (2) June 2, 2009  BOE Approval June 23, 2009    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  Page | 25   Elementary School Teaching Walls  Phase 1 Schools  A. PROJECT STATUS    The district placed this project on hold after review of the  implementation of other classroom improvements, as  recommended by the elementary school principals.  This  project has been renamed ‘Elementary Classroom  Improvements’ (see Capital Projects summary above).              B. BUDGET & SCHEDULE SUMMARY                                                  C. BOND PROJECT LIST REFERENCE: 1.9    D. PROJECT OVERVIEW:  • This project has been renamed ‘Elementary Classroom Improvements’ (see Capital Projects summary  above).  Funding  State Funds $0  Strong Schools Bond Funds $7,044,987  Other Funding $0  Total $7,044,987    Budget  Salaries and Benefits $0  Supplies $0  Contracts & Services $1,341,394  Construction & Equipment $5,498,498  Soft Costs Contingency $205,095  Total $7,044,987    Percent of Budget Expended 1.6%  Current Phase: On Hold   Schedule:  Architect Contract (2) September 30, 2008  BOE Approval October 14, 2008    Conceptual Design (2) N/A  BOE Approval N/A    Schematic Design (2) N/A  BOE Approval N/A    Submit to DSA N/A     Approval by DSA N/A    Authorize to Bid (2) N/A  BOE Approval N/A    Bid Opening N/A    Award of Contract (1) N/A    Notice to Proceed N/A    Substantial Completion N/A    Planned Occupancy N/A    * Anticipated Dates – Subject to Change  ( ) Denotes number of Board of Education Readings  OHS WEST:260388860.1 A-1 EXHIBIT A PALO ALTO UNIFIED SCHOOL DISTRICT BOND PROJECT LIST [Note: The order in which projects are listed is not an indication of priority for funding or completion. Not all listed projects will be completed at every site.] 1. ELEMENTARY SCHOOL PROJECTS Addison Barron Park Briones Duveneck El Carmelo Escondido Fairmeadow Garland Greendell Hays Hoover Nixon Ohlone Palo Verde 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Acquire and install modular classrooms, as needed. 4. Expand libraries to accommodate enrollment growth. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 9. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 10. Modernization/replacement of administration/multipurpose/library space. Numbers Added A-2 OHS WEST:260388860.1 2. MIDDLE SCHOOL PROJECTS David Starr Jordan Jane Lathrop Stanford Terman 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 3. Construct extra school-wide storage space. 4. Expand classrooms and classroom wings, library and administration spaces. 5. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 6. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 7. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 8. Renovate gymnasium, including new gym floors, doors, windows, bleachers and athletic equipment; upgrade building infrastructure, including power and water distribution. 9. Renovate swimming pool and pool deck; new filtration system; new storage and restrooms; upgrade pool equipment. 10. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. 11. Repair/Replace and/or improve concrete walkways and asphalt; canopies; parking lot and driveways. 12. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. A-3 OHS WEST:260388860.1 3. GUNN HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Demolish old library building. 3. Replace temporary classrooms with permanent classrooms. 4. Construct additional restrooms. 5. Construct second gymnasium. 6. Construct new soccer field. 7. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 8. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 9. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 10. Improve or provide new security systems, including alarms, lighting, locks, monitoring systems, fencing, etc. 11. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 12. Replace swimming pool with new 35-meter pool, pool equipment and support structures, pool decking, bleachers, storage, restrooms, showers, associated equipment. 13. Renovate gymnasium; interior renovation including gymnasium floors and bleachers; replace athletic equipment. 14. Modernize football stadium, including new bathrooms and concession stands. A-4 OHS WEST:260388860.1 4. PALO ALTO HIGH SCHOOL PROJECTS 1. Construct new permanent classrooms and classroom buildings to accommodate enrollment growth and expanded programs. 2. Replace temporary classrooms with permanent classrooms. 3. Construct additional restrooms. 4. Upgrade climate control systems, including passive technologies to conserve energy, such as shade canopies, energy-efficient windows, window coverings and shade control; install/replace heating, ventilation and air conditioning. 5. Install/improve local area network (LAN) and wide area network (WAN) infrastructure to accommodate technology upgrades; install/upgrade communications systems. 6. Building exterior and building shell renovation, including seismic structural upgrades and Americans with Disability Act (ADA) improvements to bring all buildings to current code; roofs; repainting and/or resurfacing. 7. Classroom and other school facilities modernization and building interior improvements, including infrastructure and major building system upgrades. 8. Library modernization and building interior improvements, including infrastructure and major building system upgrades. 9. Renovation or replacement of the Tower Building to accommodate administration, classroom and program support space. 10. Renovate Main Gymnasium and second gymnasium, including seismic upgrades; accessibility improvements; construction of new restrooms; install new roofing; replace doors and windows; replace gymnasium floors and athletic equipment, bleachers and renovation of interior. Renovation or replacement of weight training facility. 11. Construct new theater building. 12. Renovate and improve soccer field, including new retaining wall and bleachers; new fencing and storage. 13. Modernize football stadium, including replace bleachers; new bathrooms and concession stands. 14. Replace and/or improve play fields, including drainage and irrigation, install water meters; replace landscaping; re-surface and re-stripe hardcourts and replace outdoor athletic equipment. A-5 OHS WEST:260388860.1 5. OTHER DISTRICT-WIDE PROJECTS Furnishing and equipping of existing and newly constructed, modernized or rehabilitated classrooms and facilities on an ongoing basis, including to replace worn, broken, or out-of-date furniture and equipment for all classrooms, athletic facilities and other facilities, as needed. 1. Replace existing or acquire new computers, technology and related equipment on an ongoing basis. 2. Establish a planned maintenance fund to address maintenance work expected to be needed to all District facilities on an ongoing basis (other than as may be necessary for current maintenance, operation or repairs), in order to implement the District’s comprehensive facilities maintenance plan. 3. Acquisition of any of the facilities on the Bond Project List through temporary lease or lease- purchase arrangements, or execute purchase option under a lease for any of these authorized facilities. 4. If and as opportunities become available, and to the extent the Board of Education determines that bond funds are available for the purpose, acquisition of land and other interests in real property for future school buildings and other District facilities, and construction of such facilities, and rehabilitation/renovation of District-owned buildings and sites not otherwise listed. 5. Repair, upgrade, modify, expand, refinish, replace and construct site improvements, including off-street parking areas, pickup/dropoff, signage, paths, sidewalks and walkways, canopies, hard courts (student play areas), athletic play fields, landscaping, irrigation, permanent athletic field equipment and facilities (including nets, basketball standards, goals and goalposts, backstops), field lighting, etc. 6. ADDITIONAL NECESSARY AND INCIDENTAL PROJECTS 1. Remove, dispose of, and otherwise remediate hazardous materials, including asbestos, lead, etc., where necessary. 2. Address unforeseen conditions revealed by construction/modernization (including plumbing or gas line breaks, dry rot, seismic, structural, etc.). 3. Other improvements required to comply with existing building codes, including the Field Act, and access requirements of the Americans with Disabilities Act (ADA). 4. Site preparation/restoration in connection with new construction, renovation or remodeling, or installation or removal of relocatable classrooms, including ingress and egress, demolition of existing structures, removing, replacing, or installing irrigation and drainage, utility lines (such as gas lines, water lines, electrical lines, sewer lines, and communication lines), trees and landscaping, relocating fire access roads, traffic lights and mitigation, and acquiring any necessary easements, licenses, or rights of way to the property. 5. Rental or construction of storage facilities and other space on an interim basis, as needed to accommodate construction materials, equipment, and personnel, and interim classrooms (including relocatables) for students and school functions or other storage for classroom materials displaced during construction. A-6 OHS WEST:260388860.1 7. RENOVATION/MODERNIZATION (DEFINED) For purposes of the Bond Project List, renovation and modernization projects are intended to restore the building systems and infrastructure, weather protections, finishes, and technology, or reallocate and reorganize space, to a condition that will provide a sustainable, functional educational and administrative environment for future years, comparable to new construction. Renovation projects may include, but are not limited to nor necessarily encompass, all of the following, depending upon the age, condition and needs of each particular school facility: 1. upgrade electrical, communication, fire alarm, and similar building systems as well as main power service and distribution, which may include active and passive solar power and heating system acquisition, installation and construction 2. Replace, repair or upgrade plumbing, piping and drainage systems, including water supply, meters, water heating, and wastewater systems, plumbing fixtures and sinks, etc., within buildings and sites and to connect with city supply and drainage systems 3. Replace or modify aging heating, ventilation and air cooling systems with energy-efficient heating and air cooling systems (HVAC), including installing energy management systems (EMS); 4. Replace, modify, upgrade interior lighting and exterior safety/security lighting systems and fixtures, as necessary; 5. Repair, modify and construct structural elements of the existing structure as necessary; 6. Replace or repair aging roofs with similar materials or District standard materials; 7. Replace, repair, install and construct, as necessary, interior walls, floor and ceiling finishes, doors, door locks, windows, cabinets and casework, and equipment attached to wall surfaces (including white boards, marker boards, tack boards, television mounts, scoreboards, fire extinguishers, kitchen cabinets/equipment, etc.); 8. Upgrade, modify and construct restroom facilities; 9. Comply, as necessary, with Americans with Disabilities Act (ADA) and Title 24 requirements; 10. Refinish the exterior finishes of the school (including stucco, wood and metal trims, wood siding, paint, etc.); replace doors and windows 11. Modify, expand, separate, convert and construct school support areas; staff work and lunch areas; and educational areas to provide adequate, functional environments; 12. Modify, replace and construct functional components of altered or replaced building components (including rainwater leaders, fascias, mansards, etc.); ™ For any project involving renovation, modernization, remodeling or rehabilitation of a building or the major portion of a building, the District may proceed with new replacement construction instead (including any necessary demolition), if the Board of Education determines that replacement and new construction is more practical than rehabilitation and renovation, considering the building’s age, condition, expected remaining life, comparative cost, and other relevant factors.